HomeMy WebLinkAboutAgenda - 06-03-2014 - 7gORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: June 3, 2014
Action Agenda
Item No. 7 -g
1
SUBJECT: Orange County's Reprioritization of Transportation Projects for the Durham -
Chapel Hill - Carrboro Metropolitan Planning Organization and the Triangle Area
Rural Planning Organization
DEPARTMENT: Planning and Inspections PUBLIC HEARING: (Y /N) No
ATTACHMENT(S):
1. Resolution Reprioritizing Order of
Projects for TARPO Regional
Priority List
2. TARPO Project List Map
3. TARPO Project Order
Reconfiguration Recommendations
4. Resolution Reprioritizing Order of
Projects for DCHC MPO Priority
List
5. DCHC MPO Project List Map
6. DCHC MPO Project Order
Reconfiguration
Recommendations
INFORMATION CONTACT:
Bret Martin, Transportation Planner, 919 - 245 -2582
Tom Altieri, Comprehensive Planning Supervisor,
919- 245 -2575
Craig Benedict, Planning and Inspections Director,
919- 245 -2585
PURPOSE: To consider two (2) resolutions (Attachments 1 and 4) reconfiguring two (2) priority
lists of transportation projects within the Durham - Chapel Hill - Carrboro Metropolitan Planning
Organization (DCHC MPO) and the Triangle Area Rural Planning Organization ( TARPO)
planning areas for consideration of inclusion in the 2016 -2022 Statewide Transportation
Improvement Program (STIP).
BACKGROUND: At the BOCC's November 19, 2013 meeting, the BOCC considered and
approved two (2) lists of priority transportation projects incorporating all modes to submit to
TARPO and the DCHC MPO for the portion of Orange County within those organizations'
respective planning areas. Those lists were subsequently submitted to each transportation
planning organization for each organization's submission of projects to the State for scoring. It
was determined at the November 19, 2013 meeting by the BOCC that the transportation priority
lists for TARPO and the DCHC MPO should be revisited upon receipt of the State scores for
each project to evaluate whether the projects should be reprioritized with the benefit of knowing
their respective scores.
The lists that were considered for approval /endorsement by the BOCC were meant to serve two
roles:
1) First, the lists were meant to be Orange County's official list of projects to submit for
scoring by the State and to be considered for inclusion in the STIP and ultimately
implemented; and
2) Second, the lists were meant to act as guides for both the Transportation Coordinating
Committee (TCC) and Transportation Advisory Committee (TAC) representatives from
Orange County to strategize /prioritize their assignment of local input points to projects
during each organization's respective internal local input process.
The role of the priority lists serving as the County's official lists of projects to submit for scoring
has been fulfilled. The scores for each project have been received and are provided in
Attachments 3 and 6 for TARPO and DCHC MPO, respectively. As a continuation of Orange
County's input into the STIP development process, the order of the projects in the respective
lists for each transportation planning organization have been reconfigured to maximize the
project programming and funding potential of Orange County- endorsed projects. In
Attachments 3 and 6, the projects are listed in their new staff - recommended priority order with
references to their respective rankings in the previously approved priority lists the BOCC
adopted in November 2013 provided in the far right column. Attachments 2 and 5 are maps
depicting the locations of each of the projects and are coded to correspond to the new staff -
recommended ranking of projects reflected in the resolutions (Attachments 1 and 4). The
original transportation project priority lists can be found using the following link to the minutes of
the November 19, 2013 BOCC meeting:
http: / /server3.co. orange. nc. us:8088 /weblink8 /0 /doc /32180 /Page 1.aspx
TARPO and DCHC MPO Proiect Ranking Policies
Since the BOCC's approval of the priority lists in November 2013, both TARPO and DCHC MPO
have developed and approved project ranking methodologies that prescribe how each
organization's local input points will be assigned to projects. TARPO's policy applies points to
all projects across all modes based on the rank order of projects in each jurisdiction's priority
list. Higher ranked projects on Orange County's list will receive the greatest number of points,
and lower ranked projects will receive the fewest. As such, in order to maximize scoring output
for Orange County's projects and their potential to be funded and included in the STIP, it is
staff's recommendation to rank projects in priority order consistent with their rankings based on
their State scores and based on Orange County's financial capacity (local match requirements,
etc.) to implement such projects.
The DCHC MPO's project ranking policy is data - driven, but leaves open the possibility for the
TAC to rearrange local input points based on factors such as geographic equity, knowledge of
local jurisdictional needs, public input, coordination with division engineers, and maximization of
the MPO's opportunities for receiving funding. Nonetheless, because the adopted policy is
data - driven and is largely consistent with the State's scoring criteria, projects receiving the
higher State scores are likely to be those recommended to receive local input points, while
those receiving lower scores likely will not. It is also within the DCHC MPO policy to apply a
certain number of local input points to each mode. Therefore, the reconfigured priority list for
the DCHC MPO must be broken down by priority for each mode.
Burlington Graham MPO Prioritization Update
At its September 17, 2013 meeting, the BOCC considered and approved a list of six (6) priority
transportation projects to submit to the Burlington- Graham MPO (BGMPO), including four
highway projects, one transit/park -n -ride project, and one bike /pedestrian project. All of the
K
highway projects were subsequently included in the MPO's submission of projects to the State
for scoring. For all 12 BGMPO member jurisdictions, a total of 23 highway and 20
bike /pedestrian projects were scored. The original transportation project priority lists and
supporting information can be found using the following link to the September 17, 2013 BOCC
meeting: http: / /www.co. orange .nc.us /occlerks /130917.pdf
The BGMPO will conduct public review /comment of project scoring in June and July and also
meet with the Division Engineer to review the allocation of Division points. The BGMPO
Transportation Advisory Committee (TAC) will review the State scoring and ranking, receive a
presentation of any comments or new information at its August meeting, and give final approval
of the allocation of points to projects. TAC policy allocates MPO points to the top scoring
projects.
With very little funding available at the regional and division tier levels, it is doubtful that many
MPO projects or any of the County's projects will be funded. Statewide tier projects are the
focus. Projects related to the future Mattress Factory Road interchange were classified as
Division Level projects and scored poorly. The Buckhorn Road widening from US 70 to West
Ten Road also scored poorly. However, one of the highway projects (the 1 -85 frontage road
from Ben Wilson Road to West Ten Road) has already received partial NCDOT funding as part
of the Morinaga economic development effort, and the proposed park- and -ride facility in the
western portion of the County will likely be funded through implementation of the Bus and Rail
Investment Plan (OCBRIP) in partnership with the Piedmont Authority for Regional
Transportation (PART). Staff will continue to communicate and coordinate with BOCC Chair
Barry Jacobs, Orange County's representative to the BGMPO TAC, regarding the status of the
County's prioritized projects in the BGMPO planning area.
FINANCIAL IMPACT: There is no immediate financial impact associated with this item except
that projects specifically categorized as bicycle and pedestrian projects will require a 20 percent
local match from the County and will require the County to expend any costs related to right -of-
way acquisition and project management and administration. All bike and pedestrian projects
require a resolution or letter of commitment from Orange County indicating the County will
provide the local match if the projects are selected for funding.
RECOMMENDATION(S): The Manager recommends that the Board approve the resolutions
(Attachments 1 and 4) to reconfigure the lists of priority transportation projects submitted to the
TARPO and DCHC MPO, respectively.
Attachment 1: Resolution Reprioritizing Order of Projects for the TARPO Regional 4
Priority List (RES- 2014 -039)
ORANGE COUNTY BOARD OF COUNTY COMMISSIONERS
A RESOLUTION APPROVING THE RECONFIGURATION OF ORANGE COUNTY'S PRIORITY
TRANSPORTATION PROJECTS FOR THE TRIANGLE AREA RURAL PLANNING
ORGANIZATION ( TARPO) REGIONAL PRIORITY LIST FOR THE 2016 — 2022 STATEWIDE
TRANSPORTATION IMPROVEMENT PROGRAM
WHEREAS, the North Carolina Board of Transportation (BOT), every two years, prepares a Statewide
Transportation Improvement Program (STIP) that identifies transportation projects to be implemented
over the next seven years with State and Federal funding; and
WHEREAS, the North Carolina BOT solicits input for identifying transportation projects of local and
regional importance to be included in the FY 2016 -2022 STIP; and
WHEREAS, North Carolina has established Rural Planning Organizations (RPOs) to coordinate
regional transportation planning in rural areas in cooperation with the North Carolina Department of
Transportation ( NCDOT);
WHEREAS, Orange County is a member of the Triangle Area Rural Planning Organization ( TARPO)
charged with developing and prioritizing proposed transportation projects that the RPO believes
should be included in the STIP;
WHEREAS, Orange County gives priority to identified safety needs on existing roads and bridges, to
transportation projects that encourage alternatives to automobile travel, to projects that minimize
adverse impacts on the natural environment and cultural sites, and to those projects that foster
economic development in the County's designated Economic Development Districts; and
WHEREAS, Orange County strongly encourages the NCDOT to design all highway projects, where
appropriate, to accommodate bicycle and pedestrian traffic to provide alternative means of
transportation that may result in reduced automobile traffic and related air and water impacts; and
WHEREAS, Orange County encourages the NCDOT to design all new or replacement bridges with
sufficient clearance to allow wildlife to cross safely under them, and to allow pedestrian passage along
any existing or planned trail- system connectors; and
WHEREAS, Orange County previously outlined its transportation needs within the TARPO planning
area on November 19, 2013; and
WHEREAS, Orange County has reconfigured its transportation project priorities in ranked order within
the TARPO planning area in an attachment to this resolution;
NOW, THEREFORE, BE IT RESOLVED by the Orange County Board of Commissioners that the
Board endorses the following prioritized list of transportation projects in the TARPO planning area to
supersede the transportation project priority list for the TARPO planning area previously approved by
the Orange County Board of Commissioners on November 19, 2013, for consideration in the the FY
2016 -2022 TARPO regional priority list:
NC 54 Widening: Widen NC 54 from Orange Grove Road (SR 1006) to Old Fayetteville Road
(SR 1937/1107) from a two (2) -lane undivided thoroughfare to a four (4) -lane divided
boulevard type thoroughfare.
Attachment 1: Resolution Reprioritizing Order of Projects for the TARPO Regional 5
Priority List (RES- 2014 -039)
This project was submitted and scored as a new highway project to be considered for inclusion
in the TARPO regional priority list as well as the 2016 -2022 STIP.
2 Buckhorn Road (SR 1114) Widening: Widen Buckhorn Road from U.S. 70 to West Ten Road
(SR1144) to multiple lanes with bicycle and pedestrian facilities.
This project was previously submitted as a highway project and was reprioritized, submitted
and scored as a highway project for consideration of inclusion in both the TARPO regional
priority list and the BGMPO Metropolitan Transportation Improvement Program (MTIP) as well
as the 2016 -2022 STIP.
3 Old Greensboro Road Paved Shoulders: Widen Old Greensboro Road (SR 1005) from
Carrboro's extra - territorial jurisdiction (ETJ) (near Sturbridge Lane) to the Orange /Alamance
County line to include four (4) -foot paved shoulders.
This project was submitted and scored as a highway project to be considered for inclusion in
the TARPO regional priority list as well as the 2016 -2022 STIP.
4 Efland -Cedar Grove Road Improvements: Widen Efland -Cedar Grove Road (SR 1004) from
Highland Farm Road (SR 1332) to the northern property line of the U.S. Post Office north of
Carr Store Road (SR 1352) from a two (2) -lane, 20 -foot cross section to a 24 -foot cross
section with straightening of the roadway where needed, improvements to turn lanes, and the
incorporation of bicycle facilities.
This project was submitted and scored as a reprioritized highway project to be considered for
inclusion in the TARPO regional priority list as well as the 2016 -2022 STIP.
5 Orange Grove Road /Buckhorn Road Paved Shoulders: Widen Orange Grove Road (SR 1006)
from Dairyland Road (SR 1177) to Buckhorn Road (SR 1114) and Buckhorn Road (SR 1114)
from Orange Grove Road (SR 1006) to West Ten Road (SR 1144) to include four (4) -foot
paved shoulders.
This project was submitted and scored as a highway project to be considered for inclusion in
the TARPO regional priority list as well as the 2016 -2022 STIP.
6 Orange Grove Road Paved Shoulders (From NC 54 to Arthur Minnis Road): Widen Orange
Grove Road (SR 1006) from NC 54 to Arthur Minnis Road to include four (4) -foot paved
shoulders.
This project was submitted and scored as a new bike project to be considered for inclusion in
the TARPO regional priority list as well as the 2016 -2022 STIP if the County commits the
required 20% local match.
7 Dairyland Road Paved Shoulders: Widen Dairyland Road (SR 1004/1113/1177) from Union
Grove Church Road (SR 1111) to Orange Grove Road (SR 1006) to include four (4) -foot
paved shoulders.
This project was submitted and scored as a new bike project to be considered for inclusion in
the TARPO regional priority list as well as the 2016 -2022 STIP if the County commits the
required 20% local match.
8 Orange Grove Road /Dodsons Crossroads: Widen Orange Grove Road (SR 1006) from 1 -40 to
Dodsons Crossroads (SR 1102) and Dodsons Crossroads (SR 1102) from Orange Grove
Road (SR 1006) to Dairyland Road (SR 1177) to include four (4) -foot paved shoulders.
Attachment 1: Resolution Reprioritizing Order of Projects for the TARPO Regional 6
Priority List (RES- 2014 -039)
This project was submitted and scored as a new bike project to be considered for inclusion in
the TARPO regional priority list as well as the 2016 -2022 STIP if the County commits the
required 20% local match.
Upon motion of Commissioner , seconded by Commissioner
the foregoing resolution was adopted this the 3 d day of June, 2014.
I, Donna Baker, Clerk to the Board of Commissioners for the County of Orange, North Carolina, DO
HEREBY CERTIFY that the foregoing is a true copy of so much of the proceedings of said Board at a
meeting held on June 3, 2014, as relates in any way to the adoption of the foregoing and that said
proceedings are recorded in the minutes of said Board.
WITNESS my hand and the seal of said County, this day of 12014.
Clerk to the Board of Commissioners
Attachment 2: TARPO Project List Map 7
Alamance
O
Chatham
B -G MPO DCHC MPO
T
fyy
'Z
O
KENION RD
O
K
U
2
0
Person
Durham
1 in = 3 miles
0 1
Miles
Orange County Planning and Inspections
Brian Carson (5/2712014)
ATTACHMENT 3: Triangle Rural Planning Organization Project Order Reconfiguration Recommendations
Note: Two (2) projects were removed from the TARPO Priority List: OPT expansion vehicles to implement the Orange County Bus and Rail Investment Plan ( OCBRIP) - original project #1 and Park - and -Ride improvements at Cedar Grove
Community Center (conceptual) - original project #4. The expansion vehicles were removed because the vehicles needed to implement the OCBRIP for FY 2016 and beyond will not be used for service in the TARPO planning area. The Cedar
Grove park- and -ride project was removed because the submission of the project requires a feasibility study and other planning documents, and it was determined by staff that the site does no necessitate a park- and -ride facility but only smaller
scale kiss - and -ride improvements.
N/A
23.45
17.37
This project is moved to priority #1 in the reconfigured list because it has the highest potential of all
_
1
NC 54 Widening from Orange Grove Road
#2
to Old Fayetteville Road
highway projects to be funded based on scores received from the State.
2
Buckhorn Road Widening from U.S. 70 to
N/A
N/A
11.37
Project moved to priority #2 in the reconfigured list because it has the 2 highest potential of all
#3
West Ten Road
highway projects to be funded based on scores received from the State.
Old Greensboro Road paved shoulders
Project moved to priority #3 in the reconfigured list because it has the 3rd highest potential of all
3
from Sturbridge Lane to Alamance County
N/A
N/A
8.44
highway projects to be funded based on scores received from the State.
#9
line
Efland -Cedar Grove improvements from
m
Project moved to priority #4 in the reconfigured list because it has the 4 highest potential of all
4
Highland Farm Road to north of Carr Store
N/A
N/A
7 4g
highway projects to be funded based on scores received from the State.
#5
Road
Orange Grove Road /Buckhorn Road paved
shoulders from Dairyland Road to
Project moved to priority #5 in the reconfigured list because it has the 5`h highest potential of all
5
Buckhorn Road and Orange Grove Road to
N/A
N/A
6.43
highway projects to be funded based on scores received from the State.
#8
West Ten Road, respectively
Project remains priority #6 in the reconfigured list because it is categorized as a bikeway project
6
Orange Grove Road paved shoulders from
N/A
N/A
17.57
requiring a 20% local match. In the reconfigured list it is the highest ranked bikeway project because
#6
NC 54 to Arthur Minnis Road
it received the highest score among the Orange County- endorsed bikeway projects in the TARPO
planning area.
Dairyland Road paved shoulders from
Project remains priority #7 in the reconfigured list because it is categorized as a bikeway project
d
7
Union Grove Church Road to Orange
N/A
N/A
17.40
requiring a 20% local match. In the reconfigured list it is the 2 highest ranked bikeway project
#7
Grove Road
because it received the 2nd highest score among all of Orange County- endorsed bikeway projects in
the TARPO planning area.
Orange Grove Road / Dodsons Crossroads
Project moved to priority #8 in the reconfigured list because it is categorized as a bikeway project
8
paved shoulders from I -40 to Dodsons
N/A
N/A
15.09
requiring a 20% local match. In the reconfigured list it is the 3rd highest ranked bikeway project
#10
Crossroads and Orange Grove Road to
because it received the 3rd highest score among all of Orange County- endorsed bikeway projects in
Dairyland Road, respectively
the TARPO planning area.
Note: Two (2) projects were removed from the TARPO Priority List: OPT expansion vehicles to implement the Orange County Bus and Rail Investment Plan ( OCBRIP) - original project #1 and Park - and -Ride improvements at Cedar Grove
Community Center (conceptual) - original project #4. The expansion vehicles were removed because the vehicles needed to implement the OCBRIP for FY 2016 and beyond will not be used for service in the TARPO planning area. The Cedar
Grove park- and -ride project was removed because the submission of the project requires a feasibility study and other planning documents, and it was determined by staff that the site does no necessitate a park- and -ride facility but only smaller
scale kiss - and -ride improvements.
Attachment 4: Resolution Reprioritizing Order of Projects for the DCHC Priority List 9
(RES- 2014 -040)
ORANGE COUNTY BOARD OF COUNTY COMMISSIONERS
A RESOLUTION APPROVING THE RECONFIGURATION OF ORANGE COUNTY'S PRIORITY
TRANSPORTATION PROJECTS FOR THE DURHAM - CHAPEL HILL - CARRBORO
METROPOLITAN PLANNING ORGANIZATION (DCHC MPO) REGIONAL PRIORITY LIST FOR
THE 2016 — 2022 TRANSPORTATION IMPROVEMENT PROGRAM
WHEREAS, the North Carolina Board of Transportation (BOT), every two years, prepares a Statewide
Transportation Improvement Program (STIP) that identifies transportation projects to be implemented
over the next seven years with State and Federal funding; and
WHEREAS, the North Carolina BOT solicits input for identifying transportation projects of local and
regional importance to be included in the FY 2016 -2022 STIP; and
WHEREAS, the DCHC MPO Transportation Advisory Committee is charged with the development of
a regional priority list and Metropolitan Transportation Improvement Program (MTIP); and
WHEREAS, Orange County is a member jurisdiction of the DCHC MPO; and
WHEREAS, Orange County gives priority to identified safety needs on existing roads and bridges, to
transportation projects that encourage alternatives to automobile travel, to projects that minimize
adverse impacts on the natural environment and cultural sites, and to those projects that foster
economic development in the County's designated Economic Development Districts; and
WHEREAS, Orange County strongly encourages the North Carolina Department of Transportation
( NCDOT) to design all highway projects, where appropriate, to accommodate bicycle and pedestrian
traffic to provide alternative means of transportation that may result in reduced automobile traffic and
related air and water impacts; and
WHEREAS, Orange County encourages the NCDOT to design all new or replacement bridges with
sufficient clearance to allow wildlife to cross safely under them, and to allow pedestrian passage along
any existing or planned trail- system connectors; and
WHEREAS, Orange County previously outlined its transportation needs within the DCHC MPO
planning area on November 19, 2013; and
WHEREAS, Orange County has reconfigured its transportation project priorities in ranked order by
mode within the DCHC MPO planning area in an attachment to this resolution;
NOW, THEREFORE, BE IT RESOLVED by the Orange County Board of Commissioners that the
Board endorses the following prioritized list of transportation projects by mode in the DCHC MPO
planning area to supersede the transportation project priority list for the DCHC MPO planning area
previously approved by the Orange County Board of Commissioners on November 19, 2013, for
consideration in the FY 2016 -2022 DCHC MPO regional priority list and MTIP.
Highway Projects:
1 South Churton Street (Old NC 86) Improvements: Widen South Churton Street (SR 1009) from
1 -40 to U.S. 70 Business to multiple lanes with congestion management, limited access,
bicycle and pedestrian, and aesthetic improvements.
This project was submitted and scored as a reprioritized highway project to be considered for
inclusion in the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP.
Attachment 4: Resolution Reprioritizing Order of Projects for the DCHC Priority List 10
(RES- 2014 -040)
2 Orange Grove Road Extension: Extend Orange Grove Road (SR 1006) from the east side of
South Churton Street (SR 1009) to U.S. 70 Business.
This project was submitted and scored as a reprioritized highway project to be considered for
inclusion in the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP.
3 NC 86 Improvements North of Hillsborough: Widen NC 86 from U.S. 70 Bypass to north of NC
57 to four (4) lanes with intersection improvements at U.S. 70 Bypass and NC 57.
This project was submitted and scored as a reprioritized highway project to be considered for
inclusion in the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP.
4 U.S. 70 East/1 -85 Connector: Modify the 1 -85 Connector (SR 1239) interchange at U.S. 70 to
provide access from all directions.
This project was submitted and scored as a reprioritized highway project to be considered for
inclusion in the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP.
5 Eno Mountain Road /Mayo Street at Orange Grove Road: Realign the intersection of Eno
Mountain Road (SR 1148) and Mayo Street (SR 1192) with Orange Grove Road (SR 1006)
and make safety improvements.
This project was submitted and scored as a reprioritized highway project for consideration of
inclusion in the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP.
6 Homestead Road Bike Lanes and Sidewalks: Improve Homestead Road (SR 1777) from Old
NC 86 (SR 1009) to NC 86 to include bicycle lanes and sidewalks in sections of the corridor
where they do not exist.
This project was submitted and scored as a reprioritized highway project for consideration of
inclusion in the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP.
7 1 -40 Widening: Widen 1 -40 from four (4) lanes to six (6) lanes from the 1- 40/1 -85 interchange to
the Durham County line.
This project was submitted and scored as a reprioritized highway project for consideration of
inclusion in the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP.
8 1 -85 Widening: Widen 1 -85 from four (4) lanes to six (6) lanes from the 1- 40/1 -85 interchange to
the Durham County line.
This project was submitted and scored as a reprioritized highway project for consideration of
inclusion in the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP.
9 Eubanks Road Bike Lanes: Construct bicycle lanes on Eubanks Road (SR 1727) from Old NC
86 (SR 1009) to NC 86.
This project was submitted and scored as a highway project for consideration of inclusion in
the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP.
Attachment 4: Resolution Reprioritizing Order of Projects for the DCHC Priority List 11
(RES- 2014 -040)
Bike /Pedestrian Projects:
1 Mt. Carmel Church Road Bike /Pedestrian Improvements: Construct bike lanes and sidewalks
from US 15/501 to Bennett Road.
This project was submitted and scored as a new bike /ped project for consideration of inclusion
in the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP. In order for
the project to be funded, the County must commit to providing the required 20% local match
and agree to locally administer the project.
2 Mt. Carmel Church Road Bike Lanes: Construct bike lanes from Bennett Road to the Chatham
County line.
This project was submitted and scored as a new bike project for consideration of inclusion in
the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP. In order for the
project to be funded, the County must commit to providing the required 20% local match and
agree to locally administer the project.
3 Orange High School Road /Harold Latta Road Sidewalk Improvements: Construct a sidewalk
along the west side of Orange High School Road from Harold Latta Road to U.S. 70, construct
a sidewalk along the south side of Harold Latta Road from Cloverfield Drive to Orange Grove
Road, install high visibility crosswalks and in -road signage at school entrances and exits on
Orange Grove Road, and construct a sidewalk along entrance roads to CW Stanford Middle
School.
This project was submitted and scored as a new pedestrian project for consideration of
inclusion in the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP. The
project was submitted as a Safe Routes to School (SRTS)- eligible project; however, if it is not
funded as an SRTS project, the County will be required to commit a 20% local match and must
locally administer the project.
4 Orange Grove Road /1 -40 Pedestrian Bridge: Construct a pedestrian bridge over 1 -40 alongside
Orange Grove Road (SR 1006), construct a sidewalk along the north side of Orange Grove
Road (SR 1006) from the pedestrian bridge to Timbers Drive, construct sidewalks along both
sides of New Grady Brown School Road with a midblock crossing, and construct a sidewalk
along one side of Oakdale Drive from Cheshire Drive to Orange Grove Road.
This project was submitted and scored as a new pedestrian project for consideration of
inclusion in the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP. The
project was submitted as a Safe Routes to School (SRTS)- eligible project; however, if it is not
funded as an SRTS project, the County will be required to commit a 20% local match and must
locally administer the project.
5 Dairyland Road Paved Shoulders: Widen Dairyland Road (SR 1004/1113/1177) from Union
Grove Church Road (SR 1111) to Orange Grove Road (SR 1006) to include four (4) -foot
paved shoulders.
This project was submitted and scored as a new bike project for consideration of inclusion in
the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP. In order for the
project to be funded, the County must commit to providing the required 20% local match and
agree to locally administer the project.
6 Trail Connection from English Hill Lane to Buttonwood Drive: Construct a multi -use path
connecting English Hill Lane to Buttonwood Drive.
Attachment 4: Resolution Reprioritizing Order of Projects for the DCHC Priority List 12
(RES- 2014 -040)
This project was submitted and scored as a new pedestrian project for consideration of
inclusion in the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP. The
project was submitted as a Safe Routes to School (SRTS)- eligible project; however, if it is not
funded as an SRTS project, the County will be required to commit a 20% local match and must
locally administer the project.
7 Trail Connection from Patriot's Pointe to Timbers Drive: Construct a multi -use path connecting
the southwest corner of Patriots Pointe to Timbers Drive to shorten walking distances for
pedestrians.
This project was submitted and scored as a new pedestrian project for consideration of
inclusion in the DCHC MPO regional priority list and MTIP as well as the 2016 -2022 STIP. The
project was submitted and scored as a Safe Routes to School (SRTS)- eligible project;
however, if it is not funded as an SRTS project, the County will be required to commit a 20%
local match and agree to locally administer the project.
Transit Projects:
Request/purchase three (3), 25 -foot, 18- passenger light transit vehicles to accommodate bus service
expansion as recommended in the Orange County Bus and Rail Investment Plan (OCBRIP) and the
draft Five -Year Orange County Bus Service Expansion Program currently under development.
Expansion Vehicle #1 for FY 2016: This project was submitted and scored as a transit project
for consideration of inclusion in the DCHC MPO regional priority list and MTIP as well as the
2016 -2022 STIP.
2 Expansion Vehicle #2 for FY 2016: This project was submitted and scored as a transit project
for consideration of inclusion in the DCHC MPO regional priority list and MTIP as well as the
2016 -2022 STIP.
3 Expansion Vehicle #3 for FY 2017: This project was submitted and scored as a transit project
for consideration of inclusion in the DCHC MPO regional priority list and MTIP as well as the
2016 -2022 STIP.
Rail Project:
Hillsborough Train Station: Construct a train station in Hillsborough and implement AMTRAK
service.
This project was submitted and scored as a new rail project by Triangle Transit for
consideration of inclusion in the DCHC MPO regional priority list and MTIP as well as the
2016 -2022 STIP.
Upon motion of Commissioner , seconded by Commissioner
the foregoing resolution was adopted this the 3 d day of June, 2014.
I, Donna Baker, Clerk to the Board of Commissioners for the County of Orange, North Carolina, DO
HEREBY CERTIFY that the foregoing is a true copy of so much of the proceedings of said Board at a
meeting held on June 3, 2014, as relates in any way to the adoption of the foregoing and that said
proceedings are recorded in the minutes of said Board.
WITNESS my hand and the seal of said County, this day of 12014.
Clerk to the Board of Commissioners
Alamance
Attachment 5: DCHC MPO Project List Map 13
0
pi
0
�10 Bike /Ped Projects
CMMEM Highway Projects
Rail Project
Caswell
B -G MPO
DCHC MPO
FP
LAWS
See Inset
Person
Durham
N 1 in= 3 miles
Chatham * 1
Miles
Orange County Planning and Inspections
Brian Carson (11/15/2013)
14
ATTACHMENT 6: DCHC MPO Project Order Reconfiguration Recommendations
y�
HIGHWAY PROJECTS
South Churton Street (Old )
Project becomes highway priority #1 in the reconfigured list because it has the 2nd highest potential of all
1
Improvements from -40 to U.. 70
U.S. 7
N/A
N/A
22.36
highway projects to be funded based on scores received from the State.
#5
Business
Orange Grove Road extension from east
Project becomes highway priority #2 in the reconfigured list because it has the highest potential of all highway
2
side of South Churton Street to U.S. 70
N/A
N/A
23.67
projects to be funded based on scores received from the State.
#7
Business
Widen NC 86 from U.S. 70 bypass to north
Project becomes highway priority #3 in the reconfigured list because it has the 3' highest potential of all
3
of NC 57
N/A
24.16
19.46
highway projects to be funded based on scores received from the State.
#8
U.S. 70 East/1 -85 Connector — improve
Project becomes highway priority #4 in the reconfigured list because of the magnitude of importance of the
4
interchange to provide access from all
N/A
7.34
4.90
project for Orange County commuters /motorists; however, the project did not score well relative to other
#6
directions
Orange Count - endorsed highway ro ects.
Eno Mountain Road and Mayo Street
Project becomes highway priority #5 in the reconfigured list because of its relative importance to local Orange
5
intersection realignment at Orange Grove
N/A
N/A
5.10
County commuters /motorists, however, the project did not score well relative to other Orange County- endorsed
#11
Road
highway ro ects.
ad bike lanes and sidewalks
Homestead d Road
Project becomes highway priority #6 in the reconfigured list because it has little potential of all highway
6
from Old to NC 86
N/A
N/A
10.37
projects to be funded based on scores received from the State and because of its lack of relative importance to
#12
Orange County commuters /motorists.
Project becomes highway priority #7 in the reconfigured list because its likelihood for funding is primarily
7
I -40 Widening
41.89
30.18
23.59
based on its Statewide Tier score, which is 100% data driven and does not involve local input points. The
#14
project is eligible for funding in the regional and division tiers, however, because of the high cost of the project,
staff recommends against supporting the project for regional or division tier funding.
From east of SR
1709 to the Durham
27.92
23.01
18.15
Projects becomes highway priority #8 in the reconfigured list because its likelihood for funding is primarily
8
1 -85 Widening
County line
based on its Statewide Tier score, which is 100% data driven and does not involve local input points. The
#15
From SR 1006 near
project is eligible for funding in the regional and division tiers, however, because of the high cost of the project,
Hillsborough to east
25.07
20.27
16.14
staff recommends against supporting the project for regional or division tier funding.
of SR 1709
Eubanks Road bike lanes from Old NC 86
Project becomes highway priority #9 in the reconfigured list because of its unlikelihood of for funding based
9
to NC 86
N/A
N/A
11.75
on State scores and its relative insignificance to Orange County commuters /motorists among all Orange
#18
County-endorsed highway ro ects.
BIKE /PEDESTRIAN PROJECTS
Bike lanes and
Project becomes bike /ped project priority #1 in the reconfigured list because it scored the highest among all
sidewalks from U.S.
N/A
N/A
2306
Orange County- endorsed bike /ped projects in the DCHC MPO planning area and is part of a Statewide bicycle
15 -501 to Bennett
.
route. Project requires a local match commitment of 20% of project cost to be funded and must be locally
Mt. Carmel Church
Road
administered.
1 and 2
Road bike lanes
Bike lanes from
Project becomes bike /ped priority #2 in the reconfigured list because it complements and completes bike /ped
#20
and sidewalks
Bennett Road to
project priority #1 by providing a connection to prioritized bike lane improvements in Chatham County and is
Chatham County
N/A
N/A
18.57
part of a Statewide bicycle route. It is also the 2 d highest scoring of all Orange County- endorsed bike /ped
line
projects in the DCHC MPO planning area that have no formidable barriers to implementation. Project requires a
local match commitment of 20% of project cost to be funded and must be locally administered.
Project becomes bike /ped priority #3 in the reconfigured list because it received a relatively higher score
among all of Orange County- endorsed bike /ped projects in the DCHC MPO planning area and has fewer
3
Orange High School Road /Harold Latta
N/A
N/A
18.06
barriers to implementation such as right -of -way acquisition requirements. Project generally requires a local
#4
Road Sidewalk Improvements
match commitment of 20% of project cost to be funded and must be locally administered, except as a Safe
Routes to School, which may be funded at 100 %.
15
ATTACHMENT 6: DCHC MPO Project Order Reconfiguration Recommendations
Note: Three (3) projects were removed from the DCHC MPO priority list: Park - and -Ride Improvements in Efland (conceptual) — original project #3, Park - and -Ride Improvements in Hillsborough — original project #9, and Buckhorn Economic
Development District /Mebane Area Park - and -Ride Improvements — original project #13. The park- and -ride projects were removed from the priority list because the submission of these projects requires a feasibility study and other planning
documents. It was also determined by staff that the Efland site does not necessitate large -scale park- and -ride improvements. The implementation of a short -term Mebane area park- and -ride facility is underway, and Orange County and Triangle
Transit are working with PART to construct a long -term facility. The implementation of a short -term park- and -ride facility in Hillsborough has been executed, and a long -term facility will require a feasibility study to secure State funding.
Project becomes bike /ped priority #4 in the reconfigured list because it received a relatively higher score
among all of Orange County- endorsed bike /ped projects in the DCHC MPO planning area that have fewer
4
Orange Grove Road /1 -40 pedestrian bridge
N/A
N/A
17
barriers to implementation such as right -of -way acquisition requirements. Project generally requires a local
#1
and supporting sidewalk improvements
.44
match commitment of 20% of project cost to be funded and must be locally administered, except as a Safe
Routes to School, which may be funded at 100 %.
Dairyland Road paved shoulders from
Project becomes bike /ped priority #5 in the reconfigured list because it is ineligible for Safe Routes to School
5
Union Grove Church Road to Orange
N/A
N/A
17.40
funding and received a relatively lower score among all of Orange County- endorsed bike /ped projects in the
#19
Grove Road
DCHC MPO planning area. Project generally requires a local match commitment of 20% of project cost to be
funded and must be locally administered.
Project becomes bike /ped priority #6 in the reconfigured list because it presents formidable barriers to
6
Trail Connection from English Hill Lane to
N/A
N/A
23.05
implementation such as 100% right -of -way acquisition of private property. Project generally requires a local
#17
Buttonwood Drive
match commitment of 20% of project cost to be funded and must be locally administered, except as a Safe
Routes to School, which may be funded at 100 %.
Project becomes bike /ped priority #7 in the reconfigured list because it presents formidable barriers to
7
Trail Connection from Patriots Pointe to
N/A
N/A
20.57
implementation such as 100% right -of -way acquisition of private property. Project generally requires a local
#16
Timbers Drive
match commitment of 20% of project cost to be funded and must be locally administered, except as a Safe
Routes to School, which may be funded at 100 %.
TRANSIT PROJECTS
U.S. 70 Midday
expansion vehicle —
N/A
N/A
4.24
Project becomes transit project #1 in the reconfigured list because of its immediate need.
Orange Public
FY 2016
Transportation
Hillsborough
1, 2 and 3
expansion vehicles
to implement the
Circulator
expansion vehicle-
N/A
N/A
4.75
Project becomes transit project #2 in the reconfigured list because of its immediate need.
#2
Orange County Bus
FY 2016
and Rail Investment
Hillsborough
Plan (OCBRIP)
Circulator
N/A
N/A
3.97
Project becomes transit project #3 in the reconfigured list because of its longer term need and because it
expansion vehicle —
received the lowest score of all Orange County transit projects.
FY 2017
RAIL PROJECT
1
1 Hillsborough Train Station N/A N/A 18.97 Project re prioritized as Orange County's only endorsed rail project priority. #10
Note: Three (3) projects were removed from the DCHC MPO priority list: Park - and -Ride Improvements in Efland (conceptual) — original project #3, Park - and -Ride Improvements in Hillsborough — original project #9, and Buckhorn Economic
Development District /Mebane Area Park - and -Ride Improvements — original project #13. The park- and -ride projects were removed from the priority list because the submission of these projects requires a feasibility study and other planning
documents. It was also determined by staff that the Efland site does not necessitate large -scale park- and -ride improvements. The implementation of a short -term Mebane area park- and -ride facility is underway, and Orange County and Triangle
Transit are working with PART to construct a long -term facility. The implementation of a short -term park- and -ride facility in Hillsborough has been executed, and a long -term facility will require a feasibility study to secure State funding.