HomeMy WebLinkAboutAgenda - 05-03-1993 - VIII-D 1
ORANGE C O U N T Y
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: May 3 , 1993
Action Agenda
Item #
SUBJECT: REGIONAL BICYCLE PLAN
DEPARTMENT: PLANNING PUBLIC HEARING Yes x No
ATTACHMENT(S) : INFORMATION CONTACT: Gene Bell
- Agenda Item #11 from 3-10-93 Ext. 2589
TAC Meeting
- Excerpts from 3-10-93 TAC
Minutes TELEPHONE NUMBERS:
Hillsborough - 732-8181
Durham - 688-7331
Mebane - 227-2031
Chapel Hill - 967-9251
PURPOSE: To consider a request for additional funding for
the Regional Bicycle Plan consultant.
BACKGROUND: On October 1, 1992 the Durham-Chapel Hill-Carrboro
(DCHC) Transportation Advisory Committee (TAC) held a
public hearing in Durham to receive comment on the
proposed Regional Bicycle Plan for Durham and Orange
Counties. Comments were also requested from NCDOT.
Extensive comments were received in December and
ranged from relatively minor technical corrections to
more fundamental issues such as the target group for
which bicycle improvements are recommended.
The consultant, Greenways, Inc. , has indicated that it
will cost approximately $5,000 to conduct further
research on the NCDOT comments and revise the Plan to
incorporate them along with comments from the hearing.
The TAC discussed additional funding on March 10, 1993
and voted unanimously to request that participating
jurisdictions share the cost in the same proportion as
the original cost estimate for the project. Orange
County contributed 20.085% of the project cost making
its share of the additional funding $1,004 . The City
of Durham has committed to additional funding as
detailed in Agenda Item #11. Durham County will
consider it on April 26 and Chapel Hill is tentatively
scheduled to consider additional funding in early May.
RECOMMENDATION: The Administration recommends approval of the
additional $1,004 in funding from contingency.
DK15:5-3BIKE.DOC
44- 2
TRANSPORTATION ADVISORY COMMITTEE
4selh'Ir
1 Pr DURHAM - CHAPEL HILL - CARRBORO URBAN AREA
March 3 , 1993
MEMO TO: Transportation Advisory Committee
FROM: Mark D. Ahrendsen, TCC Chairperson
1SUBJECT: Regional Bicycle Plan
On October 1, 1992 the Transportation Advisory Committee (TAC)
held a public hearing to receive public comment on the proposed
Regional Bicycle Plan for Durham and Orange Counties. The TAC also
requested comments from NCDOT on the Plan.
Extensive comments were received from NCDOT in December.
These comments ranged from relatively minor technical corrections
to more fundamental issues such as the target group for which
bicycle improvements are recommended.
The consultant, Greenways, Inc. , has indicated that it will
cost approximately $5,000 to examine and conduct further research
on the NCDOT comments and to revise the Plan to incorporate the
comments from NCDOT and those received at the public hearing.
It is suggested that this additional cost be shared in the
same proportion as the original cost estimate for this project
($30,000) and as indicated below:
Cost Share
Percent Dollars
Carrboro 0 % 0
Chapel Hill 20. 625% 1,031
Durham 37.915% 1,896 -
Durham County 21.375% 1, 069
Orange County 20. 085% 1,004
100. 000% $5, 000
It is recommended that each of the participating jurisdictions
provide the suggested supplemental funding necessary to complete
the Regional Bicycle Plan.
MDA/cwm
CRYOFMMHAM DEPARTMENTOFTRANSPORTAT1ON 101 CITY HALL PLAZA DURHAM,N.C.27701 (919)560-4366
-----
#1 3
TRANSPORTATION ADVISORY COMMITTEE
March 10 , 1993
MINUTES OF MEETING
The Transportation Advisory Committee met on March 10, 1993 at
9: 00 a.m. in the Committee Room on the second floor of Durham City
Hall. The following attended:
**Kenneth S. Broun Town of Chapel Hill (TAC Chair)
**Alice Gordon Orange County Board of Commissioners
**Charlie Grady, Jr. N. C. Board of Transportation
**Becky Heron Durham County Board of Commissioners
**John Lloyd City of Durham/Alternate
**Frances Shetley Town of Carrboro
, 1
*Joyce Brown Town of Chapel Hill
*Shirley Marshall Triangle Transit Authority (TTA)
*Ellen Reckhow Durham County Board of Commissioners
Mark Ahrendsen City of Durham/Dept. of Transportation
Gene Bell Orange County Planning/Hillsborough
David Bonk Town of Chapel Hill
Margaret Hauth Town of Hillsborough/Planning Dept. .
Mary Hough City of Durham/Dept. of Transportation
Joe Huegy Triangle Transit Authority (TTA)
Ed Johnson City of Raleigh/Dept. of Transportation
Elvis Latiolais Carolina Trailways
Mack Little Little & Little
Cynthia Mitchell City of Durham/Dept. of Transportation
Leann. Nelson 1-85 Neighborhoods Committee
Paul Norby Durham City/County Planning
1
Felix Nwoko City of Durham/Dept. of Transportation 1
Wesley Parham City of Durham/Dept. of Transportation *
Eric Pas Duke University .
Liz Rooks Research Triangle Foundation
Bob Rose Town of Hillsborough .
John Schrohenloher FHWA ..
Juanita Shearer-Swink Triangle Transit Authority (TTA)
Bob Smith North Carolina Central University (NCCU)
Joe Stevens FHWA .
Owen Synan City of Durham/Dept. of Transportation __
Kenneth Withrow Town of Carrboro . •
**Voting Members - -
*TAC Alternates & Ex officio Members _ _ _
" I
All members were present except Sandy Ogburn and Virginia
Engelhard with the City of Durham. John Lloyd served as the
alternate for the City of Durham.
Kenneth Broun, TAC Chair, brought the meeting to order.
Charles Grady, Jr. and Juanita Shearer-Swink were introduced as the
4
TAC Minutes - 3/10/93
Page 5
lot was approved previously by the TAC. A balance of approximately
$600, 000 remains to be allocated as desired.
Becky Heron made a motion to approve the obligation of
$1,680, 080 in Direct Allocation STP funds to the projects listed
above. Alice Gordon seconded the motion. The motion passed
unanimously.
It was requested that the TCC look at the following projects
to receive STP Direct Allocation funding: (1) Bicycle/pedestrian
path from N. Greensboro Street to Elm Street in Carrboro, (2)
pedestrian improvements to existing roads without involving
widening the roads, particularly on the bus routes, (3) •
bicycle/pedestrian project bridge over Morgan Creek (in Chapel
Hill) at Arboretum/Ashe Place, (4) regional modelling process, and
(5) maintaining a contingency fund to cover any shortfalls for the
approved projects listed above.
National Highway System (NHS) :
Mark Ahrendsen summarized the National Highway System (NHS) .
This system consists of interstate routes and portions of urban and
rural principal arterial routes. It promotes interstate travel and
commerce. There was some discussion concerning the addition of
U.S. 15-501 from 1-40 south to the planning boundary in Chatham
County to the system.
Becky Heron made a motion to endorse the National Highway
System (NHS) recommended by NCDOT and to add U.S. 70 (from 1-85 to
Wake County) and the East End Connector to the NHS. Alice Gordon
seconded the motion. The motion passed unanimously.
Reference Material:
A summary of Transportation Funding Sources and a Dictionary
of Acronyms were provided to the TAC members for future reference.
Regional Bicycle Plan Supplemental Funding:
Mark Ahrendsen explained that the Regional Bicycle Plan needs
to be modified by the consultant to incorporate comments from
NCDOT. This will cost approximately $5,000. Alice Gordon made a
motion that each of the jurisdictions participating in the Regional
Bicycle Plan share in the cost of the additional $5, 000 necessary
to complete the Plan in the same proportion as the original cost
estimate for this project. Becky Heron seconded the motion. The
motion passed unanimously.