Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
~ S
Section 1.The project authorized provides funds to bring the Chapel Hill-Carrboro City
Schools system into compliance with the Americans with Disabilities Act (ADA)
standards. Proceeds from the Schools' portion of the one-half cent sales taxes
finance this project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
roug
2007-08
FY 2008-09 roug
2008-09
Sales Tax $348,150 $25,000 $373,150
I m act Fees $0 $0 $0
PSBF $0 $0 $0
1992 Bond Funds $0 $0 $0
1997 Bond Funds $0 $0 $0
Alternative Financin $25,000 $0 $25,000
Total Fundin $373,150 $25,000 $398,150
Section 4.The following amount is appropriated for this project:
roug
2007-08
FY 2008-09 roug
2008-09
Plannin Arch/En in $0 $0 $0
~and/Assoc Fees $0 $0 $0
Construction $373,150 $25,000 $398,150
E uipment/Furnishin $0 $0 $0
Other $0 $0 $0
Coritin enc $0 $0 $0
Total Costs $373,150 $25,000 $398,150
Section 5.This ordinance supersedes all previous Americans with Disabilities Act (ADA)
Capital Project Ordinances for the Chapel Hill-Carrboro City Schools system.
Section 6. This ordinance, originally adopted July 1, 1993, shall remain in effect until June 30,
2009.
Adopted this 1st day of May 2008.
Classroom/Academic Area Improvements
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to replace storage cabinets in classrooms
at Carrboro Elementary School, primary building casework and bathroom
renovations at Frank Porter Graham Elementary School, and support area
improvements at Phillips Middle School. Funding for the project comes from
proceeds from District's share of the one-half cent sales taxes and alternative
financing.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
roug
2007-08
FY 2008-09 roug
2008-09
Sales Tax $120,000 $300,000 $420,000
Im act Fees $0 $0 $0
PSBF $0 $0 $0
1992 Bond Funds $0 $0 $0
1997 Bond Funds $0 $0 $0
Alternative Financing $625,000 $0 $625,000
Total Funding $745,000 $300,000 $1,045,000
Section 4.The following amount is appropriated for this project:
Through FY
2007-08
FY 2008-09 Through FY
2008-09
Plannin /Arch/En in $0 $0 $0
Land/Assoc Fees $0 $0 $0
Construction $745,000 $300,000 $1,045,000
Equipment/Furnishin s $0 $0 $0
Other $0 $0 $0
Contin enc $0 $0 $0
Total Costs $745,000 $300,000 $1,045,000
Section 5. This ordinance remains in effect from July 1, 2002 until June 30, 2009.
Adopted this 1st day of May 2008.
Doors, Hardware and Canopies
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for interior and exterior doors, frames, and
hardware replacements at Culbreth Middle School, Estes Hills Elementary
School, Phillips Middle School, and Chapel Hill High School. Proceeds from the
Schools' portion of the one-half cent sales taxes and alternative financing fund
this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2007-08 FY 2008-
09 Through
FY 2008-09
Sales Tax $347;563 $114,154 $461,717
Impact Fees $0 $0 $0
PSBF $0 $0 $0
1992 Bond Funds $0 $0 $0
1997 Bond Funds $0 $0 $0
Alternative Financing $187,437 $0 $187,437
Total Fundin $535,000 $114,154 $649,154
Section 4. The following amount is appropriated for this project:
Through FY
2007-08
FY 2008-09 Through FY
2008-09
Plannin /Arch/En in $0 $0 $0
Land/Assoc Fees $0 $0 $0
Construction ~ $535,000 $114,154 $649,154
Equi ment/Furnishin s $0 $0 $0
Other $0 $0 $0
Contin enc $0 $0 $0
Total Costs $535,000 $114,154 $649,154
Section 5. This ordinance supersedes all CHCCS Doors, Hardware and Canopies Capital
Project Ordinances.
Section 6. This ordinance remains in effect from July 1, 2002 until June 30, 2009.
Adopted this 1st day of May 2008.
Electrical Systems
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for the installation of additional electrical
outlets in the classrooms at Carrboro Elementary School. Funding for the project
comes from a transfer from CHCCS Elementary School #9 and proceeds from
alternative financing.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2007-08 FY 2008-
09 Through FY
2008-09
Sales Tax $0 $250,000 $250,000
Im act Fees $0 $0 $0
PSBF $0 $0 $0
1992 Bond Funds $0 $0 $0
1997 Bond Funds $0 $0 $0
Transfer from Elem #9 $125,000 $0 $125,000
Alternative Financing $20,000 $0 $20,000
Total Funding $145,000 $250,000 $395,000
Section 4. The following amount is appropriated for this project:
Through FY
2007-08
FY 2008-09 Through FY
2008-09
Plannin /Arch/En in $12,000 $0 $12,000
Land/Assoc Fees $0 $0 $0
Construction $133,000 $250,000 $383,000
E uipment/Furnishin s $0 $0 $0
Other $0 $0 $0
Contin enc $0 $0 $0
Total Costs $145,000 $250,000 $395,000
Section 5. This ordinance remains in effect from July 1, 2002 until June 30, 2009.
Adopted this 1st day of May 2008.
Fire/Safety/Security Renovations
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to replace the Fire Safety Systems at
various schools throughout the district. Proceeds from the Schools' portion of
the one-half cent sales taxes and alternative financing fund this project.
Section 2
Section 3.
Section 4.
Section 5.
Section 6.
The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
The following revenue is anticipated to complete this project:
Through FY
2007-08
FY 2008-09 Through FY
2008-09
Sales Tax $1,131,665 $200,000 $1,331,665
Im act Fees $0 $0 $0
PSBF $0 $0 $0
1997 Bond Funds $0 $0 $0
Savings on Construction
Contracts ~
$90,235
$0
$90,235
Alternative Financin $264,659 $0 $264,659
Total Project Funding $1,486,559 $200,000 $1,686,559
The following amount is appropriated for this project:
Through FY
2007-08
FY 2008-09 Through FY
2008-09
Planning/Arch/Engin $60,000 $0 $60,000
~and/Assoc Fees $0 $0 $0
Construction $1,404,759 $200,000 $1,604,759
Equipment/Furnishings $21,800 $0 $21,800
Other $0 $0 $0
Contingency $0 $0 $0
Total $1,486,559 $200,000 $1,686,559
This ordinance supersedes all previous Fire/Safety/Security Capital Project
Ordinances for the Chapel Hill-Carrboro City Schools.
This ordinance, originally adopted June 30, 1997, shall remain in effect until
June 30, 2009.
Indoor Air Quality Improvements
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds for the specialized cleaning of old HVAC
equipment, classrooms, offices, and air ducts. Exterior brick pointing and building
fagade repairs are also included. Proceeds from the Schools' portion of the one-
half cent sales taxes finance this project.
Section 2.The ofFicers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
roug
2007-08
FY 2008-09 roug
2008-09
Sales Tax $124,280 $200,000 $324,280
Im act Fees $0 $0 $0
PSBF $0 $0 $0
1992 Bond Funds $0 $0 $0
1997 Bond Funds $0 $0 $0
Alternative Financin $194,218 $0 $194,218
Total Fundin $318,498 $200,000 $518,498
Section 4.The following amount is appropriated for this project:
Through FY
2007-08
FY 2008-09 Through FY
2008-09
Plannin Arch/En in $35,000 $0 $35,000
Land/Assoc Fees $0 $0 $0
Construction $283,498 $200,000 $483,498
E ui ment/Furnishin s $0 $0 $0
Other $0 $0 $0
Contingency $0 $0 $0
Total Costs $318,498 $200,000 $518,498
Section 5. This ordinance supersedes all CHCCS Fire/Safety/Security Systems Capital Project
Ordinances.
Section 6. This ordinance remains in effect from July 1, 2002 until June 30, 2009.
Adopted this 1st day of May 2008.
Mechanical Systems
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to replace obsolete mechanical equipment
including boilers and electric heating and cooling systems. Proceeds from the
Schools' portion of the one-half cent sales taxes, alternative financing, and
transfers from completed projects within the District finance this project.
Section 2
Section 3
Section 4.
Section 5.
Section 6.
The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
The following revenue is anticipated to complete this project:
Through FY
2007-08
FY 2008-09 Through FY
2008-09
Sales Tax $1,540,490 $710,000 $2,250,490
Im act Fees $0 $0 $0
PSBF $0 $0 $0
Transfers from Completed
Projects
$210,000
$0
$210,000
Alternative Financin $2,030,000 $0 $2,030,000
Total Pro'ect Fundin $3,780,490 $710,000 $4,490,490
The following amount is appropriated for this project:
Through FY
2007-08
FY 2008-09 Through FY
2008-09
Plannin /Arch/En in $112,000 $0 $112,000
Land/Assoc Fees $25,000 $0 $25,000
Construction $2,995,000 $710,000 $3,705,000
E ui ment/Furnishings $648,490 $0 $648,490
Other $0 $0 $0
Contingenc $0 $0 $0
Total $3,780,490 $710,000 $4,490,490
This ordinance supersedes all previous Mechanical Systems Capital Project
Ordinances for the Chapel Hill-Carrboro City Schools.
This ordinance, originally adopted May 21, 1997, shall remain in effect until June
30, 2009.
Adopted this 1St day of May 2008.
Mobile Classrooms
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for the purchase of mobile classrooms.
Proceeds from impact fees, pay-as-you-go funds and alternative financing fund
this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2007-08
FY 2008-09 Through FY
2008-09
Sales Tax $390,000 $110,000 $500,000
Impact Fees $1,170,000 $0 $1,170,000
PSBF $0 $0 $0
1992 Bond Funds $0 $0 $0
1997 Bond Funds $0 $0 $0
Alternative Financing $110,000 $0 $110,000
Total Funding $1,670,000 $110,000 $1,780,000
Section 4. The following amount is appropriated for this project:
Through FY
2007-08
FY 2008-09 Through FY
2008-09
Planning/Arch/Engin $0 $0 $0
Land/Assoc Fees $0 $0 $0
Construction $1,450,000 $110,000 $1,560,000
E ui ment/"Furnishings $0 $0 $0
Other $220,000 $0 $220,000
Contingenc $0 $0 $0
Total Costs $1,67.0,000 $110,000 $1,780,000
Section 5. This ordinance remains in effect from July 1, 2001 until June 30, 2009.
Adopted this 1St day of May 2008.
Paving and Parking Lot Renovations
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section 13.2
of Chapter 159 of the General Statutes of North Carolina, the following capital project is hereby adopted.
Section 1. The project authorized provides funds to repair and pave existing driveways and parking.
Proceeds from Schools' portion of the one-half cent sales tax finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within the budget
contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2007-08 FY 2008-09 Through FY
2008-09
Sales Tax $961,590 $75,000 $1,036,590
Iin act Fees $0 $0 $0
PSBF $0 $0 $0
1997 Bond Funds $0 $0 $0
Alternative Financin $65,000 $0 $65,000
Total Fundin $1,026,590 $75,000 $1,101,590
Section 4. The following amotiuit is appropriated for this project:
Through FY
2007-08 FY 2008-09 Through FY
2008-09
Planning/Arch/Engin $50,000 $0 $50,000
Land/Assoc Fees $0 $0 $0
Construction $976,590 $75,000 $1,051,590
Equipment/Furnishings $0 $0 $0
Other $0 $0 $0
Contingency $0 $0 $0
Total Costs $1,026,590 $75,000 $1,101,590
Section 5. This ordinance supersedes all previous Paving and Parl~ing Lot Renovations Capital Project
Ordinances.
Section 5. This ordinance, originally adopted June 22, 1998, shall remain in effect until June 30, 2009.
Adopted this 1St day of May 2008.
Paving and Parking Lot Renovations
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section 13.2
of Chapter 159 of the General Statutes of North Carolina, the following capital project is hereby adopted.
Section 1. The project authorized provides funds to repair and pave existing driveways and parking.
Proceeds from Schools' portion of the one-half cent sales tax finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within the budget
contained herein.
Section 3. T11e following revenue is anticipated to complete this project:
Through FY
2007-08 FY 2008-09 Through FY
2008-09
Sales Tax $961,590 $75,000 $1,036,590
Im act Fees $0 $0 $0
PSBF $0 $0 $0
1997 Bond Funds $0 $0 $0
Alternative Financin $65,000 $0 $65,000
Total Fundin $1,026,590 $75,000 $1,101,590
Section 4. The following amount is appropriated for this project:
Through FY
2007-08 FY 2008-09 Through FY
2008-09
Planning/Arch/Engin $50,000 $0 $50,000
Land/Assoc Fees $0 $0 $0
Construction $976,590 $75,000 $1,051,590
Equipment/Furnishings $0 $0 $0
Other $0 $0 $0
Contingency $0 $0 $0
Total Costs $1,026,590 $75,000 $1,101,590
Section 5. This ordinance supersedes all previous Paving and Parking Lot Renovations Capital.Project
Ordinances.
Section 5. This ordinance, originally adopted June 22, 1998, shall remain in effect until June 30, 2009.
Adopted this 15Y day of May 2008.
Technology
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds to upgrade instructional technology and other
systems throughout the district. Proceeds from the Schools' portion of the one-half
cent sales taxes and transfers from completed projects within the District finance
this project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY
2007-08
FY 2008-09 Through FY
2008-09
Sales Tax $11,798,816 $1,100,000 $12,898,816
Im act Fees $0 $0 $0
PSBF $0 $0 $0
raps er rom omp e e
Projects
$960,000
$0
$960,000
Transfer from East Chapel
Hill High Addition Savings
$0
$0
$0
Alternative Financing $223,686 $0 $223,686
Total Pro"ect Fundin $12,982,502 $1,100,000 $14,082,502
Section 4.The following amount is appropriated for this project:
roug
2007-08
FY 2008-09 roug
2008-09
Plannin /Arch/En in $0 $0 $0
Land/Assoc Fees $0 $0 $0
Construction $0 $0 $0
E ui ment/Furnishin s $12,982,502 $1,100,000 $14,082,502
Other $0 $0 $0
Contingency $0 $0 $0
Total $12,982,502 $1,100,000 $14,082,502
Section 5. This ordinance supersedes all previous Technology Capital Project Ordinances for
the Chapel Hill-Carrboro City Schools.
Section 6. This ordinance, originally adopted June 29, 1992, shall remain in effect until June
30, 2009.
Adopted this 1St day of May 2008.