SUBJECT: Contract Amendment Approval: West Ten Design Services; Phase II
DEPARTMENT: Purchasing and Recreation PUBLIC HEARING: (Y/N) No
ATTACHMENT(S):
Proposal
INFORMATION CONTACT:
Pam Jones 919 245-2652
Lori Taft 919 245-2673
PURPOSE: To consider approving a contract amendment for Corley Redfoot Zack (CRZ) to
complete design of West Ten Soccer Center-Phase II.
BACKGROUND: The Board previously approved a contract with CRZ to design Phase I of the
West Ten Soccer Center. Phase I is currently under construction.
The Board has approved the development of this phase of the project. This action authorizes
an additional $105,200 to be paid to CRZ for the completion of the design work of Phase II.
Primary elements of Phase II of this project include a building, playground, additional parking,
field lighting, well irrigation system, first aid stand and landscaping. The proposal also includes
revisions to the original master plan to accommodate future tennis courts and playground.
Construction of Phase II is anticipated to begin in late-Fall 2007.
FINANCIAL IMPACT: No additional funding is required as this action can be accomplished
within the approved budget.
RECOMMENDATION(S): The Manager recommends that the Board approve a contract
amendment with Corley Redfoot Zack in the amount of $105,200 to complete the design of
Phase II of the West Ten Soccer Center; and authorize the Purchasing Director to execute
paperwork to effect the amendment.
1 1 1
CORLEY REDFOOT ZACK ~~r.
A 1: C: 1-1 1 T (? C 'i' S E ti G 1 N E E R 5 P L A N N E P S
September 17, 2007
GLENN D. CORLEY, AIA
Presider:t, cso 1vls. Pamela K. Jones, Director
KENNET[i E
REDE00?
IA Purchasing & Central Services
.
,A
Vice President CoLUlty
Orange
MARK 7.ACK, AIA o
PO BOX 8151
VkePresident Hillsborough, NC 27278
A7ICHAEL L. HAMMEIZSLEY, PE
Principnt RE: West Ten Soccer Center
LAURENCE W. BUNCH, AIA PROPOSAL FOR ADDITIONAL PROFESSIONAL DESIGN
Associate SERVICES -Revised 9/17/07
ANDREW R. CRUICKSHANK, AIA CRZ #0310
Associate
CFiARLENE E. HANLEY, ATA Dear MS. JOrleS~
As$ocrnte
DAVID At. TAYLOR, AIA Corley Red.foot Zack, Inc., is pleased to present for your review and approval our
Associate design fee amendment proposal for the revised scope of work on the West Ten
fiARRY M.IENS£N Soccer Center.
Associate
KENNETHE.SMITH The proposed fee is for the Architectural and Engineering design of the additional
Associate work afi the site. The original proposal dated May 4, 2004, covered Phase I
construction only. The attached fee proposal includes a larger building,
additional parking lot, field lighting, well irrigation system, first aid stand,
landscaping, etc. The proposal also covers revisions to the original Masterplan to
accarnmodate the future tennis courts and playgxound.
PO Box 2368
Chape] Hill, NC 27515-2368
222 Cloister Court
Chapel Hill, NC 27514-2212
YEARS
', !i
The total fee for this revised scope of c~Tork is $105,200. If you are in agreement
with this proposal, we request that you issue an amendment to our Original
contract dated August 3, 2004.
Sincerely, /
Michael a mersley, PE
Principal
M LI-I:esw /0310-amd .2
Elzclasure
cr. Lori Taft, Marabeth Car
(919) 401-5586 Telephone
(919) 493-7306 Fax
www.carleyredfoatzack.com
`/(`)~
West Ten Soccer Center 9~17~07
PROPOSAL FOR ADDITIONAL PROFESSIONAL DESIGN SERVICES
CR7 #0310
PROPOSAL. BRTA.KDOtNN: CHANGE ORDER #1, ilcludes scope for (Master Plan
Master Planning: S 5,000
Schematic Design: 15,030
Desigl~ Development: 25,050
Construction Documents: 29,610
Biddu1g:
5,010
Construction Administration: -~,~
Total Additional Fee: 51.05,200
Fees include masterplanning for tennis courts and the playground, as well as complete design services
for Phase II, wllich included a large building, field lighting, additional parking lots, landscaping, etc.
„"\,`~,
CORLSY Rt'DPOOT ZncK ~,x~.