ORANGE COUNTY
BOARD OF COMMISSIONERS
Action Agenda
Item No. .27:r-B
ACTION AGENDA ITEM ABSTRACT
Meeting Date: March 23, 1993
SUBJECT: CONTRACT APPROVAL; ENGINEERING DESIGN FOR NEW COURTHOUSE ROOF
REPAIRS
DEPARTMENT: PURCHASING AND CENTRAL SERVICES PUBLIC HEARING: YES: NO:XX
ATTACHMENT(S): INFORMATION CONTACT:
PAM JONES, ext. 2650
Agreement from RTD Associates or WILBERT MCADOO ext 2626
Telephone Numbers-
Hillsborough 732-8181
Chapel Hill 967-9251
Mebane 227-2031
Durham 688-7331
PURPOSE: To consider an agreement with RTD Associates for design of roof replacement system
at the New Courthouse, Hillsborough, NC.
BACKGROUND: We have recently observed evidence of leaks in the Superior Courtroom.
Inspection of the roof above that area indicated deterioration of the roof. At our request,
RTD Associates did a preliminary analysis and have recommended replacement of the built up
portions of the roof. This includes approximately 5600 square feet of roof.
RTD Associates worked with us to replace the roof at the Central Recreation Center in Hillsborough,
with very satisfactory results. They have demonstrated strong expertise in the design and installation
of roofing systems and have worked with us to bring the project in within the budget allocated. For
these reasons, we are recommending that the Board accept their attached proposal for design
engineering and contract administration services in an amount of $3,275.
Funds to replace the roof are included in the Capital Improvements Plan ($50,000). It is anticipated
that the bids for roof replacement will be solicited within the next 60 days.
RECOMMENDATION: The Manager recommends approval of an agreement with RTD Associates,for
engineering design and contract administration services for the New Courthouse roof, in an amount
not to exceed $3,275; and authorize the Chair to sign on behalf of the Board.
Roof Engineering Technology
R D Diagnostics and Design
5500 Executive Center Dr., Suite 117
Associates, Pal. Charlotte, NC 28212 704-536-3322 ,.
1"- 2
February 25, 1993 MAR -3 1
pin r : .
j
Mr. Wilbert J. McAdoo Re : New County Courthouse
Orange County Hillsborough, NC
P.O. Box 8181
Hillsborough, NC 27278
Dear Mr. McAdoo:
As a Professional Engineering firm specializing in the specific
area of Roof Diagnostics, Engineering, Design and Project
Management, we respectfully request your consideration of the
following proposal .
We propose to provide our specialized Roof Engineering expertise as
listed below for the above-referenced project.
ENGINEERING DESIGN AND CONTRACT ADMINISTRATION SERVICES
Phase # 1 : Project Planning and Staffing
A Project Manager shall be selected within our firm to
work closely with the Owner 's representative from
inception to successful completion of the project.
Phase # 2 : Project Requirements Review
A careful and methodical study of the previously
prepared Roof Diagnostic Report (as prepared by our
firm) shall be performed to correlate the existing
conditions, problems and viable solutions for
corrective action.
Phase # 3 : Project Scheduling
We shall prepare a tentative work sequence schedule for
the Owner's representative, to establish time frames
for all phases of Engineering, Design, and Construction
work to be performed.
Phase # 4 : Performance Criteria Analysis
Due to the sensitive and reactive nature of the roofing
systems available today, a Performance Criteria
Analysis shall be developed in order to determine the
actual requirements of the roof membrane, insulation,
attachment procedure, drainage, customized details,
etc.
COMPANY NAME: Orange County Page 3
PROJECT NAME : New County Courthouse
LOCATION: Hillsborough, North Carolina
Phase # 4 : Performance Criteria Analysis Cont 'd.
This Performance Criteria shall consist of a site visit
to evaluate all conditions which must be considered
during the roof system selection process, in regard to
building and Owner requirements .
Phase # 5 : Roof System Evaluation and Selection
Once the Performance Criteria has been established,
research shall be performed to determine which of the
many systems available have technical capabilities
which are strictly compatible with this criteria. The
significance and importance of this phase is to
properly select the right system, which will provide
our client a successful roof system with maximum
longevity, minimum annual maintenance costs, and
maximum return on investment.
Phase # 6 : (Schematic) Roof Engineering and Design
A preliminary engineering and design shall be performed
to establish the requirements for the various
components of the roofing system, such as membrane,
insulation, attachment procedure, associated details ,
etc. , and to organize the content and format of the
technical portion of the design specifications, which
will become an integral part of the Contract Documents .
This technical section dictates the standard of quality
in materials and workmanship. It also outlines the
existing conditions, scope of work, materials to be
used, and
execution of work to be performed.
Phase # 7 : (Schematic) Drawings and Customized Detail Design
Documentation
During the site visit referred to in Phase #4, the
Project Manager will evaluate each and every different
detail requirement such as base flashings, edge
flashing, vent pipes, equipment curbs, etc. , for
customized detail development and illustration. Also,
a comprehensive roof plan will be developed to show
local placement of equipment, drainage dimensions and
other pertinent data for final working drawings
development.
RTD Roof Engineering Technology
Diagnostics and Design
5500 Executive Center Dr..Suite 117
Associates.PA. Charlotte,NC 28212 704.506-3322
COMPANY NAME: Orange County Page *
PROJECT NAME : New County Courthouse
LOCATION: Hillsborough, North Carolina
Phase # 8 : Front-end Portion of the Bid Document Development
In the best interest of the Owner, it is imperative
that the total bid document package contain legalities
pertaining to general conditions of the project,
insurance requirements, job-site use and behavior by
Contractor, time of completion, liquidated damages,
quality control statements, Performance and Payment
Bonds, etc. , to ensure all parties have a clear
understanding of who is responsible for what.
An interview with the Owner's representative will be
conducted by the Project Manager, to discuss the
various items necessary for the front-end documents, in
order to comply with professional contracting practices
and your organizational policies . Also, certain times,
dates and places will be established within these
front-end documents for the bid advertisement, pre-bid
meeting, bid receipt and contract award, etc.
Phase # 9 : Final Engineering, Design, Drawings/Details , and
Specification Development (Bid Package)
Under this phase, the completion, correlation and
merging of all comprehensive components of the bid
documents shall be completed and submitted to the
Owner 's representative for approval .
The Bid Package shall include:
( 1) Invitation to Bid
(2 ) Statement re General Conditions (AIA - A201 )
( 3) Supplementary General Conditions
(4 ) Statement re Instructions to Bidders (AIA - A701 )
( 5) Supplementary Instructions to Bidders
( 6) Form of Proposal.
(7 ) Bid Bond
( 8) Statement re Form of Agreement (AIA - A101 )
(9 ) Performance Bond
( 10) Payment Bond
( 11) Division 7 - Roofing Technical Specifications
( 12 ) Working Drawings and Customized Details
NOTE: 10 sets of Contract Documents shall be
provided for Owner and Contractor use.
RTC Roof Engineering Technology
Diagnostics and Design
5500 Executive Center Dr.,Suite 117
Associates,PA. Charlotte.NC 28212 704.596-3322
COMPANY NAME: Orange County Page 4
PROJECT NAME: New County Courthouse
LOCATION: Hillsborough, North Carolina
Phase #10 : Contractor - e-•ualification
Investiga ve research sh. be performed 'ithin the
t j roof in. contracting co ' •nity to determ' -e and select
0
• qual ' y roofing con- actors who - e suited and
qua ified for this r oject.
e desired qu. ifications sh. 1 include: rack
record, size, = perience, manp• er, financial tatus,
c),,OP‘ approved appl ' cator of the sys em specified, ility to
perform wor. within the stir lated time pe iods, etc.
Phase #11 : Invitation to Bid
Upon receipt of your approval of the Bid Documents, the
pre-qualified, selected roofing contractors will be
contacted and forwarded a complete set of the Bid
Documents for bid preparation. it is the intent to
invite a sufficient number of contractors to bid in
order to receive a minimum of three bids on the
project.
Phase #12 : Pre-bid Conference
On the pre-established date, the Pre-bid Conference
will be conducted by the Project Manager at the project
site. This meeting shall be attended by the Owner's
representative and invited contractors . The Pre-bid
Meeting shall be divided into two sessions:
1st Session: Inside the facility, preferably a
Conference Room.
During this session, the contents of
the Bid Documents shall be discussed
and any questions answered, in order
to thoroughly explain and clarify the
full scope of work to ensure
comparable bidding understanding.
2nd Session: On the roof.
All parties shall be given the
opportunity to tour the roof to verify
existing conditions and scope of work
involved.
Minutes of the meeting shall be recorded and will
become an integral part of the Project Manual.
Roof Engineering Technology
RTD Diagnostics and Design
5500 Executive Center Dr.,Suite 117
Associates.PA. Charlotte,NC 28212 704.536.3322
COMPANY NAME: Orange County Page 5
PROJECT NAME: New County Courthouse
LOCATION: Hillsborough, North Carolina
Phase #13 : Receipt and Tabulation of Bids
On the pre-established time, date and place, the
Project Manager shall assist the Owner's representative
in receiving, opening, and tabulating the contractors '
bids.
A careful review of each bid shall be performed to
verify the completeness, and extent of each bid as
required by the bid package. The bids shall be
tabulated to determine the apparent low bidder.
Phase #14 : Contract Administration
Upon confirming the bids to be in strict compliance
with the bid documents and project requirements, a
recommendation for award shall be made to the Owner.
After receiving approval by the Owner, the Contract
Documents shall be prepared by the Project Manager, in
triplicate, to be executed by the Contractor and then
the. Owner.
During the Contract execution process, a Letter of
Intent shall be issued to the Contractor (with Owner's
authorization) , so that the Contractor can proceed with
his scheduling.
Once all three copies of the Contract have been
executed, the Owner, the Contractor and RTD Associates
will maintain a copy for their record.
PROJECT MANAGEMENT SERVICES
Phase #15 : Pre-Construction Conference
On the pre-established time, date and place, the Pre-
Construction Conference shall be conducted by the
Project Manager. During this meeting, the full scope
of work shall be reviewed by all parties present.
Other pertinent project requirements shall be discussed
and agreed upon such as : staging areas, schedules, pay
requests, communication channels, use of facilities,
submittals, etc.
Minutes of this meeting shall be recorded and will
become an integral part of the Project Manual .
RTD Roof Engineering Technology
Diagnostics and Design
5500 Executive Center Dr..Suite 117
Associates.PA. Charlotte,NC 28212 704.596.3322
COMPANY NAME: Orange County Page 6
PROJECT NAME: New County Courthouse
LOCATION: Hillsborough, North Carolina
Phase #16 : Submittal Review and Approval
Upon receipt of the submittal package, as provided by
the Contractor, the Project Manager shall carefully
review all material samples, material technical data,
etc. , to confirm compliance with the requirements of
the Specifications and Bid Documents .
Phase #17 : Verification of Material Delivery and Proper Storage
The Project Manager shall visit the project site to
inspect and verify the type, condition and quantities
of materials stored are in compliance with the material
requirements as specified.
The type and quality of storage facility, covers, etc.
shall be inspected to verify proper protection from
damage and weather as specified.
Phase #18 : On-site Inspection
The Project Manager shall visit the project site at
such intervals as stipulated by the agreement between
RTD Associates and the Owner. During the on-site
inspection, the quantities and quality of application
shall be carefully inspected to verify strict
compliance with the contract specifications.
Progress update reports shall be provided to the Owner
as required and shall consist of written and
photographic documentation of work performed to date.
Upon request, RTD Associates will be available during
and after project completion to assist the Owner with
additional services beyond the scope of this agreement,
i.e. , quality assurance, non-destructive moisture
tests, warranty enforcement, warranty inspections,
trouble shooting and moisture intrusion identification.
Phase #19 : Pay Request Review, Verification and Approval
Upon receipt of the Contractor's Pay Request, the
Project Manager shall review, verify and approve
properly substantiated payments due and forward to the
Owner for payment.
1
RTD Roof Engineering Technology
Diagnostics and Design
5500 Executive Center Dr.,Suite 117
Associates.PA. Charlotte,NC 28212 704.506-0022
COMPANY NAME: Orange County Page 7
PROJECT NAME: New County Courthouse
LOCATION: Hillsborough, North Carolina
Phase #20 : Final Inspection and Project Compliance Verification
Upon notification by the Contractor that all work has
been completed, the Project Manager shall perform a
final inspection to verify that all project and
contract document requirements have been successfully
satisfied and completed.
Phase #21 : Assembly and Submission of Project Close-out Documents
The Project Manager shall co-ordinate and assemble all
project close-out documents, such as Warranties,
Certificates of Compliance, etc. , to be forwarded to
the Owner, along with the approved final Contractor pay
request.
RTD Roof Engineering Technology
Diagnostics and Design
5500 Executive Center Dr.,Suite 117
Associates,PA Charlotte,NC 28212 704536.3322
COMPANY NAME: Orange County Page 8
PROJECT NAME: New County Courthouse
LOCATION: Hillsborough, North Carolina
SCOPE OF WORK AREA (SF) FOR THE SUM OF:
Engineering, Design & Built-up
Contract Administration Roof Areas
Project Management Services
Phases 1-17, 19-21
On-Site Inspections
Phase 18 (includes 2 inspections :
1 project startup and 1 interim)
Total $ 3,275 . 00
Includes Travel and Per Diem
NOTE: Additional services provided on this project by RTD
Associates at the request of the Owner which exceed the Scope of
Work as listed herein will be invoiced at the appropriate rate.
All services provided by RTD Associates shall be performed by our
staff of professional, experienced and qualified individuals in
order to provide you (our client) with not only a successfully
completed project, but an opportunity of joining our valued list of
satisfied clients.
On behalf of our entire staff, we thank you for the opportunity of
presenting this proposal and your consideration of allowing us to
become a vital part of this project .
Respectfully submitted,
RTD ASSOCI� ES, P.A.
/,/,,ni Bob 0. Bryn, P.E.
President
BB: 11
Accepted B :
P Y \_
Title: �.�.. -(//'�
Date:
RTDf Engineering Technology
Diagnostics and Design
5500 Executive Center Dr.,Suite 117
Associates,PA. Charlotte,NC 28212 704-536-3322
TERMS OF PAYMENT & GENERAL CONDITIONS
1 . Roof Analysis : 50% upon initiation of contract,
50% upon delivery of report.
Specifications : 50% upon initiation of contract,
50% upon completion of specification pkg.
On-Site Inspection: 50% upon initiation of contract.
Balance paid in proportion to progress of
work.
2 . Finance charges of 1 1/2% per month will be assessed on all
unpaid balances beyond the terms outlined above.
3 . The owner shall be responsible for providing: (A) Access to
the job-site and the roof; (B) Removal of sny ponding water
on the roof surface.
4 . We require a letter of acceptance, a signed copy of this
proposal or a written purchase order from your company, prior
to performing this work.
5 . RTD Associates, P.A. reserves the right to invoice for any
additional area, over and above the specified area and any
services performed that are not included in this proposal such
as warranty enforcement ( $52/Hr. ) consultations ( $52/Hr. ) , per
diem ( $75/Day) , travel expenses ( $ . 35/Mi. ) , or any other
related costs above and beyond the herein listed scope of
work. Duplicated copies of diagnostic report - $150;
photocopies of diagnostic report - $25-$50 (depending on size
and nature of report) ; extra copies of specs, plans & contract
documents - $50 .
6 . Please note that this proposal may be withdrawn if not
accepted within ( 30 ) days from the date on the proposal .
7 . A Certificate of Insurance will be furnished upon request.
8 . Delay Clause: Should the work be delayed of no fault of RTD
Associates, the additional time shall be invoiced at the rate
of $52 . 00/hour.
9 . Should the roof be under warranty, all core cuts and moisture
probes shall be performed by the warranty issuer or
contractor. Any charges for core cuts or probes shall be the
responsibility of the owner or contractor.
10 . The drawings, specifications and other documents furnished by
RTD Associates are instruments of service and shall not become
the property of the Owner whether or not the Project for which
they are made is commenced. Drawings, specifications and
other documents furnished by RTD Associates shall not be used
by the Owner on other projects, for additions to this Project,
for completion of this Project by others, except by written
agreement relating to use, liability and compensation.