HomeMy WebLinkAboutAgenda - 10-21-2014 - 7cORANGE COUNTY BOARD OF COMMISSIONERS ACTION AGENDA ITEM ABSTRACT Meeting Date: October 21, 2014 Action Agenda Item No. 7 -c 1 SUBJECT: Central and Rural Orange County Five -Year Bus Service Expansion Program — Orange Public Transportation DEPARTMENT: Planning and Inspections PUBLIC HEARING: (Y /N) No ATTACHMENT(S): 1. Staff - Recommended Bus Service Expansion Program Budget Summary 2. Staff - Recommended Bus Service Expansion Program Notes 3. Staff - Recommended Bus Service Expansion Concepts Map — Rural Deviated Fixed -route Zones 4. Staff - Recommended Bus Service Expansion Concepts Map — Fixed Routes INFORMATION CONTACT: Craig Benedict, Planning Director, 919 - 245 -2592 Bret Martin, Transportation Planner, 919 -245- 2582 Tom Altieri, Comprehensive Planning Supervisor, 919 - 245 -2579 Peter Murphy, Transportation Administrator, 919- 245 -2002 PURPOSE: To consider endorsement of the staff - recommended Orange Public Transportation five -year bus service expansion program in central and rural Orange County. BACKGROUND: The Orange County Bus and Rail Investment Plan ( OCBRIP) was approved by the BOCC in June 2012. The OCBRIP provides local and regional transit opportunities including expanded bus service and proposed light rail. Voters in November 2012 approved a one -half cent sales tax and vehicle registration fee increase to fund the local financial contribution to projects recommended in the Plan, and collection of these revenues began on April 1, 2013. Additional background documents such as the adopted OCBRIP can be found via the following link, listed under Transportation Documents- ht!p-://www.co.oran e.nc.us/planninq/transportation.asp At its September 11, 2014 work session, the BOCC received a presentation on two (2) options each containing a suite of concepts for expanding Orange Public Transportation (OPT) bus operations in central and rural Orange County over the next five years. Following are the general service elements associated with each option. The BOCC indicated a preference for the mix of options noted in the orange- shaded box and bolded /italicized (i.e., Option #2 revised to include the Efland — Hillsborough commuter loop). 2 ROUTE /SERVICE OPTION #1 OPTION #2 NE /NW County Zonal Routes 1 day /week (Tuesday or 2 days /week (Monday and Thursday) Thursday or Tuesday and Friday) Southern County Zonal Routes No 2 days /week (Monday and Thursday or Tuesday and Friday) Later Senior Center Service Yes (same in both options) U.S. 70 Midday Service Mebane - Efland- Hillsborough- Mebane - Efland- Hillsborough (1- Durham 2 -hour headways) hour headways) Efland- Hillsborough Commuter Loop Yes No Route 420 Expansion Yes (same in both options) Hillsborough Circulator Yes (same in both options) To review, the primary differences between Options #1 and #2 are: • Option #2 provides two -day per week service to the rural, low- density northern and southern areas of the county while Option #1 provides one -day per week service to only the rural northern areas; • Option #2 involves one -hour directional headways for the U.S. 70 midday service and provides a fixed -route connection among Mebane, Hillsborough and Efland, whereas Option #1 involves two -hour directional headways and an extended connection to Durham; and • Option #2 does not provide the Efland- Hillsborough commuter loop service, whereas Option #1 does. At the September 11, 2014 work session, the BOCC indicated a general preference for the service concepts provided in Option #2, but with an interest to also fund the proposed Efland- Hillsborough Commuter Loop concept as provided in Option #1. Federal and /or State Funding Assumptions Subsequent to the September 11, 2014 work session, Orange County planning staff and the County Manager met to discuss and assemble a staff recommendation based on BOCC input in response to the presented options (Attachments 1, 2, 3 and 4). It was determined that the staff - recommended bus service expansion program include reasonable assumptions of the amount of federal and /or state funding for operating assistance that could be leveraged to support the service concepts presented, as well as a reasonable assumption of fare revenue that could be collected (Attachment 1). Descriptions of each staff - recommended service concept are provided in Attachment 2. The budget for the staff - recommended service concepts includes only those revenues from federal and /or state sources that have been identified as being accessible to Orange County through existing or pending funding distribution policies. Beyond that represented in the budget, there may be additional capacity for federal and /or state revenue for operating assistance to be leveraged to potentially support the prioritized list of unfunded concepts provided on page 2 of Attachment 1. ' As a result of this change, the staff - recommended program includes: • Two - day - per -week service to the northeastern, northwestern and southern rural zones of the county; • One -hour directional headways for the U.S. 70 midday service with a fixed -route connection among Mebane, Hillsborough and Efland but no extension to Durham; and • The Efland- Hillsborough Commuter Loop. These service concepts are spatially depicted in Attachments 3 and 4. Next Steps for BOCC If the BOCC chooses to endorse the staff recommendation for OPT's expansion concepts, Orange County planning staff will implement accordingly and will include the concepts in OPT's Community Transportation Service Plan (CTSP). Public outreach, education, and marketing of these new routes will be ongoing over the next several months prior to and during the initiation of service. Results of prior public outreach conducted by both Orange County and Triangle Transit staff are accessible using the following link: http: / /www.co.orange. nc. us /occlerks /140617. pdf FINANCIAL IMPACT: Although this item does not have an immediate financial impact, the associated activity relates to the process to expend half -cent transit sales tax revenue and the $7 county vehicle registration fees as conceptually identified in the OCBRIP. As conceptually identified in the OCBRIP, the expansion of the proposed OPT services are to be financially supported by these revenue sources. In addition to OCBRIP- assumed grant revenues, ongoing grant revenues from federal sources are being pursued and will expectantly be secured by the County in its annual requests. In order to take advantage of these grant revenues, the County will be positioning itself administratively to take advantage of Section 5307 funding for use within the Durham and Burlington Urbanized Areas. Annually these revenue sources and costs will be evaluated in the division budget. The FY 2014 -15 budget estimated these general concepts accordingly. RECOMMENDATION(S): The Manager recommends the Board endorse the staff - recommended bus service expansion program (Attachments 1, 2, 3 and 4). NOTE: This five (5) -year program will be updated each year. ATTACHMENT 1: Staff - Recommended Bus Service Expansion Program Budget Summary* Route /Service Concept Map ID* Start Date""" Estimated Weekday Service Hours Estimated Annual Weekdays Estimated Annual Service Hours Estimated Total Annual Operating Cost Projected Federal Funding Share + Farebox Revenue" Projected Local Share Cost No service implementation programmed for FY 2014 N/A N/A N/A N/A N/A N/A N/A N/A Al M iii . I - J - - - NE Zonal Route 2 days/week) 1A 1/1/2015 5 52 260 $12,165 N/A N/A NW Zonal Route (2 days /week) 1 B 1/1/2015 5 52 260 $12,165 Southern Zonal Route 2 days/week) 1 C 1/1/2015 5 52 260 $12,165 Later Senior Center Service 2 1/1/2015 3 125 375 $17,545 U.S. 70 Midday Route 3 1/1/2015 5 125 625 $29,242 Efland - Hillsborough Commuter Loop 4 1/1/2015 5 125 625 $29,242 Route 420 expansion 5 1/1/2015 9 125 11125 $52,635 FY 2016 Antici ated Operating Expenditures -- -- 3,630 $166,169 $8,406 $166,764 NE Zonal Route 2 days/week) 1A 1/1/2015 5 104 520 $25,083 N/A N/A NW Zonal Route 2 days/week) 1 B 1/1/2015 5 104 520 $25,083 Southern Zonal Route 2 days/week) 1 C 1/1/2015 5 104 520 $25,083 Later Senior Center Service 2 1/1/2015 3 250 750 $36,178 US 70 Midday Route 3 1/1/2015 5 250 1,250 $60,296 Efland - Hillsborough Commuter Loop 4 1/1/2015 5 250 1,250 $60,296 Route 420 expansion 5 1/1/2015 9 1 250 2,250 $108,534 Hillsborough Circulator add 1 hour/day) 6 7/1/2015 9 1 250 2,250 $108,534 FY 2016 Anticipated Operating Expenditures -- -- -- -- 9,310 $449,087 $81,997 $367,090 I NE Zonal Route 2 days/week) 1A 1/1/2015 5 104 520 $25,861 N/A N/A NW Zonal Route 2 days/week) 1 B 1/1/2015 5 104 520 $25,861 Southern Zonal Route 2 days/week) 1 C 1/1/2015 5 104 520 $25,861 Later Senior Center Service 2 1/1/2015 3 250 750 $37,299 US 70 Midday Route 3 1/1/2015 5 250 1,250 $62,166 Efland - Hillsborough Commuter Loop 4 1 1/1/2015 1 5 250 1 1,250 $62,166 Route 420 expansion 5 1/1/2015 1 9 250 2,250 $111,898 Hillsborough Circulator (add 1 hour /day) 6 7/1/2015 9 250 2,250 $111,898 FY 2017 Anticipated Operating Expenditures -- 9,310 $463,010 $139,171 1 $323,839 NE Zonal Route 2 days/week) 1A 1/1/2015 or- 5 104 520 iii Made Available $26,663 $196,600 Made Available N/A N/A NW Zonal Route (2 days /week) 1 B 1/1/2015 5 104 520 $26,663 Southern Zonal Route 2 days/week) 1 C 1/1/2015 5 104 520 $26,663 Later Senior Center Service 2 1/1/2015 3 250 750 $38,456 US 70 Midday Route 3 1/1/2015 5 250 1,250 $64,093 Efland - Hillsborough Commuter Loop 4 1/1/2015 5 250 1,250 $64,093 Route 420 expansion 1 5 1 1/1/2015 9 1 250 2,250 $115,367 Hillsborough Circulator add 1 hour/day) 6 1 7/1/2015 9 1 250 2,250 $115,367 FY 2018 Anticipated Operatinq Expenditures All previously implemented services carried forward 9,310 9,310 $477,366 iii Made Available $492,163 $196,600 $198,636 Made Available 1 $198,636 $280,766 $293,627 ATTACHMENT 1: Staff - Recommended Bus Service Expansion Program Budget Summary* 5 Staff - Recommended Bus Service Expansion Program Budget Summary Notes: *See attached maps depicting locations of service concepts (Attachments 3 and 4) and attached notes for explanation of service concepts (Attachment 2). * *Budget assumes reasonable leveraging of identified federal grants for operations and assumes operational cost of $45.38 /hour in FY 2014 dollars with cost escalation of 3.1% per year. Budget also assumes a conservative rate of fare collection based on historical performance metrics. The implementation and continuation of this program is contingent upon OPT's accessibility to federal funding. ** *Exact schedule of route concept implementation depends on availability of eligible bus capital and staffing. Staff - Recommended Unfunded Service Concepts In Priority Order Estimated Additional Estimated Additional Estimated Estimated Total Annual Route /Service Weekday/Weekend Annual Annual Service Operating Cost Service Weekdays/Weekend Hours in FY 2015 Hours Days Dollars Expand U.S. 70 midday service to Durham and continue hourly 5 250 1,250 $58,484 headways Expand Hillsborough Circulator to run in the reverse direction Up to 9 250 Up to 2,250 Up to $105,270 Hillsborough Circulator Saturday Service 6 52 312 $14,598 Expansion of Route 420 Peak Service to Cedar Grove 4 250 1,000 $46,787 Saturday Cross - County Service (same as U.S. 70 midday service) 5 52 260 $12,165 ATTACHMENT 2: Staff - Recommended Bus Service Expansion Program Notes 1) A) Northeastern, B) Northwestern and C) Southern County Zonal Routes — Routes would tentatively come online early 2015, would be two (2) days per week on a Monday and Thursday or Tuesday and Friday schedule for each respective zone running up to five (5) hours per day with one (1)- to two (2) -hour headways during off -peak periods, and would run a deviated fixed -route schedule. The results of additional public outreach conducted in August 2014 indicated a demand among rural residents for a more certain fixed -route schedule as opposed to a demand - response method. Fixed -route stops have not yet been developed for this concept. The routes would connect rural residents in northern and southern Orange County to destinations and additional transit connections in Mebane, Hillsborough, Chapel Hill and Durham. The service would involve a nominal fare for general public riders (with the possibility of vouchers issued to low- income riders who qualify for other services with the Department of Social Services). The zones within which deviated fixed -route concepts would be developed are depicted in Attachment 3. 2) Later Senior Center Service — Route would tentatively come online in early 2015, would be a daily weekday service running approximately three (3) hours per day (two, 1.5 -hour run time structured routes), and would run a deviated fixed -route or point- deviated demand response schedule. The route would provide later service from Orange County senior centers (with an emphasis on the Central Orange Senior Center) beyond times the service is currently provided. The service would be fare -free. Orange County Planning and Inspections and Department on Aging staff have secured grant funding to cover this service for FY 2016 from another source and will continue to pursue the same grant funding for this service in subsequent years. This route is depicted in Attachment 4. 3) US 70 Midday Service — Route would tentatively come online in early 2015, would be a daily weekday fixed - route service running approximately five (5) hours per day during off -peak periods with one (1) -hour headways per direction and a total 30- minute directional run time. The route would connect Mebane /Buckhorn and Efland with destinations and additional transit connections in Hillsborough. This concept would not connect to Duke/VA Hospital in Durham. The service would involve a nominal fare if OPT is able to position itself to accept fare cards used by Triangle Transit customers with the possibility of vouchers issued to low- income riders who qualify for other services with the Department of Social Services. This service is being designed to correspond with and complement Triangle Transit's proposed peak period Orange- Durham Express (ODX) service. This route is depicted in Attachment 4. 4) Efland - Hillsborough Commuter Loop — When Phase II of Triangle Transit's Orange- Durham Express commences in early 2015, OPT will run an Efland- Hillsborough commuter loop to provide peak - period and peak- direction service from Efland to link into the Triangle Transit Orange- Durham Express service in Hillsborough. After providing the short Efland to Hillsborough run, the route would then be run to provide an employment commuting- oriented, pre - Hillsborough Circulator service to connect transit - dependent residential origins in northern Hillsborough to service sector employment destinations in southern Hillsborough before heading back to Efland to provide the next Efland to Hillsborough commuter link service run. The service would involve a nominal fare if OPT is able to position itself to accept fare cards used by Triangle Transit customers with the possibility of vouchers issued to low- income riders who qualify for other services with the Department of Social Services. This route is depicted in Attachment 4. 5) Route 420 Expansion — Route would tentatively come online in early 2015, would be a daily weekday service running up to an additional nine (9) hours per day with one (1) -hour headways, and would run a fixed -route schedule. This is in addition to the existing three (3) service hours per day currently run by the midday Route 420; the full service schedule would involve a total of twelve (12) midday service hours (six [6] hours each northbound and southbound). This assumes a one (1) -hour run time each way. The existing Route 420 would be expanded to connect Cedar Grove with destinations and additional transit connections in Hillsborough and would continue on to destinations and additional transit connections in Chapel Hill. The service would involve a nominal fare if OPT is able to position itself to accept fare cards used by Triangle Transit customers with the possibility of vouchers issued to low- income riders who qualify for other services with the Department of Social Services. This route is depicted in Attachment 4. 6) Hillsborough Circulator with Additional Noon Hour Service — Route would begin using OPT OCBRIP funding July 2015 and would continue the existing Hillsborough Circulator service with an additional hour added for 12pm -1 pm. This service would continue to be fare free. This route is depicted in Attachment 4. ATTACHMENT 3 Staff - Recommended Bus Service Expansion Concepts: 7 Rural Deviated Fixed -Route Zones Caswell Person i i 49 157 86 I d I V C 57 a i i Durham i 70 m m 70A -�-� 70 I 751 86 { j I Northeastern County 1A Deviated Fixed -Route Zone I Northwestern County j 1B Deviated Fixed -Route Zone Southern County 15 r1C Deviated Fixed -Route 501 Zone 54 Chapel Hill Transit 5 °D Service Area 54 Zones are service areas within which a deviated fixed route will be structured 15 I when concept is endorsed. � - - -- - - - -- _ —___— 501 I N 1 in =2.9 miles � - ------ -- --'--- ---- -- ---- ,^. Miles Chatham Orange County Planning and Inspections -.l Brian Carson (10/14/2014) ATTACHMENT 4 Staff - Recommended Bus Service Expansion Concepts: Fixed - Routes Caswell m v c ca E ca F II----- Chatham 15 Person Durham Routes N 1 in = 2.9 miles Later Senior Center 0 1 Service NO US 70 Midday Service mellm Efland- Hillsborough Carson (10/14/2014) Commuter Loop mO Route 420 Expansion Hillsborough Circulator With Additional Noon Hour Service N 1 in = 2.9 miles 0 1 Miles Orange County Planning and Inspections Brian Carson (10/14/2014)