HomeMy WebLinkAboutS Change Order 1 for Magnolia Place Housing Development Program 1W
CHANGE ORDER No. 1
Dated:November 9, 1994
OWNER's Project No. ENGINEER's Project No. Magnolia
Project: Magnolia Place Subdivision
CONTRACTOR:Ralph Hodge Construction Company
Contract For: Site Improvements Contract Date: May 9, 1994
To: William P.Bartlett,Vice President,Ralph Hodge Construction
contractor
You are directed to make the changes noted below in the subject Contract:
Owner: Oran a County
By:
Dated:
Nature of the Changes:
Contractor to provide and install pump station and force main in accordance with plan sheets C-10 and
C-11 of the Magnolia Place Subdivision plans dated September 27, 1994.
t
These changes result in the following adjustment of Contract Price and Completion Date:
Contract Price Prior to This Change Order $415,883.00
Net(Increase)(neerease)Resulting from this Change Order $ 51,000.00
Current Contract Price Including This Change Order $466,883.00
Completion Date(Subdivision) December 15, 1994*
Completion Date(Pump Station Only) March 5, 1995
(150 days from October 6, 1994 acceptance)
u 'n. Should the project not be I f'
completed by December 15 and it cannot be verified by the Owner and/or the Owner's Representative that the W
delay was due to adverse weather,then a late penalty will be applied in accordance with the original contract.
The Above Changes Are Approved
Engineer: Associptes
By: KLA
Dated:
The Above Changes Are Accepted
Contractor: Ralph Hodge Construction Company
By: •(l
f Date: