HomeMy WebLinkAboutAgenda - 05-13-2014 - 1ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: May 13, 2014
Action Agenda
Item No. 1
SUBJECT: Southern Branch Library Siting Criteria Update
DEPARTMENT: Library, Asset Management PUBLIC HEARING: (Y /N) No
Services (AMS), Planning
ATTACHMENT(S):
A. BOCC Approved Southern Library
Siting Criteria
B. Criteria Report — 120 Brewer Lane
C. Presentation: Available at
http: / /orangecountync.gov /library /doc
uments /BOCCPresentation. pdf
PURPOSE: To:
INFORMATION CONTACT:
Lucinda Munger, 919 - 245 -2528
Jeff Thompson, 919 - 245 -2658
Michael Harvey, 919 - 245 -2597
1. Receive an update and provide feedback regarding the 120 Brewer Lane Primary Phase
Public Input process and Southern Branch programming report delivered by County staff
and Freelon Group Architects of Durham; and
2. Provide direction to the Manager with regard to authorizing further due diligence to be
performed on the 120 Brewer Lane site for the development of the Southern Branch
Library.
BACKGROUND: On September 18, 2012 the Orange County Board of Commissioners
(BOCC), in conjunction with the Carrboro Board of Aldermen, approved a set of guiding
principles and a comprehensive site selection criterion (Attachment A) for locating the new
Southern Branch of the Orange County Library (hereafter "the Branch "). Since that time the
Town has submitted several properties for review by County staff consistent with the approved
Branch siting process.
On November 5, 2013 the BOCC authorized staff to continue with a more granular level of
Preliminary Phase I analysis regarding the 120 Brewer Lane site. Attachment B summarizes
the overall due diligence findings of the site, as framed by the Site Selection Criteria.
On January 23, 2014 the Board authorized the engagement of Freelon Associates of Durham,
NC to facilitate the Primary Phase Public Input ( "Primary Phase ") for the Brewer Lane site.
Freelon Associates began working with the project staff in February 2014. Freelon completed a
thorough assessment of library space needs, and developed alternatives based on maximum
efficiencies, known statistical information regarding the library and demographic projections.
Input from the community, the library staff, Friends group, and the Southern Branch Library
project team, was included in the development of this recommendation.
Freelon Associates and County staff conducted two community engagement workshops and a
middle school workshop, gleaned input from the Carrboro Community Dinner attendees, and
offered an online survey and public comment cards to collect data to assist in defining the
recommendation.
Based on this process and public input, Freelon Associates recommends the Southern Branch
Library size be between 15,650 and 18,475 square feet (minimum net square footage).
Freelon Associates noted that while this recommendation accommodates the basic current
needs of the community, it does not account for the standard 20 -year projected
population /library growth. Building in flexibility will allow for a measure of changeability, but will
not accommodate the potential expanded needs of 20 years in the future. A plan for future
expansion opportunity should be considered.
Freelon's recommendation on distilling this square footage into a flexible and adaptable program
to serve the southern area of Orange County is below.
Recommended Conceptual Program
PUBLIC SPACES
Adults/Teens /Children
53%
Meeting /Gathering Spaces
15%
Marketplace
12%
Creation spaces
10%
NON PUBLIC
10%
SPACES
Adults/Teens /Children: Collections, Seating, Computers, Small Study Spaces, Group Spaces
Meeting /Gathering: Multipurpose flexible meeting space, Conference room
Marketplace: Entry, Service Desk, Self- Checkout, Returns, Holds, New Releases, Display,
Gallery, Download Hubs, Technology Vending, Book Sales
Creation: Technology /Media Lab, Training Classroom, Flexible Multipurpose Lab
Non Public: Staff Workspaces, Shipping /Receiving, Book Return
These areas will be designed to provide support to these critical components of a 21St century
library:
Flexibility: Flexibility is key in new library design. Future services and rearrangements must be
taken into account. This ranges from flexibility within the infrastructure and technology, to
flexible furniture.
Collections: This conceptual program takes into account the changing world of library
programming. As new neighborhood libraries open with innovative programs tailored to meet
K
the specific community's needs, circulation counts are known to double and in some cases even
triple. The use of a floating collections concept along with strong ILL (Inter - library loan)
partnerships allows libraries to maintain smaller shelving footprints while increasing the range of
available materials.
Programs: This coincides with the ever - increasing need to provide more "people space."
Communities need access to the latest technology, training, meeting and collaborative space.
As customers find fewer locations outside of the home for quiet study and reading, it is
increasingly important to provide these opportunities within the library. Children's spaces are
expanding to include more exploratory learning opportunities. And teen spaces are including
zones not only for hanging out but also for creating. Access to high and low tech creation
spaces allows the synergies between age groups to be utilized and are essential to providing a
complete library experience.
Operations: To minimize operational costs and increase security, the library spaces should be
open and visible. This is accomplished with a single main entry point, lower shelving heights
and smaller touchdown hubs for floating staff to consult with customers. Operational costs are
also minimized by consolidating technical services work (cataloging, processing, etc.) at the
Main Branch Library.
Representatives of Freelon Associates will present a more in -depth report outlining the process,
findings and associated recommendations to the Board and will be available for questions. The
meeting presentation for this item (Attachment C) is available at
http: / /orangecountync.gov /library /documents /BOCCPresentation. pdf
If the Board determines that staff should continue with the due diligence process regarding the
120 Brewer Lane property as the potential site for the Southern Branch library, staff will be
prepared to present estimated development costs and more detailed project information at the
June 17, 2014 regular Board meeting.
Should the Board direct staff to continue with the due diligence, the general schedule will be as
follows:
TASK
PROPOSED
END BY DATE
BEGINNING
DATE
BOCC Action: Workgroup and Consultant report to the
May 13, 2014
May 13, 2014
BOCC for feedback (to include public input summary and
programming parameters to assist in potential future
design of Southern Library)
BOCC Action: Decision to allow further due diligence to be
June 17, 2014
June 17, 2014
performed through the 2014 summer break
BOCC Action: Potential Development Agreement review
October, 2014
October, 2014
and approval to move forward with developing the 120
Brewer Lane Site
Designer Request for Qualification process
October, 2014
December, 2014
BOCC Action: Approval of Project Designer
January, 2015
January, 2015
Design Process (with several design updates to the BOCC;
February, 2015
December, 2015
public design input continues throughout process)
Construction Bid Advertisement and Process
January, 2016
Aril, 2016
BOCC Action: Bid Award
May, 2016
May, 2016
Facility Construction and Commissioning 15 months
June, 2016
Sep tember, 2017
Facility Stocking
September, 2017
October, 2017
Grand Opening
October, 2017
October, 2017
M
FINANCIAL IMPACT: Costs related to the due diligence activities of the 120 Brewer site total
$36,000, including site title work as well as the public process facilitation process. An additional
$15,000 is encumbered for current and potentially future legal counsel related to the drafting
and negotiation of the Development Agreement with the Developer.
The Board has appropriated $650,000 within the FY2012 -13 and FY2013 -14 Capital Investment
Plan for due diligence and land acquisition costs for the Southern Branch library.
RECOMMENDATION(S): The Manager recommends that the Board:
1) Receive an update and provide feedback regarding the 120 Brewer Lane Primary Phase
Public Input process and Southern Branch programming report delivered by County staff
and Freelon Group Architects of Durham; and
2) Provide direction to the Manager with regard to authorizing further due diligence to be
performed on the 120 Brewer Lane site for the development of the Southern Branch
Library.
Attachment A
ORANGE COUNTY SOUTHERN BRANCH LIBRARY LOCATIONAL CRITERIA
Guiding Principles
When selecting a site for a new or expanded library, the Library system takes into
account three fundamental factors:
o The Library System recognizes that as a regional service provider, the
location of libraries must provide for optimal service to the most number of
residents within the entire System service area. This takes precedence
over political boundaries or undeveloped neighborhoods.
o The Board is committed to providing an equitable level of service
throughout the entire County.
o The placement of a library in a manner that maximizes its use will be more
valuable over the long term than the original investment made in land or
building. Typically, the original cost of a new building is exceeded in just
three years by its cumulative operating costs.
" As aruended by the BOCC at its June 14, 2012 tivork session
PRELIMINARY PHASE--- TECI- INICAL SITE REVIEW AND ASSESSMENT
Visibility:
• Visible from the street
• Classification of street where property will be accessed from (i.e. private, local,
arterial, collector, major thoroughfare, etc.).
• Visual appeal
Site Capacity:
._.. Able...._to...provide._... comprehensive _ librar_y.....services_ to.. all . the residents .......... of southern. -
Orange County.
Meets - minimum acreage (urban services vs:- rural- services)
• Space for building and on -site parking
• Adequate utilities and availability
• Space for future expansion (building to allow for additional library services, parking,
etc.) to serve all the residents of southern Orange County.
• Space to accommodate the necessary setbacks, road expansions and other site
amenities.
Access:
• Accessibility for pedestrians
• Accessibility for vehicles
• Accessibility for public transportation
• Design capacity and existing traffic load of roadway proposed to access site.
Alignment with Planning Tools (Comprehensive Plan):
Alignment with planning tools applicable for the subject property (County Comprehensive
Plan, adopted Small Area Plans, Strategic Plans, etc.)
Lease versus Purchase:
Analysis of the long term viability of the site
• Availability of property for lease
Centrality of Location:
• Existing and potential future population in a given area
• Growth and development opportunities /constraints in a given area (i.e. what is future
development, as embodied in applicable plans, going to look like and how will it
impact the proposed library)
• Proximity to schools
• Proximity to retail
• Proximity to other libraries
Site Conditions, Allowances, and Constraints:
• The cost - benefit conclusions of physical, legal, and land -use allowances /constraints
• Technical and environmental assessments (planning /zoning, jurisdictional processes,
etc.)
• Environmentally sustainable (C &A, storm water mgt, buffers, energy "net zero"
capacity)
• Operationally sustainable
• Defeats obsolescence
Cost and Availability:
• Cost for site acquisition
Availability __of_pr_o.perty__fo.r_le.ase
• Analysis of long term viability of site
• Timeframe for development of the site
• Terms for site control necessary for development process
C
ORANGE COUNTY SOUTHERN BRANCH LIBRARY LOCATIONAL CRITERIA:
** As amended by the BOCC at its June 14, 2012 wort; session
PRIMARY PHASE -- PUBLIC INPUT AND ASSESSMENT
Community Preference
• Input from elected officials
• Input from a board cross- section of the area to be served
• Orange County & Carrboro Friends of the Library
Partnerships
• Co- location with other private or public entity
• Mutually beneficial joint development
• Enhances service possibilities
SITE EVALUATION CRITERIA:
PHASE 1 - PRELIMINARY ASSESSMENT
VISIBILITY
Attachment B
120 Brewer Lane
Library building will not be directly visible from Main Street or other major
roadway. Off -site directional signage, including directional signage within the
300 East Main property, will be necessary directing motorists and pedestrians
Visible From Street
to the site.
Classification of Street where property will be access from
Arterial
Building housing proposed library shall be part of a mixed use development
Visual Appeal
comprised of residential and non - residential land uses as well as a parking deck.
Rear of the property looks over wooded area. An existing, unused, building is
to be demolished.
SITE CAPACITY
120 Brewer Lane
Able to provide comprehensive library services to all the
residents of southern Orange County
Yes
Meets minimum acreage
Yes
Space for building and on -site parking
Yes
Adequate utilities and availability
Yes
Space for future expansion (building to allow for additional
library services, parking, etc.) to serve the residents of
southern Orange County.
Sufficient flood space shall be available to accommodate anticipated library
based on County consultant and Library Project Team estimates.
Space to accommodate the necessary setbacks, road
expansions, and other site amenities
IYes
10
ACCESS
120 Brewer Lane
Property is downtown and will be adjacent to a proposed parking deck as well
as an existing sidewalk system affording pedestrian access off of Main Street.
The property is part of a master planned development with internal access
Accessibility for Pedestrians
points for various residential /non - residential uses located on -site.
Access would be off of Main Street and 'Brewer Lane' (undeveloped street
Accessibility for Vehicles
access)
Accessibility for public transportation
Public transportation access will be possible
Design capacity and existing traffic load of roadway proposed
Based on comments from Town of Carrboro this should not be an issue but will
Ito access sit
lhav e to be addressed by the developer as part of the permit review process.
11
ALIGNMENT WITH PLANNING TOOLS (COMPREHENSIVE PLAN)
LEASE VERSUS PURCHASE
120 Brewer Lane
Alignment with planning tools applicable for the subject
property (County Comprehensive Plan, adopted Small Area
Plans, Strategic Plans, etc.)
This property satisfies various 'goals' with respect to the location of a library
from both the County and Carrboro's standpoint.
Analysis of long -term viability of site
with the developer
LEASE VERSUS PURCHASE
120 Brewer Lane
This will be a lease /puchase situation for the County as part of an agreement
Analysis of long -term viability of site
with the developer
This will be a lease /puchase situation for the County as part of an agreement
Availability of property for lease
with the developer
12
CENTRALITY OF SITE
120 Brewer Lane
Site would provide access to existing and future, local, population. County
Existing and potential future population in given area
residents will have parking available to make use of the facility.
The size of the 'space' for the library will be limited to a lease /purchase
agreement with the developer. Expansion will be viable only if there are
Growth and development opportunities /constraints in a
vacancies in other proposed 'store fronts' allowing the County to
given area
lease /purchase for expansion.
Proximity to schools
Approxiamtely 2 miles from Carrboro elementary School
Proximity to retail
Will be in the heart of a retail /residential mixed use development.
Approxiamtely 4 miles from existing library located within the Town of Chapel
Proximity to other libraries
Hill
13
SITE CONDITIONS, ALLOWANCES, AND CONSTRAINTS
120 Brewer Lane
The cost - benefit conclusions of physical, legal, and land use
The County's Attorney (B. Ferrell) and Library Project Team have concluded
allowances /constraints
project is viable and constraints are either negligable or manageable.
Technical and environmental assessments (Planning /Zoning,
Developer will address permit process. Could involve a heightened level of
jurisdictional process, etc.)
permit review by Carrboro (i.e. Special Use Permit).
No apparent issues. Project can accomplish several stated goals of the BOCC
and Carrboro Board of Alderman with respect to the building /development
being sustainable. Please note library will only be a small component of the
Environmentally Sustainable (C and A, stormwater
total development of the property. The library project team cannot make
management, buffers, energy, 'net zero capacity')
committments on sustainability for the developer.
Operationally Sustainable
Yes.
Conceptual layout for library space maximizes adaptability for the library
Defeats obsolescence
overtime to address issues of obsolence.
14
COST AND AVAILABILITY
PHASE 2 - PUBLIC INPUT AND ASSESSMENT
COMMUNITY PREFERENCE
120 Brewer Lane
Input from Elected officials
Developer has indicated a strong desire to discuss lease /purchase options for a
Cost for site acquisition
space to house the library.
Orange Couty and Carrboro Friends of the Library
Developer has indicated a strong desire to discuss lease /purchase options for a
Availability of property for lease
space to house the library.
Property offers potential for reasonable expansion , assuming willingness of
developer and vacancies, and partnership opportunities to support long -term
Analysis of long -term viability of the site
provision of library services.
Pending on permitting from Carrboro but appeas consistent with establised CIP
Timeframe for development of site
program guidelines /timeframes
Terms of site control necessary for the development of the
site
Being handled by the developer
PHASE 2 - PUBLIC INPUT AND ASSESSMENT
COMMUNITY PREFERENCE
120 Brewer Lane
Input from Elected officials
Completed
Input from a broad cross - section of the area to be served
Completed
Orange Couty and Carrboro Friends of the Library
Completed
15
PARTNERSHIPS
120 Brewer Lane
Co- location with other private or public entity
Mutual beneficial joint development
Enhances service possibilities