HomeMy WebLinkAboutAgenda - 09-29-2015 - AgendaAGENDA
Orange County Board of Commissioners
Chapel Hill — Carrboro Board of Education
Orange County Board of Education
Joint Meeting
September 29, 2015
7:00 p.m.
Richard Whitted Meeting Facility
300 Tryon Street, Hillsborough
1. Welcome and Opening Remarks - Chair Kelley, Chair Piscitelli and Chair
McKee
2. School Capital Needs Prioritization
• Chapel Hill - Carrboro City Schools — Presentation of Capital Needs
• Orange County Schools — Presentation of Capital Needs
3. Discussion of Potential Comparative Analysis of School Capital Needs
• Third Party Professional to Rank and Rate Needs based on
Determined Criteria
4. Impacts of State Approved Budget
• Chapel Hill - Carrboro City Schools
• Orange County Schools
5. Discussion of School Related Topics
• Collaborative Opportunities between Districts
• Expanding Innovations (e.g. Magnet Schools, Year Round Schools)
• Programs /Plans to Address Achievement Gap
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: September 29, 2015
Action Agenda
Item No. 1 -5
SUBJECT: Joint Meeting — Board of County Commissioners, Chapel Hill - Carrboro City
Schools Board of Education and Orange County Schools Board of Education
DEPARTMENT: County Manager /Finance and PUBLIC HEARING: (Y /N) No
Administrative Services
ATTACHMENT(S): INFORMATION CONTACT:
As Listed in the "Background" Section
Bonnie Hammersley, 919 - 245 -2300
Paul Laughton, 919 - 245 -2152
Dr. Tom Forcella, 919 - 967 -8211
Dr. Todd Wirt, 919 - 732 -8126
PURPOSE: To discuss School Capital Needs prioritizations, the impacts of the State Approved
Budget on Schools, and various other School related issues that are of interest to the Board of
County Commissioners, Chapel Hill - Carrboro City Schools (CHCCS) Board of Education and
Orange County Schools (OCS) Board of Education.
BACKGROUND: The County /Schools Collaboration Work Group and the Board of County
Commissioners established the following agenda items for this Joint meeting:
1. Welcome and Opening Remarks — Chair Kelley, Chair Piscitelli, and Chair McKee
2. School Capital Needs Prioritization
Both Chapel Hill - Carrboro City Schools and Orange County Schools have completed
facilities assessments reflecting needs totaling approximately $330 million related to the
repair, renovation, and upgrading of existing older school facilities. The scope of the study
for Chapel Hill - Carrboro City Schools included the district's ten oldest schools, while the
Orange County Schools study included all district buildings.
At tonight's meeting, both school systems will present the prioritization of their School
Capital Needs.
Attachment 2a: CHCCS Older Facility Recommendations and Prioritization
Attachment 2b: OCS Facility Recommendations and Prioritization
2
3. Discussion of Potential Comparative Analysis of School Capital Needs
Discussion regarding an analysis by a third party professional, potentially hired by the
County, who rates and ranks the relative merits of each facility improvement addressed in
the upcoming bond referendum regardless of district based on public safety, health and
safety, structural deficiencies and capacity considerations.
4. Impacts of State Approved Budget
The N. C. General Assembly approved a State budget on September 18, 2015 for the 2015-
2017 fiscal biennium, and the Governor signed the legislation the same day. The following
attachments provide information related to the impacts of the State Approved Budget on
each district.
Attachment 4a: CHCCS — Impacts of State Approved Budget
Attachment 4b: OCS — Impacts of State Approved Budget
5. Discussion of School Related Topics
Discussion regarding School Collaborative Opportunities between districts, Expanding
Innovations -whether districts are considering additional or expanding innovations (e.g.
Magnet Schools, Year -Round Schools), and Programs /Plans to Address Achievement Gap.
FINANCIAL IMPACT: There is no financial impact tied directly to the discussion at this work
session; however, decisions that the Board of County Commissioners and Boards of Education
will make at subsequent meetings are likely to have significant implications for future capital and
operating budgets.
SOCIAL JUSTICE IMPACT: The following Orange County Social Justice Goal is applicable to
this agenda item:
GOAL: ENABLE FULL CIVIC PARTICIPATION
Ensure that Orange County residents are able to engage government through voting and
volunteering by eliminating disparities in participation and barriers to participation.
RECOMMENDATION(S): The Manager recommends that the Boards discuss the issues noted
and provide direction to staff, as appropriate.
HAPEL HILL— 2a
Older Facility Recommendations 3
ORO and the 2015 -25 CIP
CITY SCHOOLS
Key Elements of Older Facility Recommendations
(included in the 2015 -25 CIP Recommendation)
The recommendations are for a comprehensive program that focuses on the district's
ten oldest schools that accommodate almost 50% of district students.
Facility recommendations include:
✓ Correction of building code violations;
✓ Improved safety by consolidating operations and controlling entry;
✓ Indoor air quality deficiencies and health concerns addressed;
✓ Replacement of malfunctioning mechanical equipment;
✓ Relief of traffic congestion problems;
✓ Deconstruction of some inefficient buildings;
✓ Extending the life of the schools.
Implementation of the recommendations eliminate mobile classrooms (also in need of
renovations) while providing additional student capacity.
✓ Elementary school capacity increase = 555.
✓ High school capacity increase = 230 +/-
Increased student capacity would result in deferment of new elementary school and
high school additions well beyond the ten -year CIP window.
✓ Board requesting the redirection of $57.6 million in projected capital expenditures
for new schools towards "Phase 2" older facility recommendations.
✓ Delays significant operational increases with opening a new school.
• Bond funds and future capital funds directed to the ten oldest schools will make
available CIP (Paygo) revenue for needed maintenance at district's other "newer"
schools that are 20 -30 years of age.
X20;. _
� x
rFdvca .r
Chapel Hill- Carrboro City Schools
750 S. Merritt Mill Road — Chapel Hill, NC 27516 — 919 - 976 -8211 — http: / /www.chccs.kl2.nc.us
750 S. Merritt Mill Road— Chapel Hill, NC 27516 1919-967-8211 x28227 I http: / /www.chccs.kl2.nc.us
CHAPEL HILL - CARRBORO CITY SCHOOLS
Facilities Assessment of Oldest Schools
Phasing Plan
School Name Scope of Work Est. Cost and
Funding Source
- Eliminates dead -end corridors in 100 wing by deconstruction and
building new academic wing
Phase 3
CARRBORO
Provide a new administration suite & main entrance
$13.55M
Unfunded
ELEMENTARY
Moves queuing off of the road
Future Capital
Increase capacity by 52 seats
Deconstruct all of Building "A"
Creates a new entry/ admin suite that is accessible and secure
Phase 1
CHAPEL HILL
Addresses oldest building and major mechanical issues
$52.41M
Potential 2016
HIGH SCHOOL
BOND
Connects more of the campus
Referendum
Increases capacity by 105 seats
Phase 3
CULBRETH
Renovate existing building
$5.80M
Unfunded
MIDDLE
Future Capital
Renovate & reorganize the layout of the main building
Phase 2
Relocated the administration suite to the street front & provide a
Request Access
EPHESUS
new main entry
$15.54M
to Planned
ELEMENTARY
- Provide additional program space to eliminate mobiles & bring
New Schools
school up to space standards
Funds
Increase capacity by 137
Provide an administration addition at front to provide necessary
staff space as well as a secure main entry
Phase 2
- Classroom wing deconstruction and addition at rear of the school
Request Access
ESTES HILLS
Enclose breezeways to connect all classrooms with interior
$16.73M
to Planned
ELEMENTARY
corridors
New Schools
- Provide new queuing configuration
Funds
Increase capacity by 58 seats
Renovate admin area and main building lobby
FRANK PORTER
Phase 3
GRAHAM
Add new lobby entry for security and additional admin space
$5.48M
Unfunded
Provide more prominent front door and secure main entrance
ELEMENTARY
Future Capital
Renovate existing buildings
Phase 1
Maintain existing buildings
GLENWOOD
Provide small administrative addition to Provide secure main
$0.82M
Potential 2016
ELEMENTARY
BOND
entrance and necessary staff space
Referendum
- Deconstruct the existing Lincoln Center
Phase 1
- Construct a building to house both Pre -K program & new central
LINCOLN
office
$22.62M
Potential 2016
CENTER
BOND
Increase elementary capacity by 189
Referendum
Increase high school capacity by 50 - 100
Phase 2
Renovate existing building
Request Access
PHILLIPS
Provide additional program space to meet space standards including
$9.40M
to Planned
MIDDLE
increasing the admin suite to provide a secure main entry
New Schools
Funds
- Deconstruct the five classroom pod
Phase 2
Renovate the existing buildings
Request Access
SEAWELL
Provide additional program space to meet space standards &replace
$15.74M
to Planned
ELEMENTARY
deconstructed classrooms
New Schools
Incrase capacity by 119
Funds
Preliminary Construction Phasing & Temp. Facilities Cost: $2.98M
Total Estimated Cost: $161.08M
RECOMMENDATIONS
• Eliminates life safety issues in Building 100 by deconstruction
and building new academic wing
• Provide a new administration suite main entrance
• Moves queuing off of the road
• Connects all existing building internally
• Renovate all existing buildings
• Increase capacity by 52 seats.
MOSELEYARCHITECTS
CARRBORO ELEMENTARY SCHOOL
CURRENT CONDITIONS: 5
• One mobile unit on -site
• 100 classroom wing has dead -end corridors and does not meet
the current NC State Building Code
• Administration area, cafeteria, kitchen and staff support spaces
are too small
• Program deficiencies - art room and 5 smaller classroom spaces
• Existing queueing for parent drop -off occurs on Shelton Street
• Stacking traffic onto the public right of way is a safety concern
• Aging mechanical system
• Campus -style layout lacking connection from main building to
the multipurpose building
• Modular walls between classrooms causing noise transfer
between classrooms
Year Built: 1957
Additions: 1964, 1989
Last Renovation: 2011
Area: 61,562 sf
Acres: 17.7
Student Capacity (per SAPFO): 533 Students
2013 ADM: 468 Students
Construction: Precast concrete frame with brick infill and
built -up roof
HAPEL HILL
A�ORO
,i .,.;t�C;,.11.s
RECOMMENDATIONS
• Deconstruct Building A and construct an addition to house
the current program spaces as well as the deficient program
spaces
• Create a new accessible and secure main entry for students,
staff and visitors.
• Address the oldest building on the high school campus and the
major mechanical issues.
• Connects more of the campus internally
• Renovate all existing buildings
• Eliminate mobiles on site
MOSELEYARCHITECTS
CHAPEL HILL HIGH SCHOOL
CURRENT CONDITIONS: 6
• Deteriorated facility conditions
• Building "A" houses most of the classrooms and science rooms
that are smaller than the School Construction Standards
• Fourteen mobile units on -site housing 9 academic classrooms,
Ridge, 2 Blue Ribbon classrooms, & 2 health classrooms
• Drama, dance, wrestling, & weight rooms are significantly
undersized
• Staff support space is undersized and inefficiently configured
• Campus -style layout lacking connection between the four
buildings
• Major site drainage issues
• Main entrance is not ADA accessible
• Ramp between Main Building "A" and A2 does not meet Code
• Aging mechanical systems causing humidity issues
Year Built: 1965
Additions: 1969, 1973, 1975,1983, 1990, 1994, 1996, 1997, 2003
Last Renovation: 2007
Area: 256,405 sf
Acres: 87.4
Student Capacity (per SAPFO): 1520 Students
2013 ADM: 1,432 Students
Constructio Load - bearing concrete block & steel frame
HAPEL HILL
ARRBOR0
i` ._ir1 0 4-'e Hn;>>.s
RECOMMENDATIONS
Renovate existing building.
MDSE LEYARC H I TECTS
CULBRETH MIDDLE SCHOOL
CURRENT CONDITIONS: 7
• Operating slightly over capacity
• No mobile units
• Six science classroom addition under construction
• Additional staff support space needed
• Location of administration suite presents security concerns
• Modular partition walls between classrooms allow sound
transfer between classes
• Water infiltration issues into the lower level Band room
• Major damage to EIFS on exterior of building
Year Built: 1968
Additions: 1977, 1988, 1989, 1997, 1999, 2001
Last Renovation: 2013
Area: 108,058 sf
Acres: 35.4
Student Capacity (per SAPFO): 674 Students
2013 ADM: 696 Students
Construction: Load- bearing CMU wall construction
INrnrlav mrifnnl nrrhifarfx
HAPEL HILL -
ARRBaRo
RECOMMENDATIONS
• Renovate & reorganize the layout of the main building
• Relocate the administration suite to the street front & provide
a new secure, main entry
• Provide additional program space to eliminate mobiles & bring
school up the space standards
• Increase capacity by 137.
MOSELEYARCHITECTS
EPHESUS ELEMENTARY SCHOOL
CURRENT CONDITIONS: 8
• Seven mobile units on -site housing Pre-K, music, ESL, &
administration/guidance offices
• Administration area & cafeteria /kitchen are too small
• Additional classrooms, science project room, music classroom,
& administration/staff support spaces are needed
• Main entrance through the atrium does not provide a secure
and easily monitored entry point
• interior layout of existing building is inefficient, many
classrooms have no windows
• Aging mechanical system
Year Built: 1971
Additions: 1975. 1989
Last Renovation: 2012
Area: 66,952 sf
Acres: 13.4
Student Capacity (per SAPFO): 448 Students
2013 ADM: 441 Students
Construction: Load - bearing CMU wall construction
HAI'EL HILL
TORO
RECOMMENDATIONS
Provide an administration addition at front to provide necessary
staff space as well as a secure main entry
• Classroom wing deconstruction and addition at rear of the
school including Pre -K classroom
* Enclose breezeways to connect all classrooms with interior
corridors
* Realign the parent drop -off and combine the bus loop with
Phillips Middle School to eliminate stacking on Estes Drive
Connect internally most of the campus
Eliminate mobile classrooms
• increase capacity by 58 seats
ESTES HILLS ELEMENTARY SCHOOL
CURRENT CONDITIONS: 9
• Two mobile units on -site housing Pre -K and a science room
• Most classrooms are 28 to 33% smaller than the current School
Construction Standards program
• Program deficiencies, including 4 smaller classroom spaces,
administration and staff support spaces
• Classrooms in the 1957 building exit to exterior breezeways and
are not secure
• Aging mechanical system
• Queuing forces stacking in the public right of way
Year Built: 1957
Additions: 1985, 1998
Last Renovation: 2011
Area: 58,442
Acres: 33.1
Student Capacity (per SAPFO): 527 Students
2013 ADM: 499 Students
Construction: Load- bearing CMU walls with brick veneer &
built -up roof over a poured- gypsum deck.
Ap�ffll
LWI
I WEL HILL -
CISELEYARCH ITE TS �oR0
ti., r r • 0 _
RECOMMENDATIONS
• Construct addition for expansion of administration and
dining/kitchen.
• Provide more prominent front door and secure main entrance
• Renovate existing buildings.
FRANK PORTER GRAHAM ELEMENTARY
CURRENT CONDITIONS: 10
• Magnet Spanish dual - language school
• Two mobile units on -site
• Kitchen. dining, & staff support areas are too small
• Existing reception area is in a large open lobby that is not secure
• Water infilitration issues in Building 5
• Campus -style layout
• Aging mechanical system
Year Built: 1969
Additions: 1977, 1989
Last Renovation: 2012
Area: 68,513sf
Acres: 9.8
Student Capacity Taper SAPFO): 538 Students
2013 ADM: 491 Students
Construction: Load bearing CMU walls with brick veneer;
built -up roof over a poured- gypsum deck & pre -cast exterior wall
construction
f
HAPEL HILL -
MOSE LEYARC H I TECTS APMaRo
RECOMMENDATIONS
• Maintain existing buildings
• Provide small administrative addition and necessary staff space
• Provide secure main entrance
MOSELEYARCH ITECTS
GLENWOOD ELEMENTARY SCHOOL
CURRENT CONDITIONS: 11
• Operating over capacity
• Oldest school in the district
• Five mobile units on -site housing 1st & 2nd grade classes
• Basement level rooms are substandard and being used for
kindergarten, exceptional education & staff offices
• Administration area, cafeteria, physical education area, media
center, & staff support areas are too small
• Existing administration suite is undersized and spread out
• Lack of staff toilet rooms
• Aging mechanical system
Year Built: 1952
Additions: 1959, 1986
Last Renovation:
Area: 55,372 sf
Acres: 9.6
Student Capacity (per SAPFO): 423 Students
2413 ADM: 513 Students
Construction: Load- bearing brick in the original building and
CMU wall construction in the later additions
or
�
ia
�
HAI'EL HILL
TORO
I 1'rGYM "
R E N
F• '_ � � �' ;�� CSI -- - - _ �'ti
4
PRE -K
PLAYGRO ND '
E' , �-
A N PRE -K CE TE
W/2ND FLOOR
erz n / MiNIST1lMWE OFF�14.
VA
I-V ■` ��I + J*#i.
ati
I it
N'. EW P4 (3 NIX
i
J
ACADEMY &
BRIDGE
ROGRAM
r
All
• � .nom- r
• Deconstruct the existing Lincoln Center building and Phoenix
Academy. Gymnasium & maintenance building to remain
• Construct a building to house both Pre-K program & new central
office
• Construct separate building to house Phoenix Academy &
Bridge Program
• Increase elementary capacity by 189
• Increase high school capacity by 50 to 100
• Work with Community to preserve historic aspects of building
and site
`` . '~ . "ARCHITECTS
LINCOLN CENTER
CURRENT CONDITIONS: 12
• Inefficient layout for departments
• Lack of sufficient space for all central office personnel
• Aging mechanical system creating major humidity issues
• Lack of necessary parking
• Lack of Professional Development space
Year Built: 1950
Additions: 1977 (Maintenance building)
Last Renovation: Phoenix Academy - 2008
Area: Lincoln Center - 33,731 sf
Phoenix Academy - 5,622 sf
Maintenance Building - 22,388 sf
Acres: 12.8
Construction: Load - bearing CMU walls
HAP HLLL-
A�LJoRSo
RECOMMENDATIONS
• Renovate existing building
• Provide additional program space to meet space standards,
including increasing the administrative suite to provide a secure
main entry
• Provide new queuing configuration
MOSELEYARCHITECTS
PHILLIPS MIDDLE SCHOOL
CURRENT CONDITIONS: 13
• No mobile units
• Art education & music spaces and a foreign language classroom
are deficient
• Existing main entrance is not secure
• Major water infiltration issues in the basement
• Aging mechanical system
Year Built: 1962
Additions: 1978, 1990
Last Renovation: 2011
Area: 109,498 sf
Acres: 33.1
Student Capacity (per SAPFO): 706 Students
2013 ADM: 659 Students
Construction: Steel frame construction with brick veneer
exterior walls and load bearing masonry walls at the gymnasium
and concrete retaining walls at the lower level
HAPEL HILL
TORO
RECOMMENDATIONS
• Deconstruct the five classroom pods.
• Renovate the existing administration/dining building & Lowler
Building.
• Eliminate use of mobiles as classrooms
• Provide additional program space to meet space standards &
replace deconstructed classroms (do not increase kitchen).
• Increase capacity by 119.
MOSELEYARCHITECTS
SEAWELL ELEMENTARY SCHOOL
CURRENT CONDITIONS:
14
• Operating over capacity
• Six mobile units on -site housing classroom space
• Administration area, physical education area & staff support
areas are too small
• Media center support spaces are lacking
• Lack of storage rooms
• Aging mechanical system
• Campus -style layout with classrooms exiting to the exterior
• Aging kitchen equipment
• Exterior structural remediation needed at one of the classroom
pods
Year Built: 1969
Additions: 1975, 1989
Last Renovation:
Area: 55,629 sf
Acres: 87,5
Student Capacity (per SAPFO): 466 Students
2413 ADM: 539 Students
Construction: Load bearing brick construction appears to be the
main structural system for the original building and load bearing
CMU and steel frame construction for the 1989 addition
HAPEL HILL
TORO
,i I T, 0 F'r CC ,,,1.s
M
15
OCS Facility Recommendations
1844
• 2013 Facilities Assessment reflected needed repairs /replacements /additions in excess of $160M
as of the date of the assessment.
• OCS receives approximately $2.6M for capital funding annually.
Of the $160M overall needs, OC Board of Education prioritized projects to funding levels of $50,
$60 and $70M, with projects in the following areas given highest priority:
• Safety;
• Replacement of antiquated and failing mechanical equipment that would exceed normal
CIP funding capabilities;
• Cedar Ridge High School classroom wing addition;
• Replacement of Transportation facilities;
• Upgrade and replacement of food service facilities and equipment.
• Phase 1 projects per the attached sheet would be completed assuming a $50M allocation of the
potential 2016 bond.
• Unfunded projects would be addressed if higher allocation from potential 2016 bond were
allocated and /or through future CIPs.
• Based on approved CAP Certificates to date, OCS has adequate elementary and middle school
capacity for the current 10 -year CIP period. The Cedar Ridge classroom addition will address the
needed high school capacity, which is projected to reach SAPFO capacity by 2022. A
planning /constructing /opening period of approximately three years is anticipated.
• Replacement and consolidation of Transportation facilities is included in the OCS Phase 1
request, but is envisioned as a joint project with CHCCS. OCS is the recognized LEA for
Transportation for both OCS and CHCCS (State only recognizes one per County). The 1950's
vintage Transportation facilities for both CHCCS and OCS are woefully inadequate. Some buses
will not fit and still close the bay doors, for example.
• Potential bond funds will allow OCS to divert future pay -as- you -go CIP funds to other critical
projects addressed in the Facilities Assessment, but not included in Phase 1.
Orange County Schools Facilities Assessment Priorities 201 �5 16
*All safety /security funding included in "District -Wide Safety" total
* *Transportation facility estimate assumes TBD funding contribution by CHCCS.
Prioritization for
Location
Scope of Work
Est. Cost
Potential Bond Funding
Phase 1; Assumes $54M
potential bond funds allocation
A.L. STANBACK
-- Replace antiquated /failing mechanical systems;
MIDDLE
-- Address building infrastructure and major
maintenance issues;
-- Upgrade and replace antiquated and
non - compliant food service facilities and
$4.6 M*
Phase 1
equipment;
-- Upgrade Science classrooms to DPI standards; and
-- Implement Safe Haven International (SHI) safety
recommendations *
CAMERON PARK
-- Replace antiquated /failing mechanical systems;
EI.ItMtNTARY
- Upgrade and replace antiquated and non-
$1.21V*
Phase 1
compliant food services facilities and equipment,
-- Address building,infrastructure issues,,
--lmplemerrt SH [safety recommendations*
CEDAR RIDGE
-- Upgrade Science classrooms to DPI standards;
HIGH SCHOOL
- -New classroom wing increases capacity by 500
$14.7 M*
Phase 1
students
-- Implement SHI safety recommendations*
CENTRAL
- Replace antiquated/failingmechrahical systems,
ELEMENTARY'
r- Upgrade and replace antiquated and non -
$1.SM*
Phase 1
compliant food services facilities and equipment,
--Address building,infrastructure issues,
--tmplemerrt SH [safety recommendations*
C.W. STANFORD
-- Upgrade and replace antiquated and non -
MIDDLE
compliant food services facilities and equipment;
-- Upgrade Science classrooms to DPI standards;
$440,000*
Phase 1
-- Implement SHI safety recommendations*
EFLAND-CHEEKS
-- Replace antiquated /failing:mechanical systems;
EI.ItMtNTARY': "
-- Upgrade and replace antiquated and non-
compliant flood services facilities and equipment,
-- Majibr renovation of office area to address safety
$33M *
Phase 1
issues;
-- Address building,infrastructure issues,
-- tmplemerrt Slitsafety, recommendationO
GRADY BROWN
-- Upgrade and replace antiquated and non -
ELEMENTARY
compliant food services facilities and equipment;
$1.4 M*
Phase 1
-- Address building infrastructure issues.
-- Implement SHI safety recommendations*
GRAVELLY HILL
- -tr1plement SH11 safety recommendations*
Phase 1
MOD1E
HILLSBOROUGH
-- Upgrade and replace antiquated and non -
ELEMENTARY
compliant food services facilities and equipment;
-- Replace antiquated /failing mechanical systems;
$3.6 M*
Phase 1
-- Create enclosed building connectors for safer
student movement throughout the campus;
-- Implement SHI safety recommendations*
NEW HOPE
-- Replace antiquated /fail,ing,mechanical systems
EI.ItMtNTARY: "
- -- Upgrade and replace antiquated and parr-
$1.5M*
Phase 1
Compliant food services facilities and equipment;
-- Implement Slit safety recommendations*
*All safety /security funding included in "District -Wide Safety" total
* *Transportation facility estimate assumes TBD funding contribution by CHCCS.
Orange County Schools Facilities Assessment Priorities " " "'m 17
*All safety /security funding included in "District -Wide Safety" total
* *Transportation facility estimate assumes TBD funding contribution by CHCCS.
ORANGE HIGH
-- Upgrade and replace antiquated and non -
SCHOOL
compliant food services facilities and equipment;
-- Replace antiquated /failing mechanical systems;
-- Address major building infrastructure and
$8.2 M*
Phase 1
maintenance issues;
-- Implement SHI safety recommendations*
PARTNERSHIP
-- Implement SHI safety recommendations*
Phase 1
ACADEMY
PATHWAYS
ELEMENTARY
-- Implement SHI safety recommendations*
Phase 1
DISTAIC -WIbE
;-- Implement SHI safety recommendations.
$2.7
Phase 1
SAFETY
TRANSPORTATION
- -Joint project with CHCCS: Replace two 1950's
vintage facilities with co- located, code - complaint
operations and maintenance base. OCS is the LEA of
$9 M **
Phase 1
record with the State of NC for Transportation
services.
Total Phase 1 Projects for Proposed 2016 Bond
$52,140,000 **
Major OCS Projects Unfunded at $50
Allocation Level
Efland- Cheeks
-- Classroom expansion wing to accommodate
$2.7M
Unfunded
Elementary
expected growth from growth in western Orange
- -Pre -K addition
Orange High
;-- Replace Ag,Building,,
$3.7
Unfunded �
Central
- -Media center expansion
$700,000
Unfunded
Elementary
Various schools
- -HVA£ system replacements identified in 2013
$4,544,000
Unfunded
Facilities Assessment and not included irr Phase 1.
Various schools
-- Infrastructure and major maintenance identified
in 2013 Facilities Assessment and not included in
$500,000
Unfunded
Phase 1
Unfunded OC Board of Education 066rity;Projects'
$12,144,000
*All safety /security funding included in "District -Wide Safety" total
* *Transportation facility estimate assumes TBD funding contribution by CHCCS.
4a 18 ORO
1, : %e 1, C I ..I.. Y S C� 1.1 0 0 L._ S
Date: September 23, 2015
To: Bonnie Hammersley, Orange County Manager
From: Todd LoFrese, Assistant Superintendent for Support Services
Re: Fiscal -year 2015 -16 Operating Budget
Last Friday Governor McCrory signed the state budget for the next biennium into law. Now that we
have greater clarity on state funding, we can finalize our local budget and seek formal budget approval
from the Board of Education. We plan on presenting a recommendation to the Board of Education on
October 1, 2015. The recommendation will be based on the priorities determined by the Board of
Education and the district's long range plan reconciled against the action taken at the state level. We
shared these priorities with the Board of Commissioners at our joint meeting last spring and during the
local budget development process. A brief summary of the relevant provisions of the state budget and
their local impact on education funding are described briefly below. Administration will be prepared to
answer questions that Commissioners may have.
• Teacher Assistants: Teacher assistant funding was preserved in the final state budget. The
funding formula has changed slightly which could result in a small decrease in funding for
CHCCS and there is reduced budget flexibility as teacher assistant money can no longer be
transferred. The district funds additional teacher assistants locally so the reduced flexibility does
not impact us.
Salary and Bonuses: The state budget increased beginning teacher pay to $35,000 and provided
funding for teacher step increases. Since there are only 5 steps in the teacher schedule, it is
estimated that approximately 65% of teachers will not receive a salary increase. Some principals
will receive step increases, although most will not. Classified employees and central office
administrators were not provided any salary increase. The state did provide a one -time bonus
for all school employees of $750. We estimate that it will cost just under $1.1 million in local
dollars to provide salary increases and bonuses for locally paid staff. This is about $100,000 less
than we had estimated in our original budget request.
• Driver Education: The state budget provided funding for driver education. We do not anticipate
needing additional local money for driver education this year and do not anticipate charging a fee
to students.
1st Grade Class Size Reduction: The budget included funding for a class size decrease of 1
student per class in grade 1 in fiscal year 2016 -17. This is additional funding for an estimated 5
additional teachers across the district, however it may reduce our available school capacity.
This week legislation (House Bill 539) was reintroduced that may require the sharing of the special
district tax with charter schools outside of our district along with access to other types of funding. If
passed as currently written, this would cost the district in excess of $250,000. We are monitoring this
legislation closely.
w
5
Date: September 23, 2015
To: Bonnie Hammersley, Orange County Manager
From: Todd Wirt, Superintendent
Re: Fiscal -year 2015 -16 Operating Budget
4b 19
On Friday, September 18f, Governor McCrory approved the state budget for the next biennium. We can now
move forward with finalizing our local budget for Board approval. We will present a budget recommendation to
the Board of Education on November 9, 2015 and seek approval on November 23, 2015. A brief summary of the
individual changes to the state budget and the total impact on education funding are described below.
Administration will be prepared to answer questions that Commissioners may have.
Benefit Rates: The state budget increased both state retirement rates and state health plan rates. These
rate increases were not included in the original budget request and will impact the local budget by $36K.
Teacher Assistants: The state budget preserved teacher assistant funding for the 2015 -2016 school year.
We will see a small decrease of $15K in funding for Orange County Schools due to a slight change in the
funding formula. Teacher assistant funding can no longer be transferred. This is not an issue for Orange
County Schools. We do not transfer teacher assistant funding.
Salary Increases: The state budget increased teacher pay for beginning teachers from $33K to $35K. It
also included funding for teacher step increases. There are only 5 tiers in the teacher pay schedule.
Therefore, only those teachers moving from one tier to the next will receive a step increase.
Approximately 59% of our teachers will not receive a pay increase in this fiscal year. We estimate that it
will cost $227K in local dollars to provide salary increases for locally paid employees. This was not
budgeted in our original budget request. No other school employees will receive a salary increase.
• Bonuses: A one -time bonus of $750 will be given to all school employees. We estimate that it will cost
$226K in local dollars to provide bonuses for locally paid employees. This was not budgeted in our
original budget request.
• Ist Grade Class Size Reduction: The FY 2016 -2017 budget will reflect impacts, yet to be determined, for
the state - approved class size reduction of 1 student per class in grade 1.
• Transportation: The state budget reduced by approximately 5% the total budget for the transportation
allotment which supports the salaries of transportation personnel, diesel fuel, replacement parts and the
maintenance of yellow school buses. This negatively impacts the local budget by $154K.
• Driver Education: The state budget provides funding for driver education for two years. We currently
charge a $40 fee to students and do not anticipate a change in this fee.
This week legislation (House Bill 539) was reintroduced that may require the sharing of funds with charter
schools that are not currently shared. If passed as currently written, this would cost the district approximately
$75K. We are monitoring this legislation closely.