HomeMy WebLinkAboutAgenda - 05-08-2014 - 7aORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: May 8, 2014
Action Agenda
Item No. 7 -a
SUBJECT: Cedar Grove Community Center Project Update
DEPARTMENT: Asset Management Services PUBLIC HEARING: (Y /N) No
( "AMS "), Department of
Environment, Agriculture,
Parks & Recreation ( "DEAPR ")
ATTACHMENT(S):
1) Base Plan Site Plan
2) Alternate Plan Site Plan
3) Preliminary Cost Estimate
Comparison
4) Alternate Plan Storage Illustrative
5) PowerPoint Presentation Located at
http : / /orangecountync.gov /AssetMg
mt /index.asp
PURPOSE: To:
INFORMATION CONTACT:
Jeff Thompson, (919) 245 -2658
David Stancil, (919) 245 -2522
Steve Brantley, (919) 245 -2326
1
1) Confirm the project plan as approved in the FY2013 -14 Capital Investment Plan and
presented to the Board of County Commissioners during the November 12, 2013 and
March 11, 2014 work sessions (Attachment 1, "Base Plan "); or
2) Amend the project plan by directing staff to maintain the classroom wings for future
occupancy and /or minimally conditioned storage available for both County
department and County tenant use (Attachment 2, "Alternate Plan "); or
3) Provide new direction to staff.
BACKGROUND: On November 12, 2013, County staff and its project designer, MBAJ
Architecture, presented the schematic design of the Cedar Grove Community Center for the
Board's comment and feedback. Staff and designer also presented a cost benefit analysis of
the "mothball" option of the two classroom wings.
The November 12, 2013 presentation was the capstone event of the work performed by the
designer, staff and the Resident Advisory Work Group through the summer and early fall of
2013. This group worked in a diligent, thoughtful and productive manner to achieve consensus
on a schematic design for the Board's review, comment, and, hopefully, authorization to move
forward with construction document preparation and construction bidding in the spring- summer
of 2014.
2
The following joined Commissioners Barry Jacobs and Renee Price as members of the
Resident Advisory Work Group:
Melinda Bradsher
Luther Brooks
Sue Florence
Jacqueline McConnell -Graf
Nancy Graves
Malcolm Hester
Sucovis Hester
Vivian Herndon Latta
Sheila Vanhook McDonald
David Ogburn
Clifford Rogers
Roger Traynham
Brenda Vanhook
Hattie Vanhook
Cumilla White
Staff and the designer provided additional information and responses to Board questions and
concerns during the March 11, 2014 work session. The feedback from the Board during these
two work sessions are reflected in two options for the Board's consideration:
Base Plan: Approximately 13,600 usable square foot community center, deconstructed
classroom wings, park & ride lot with bus shelter, including the additional 720 square
foot class rooms space as discussed during the March 11, 2014 work session (see
Attachment 1, "Base Plan ").
Alternate Plan: Base Plan plus the "mothball" renovation option for the classroom wings
for potential future use as well as interior wing renovations for County department or
County tenant storage (see Attachment 2, "Alternate Plan ").
The preliminary cost estimate comparison of both plans is reflected in the Attachment 3.
The Board may recall asking for more information with regard to immediate storage within the
classroom wings should the Alternate Plan be selected to move forward with in design. The
County has an immediate need for recycling roll cart storage and additional conditioned records
storage space. A County tenant, the Piedmont Food and Agricultural Processing Center
( "PFAP "), located at 300 Valley Forge Road in Hillsborough, is requesting additional dry storage
to accommodate its growth and program success. Attachment 4, "Alternate Plan Storage
Illustrative ", illustrates these potential needs and the storage spaces that could accommodate
the needs.
Steve Brantley, Director of Orange County Economic Development, will present the possible
economic development impacts of such a use for PFAP and Orange County. Should the PFAP
storage spaces be approved by the Board in concept, staff will work with PFAP on a rental use
and rate structure to be presented to the Board at a point in the future.
Should the Board approve moving forward with the Base Plan for this project, the general
development timeline would be as follows:
TASK
PROPOSED
BEGINNING
DATE
END BY
DATE
BOCC Action: Approval of either Cedar Grove Base Plan or
Alternate Plan
5/8/14
5/8/14
BOCC Action: Final approval of bid documents prior to bid
9/16/14
9/16/14
Project final design, bid document preparation
9/17/14
10/10/14
Project Bid process
10/10/14
11/13/15
BOCC Action: Bid Award
12/9/14
12/9/14
Construction, Commissioning, Opening (est. 8 months duration)
1/15/15
8/30/15
3
Should the Board choose moving forward with the Alternate Plan, an additional two months
would be required for the design phase of the project.
Concurrent to the design efforts, staff will moderate a process with regard to programming
needs and interests.
FINANCIAL IMPACT: The Board approved the FY2012 -17 Capital Investment Plan ( "CIP ")
that included $250,000 in FY 2012 -13 for deconstruction of sections of the facility in preparation
for the future use on the site. The Board also approved $2.0 million in FY2014 -15 for the
design and construction of the new facility that, when combined with the $250,000 authorized in
FY 2012 -13, brings the total project capital budget to $2,250,000.
Should the Board approve the Base Plan, the cost of the project is estimated at $2,363,526.
Estimated additional funds of $113,526 would need to be appropriated to the project. This total
project cost includes the additional classroom space discussed in the March 11, 2014 work
session, the potential park and ride lot shelter, and an increased construction contingency
amount (15 %) driven by the forecast increased construction costs as the economy continues to
improve.
Should the Board approve the Alternate Plan, the cost of the project is estimated at $3,072,226.
Estimated additional funds of $822,226 would need to be appropriated to the project. This total
project cost includes the additional elements discussed above in the Base Plan, plus the
estimated $708,700 needed for the Alternate Plan additional scope. This scope also includes
an estimated $75,000 for a dock door system to be installed for the potential PFAP or other
tenant use.
RECOMMENDATION(S): The Manager recommends the Board:
1) Confirm the project plan as approved in the FY2013 -14 Capital Investment Plan and
presented to the Board of County Commissioners during the November 12, 2013 and
March 11, 2014 work sessions ( "Base Plan "); or
2) Amend the project plan by directing staff to maintain the classroom wings for future
occupancy and /or minimally conditioned storage available for both County
department and County tenant use ( "Alternate Plan "); or
3) Provide new direction to staff.
444.78'
_
4
ATTACHMENT 1 �— —� _�.-- _ —
N8_400124- E
Fol
1.
o .
v 1 w s
CONNECTION
TO WALKING '
TRAIL
a
o�
o . 1
I o 1
Aim
I �
P X�E 1�
OPOL
__1- - - -- -- MEM
CONNECTION It 1
TO WALKING `
TRAIL
p4AZP
. 1 .
Preliminary Cost Estimate - Base Plan
General Conditions
172,712
Deconstruction & Abatement
294,881
Renovation
1,029,247
Site Work
253,255
Audio Visual
20,000
Construction Total
1,750,095
Construction Contingency (15 %)
262,514
Professional Fees
173,500
Cultural & Archaeological Study
5,000
Construction Materials Testing
15,774
Permits and Fees
2,000
Audio Visual
20,000
Signage
3,500
Furniture, Fixtures and Equipment
94,643
Additional Classroom
29,000
Park & Ride Shelter
7,500
Base Plan Total 2,363,526
Current Appropriation 2,250,000
Additional Funds Requested 113,526
Total Project Cost per Usable Square Foot 173
Attachment 3 6
Preliminary Cost Estimate - Alternate Plan
General Conditions 172,712
Deconstruction & Abatement 294,881
Renovation 1,029,247
Site Work 253,255
Construction Total 1,750,095
Construction Contingency (15 %) 262,514
Professional Fees
173,500
C &A
5,000
CMT
15,774
Permits and Fees
2,000
Audio Visual
20,000
Signage
3,500
Furniture, Fixtures and Equipment
94,643
Additional Classroom
29,000
Park & Ride Shelter
7,500
Classroom Wing Mothball Work
579,900
Classroom Wing Design Fees
28,800
Storage Improvements
100,000
Mothballed Wings /Storage Total
708,700
Alternate Plan Total
3,072,226
Current Appropriation
2,250,000
Additional Funds Requested 822,226
Mothballed Wings /Storage Cost per Usable Square Foot 50
COMMUNITY CENTER AREA
ATTACHMENT 4
CEDAR GROVE FACILITY
CURRENT GROSS SQUARE FOOTAGE: 30,782
EXISTING
WELL HOUSE
GROSS SQUARE FOOTAGE (15,491 SQFT) b TO REMAIN
PFVFF
USABLE SQUARE FOOTAGE (13,694 SQFT) I@
is
COAL BIN
(TO BE
REMOVED)
1..
7
POTENTIAL STORAGE AREAS
POTENTIAL STORAGE AREAS = GROSS SQFT (15,291)
POTENTIAL STORAGE AREAS = USABLE SQFT (14,228)
J PFAP (4,386 SQFT)
® DEAPR ( 1,462 SQFT)
RECORDS STORAGE (4,320 SQFT)
- ROLL CARTS (2,160 SQFT)
STORAGE AREA CORRIDORS (1,900 SQFT)