HomeMy WebLinkAboutAgenda - 02-19-2008-6aORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: February 19, 2008
Action Agenda
Item No. 74
SUBJECT: Northern Buckhorn Community/Central Efland Sewer Expansion Project
Update and Scheduling Public Hearing for Engineer's Report
DEPARTMENT: County Manager PUBLIC HEARING: (Y/N) No
ATTACHMENT(S):
INFORMATION CONTACT:
County Engineer's Project Update and
Projected Timeline County Engineer, 919-245-2303
Draft advertisement for Public Hearing
Preliminary Engineer's Report
(Notebooks Previously Provided to
BOCC at February 5, 2008 Regular
Meeting)
PURPOSE: To present: 1) an update on the northern Buckhorn community/central Efland
sewer expansion project; 2) the draft or preliminary Engineer's Report for BOCC review; and
3) a proposal to schedule the. EPA-required (for. grant funded projects) public hearing for the
Engineer's Report.
BACKGROUND: The planning process for the construction project for expanding or providing
the northern Buckhorn and central Efland communities access to a wastewater collection
system has been on the planning board since January, 2005. At the outset of the project, it was
intended to include not only the areas referenced above, but the water and wastewater systems
designated to serve the southern Buckhorn community, the Buckhorn EDD and the Gravelly Hill
Middle School as well. The portion of the project serving the southern Buckhorn community,
the Buckhorn EDD and the Gravelly Hill Middle School was split out of the larger project, to
enable the Gravelly Hill school to open in the Fall of 2006. That project has been completed,
but some issues involving the capacity of the City of Mebane's Industrial Drive wastewater
pumping station to serve the northern Buckhorn community remained to be resolved. The City
of Mebane has advised, as of late 2007, that the capacity issues have been resolved by
replacing the existing pumps in the pumping station.
The County is now able to move forward with the northern Buckhorn community/central Efland
portion of the project. The cost figures contained in the Engineer's Report for both elements of
the project indicate that the total cost of this portion of the project are currently estimated to be
approximately $4.27 million or $1.72 million more than the original estimate and the project
budget. That problem is compounded by the County's existing and allocated debt capacity
limits through FY 2009-10. If the Board elects to move forward with the project as currently
2
planned, the Budget Director indicates that the County can essentially borrow money from FY
2010-11 to cover costs incurred in the prior fiscal year.
The process involved for State and Tribal Assistance Grants (STAG) funding of the Buckhorn
utility project requires that a public hearing be held on the Preliminary Engineering Report. The
requirements for that hearing and for reporting the outcome of the hearing are as outlined
below: The public hearing must be held prior to submitting the Engineer's Report (the first step
in the formal state/federal project review/approval process) for review.
Advertisements for Efland and Buckhorn projects are placed in the Chapel Hill Herald and the
Mebane Enterprise. The Herald is a daily paper and the Enterprise is a weekly paper that
comes out on Wednesday's. For the ad to appear in either the Herald or Enterprise, the
advertisement has to be given to the paper the Friday before the Wednesday the add appears.
If the Board approves the advertising for a public hearing on February 1 gth, the advertisement
can appear on February 27th for a hearing no sooner than March 12th. If the BOCC wants the
public hearing to occur during a regular meeting of the Board, it could occur either at the March
18th or the April Vt meetings
Public Participation
1. One public hearing, with a 2-week notification, is required.
• A copy of the Engineering Report should be available for review by the public at
least 2 weeks prior to the public hearing
2. An advertisement for the hearing shall be placed in a newspaper having local area
circulation, and should include the following information:
• Identify the time and location of the public hearing
• Advise when and where a copy of the Engineering Report can be reviewed
• Provide a brief description of the proposed project
• Advise how much funding is required and identify the source of funding
3. The information presented during the public hearing must:
• Identify the problem
• Discuss the selected alternative
• Identify the amount of the anticipated loan or grant
• Discuss any required inter-local agreements
• Identify the effect this project will have on the monthly sewer bill for a typical
residential user of 5000 gallons per month
4. Provide a summary of the hearing
5. Provide an affidavit of publication of the hearing notice
The preliminary Engineering Report is in hand at this time and will be made available for public
viewing as appropriate. Given that there is a requirement for at least fourteen days notice, it is
necessary for the BOCC to approve the public hearing at this time so that staff can advertise
the hearing for the March 18, 2008 or April 1, 2008 regularly scheduled BOCC meetings.
FINANCIAL IMPACT: There is little to no financial impact associated with the public hearing.
The projected fiscal impact of the northern Buckhorn community/central Efland sewer
expansion project is approximately $ 4.27 million, of which approximately $2.55 million is
currently budgeted.
RECOMMENDATION(S): The Manager recommends that the Board:
• Receive and review the County Engineer's update/status report; and
• Receive and review the preliminary Engineer's Report; and
• Approve a public hearing for the northern Buckhorn community/central Efland sewer
expansion project Preliminary Engineering Report at either the March 18, 2008 or April 1,
2008 regularly scheduled BOCC meetings; and
• Approve the draft advertisement for the Public Hearing
MEMORANDUM L'
TO: Laura Blackmon, County Manager
COPIES: - Willie Best, Asst. County Manager
Donna Coffey, Budget Director
FROM: Paul Thames, PE, County Engineer
DATE: February 14, 2008
SUBJECT: Central Efland Bond/northern Buckhorn community sewer expansion
financing challenges
As per our recent conversations and your request for an update to the BOCC with material
for their review, please be advised of the following circumstances: 1) construction plans
and specifications are complete, subject to revision based on BOCC review of the draft
Engineer's Report and cost estimates and subject to revisions required by various review
agencies; 2) all ancillary permits (NCDOT, erosion control, etc.) have been acquired.
Furthermore, as of February 5, 2008, a draft or preliminary Engineer's report containing
the latest construction cost estimate for the above referenced project from the County's
engineering consultant, Coulter Jewell Thames (CJT) was submitted to the BOCC, the
County Attorney and yourself for review. As you can see from this report, the estimate
has dramatically increased (approximately $1.72 Million) above the amount we have
budgeted for this portion of the Efland/Buckhorn projects and from the estimates we
received during the effort to move forward with the Buckhorn EDD/southern Buckhorn
Community/Gravelly Hill Middle school project.
This represents a problem on several fronts. According to the Budget Director, the
County's outstanding and near term allocated debt capacity is maxed out through the
2009/2010 fiscal years. She also indicated that the County could "loan" itself sufficient
funds to complete the project near the end of FY 2010/2011, a strategy made practicable
given the fact that we will not be able to begin the process to actually start construction on
the project until early Spring 2009.
The progress of the project should follow the following outline:
• The County must hold a public hearing that has been advertised for at least two
weeks on the draft Engineer's report.
• The BOCC will have the draft report well ahead of the public hearing and must
determine whether to pursue the entirety of the central Efland and the northern
Buckhorn Community sewer expansion project; adopt a strategy that breaks down
the overall project into several smaller projects funded and constructed over an
extended period of time; or adopt some other strategy to move the project forward.
It is critical to note here that the scope of the project shown in the Engineer's
Report and submitted, reviewed and approved by all of the approval agencies (NC
Construction Loans and Grants Section, the EPA, Corps of Engineer's, etc., must
be constructed in its entirety as shown in the Engineer's Report.
• The Engineer's report is submitted to the NC Construction Loans and Grants
Section, which will review the documents and make a recommendation as to
whether the project requires the preparation and submittal of additional
environmental documents (an Environmental Assessment [EA] or Environmental
Impact Statement [EIS]) or receives a "Categorical Exclusion" meaning that no
additional environmental documents have to be prepared.
• NC Construction Loans and Grants Section, upon completing its review, will submit
the Engineer's report along with its own findings and recommendation to the US
Army Corps of Engineers, the US Fish and Wildlife Agency and the NC Office of
Cultural Resources for their independent review and comment.
• Assuming that these agencies concur with the finding fora Categorical Exclusion,
their findings and comments, along with the Engineer's Report, will be submitted to
the EPA for its review and release of the STAG funds.
• The County will secure the necessary railroad right of way
• Once the Construction Loans and Grants Section makes its findings on the
Engineer's Report and all necessary changes made and questions addressed, the
Consulting Engineer will submit the completed plans and specifications.
• When the plans and specifications have been reviewed/revised, if required, and
approved, the Construction Loans and Grants Section will authorize the County to
advertise the project for bids as soon as EPA approval of the Engineer's Report is
given.
• The project will be advertised for approximately six weeks, then bids will be taken.
• The bids will be evaluated by staff and submitted to the BOCC for its approval.
• The County Attorney and the EPA will review and approve the construction contract
and a Notice to Proceed will be issued.
• The construction project will commence and will take some 18 to 24 months to
complete.
A projected timetable for the events or steps listed above is outlined below. This timetable
is based on usual time for reviews and envisions that: a) the BOCC will approve the
Engineer's Report as submitted; and b) all review agencies will concur in a finding of
Categorical Exclusion. If additional environmental evaluation and associated documents
are required to be undertaken, submitted and approved, additional work is required;
additional review agencies become involved; and the project timeline lengthens by an
unknown but significant amount of time.
6
PROJECT TIME LINE PROJECTION
BOCC approves initiation of process to advertise and hold a public
hearing on the Engineer's Report for the scope of construction for
the northern Buckhorn/central Efland sewer expansion project. 2/19/08
BOCC holds public hearing at its first available regular meeting 3/18/08
BOCC directs that scope of project outline in the Engineer's Report
be modified or submitted as presented 4/1/08
Engineering Consultant submits unmodified Engineer's Report to NC
Construction Loans and Grants Section 4/8/08
Construction Loans and Grants Section completes review of Engineer's
Report and forwards the report and its findings to review agencies 7/8/08
Review agencies complete review of Engineer's Report and forward
their findings back to the Construction Loans and Grant Section 9/8/08
Engineering Consultant submits construction plans and specifications
to Construction Loans and Grants Section ' 9/15/08
Construction Loans and Grants Section forwards reports and findings
to US EPA for review and award of grant funding, completed by 11/11/08
Construction Loans and Grants Section authorizes advertising project for
Bidding 11/18/08
County advertises the project for Bidding 11/25/08
County completes purchase of easements in the railroad right-of-way 12/5/08
Bids are opened 1/6/09
Bids are submitted for BOCC approval 2/17/09
Notice to Proceed issued 3/17/09
Construction complete, system operational
9/17/2009 -3/17/2010
If I may provide any additional information or clarification of this information, please
advise.
NOTICE OF PUBLIC HEARING `
ORANGE COUNTY BOARD OF COMMISSIONERS
A public hearing will be held at the Regular Meeting of the Orange County Board
of Commissioners on Tuesday, March 18, 2008 at 7:30 p.m. in the Southern
Human Services Center, 2501 Homestead Road, Chapel Hill, NC, for the
purpose of giving all interested citizens an opportunity to learn about and speak
for or against the following item:
PRELIMINARY ENGINEERING REPORT FOR SANITARY SEWER
SYSTEM IMPROVEMENTS TO SERVE THE NORTHRN BUCKHORN
ROAD (BETWEEN INTERSTATE 85/40 AND NORFOLK-SOUTHERN
RAILROAD LINE) COMMUNITY AND CENTRAL EFLAND
The proposed project will involve the construction of:
1. sanitary sewer collector line along Buckhorn Road between Interstate
40/85 and the Norfolk-Southern Railway line; and
2. sanitary sewer collector line along Industrial Drive between the General
Electric plant and Buckhorn Road
3. sanitary sewer collector lines extending into the portion of the community
immediately on the east side of Buckhorn Road between Interstate 40/85
and the Norfolk-Southern Railway line; and
4. A wastewater pumping station on Brookhollow Road approximately 200
feet south of the Brookhollow Road crossing of McGowan Creek; and
5. sanitary sewer collector line along US Hwy 70 between the Efland Fire
Station to a point approximately 750 east of the intersection of US 70 and
Forrest Ave.; and
6. sanitary sewer collector line along Efland-Cedar Grove Road between
Forrest Ave. and the McGowan Creek Wastewater Pumping Station
7. sanitary sewer collector line along Brookhollow Road between the new
Brookhollow Wastewater pumping station and a point approximately 300
feet north of the intersection of Brookhollow with US 70; and
8. sanitary sewer collector line along Brookhollow Road between US 70 and
a point approximately 220 feet south of the intersection of Brookhollow
Road with US 70; and
9. sanitary sewer collector line along Oak St. from Forrest Ave. to the north
end of Oak St. and thence to the new Brookhollow Wastewater pumping
station; and
10. sanitary sewer collector line along Forrest Ave. from a point approximately
320 west of the intersection of Forrest Ave. with Efland-Cedar Grove road
to the intersection of Forrest Ave. with US 70; and
11. sanitary sewer collector line along Maple Street from a point
approximately 330 feet south of US 70 to US 70; and
12. sanitary sewer collector line along Gym Rd. from Forrest Ave. to a point
approximately 750 feet east of the intersection of Gym Rd. and Forrest
Ave.
13. sanitary sewer collector line along the eastern extension of Sanders St.
from the eastern-most existing sanitary sewer manhole to a point
approximately 850 east of that manhole; and
14. a sanitary sewer force main from the Brookhollow wastewater pumping
station south up to and along Oak St. to a manhole at the intersection of
Oak St. and US 70.
Copies of the Preliminary Engineering Report are now available for review in the
offices of the Clerk to the Board of County Commissioners and the County
Engineer, both offices in the Orange County Central Government Services
Building at 200 South Cameron Street in Hillsborough, NC.
The estimated cost of this project is approximately $4,200,000 funded in part,
approximately $1,350,000, by an EPA State and Tribal Assistant Grant (STAG)
with the remainder funded by Orange County unless additional loan or grant
funding can be acquired.
The purposes of this public hearing are to hear a brief report that will:
• Identify the situation this project is intended to address; and
• Discuss the selected the project design; and
Identify the amount of the anticipated loan or grant; and
Discuss the required inter-local agreements; and
Identify the effect this project will have on the monthly sewer bill for a
typical residential user of 5000 gallons per month.
Accommodations for individuals with physical disabilities can be provided if the
request is made to the Clerk to the Board of County Commissioners at least 48
hours prior to the Public Hearing by calling the appropriate number listed below.
Questions regarding the Report may be directed to the Orange County Engineer
located in the Orange County Central Government Services Building at 200
South Cameron Street in Hillsborough, NC. Office hours are from 8:00 a.m. to
5:00 p.m. Monday through Friday. You may also call 919-245-2300. You will be
directed to a staff member who will answer your questions.