RESOLUTION OF ORANGE COUNTY
BOARD OF COMMISSIONERS
CRITERIA FOR DESIGN-BUILD DELIVERY METHOD FOR CONSTRUCTION CONTRACT
The State of North Carolina recently passed Session Law 2013-401 authorizing local governmental
entities in North Carolina to utilize the design-build method for construction contracting pursuant NC
G.S. 143-128.1A. The design-build method is an integrated approach to a construction project that
delivers both design (architectural and engineering) and construction services under one contract with a
single point of responsibility. Under this delivery method, the County is provided the benefit of the
design team and contractor working together to achieve the County's objectives under a single
contract. The statute requires the County to establish written criteria for determining when the design-
build method is appropriate for a project. The statute also requires the County to use the criteria in
evaluating each project contemplated for the design-build method. The statute provides the following
six factors that, at a minimum, the County must address in establishing its criteria:
1. The extent to which the County can adequately and thoroughly define the project requirements
prior to the issuance of the request for qualifications (RFQ) for a design-builder.
The design-build method may be used if it is determined that, for the project, the County has
professional staff that are qualified to thoroughly define project requirements prior to the
issuance of a request for qualifications (RFQ) for a design-builder. Consideration will be given to
the qualifications and experience of County staff and the availability of professional staff in the
areas of purchasing, finance and legal to assist in the development of an RFQ.
2. The time constraints for the delivery of the project.
The design-build delivery method may be used if a project has an established date by which a
facility must be operational to meet the County's needs and a traditional delivery method (i.e. an
RFQ, finalized design and specifications, bidding, and construction) is not likely to provide a
finished project in a timely manner.
3. The County's ability to ensure that a quality project can be delivered.
The design-build delivery method may be used if it is determined that, for the project, the
County has staff experienced in design and construction to help ensure that the design-build
firm will provide a quality project within the budget constraints established by the Board of
Commissioners.
4. The capability of the County to manage and oversee the project, including the availability of
experienced staff or outside consultants who are experienced with the design-build method of
project delivery.
The design-build delivery method may be used if it is determined that, for the project, the
County has qualified staff experienced in construction administration and project management
who will be involved during the design and construction of the project. However, overall project
management is a primary function of the design-build team.
5. A good-faith effort to comply with historically underutilized business participation requirements
(NCGS 143-128.2, NCGS 143-128.4), and to recruit and select small business entities.
The design-build delivery method may be used if it is determined that, for the project,
requirements will be imposed which ensure that contractors will comply with the MNVBE goals
adopted by the Board of Commissioners.
6. The criteria utilized by the County, including a comparison of the advantages and disadvantages
of using the design-build delivery method in lieu of traditional construction and bidding methods.
The criteria utilized by Orange County when considering Design-Build delivery method for each
project are as follows:
1. The project is well defined, including qualitative and quantitative characteristics, and possesses
one or more unique element that would benefit from the design-build delivery method;
2. The project timeline is an important factor in making the facility operational within a short
timeframe so as not to excessively burden County operations;
3. The County has experienced staff and adequate resources to assure that a high quality project
can be delivered within the budget appropriated by the Board of Orange County
Commissioners;
4. There is a maximum budget that must be adhered to in order to allow negotiations and flexibility
to make appropriate decisions on scope as the project progresses;
5. It will be necessary to have partial occupancy of a portion of the facility and/or site while the
project construction is ongoing;
6. The project requires good-faith efforts to comply with historically underutilized business
participation requirements (NCGS 143-128.2, NCGS 143-128.4), and to recruit and select small
business entities;
7. As a result of a more integrated, fluid and flexible delivery process, the design-build delivery
method meets the operational goals established for the facility, the desired level of quality of the
finished product, and is a comparatively more desirable delivery method over traditional
construction and bidding methods.
NOW THEREFORE BE IT ORDAINED by the Board of range Cou Qommissioners that this
solution i ective'upon approval. Upon motion by 601 ecorjded by
foregoing resolution was adopted this the day of
2015.
I, Donna S. Baker, Clerk to the Board of Commissioners for the County of Orange, North
Carolina, DO HEREBY CERTIFY that the for oing -s a tr y of so much of the
proceedings of said Board at a meeting held on , 2015, as relates in any
way to the adoption of the foregoing and that said pro eedings are recorded in Minute Book No.
of the minutes of said Board.