SUBJECT: Orange County Detention Center Project Update
DEPARTMENT: Asset Management Services PUBLIC HEARING: (Y/N) No
ATTACHMENT(S): INFORMATION CONTACT:
Jeff Thompson, 919-245-2658
Gordon Dively, 919-245-2628
PURPOSE: To receive an update on the progress of the Detention Center and to provide
feedback on the schematic design to staff and the designer.
BACKGROUND: On June 2, 2015, the Board of Orange County Commissioners authorized the
Manager to execute a professional services agreement with a qualified design firm selected
through a Request for Qualifications ("RFQ") process over the summer break. Moseley
Architects of Charlotte was selected through this process and began schematic design in
August.
As part of the initial design work, Moseley has collected extensive stakeholder input that will
serve as a basis for the overall design and operation of the facility. Moseley representatives will
join staff in presenting a project progress update that will highlight key design principles, findings
from the stakeholder input process, and going forward schedule milestones.
Utility and site construction is anticipated to begin in the summer of 2016, followed by the
building construction in early 2017. The detention center is anticipated to be complete in the
fall-winter of 2018.
FINANCIAL IMPACT: There is no financial impact associated with receiving this update.
SOCIAL JUSTICE IMPACT: The design, construction and operation of the Orange County
Detention Center address the following social justice goal:
• GOAL: CREATE A SAFE COMMUNITY
The reduction of risks from vehicle/traffic accidents, childhood and senior injuries, gang
activity, substance abuse and domestic violence.
RECOMMENDATION(S): The Manager recommends the Board receive an update on the
progress of the Detention Center and provide feedback on the schematic design to staff and the
designer.