HomeMy WebLinkAboutAgenda - 04-14-2015 - 1ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: April 14, 2015
Action Agenda
Item No. 1
SUBJECT: Durham - Orange Light Rail Transit Report
DEPARTMENT: Planning and Inspections PUBLIC HEARING: (Y /N) No
ATTACHMENT(S): INFORMATION CONTACT:
A. GoTriangle PowerPoint Bonnie Hammersley, Orange County Manager, 919 -
Presentation 245 -2300
David King, Triangle Transit General Manager, 919-
485 -7424
PURPOSE: To receive GoTriangle's report on the Durham - Orange Light Rail Transit project.
BACKGROUND: The Durham - Orange Light Rail Transit project (D -O LRT) was approved by
the BOCC in June 2012 as part of the Orange County Bus and Rail Investment Plan ( OCBRIP).
The OCBRIP provides local and regional transit opportunities including expanded bus service
and proposed light rail. Voters in November 2012 approved a one -half cent sales tax to fund the
local portion of the Plan.
Attachment A is a copy of the PowerPoint presentation that GoTriangle (formerly Triangle
Transit) staff is using to provide its report. A fly- through video, designed to help visualize the D-
O LRT project, will also be shown at the meeting. The video can be accessed via the following
link: http: / /ourtransitfuture.com /projects / durham- orange/
GoTriangle's Presentation Covers:
• Recent Project Update
• What We Study for the Environmental Impact Statement (EIS)
• Five Key Decisions in EIS: Reviewing the Data
• Build or No Build
• Little Creek Crossing
x Duke /VA Station Location Choice
x Rail Operations and Maintenance Facility (ROMF) Site
x New Hope Creek Crossing
Project Next Steps:
• March -June 2015 — Local Governments & Public Review Data on Benefits / Impacts of
Alternatives
• April — May 2015 — GoTriangle Develops Recommended National Environmental Policy
Act (NEPA) Preferred Alternative
• September /October 2015 — Official 45 -day comment period: Local Governments and
Citizens provide comments on Key Decisions and any other items related to the D -O LRT
Project
• Fall/Winter 2015 — GoTriangle Develops Final EIS
• February 2016 — Record of Decision issued by Federal Transit Administration (FTA)
FINANCIAL IMPACT: There is no financial impact associated with receiving the report.
RECOMMENDATION(S): The Manager recommends the Board:
1. Receive the report;
2. Ask questions as appropriate; and
3. Be prepared for this item to be placed on a future agenda by Planning staff to document
BOCC comments on the Key Decisions.
Attachment A
in M-
i 4h
rin ta��
Presentation Agenda
- Recent Project Update
• What We Study for the EIS
• Five Key Decisions in EIS: Reviewing the Data
Build or No Build
o Little Creek Crossing
x Duke /VA Station Location Choice
x Rail Operations and Maintenance Facility (ROMF) Site
x New Hope Creek Crossing
- Ask Questions Along the Way
No Action Required At This Meeting
Q
1
2
Elected Official Corridor Tours
0 J
Officials from Durham and Orange County
Tour D -0 LRT corridor in March
5
What We Study
------------------------------- - - - - -- 0 - ----------------------------------
Transit Ridership
Regional Travel Patterns
• Capital & Operating Costs
Noise / Vibration
• Cultural & Historic Resources
Public Parklands
• Natural Resources
Energy Use
• Traffic
Utilities
Air Quality
• Water Quality
• Land Use
• Bicycle & Pedestrian Facilities
• Visual & Aesthetic
• Minority & Low - Income
Population Impacts
• Neighborhoods
• Business & Residential
Impacts
• Population Served
• Employment Served
Construction Impacts
Five Key Decisions
Build or No Build
Little Creek Crossing
Duke /VA Station Location Choice
Rail Operations and Maintenance Facility
(ROMF) Site
New Hope Creek Crossing
3
Select
Alignment over
Little Creek
a
88
DakelVA Medical Centers I Duke/VA Medical Centers
Duke Eye Center alternative. Trent! Flowers Drlve alternative
761
LaSalle Street" ° Buchanan
- Boulevard
Ninth Street Durham Sration
- �Dlllard Sv I
ra
R Durham Alston Avenues •
South Square _. 147
O
4 \ Martln Luther King jr Parkway)
I
Gateway-
Patterson Place
(2 alternatives]
0. Ill
Transit
R
F
Chapel Hill
R
Durham-Orange
'Medaowm tLane -
]Lekgh Village.
UNC Hospiels
Sj
•t
�Woodrn.m
Mason F mra Road
Hamilton Road .Friday Center Drive
(3 alternatives]
p I 2
Miles NORTH
Map Cafe by Esri, URS Cap.
end others. Copyright 2015 Tdenghhensit. Altrighis reserved. Revised Feb.20 &
I
C I A Alternative --/
Meadewmont Lane
k
R
C2A
a Alternative k
Hamilton Road
Friday Center Driver
(; alternatives)
Map Data: Triangle Transit. AECOM, Esri,
Copyright 2015 Triangle Transit, All Rilll E
1
Locally Preferred
Alternative
(LPA)
C I
Alternative /
Woodmant
C2 Alternative
IMap and others.
Legend
LRT stations '
Q Proposed Maiion
QQ Proposed station alto mative
Aerial sections of alignments
0 0.25 05 Miles
I i i I
Little Creek: C1 Eliminated
ANOOF --------- - - - - -- - - --------- - - - - --
US Army Corps of Engineers
provided a letter stating that
C1A, C2, and C2A were viable
alternatives but that C1 was not.
USACOE would not authorize use
of federal government property
(game lands and a waterfowl
impoundment) for C1 "given the
availability of less damaging
alternatives."
7
5
W
Little Creek: Travel Time
Minutes: Seconds 6:59 6 :03 5 :53
• C2 time 56 seconds shorter than C1A
• C2A time 10 seconds shorter than C2
Little Creek: Ridership
Additional Daily -- +720 +730
Boardings
• Lowest ridership alternative: CIA, NHC2, Duke Eye Care Center Station with 23,560
daily riders
• C2 and C2A both add over 700 daily riders compared to CIA
O
Little Creek: Capital Cost
Additional Cost + $36.o m -- +$7.6 m
($2015 millions)
• Lowest capital cost alternative: C2, NHC -LPA, either Duke /VA station at $1.522
billion
• C2A adds $7.6m in capital cost
i
• C1A adds $36.0m in capital cost
R
Little Creek: Operating Cost
---------------------------------------------------------------------------------------
Additional Cost ($) + $82,1oo /year + $56,goo /year + $56,goo /year
• Lowest operating cost alternative: C1 (eliminated),
NHC -LPA, either Duke /VA station at $16,846,000/year
• C2 and C2A add $56,900 /year in
operating /maintenance cost
• C1A adds $82,100 /year in operating /maintenance cost
7
10
Little Creek: Public Parklands-4(f)
Acres Impacted 1.6
2.1
1.0
• Section 4(f) requires consideration of park and recreational lands,
wildlife and waterfowl refuges, and historic sites in transportation
project development.
• Before approving a project that uses Section 4(f) property, FTA
must either:
(1) determine that the impacts to the property are de minimis (will not
adversely affect the activities, features, or attributes of property), or
(2) undertake a Section 4(f) Evaluation.
• C2A has least impact to Section 4(f) properties
Little Creek: Natural Resources
Bottomland (Acres) 1 1 1
Alluvial (Acres) 1 1 --
Mesic Mixed (Acres) 9 8 5
Maintained /Disturbed (Acres) 12 15 19
Total Biotic Resources Impacted 23 25 25
(Acres)
11
Little Creek: Water Resources
Stream Impacts (Linear Feet) 434 587
519
Riparian Zone 1 Impacts (Acres) 0.3 0.4
0.3
Riparian Zone 2 Impacts (Acres) 0.2 0.2
0.3
Wetland Impact (Acres) 0.07 0.07
0.12
Pond Impacts (Acres) 0.02 0.07
0.01
loo -Year Floodplain Impacts (Acres) 0.3 0.6
0.6
• Low Impact Design techniques have kept total acreage
and linear feet impacts low for project of this size
Timeline for Local Gov't Participation
Jan 2015 — Review Five Key Decisions
March -June 2015 — Local Governments & Public Review
Data on Benefits / Impacts of Alternatives
• April —May 2015 — GoTriangle Develops Recommended
NEPA Preferred Alternative
- September /October 2015 —Official 45 -day comment period:
Local Governments and Citizens provide comments on Key
Decisions and any other items related to the D -0 LRT Project
• Fall /Winter 2015 — GoTriangle Develops Final EIS
• February 2016 — Record of Decision issued by FTA
O
Discussion
OurTransit
F U T U R E..
For more information, please
check OurTransitFuture.org
12