HomeMy WebLinkAboutAgenda - 11-01-94-IX-A 1
ORANGE COUNTY
BOARD OF COMMISSIONERS
Action Agenda
Item No. 4
ACTION AGENDA ITEM ABSTRACT
Meeting Date: November 1,1994
SUBJECT: PROJECT REVIEW AND APPROVAL; JAIL PROJECT AND COURTHOUSE ADDITION
DEPARTMENT:PURCHASING AND CENTRAL SERVICES PUBLIC HEARING: YES: NO: %
ATTACHMENT(S): INFORMATION CONTACT:
PAM JONES, ext.2650
Telephone Number-
Hillsborough 732-8181
Chapel Hill 967-9251
Mebane 227-2031
Durham 688-7331
PURPOSE: To review and approve the plans for the Jail and the Courthouse projects.
BACKGROUND: The Jail project has been under development for more than a year. The County
received approval in April, 1994, for an additional $1,000,000 from the Federal Marshal's office.
Although original plans had been reviewed and approved by the State,this significant modification
served to restart the approval process. Presently, both the schematic and the design development
drawings for the expanded project have been approved by the State. It is anticipated that construction
documents will be submitted to the State by the end of October and approval received within four to
six weeks thereafter. The total budget for this project is$2,000,000.
The Board approved additional funds for the Courthouse addition in August, 1994. The architect has
worked diligently with Judge Battle to establish an acceptable program within a short time frame in
anticipation that the Courthouse addition could be bid in tandem with the Jail project. Theoretically,
by bidding the two projects together,economy of scale will allow the funds to go further on the smaller
project. The total budget for this project is$435,000.
Alan Baldwin,Grier-Fripp Architects,will be present to share the plans for both projects and answer
any questions which the Board may have.
RECOMMENDATION: The Manager recommends that the Board accept the report as information and
approve the plans as presented.