HomeMy WebLinkAboutAgenda - 05-17-2016-13-4 - Information Item - Jordan Lake Allocation Update INFORMATION ITEM
BOCC INFORMATION REQUEST OUTLINE
Meeting Date: 3/22/2016 Response Date: 4/08/2016
NOTE: This outline is an abridged version of the Unified Development Ordinance (UDO)Amendment Outline. Many of
these requests may evolve into an ordinance change if the BOCC suggests pursuit of the amendment idea.
ISSUE: Jordan Lake Allocation Update
Responding Department: Planning & Inspections
A. AMENDMENT TYPE
Map Amendments
Land Use Plan: Yesn NoN Maybes
Zoning Yesn No Maybes
Text Amendments
n Comprehensive Plan Text: Yesn NoN Maybes
n
UDO Text:
fUDO General Text Changes Yesn NoN Maybes
fUDO Development Standards Yesn No Maybes
fUDO Development Approval Yesn NoN Maybes
Processes
Section(s): Not Applicable at this time
B. RATIONALE
1. Purpose/Mission
At the March 22, 2016 BOCC meeting, Commissioner Jacobs requested information
regarding the ongoing round of Jordan Lake Allocations, specifically as it relates to
Raleigh and Wake County municipalities.
2. Analysis
Orange County currently has a 1`)/0 allocation of the Jordan Lake Water Supply Pool,
which is equivalent to approximately 1 million gallons per day (MGD). The annual
cost for this allocation is outlined in the Fiscal Impact portion of this report. Despite
the fact that Orange County has no water distribution facilities, this allocation is held
to provide water as needed in the future to the City of Durham or the Town of
Hillsborough for development in the County's economic development areas, which
will be served by their respective utility systems. In conversations with these two
municipalities, along with the City of Mebane, they have reported that they are
actively planning for their own long term water supply. However, Durham and
Hillsborough are not accounting for the areas the County has outlined as economic
development areas. Though there will likely be available supply through the
municipalities in the near future if these areas develop quickly, it is still prudent to
secure and maintain our own water supply for the future of these areas. In addition,
the allocation provides redundancy of supply in times of drought, which can be
particularly difficult on the water supply in the "headwater" portion of the Piedmont
where Orange County is located.
1
At this time, a total 63% of the estimated 100 MGD Water Supply Pool is allocated to
six different entities (Cary, Chatham County, Durham, Holly Springs, Orange Water
and Sewer Authority, and Orange County). Please note that the Cary allocation
serves not only the Town of Cary, but also Apex, Morrisville and a portion of the
Research Triangle Park. For more information regarding the Water Supply Pool and
the other storage "accounts" into which the total volume of the lake is divided, see the
attached sheet.
The North Carolina Division of Water Resources (DWR) received allocation requests
for water from Jordan Lake in November of 2014, including a request for an
additional 0.5% allocation from Orange County (which would bring our total allocation
to 1.5%, or approximately 1.5 MGD). The applications for Jordan Lake allocation
were supposed to project the applicant's water demands through the year 2045. The
allocation requests from the various applicants amounted to 105.9% of the Water
Supply Pool (see attached table from a DWR presentation summarizing the
requests). As shown on the attached table, the Town of Hillsborough is applying for
an allocation in this round, but did not have an allocation previously. DWR staff has
been reviewing these applications and comparing them to the combined Neuse-Cape
Fear River water supply model to estimate the effects of the increased allocations on
Jordan Lake and downstream users. DWR submitted draft recommendations for
allocating the Jordan Lake water supply pool to the Environmental Management
Commission (EMC) Water Allocation Committee (WAC) at its January 2016 meeting.
The DWR recommendation was for approval of all the submitted allocation requests,
with the exception of Fayetteville and Raleigh. This recommended approval would
allocate 91.2% of the Water Supply Pool. The WAC agreed with denying the
Fayetteville request but wanted the Raleigh request to be included in the
recommended allocation presented to the public for comment. If approved, this
would bring the total allocation percentage to 95.9% to cover water demands through
the year 2045.
The WAC requested public meetings be held by DWR to present the allocation
requests and receive feedback. The public meetings were held on March 22, 2016
and March 30, 2016, in Pittsboro and Wilmington, respectively. This public comment
period will be open until May 18, 2016. At that point, DWR staff will review the
allocation recommendations and make a final recommendation to the WAC in July
2016. A final ruling by the full EMC on the water supply allocations is expected in
September 2016.
With regards to Wake County municipalities and specifically, Raleigh, there are two
allocation requests which have been made. Cary, Apex, Morrisville and Wake
County (supplying water to a portion of Research Triangle Park) have combined to
request a total allocation of 46.2%, which is an increase of 7.2% from their current
combined allocation. The City of Raleigh has requested an allocation of 4.7% in this
round. Raleigh does not currently have a Jordan Lake Water Allocation.
All of the requests made by the various municipalities, with the exception of the City
of Fayetteville, are consistent with the Triangle Regional Water Supply Plan (Plan).
This Plan was developed by the Jordan Lake Partnership, a regional collaborative
partnership consisting of Apex, Cary, Morrisville, Durham, Holly Springs,
Hillsborough, Pittsboro, Raleigh, Chatham County, Orange County, Wake County
and the Orange Water and Sewer Authority (OWASA). The Raleigh allocation was
2
not included in the preferred alternative outlined in the Plan for meeting the region's
water needs. At the time of the development of the plan, Raleigh was planning on
being able to meet all of its water needs with sources other than Jordan Lake.
However, as the deadline for allocation application approached, Raleigh decided that
it needed to apply for the small allocation as insurance in case some of the
alternative sources either were not approved or did not come on line soon enough to
cover their water demand at the time. The City has committed to utilizing the
allocation, if it is needed, in a manner consistent with the Plan and the infrastructure
planning of the other Jordan Lake Partners. To this end, Raleigh has agreed to
include a contractual sunset of their allocation in the year 2045.
One important conclusion of the Plan is that all Triangle water supply systems, as
well as water users downstream of Jordan Lake, will be able to meet their projected
water needs for at least the next 50 years. This was determined by using the
hydrologic water supply model for the basin and comparing the water demands
through the year 2060 to the full range of recorded hydrologic conditions of the past
80+ years.
3. Comprehensive Plan Linkage (i.e. Principles, Goals and Objectives)
N/A
4. New Statutes and Rules
N/A
C. PROCESS
1. TIMEFRAME/MILESTONES/DEADLINES
a. BOCC Authorization to Proceed
Not Applicable at this time
b. Quarterly Public Hearing
Not Applicable at this time
c. BOCC Updates/Checkpoints
Staff will update the BOCC in the upcoming months with the results of the EMC's
decision on granting Orange County's Jordan Lake allocation request.
2. PUBLIC INVOLVEMENT PROGRAM
Mission/Scope:
a. Planning Board Review:
b. Advisory Boards:
c. Local Government Review:
d. Notice Requirements:
e. Outreach
3. FISCAL IMPACT
The additional allocation, if granted, will result in additional cost to maintain the water
allocation. The current allocation costs the County approximately $2,500 per year. If
the allocation request is approved, the annual costs will be approximately $4,000,
which has already been projected in the budget for the upcoming fiscal year 2017.
3
D. AMENDMENT IMPLICATIONS
N/A
E. SPECIFIC AMENDMENT LANGUAGE
Not Applicable at this time
Primary Staff Contact:
Kevin Lindley, PE
Planning and Inspections
919-245-2583
klindley @orangecountync.gov
Craig Benedict, Director
Planning and Inspections
919-245-2592
cbenedict @orangecountync.gov
4
Jordan Lake Storage y, ;_ ;: -_
Divided into 4 separate accounts �
Flood Control -- manage downstream flows during high precipitation events
Water Supply -- allocated by EMC
Water Quality -- augment downstream flows to meet management target
Sediment Storage -- compensation for storage loss due to sedimentation
D art Flood Storage
Surface A:ea 31.Z)10 Aa ;e El 240
top offloc.I 216-240 ft-msl
coax d Fad
Flca•3 .^.4.30 •r:e feet
Cccztsol
Stccage
S'_::fa:e r.:ea 13.900 Acres E1ev 210
top of Water Quality 67.38%
Water Supply ccnse:vat:cn
45,800 acre-feet !Doti
Cons#:vats 202-216 ft-msl
cn
Stce age
Eb 01 et
Sediment Storage
o
C CMG ei va ti on
Seclm•r3 II pool below 202 ft-msl
Stn:age
ft-msl = feet mean sea level
Department of Environmental Quality
Requested Allocations �' ► - -- - i
- V \
i �,
63% water supply Jordan Lake Water Supply Pool
storage allocated JLA-4
Applicant Current Requested
DWR received
Allocation Allocation
• 10 applications for Percent Percent
• 13 local governments Cary Apex Morrisville RIP 39 46.2
105.9% Total Round 4 Chatham Co North* 13
allocation requests Durham* 10 16.5
Holly Springs 2 2
Hillsborough 0 1
OWASA* 5 5
Orange Co 1 1.5
Pittsboro* 0 6
Raleigh 0 4.7
Fayetteville 0 10
Total Percent 63.0 I 105.9
*Western Intake Partners
Department of Environmental Quality
NIZ