HomeMy WebLinkAboutORD-2014-029 Bid Award - Morinaga Area Water and Sewer Infrastructure and Approval of Budget Amendment #9dORD- 2014 -029
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: June 17, 2014
Action Agenda
Item No. 6 -n
SUBJECT: Bid Award — Morinaga Area Water and Sewer Infrastructure and Approval of
Budget Amendment #9 -D
DEPARTMENT: Planning, Finance & PUBLIC HEARING: (Y /N) No
Administrative Services, Asset
Management Services (AMS)
ATTACHMENT(S):
INFORMATION CONTACT:
1) Certified Bid Tabulation
Craig Benedict, Planning, (919) 245-
2) Award Recommendation Letter from
2592
McGill Associates
Clarence Grier, Manager's Office/
3) Map of Project Area
Finance & Administrative Services,
(919) 245 -2453
John Roberts, Attorney, (919) 245 -2318
Kevin Lindley, Planning, (919) 245 -2583
Jeff Thompson, AMS, (919) 245 -2658
David Cannell, Finance & Administrative
Services, (919) 245 -2651
PURPOSE: To consider:
• Approval of Budget Amendment #9 -D for the acceptance of the Community
Development Block Grant (CDBG) of $750,000, and the use of the required match of
$250,000 and a $75,000 construction contingency from Article 46 Sales Tax proceeds;
• Awarding the bid and approving a construction contract to J.F. Wilkerson Contracting
Co., Inc. of Morrisville, NC, in the amount of $747,840 for the construction of the
Morinaga Area Water and Sewer Infrastructure;
• Authorize the Manager to sign the contract and other documents necessary to begin
project on behalf of the Board of County Commissioners, subject to final review by the
County Attorney; and
• Authorize the Manager to execute individual change orders within the limit of Manager's
authority ($250,000) up to the extent of the project budget.
BACKGROUND: The area to be served is covered by a water and sewer service agreement
with the City of Mebane (2004 and as amended in 2012). The project consists of approximately
2,100 linear feet of 12" gravity sewer line and approximately 5,500 linear feet of 12" and 16"
water line. The sewer portion of the project will connect the Morinaga site to the 18" sewer line
recently constructed as part of the Buckhorn Mebane Phase 2 Utilities project, which was
funded by money set aside in Article 46 sales tax account for economic development
infrastructure. The City of Mebane's water infrastructure is being extended from the subdivision
to the west of the Morinaga Candy Company site. In addition to providing water to the Morinaga
site, the water line will also be looped
make future extensions more feasible.
incentive package provided by Orange
extension project is being funded by a
25% local match being paid from the
infrastructure.
2
along Ben Wilson Road to better serve the area and
The extension of utilities to the site is part of an overall
County, the City of Mebane and the State. This utility
Community Development Block Grant (CDBG) with a
Article 46 sales tax fund for economic development
Bid Information
The design, permitting, and bidding phases have been completed using Article 46 Sales Tax
funds approved by the Board of County Commissioners at its October 15, 2013 meeting. The
project was advertised for competitive bid in late April and bids were opened on May 29, 2014.
Four bids were received, and after a period of review by County staff and the County's
engineering consultant, McGill Associates, J.F. Wilkerson Contracting Co., Inc. was determined
to have the lowest responsible, responsive bid with a total bid of $747,840 (see Attachments 1
and 2). The bid is higher than anticipated by the County's engineering consultant. Though it
does fall within the established budget for this project, it leaves no contingency available for the
project. Because of this, staff recommends adding a 10% construction contingency ($75,000)
to cover any necessary construction materials testing or any changes necessitated by field
conditions.
The following timeline represents the project delivery and completion:
TASK
PROPOSED
END BY
FY 2013 -14
Revised
BEGINNING
DATE
$750,000
DATE
Article 46 Sales Tax Proceeds
BOCC Action: Approve bid award to J.F. Wilkerson
6/17/14
6/17/14
Contracting Co., Inc.
$0
1 $1,075,000
Construction Period est. 180 days)
8/1/14
1/30/15
System Commissioning and Certification, Completion of As -Built
2/2/15
2/20/15
-Drawings
FINANCIAL IMPACT: An amount of $1,000,000 is available for this project as part of the
FY2013 -14 Capital Improvement Project budget. This project is being funded by a CDBG
economic development infrastructure grant of $750,000, with a 25% County match totaling
$250,000 from Article 46 sales tax revenue that is being used to fund design, permitting, bid
services and construction oversight. In addition, staff recommends adding a 10% construction
contingency of $75,000 from Article 46 sales tax revenue. This Budget Amendment #9 -D
provides for the receipt of the CDBG grants funds of $750,000 and the use of $325,000 from
Article 46 sales tax revenue, and establishes the following Economic Development
Infrastructure Capital Project Ordinance:
Economic Development Infrastructure: Project # 30047
Revenues for this project:
Current
FY 2013 -14
FY 2013 -14
Amendment
FY 2013 -14
Revised
CDBG Funds
$0
$750,000
$750,000
Article 46 Sales Tax Proceeds
$0
$325,000
$325,000
Total Project Funding
$0
1 $1,075,000
1 $1,075,000
3
Appropriated for this protect:
RECOMMENDATION(S): The Manager recommends that the Board:
1.) Approve Budget Amendment #9 -D;
2.) Award the bid and approve a construction contract to J.F. Wilkerson Contracting Co., Inc.
of Morrisville, NC, in the amount of $747,840 for the construction of the Morinaga Area
Water and Sewer Infrastructure;
3.) Authorize the Manager to sign the contract and other documents necessary to begin
project on behalf of the Board of County Commissioners, subject to final review by the
County Attorney; and
4.) Authorize the Manager to execute individual change orders within the limit of Manager's
authority ($250,000) up to the extent of the project budget.
Current FY
2013 -14
FY 2013 -14
Amendment
FY 2013 -14
Revised
Professional Services
$0
$250,000
$250,000
Construction
$0
$747,840
$747,840
Contingency, Easements, Legal
$0
$77,160
$77,160
Total Costs
$0
$1,075,000
$1,075,000
RECOMMENDATION(S): The Manager recommends that the Board:
1.) Approve Budget Amendment #9 -D;
2.) Award the bid and approve a construction contract to J.F. Wilkerson Contracting Co., Inc.
of Morrisville, NC, in the amount of $747,840 for the construction of the Morinaga Area
Water and Sewer Infrastructure;
3.) Authorize the Manager to sign the contract and other documents necessary to begin
project on behalf of the Board of County Commissioners, subject to final review by the
County Attorney; and
4.) Authorize the Manager to execute individual change orders within the limit of Manager's
authority ($250,000) up to the extent of the project budget.
Attachment 1 4
CERTIFIED BID TABULATION with UNIT PRICES
Morinaga Facility infrastructure Improvements
Orange County,North Carolina
BIDDERS
J.F.Wilkerson Contracting Co.,Inc. Moffat Pipa,lna Ralph Hodge Const Co.,lnc. Haren Const Co.,Inc.
No Descri tion Q Unit Price Extension Price Extension Price Extension Price Extension
1 MobY¢ation 1 LS $12,500.00 $12,500_00 $25,000.00 $25,000.00 322,310.00 $?2,310.00 $20,000.00 $20,000.00
, 2 12'SDR 35 PVC Gravi Sewers,fUl Depths 2015 LF 544.00 $88,660.00 543.00 $86,645.D0 $43.00 $86,645.00 $80.00 $161,200.00
3 20"x 0.25'Wall Thidaiass Steel Encasemant Pipe,Bore&Jacked 150 LF �750.00 $?2,500.00 $210.00 $31,500.00 $350.00 $52,500.00 $325.00 $48,750.00
, 4 24"x 0.25'Wall Thidmess Stael Encasement Pipe,Bore&Jacked 115 LF $770.00 $19,550.00 $215.00 $24,725.00 $587,00 $67,505.00 $350.00 $40,250.00
5 Gravel Drive Repa'v 100 LF $14.00 $1,400.00 573.00 $1,300.00 $13.00 $1,300.00 $16.50 $1,650.00
6 Concrete Drive Repair 15 lF $120.00 51,800.00 $150.00 $2,250.00 $88.00 $1,320.00 $95.00 $1,425.00
7 AsphaR Drive Repair 50 LF $80.06 54,000.00 $78.00 $3,900.00 $71.OD $3,650.00 563.00 $3,150.00
8 4'Diameter Standard Manhole,All Depths 8 EA $4,300.00 534,400.00 $3,700.00 $29,600.D0 $3,500.00 $28,000.00 $2,550.00 $20,400.00
9 Connection to E�dsting Manhole 1 EA $2,000.00 52,000.00 $2,400.00 $2,400.00 54,000.00 $4,000.00 $7,500.00 $7,500.00
10 12°Class 350 DI Watet Une t720 LF $42.00 $72,240.00 $51.50 $88,580.00 $45.80 $78,776.00 $60.00 $103,200.00
11 12"Class 350 Restrained Joint DI Water Line 80 LF $60.00 54,800.00 $61.00 $4,880.00 558.00 $4,640.00 $75.00 $6,000.00
12 i8'Class 350 DI Water llna 3730 LF $58.00 $216,340.00 564.00 $238,720.00 $66.00 $246,180.OD $72.00 $266,b60.00 D '
t3 i6"Class350Restrained.bintDlWaterLine 100 LF $85.00 38,500.00 591.00 $9,�00.00 $88.00 $8,800.00 g85.00 $8,500.OD ,�
t4 FireHydrantAssembrywithValveandTea 10 EA 53,900.00 $39,000_00 �5,550.00 $55,500.00 $S,OOO.DO 560,000.00 $4,500.OD 545,000.00 � 'i
15 12"Gate VaNe&Box 8 FJ1 52,500.00 $20,000.00 $2,750.00 $22,000.00 .$2,160.00 $17,280.00 $2,250.00 $18,000.00 3
16 t6'Caate Vahre&Box 5 EA $7,200.00 $36,000.00 $6,650.00 $43,250.00 $6,130.00 $30,650.00 $4,700.00 $23,500.00
77 TemporaryCo�structlonEntrance 2 EA 52,000.00 $4,000.00 $1,100.00 $2,200.00 $9,260.00 $2,520.00 $1,200.00 $2,400.00 � I!i
18 Washed Stone Undercut 6'Depth as Directed by Engineer 500 LF $1.00 5500.00 53.50 $1,750.00 $9.00 54,500.00 $3,25 51,625.00 �
19 TemporaryDitchLiner 1500 LF $2.00 $3,000.00 $2.60 $3,750.00 $1.85 $2,775.00 $3.85 55,775.00 �
�
20 Straw Roil Wattle Chack Dam 25 EA 5230.00 $5,750.00 $72.00 51,800.00 560.00 59,500.00 $80.00 52,000.00
27 Silt Fence Installad Per Details 2500 LF $2.20 55,500.00 3200 55,000.00 $220.00 $550,000.00 $2.40 $6,000.�
22 RodcEUCavaBon 1000 CY 5100.00 $100,000.00 $1D0.00 $100,000.00 $�00.00 $100,000.00 $100.00 $100,000.00 '
23 Compact Ductile Iron FitG'ngs and Thrust Blocks 3500 LBS $7.00 $24,600.00 $7.50 526,250.00 $6.75 523,625.00 $5.25 a18,375.00
24 Connectlon to Existing Water Line 4 EA $3,500.00 $14,0OO.OD $2,800.00 511,600.00 $4,600.00 $16,400.00 $3,000.00 S72,OOp.00
25 3inch CombinaUon Afr Vatve 1 EA $3,7�.00 53,700.00 $8,500.00 58,500.00 53,600.00 $3,600.00 $4,OOOAO $4,000.00
26 2-inch Blow Off Assembly 1 EA $3,200.00 S;i,200.00 54,000.00 54,000.00 51,780.00 $1,780.00 $Z,000.00 $2,000.00 ,
TOTAL LN1T PRICE AMOUNT: $747,840.00 $834,200.00 $7,412,256_00 $931,260.00 I
This is to certiy tNat the bids tabulated derein ware aecompanied by a 5%bid bond or certified check and publicly opened and read atoud at 200 pm local Gme on the 29th day of May,2014,in the Orange Coanry West Campus Office �
Buikling Lowar Levei-Room 004-131 West AAargaret Lane,Halsborough,NoRh Carolina 27278. ��,�����4r�
DOUGLAS G.CHAPMAN,PE Mathematical errors do not affect outcome of contract award ,��.`��N„��/�,
�McG111 � � � �
..•�.o
ASSO � , ATES ' =4QSfcAl/�
ENG[NE6R3NC•PLANNING•FINANCS ZOvZG
Post Offite 8ox 7138 =�• Z
:��
IilckaY,Narth Carolina 28803 i,�i(�tiy�G'� .
Fum Licensa No.G0459 ,�iai��� I
�ki,�", t y��"�
,
l �,
Attachment 2
'��McGiff
A S S O C I A T E S
May 30, 2014
Mr. Kevin Lindley, PE
Staff Engineer
Planning & Inspections Department
Orange County
Post Office Box 8181
Hillsborough, North Carolina 27278
RE: Award Recommendation
Morinaga Facility Infrastructure Improvements
Orange County, North Carolina
Dear Mr. Lindley:
A total of four (4) bids were received on May 29, 2014 for the Morinaga Facility
Infrastructure Improvements project. JF Wilkerson Contractors of Morrisville, North Carolina
submitted the lowest bid with a total unit bid item amount of $747,840.00.
JF Wilkerson Contractors is appropriated licensed with the North Carolina General
Contractor Board to perform this project and has successfully completed utility projects for
Orange County in the past. We therefore recommend award of the Morinaga Facility
Infrastructure Improvements project to JF Wilkerson Contractors in the amount of $747,840.00.
Enclosed for your use is the Certified Bid Tabulation with Unit Prices. If you have any
questions, please do not hesitate to contact us at (828) 328 -2024.
Sincerely,
McGILL ASSOCIA
�G
ect
DC :je
Enclosures
cc: Mr. Craig Benedict, Orange County
Mr. David Cannell, Orange County
.A.
, PE
1240 19th Street, Lane NW P.O. Box It 36 823.325.2024
Hickory, North Carolina 28601 Hickory, North Carolina 28603 828.328.3870 �ci o.mcgillengineersxn ❑�
5
Site and Proposed Infrastructure for Morinaga Facility (Conceptual Layout) 6