ACTION AGENDA ITEM ABSTRACT
Meeting Date: October 17, 2006
Action Agenda
Item No. ~ - P_..
SUBJECT: Approval of Chapel Hill-Carrboro City Schools Alternative Financed Capital
Project Ordinances for School Renovation Projects
DEPARTMENT: Budget PUBLIC HEARING: (Y/N) No
ATTACHMENT (S):
Attachment 1. Chapel Hill-Carrboro City
Schools Alternative Financed Renovation
Capital Project Ordinances
INFORMATION CONTACT:
Donna Dean Coffey 245-2151
PURPOSE: To approve Chapel Hill-Carrboro City Schools (CHCCS) alternative financed
capital project ordinances for school renovation projects.
BACKGROUND:
During the 2001 Capital Needs Advisory Committee meetings, CHCCS identified the need for
$11.1 million to renovate older school facilities. Commissioners agreed to fund the renovations
with alternative financing rather than include the items on the 2001 bond referendum. The
County's debt issuance plans, originally approved by the Board in September 2002, have
planned for debt financing the renovations. During the planning stages of Carrboro High
School, the Chapel Hill-Carrboro Board of Education requested, and the Board of
Commissioners approved, a plan that would defer $2.5 million in renovations of older facilities
towards construction of the new high school, leaving $8.6 million for renovations.
In spring 2006, the County issued $22 million in alternative financing which included $5.1 million
for CHCCS renovation projects. At the September 14, 2006 work session, Commissioners
approved plans that allowed for $3.5 million in debt issuance this fiscal year to complete
renovation work at CHCCS. Attachment 1 of this agenda abstract contains the CHCCS
renovation related capital project ordinances, and allows CHCCS to complete the associated
renovation work this year.
FINANCIAL IMPACT: Alternative financing for CHCCS renovation projects totals $8.6 million.
Anticipated debt service associated with CHCCS' portion of the two financing arrangements
totals $686,950 in fiscal year 2007-08 or the equivalent of .55 cents on the tax rate.
RECOMMENDATION (S): The Manager recommends that the Board of County Commissioners
approve the attached Chapel Hill-Carrboro City Schools (CHCCS) alternative financed capital
project ordinances for school renovation projects.
Chapel Hill-Carrboro City Schools
Alternative Financed Renovation Projects
Total Alterna#ive
Proiect Financing
Abatement Projects $120,000
Athletic Facilities $1,090,000
ClassroomlAcademlcRrea Improvements $625,000
Doors, Hardware and Canopies $187,437
Electrical Systems $20,000
Fire/Safety/Security Renovations $264,659
Indoor Air Quality Improvements $194,218
Mechanics} Systems . $2,034,000
Mobile Ciassroams $114,000
Paving and Parking Lot Renovations $65,044
Roofing Projects $3,015,000
Technology $223,686
Window Replacements $655,000
Total Chapel Hill Carrboro city Schools
Alternative Financed Renovation Projects
$8,fi00,000
Attachment i
Abafemenf Projects
Chapel Hill-Carrboro Cify Schools
Capital Projecf Qrdinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13..2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds far the District to comply wifh OSHA
regulations related to removal of hazardous building materials such as asbestos
flooring and ceiling tiles. Proceeds from the Schools' portion of the one-half cent
sales taxes and alternative financing fund this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The fallowing revenue is anticipated to complete this project:
Through FY
2005-06
FY 2006-07 Through FY
2006-07
Sates Tax $260,000 $D $260,000
im act Fees $0 $0 $0
PSBF $0 $D $0
1992 Bond Funds $0 $0 $0
1997 Bond Funds $0 $0 $0
Alternative Financin $0 $120,000 $120,000
Totat Funding $260,000 $120,000 $380,000
Section 4. The following amount is appropriated for this project:
Through FY
2005-06
FY 2006-07 Through FY
2006-07
Plannin /Arch/Engin $0 $0 $0
Land/AssocFees $0 $0 $0
Construction $260,000 $120,OOD $380,000
E ui ment/Furnishin s $0 $0 ~ $0
other $0 $0 $0
Contin enc $0 $0 $0
Tota[ Costs $260,000 $720,000 $380,000
Section 5. This ordinance supersedes previous CHCCS Abatement Capita! Projects,.
Section 6. This ordinance remains in effect from July 1, 2002 until June 30, 2007..
Adapted this 17th day of October 2006_
.q.
Athletic Facilities lmprovemenfis
Chapel Hill-Carrboro City Schools
Capifial Projecfi Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Catalina, the fallowing capital project is
hereby adopted.
Section 1. The project authorized provides funds to replace equipment and improve athletic
facilities at various schools throughout the L7istrict. Proceeds from the Schools'
portion of the one-half cent sales taxes and alternative financing fund this
project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project;
Through FY
2005-06
FY 2006-07 Through FY
2006-07
Sales Tax $ i ,287,387 $0 $1,287,387
Im act Fees $0 $0 $0
PSBF $0 $0 $0
Alternative Financing $210,000 $880,000 $1,090,000
1992 Bond Funds $0 $0 $0
9997 Bond Funds $0 $0 $0
Transfer from Scroggs
Elementary Gapital Project
$70,000
$0
$70,000
Total Project Funding $1,567,387. $880,000 $2,447,387
Section 4. The following amount is appropriated for this project;
Through FY
2005-06
FY 2006-07 Through FY
2D06-07
Plannin lArchlEn in $45,000 $0 $45,000
Lend/Assac Fees $0 $0 $0
Construction $1,522,387 $880,000 $2,402,387
E ui mentlFurnishings $0 $0 $0
Other $0 $0 $0
Contin enc $0 $0 $0
Total $1,567,387 $880,OtPD $2,447,387
Section 5. This ordinance supersedes all previous Athletic Facilities and Playgrounds
Capita( Project Ordinances for the Chapel Hill-Carrbara City Schools.
Section 6. This ordinance, originally adopted June 29, 1992, shall remain in effect until
June 3q, 2g07.
Adopted this ~ 7th day of October 2gg6.
ClassroomlAcademic Area Improvements
C_ hapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13..2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted,
Section 1. The project authorized provides funds to replace storage cabinets in classrooms
at Carrboro Elementary School, primary building casework and bathroom
renovations at Frank Porter Graham Elementary School, and support area
improvements at Phillips Middle School. Funding for the project tames from
proceeds from District's share of the one-half cent sales taxes and alternative
financing.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
roug
2005.06
FY 2006-07 raug
2006-07
Sales Tax $120,000 $0 $120,000
Im act Fees $0 $0 $0
RSBF $0 $0 $0
1992 Bond Funds $0 $0 $0
1997 Bond Funds $0 $0 $0
Alternative Financin $fi25,000 $0 $625,000
Total Funding $745,000 $0 $745,000
Section 4.The following amount is appropriated for this project:
Through FY
2005-06
FY 2006-07 Through FY
2006-07
Plannin lArchlEn in $0 $0 $0
LandlAssoc Fees $o $0 $o
Construction $745,000 $0 $745,000
E ui ment/Furnishin s $0 $0 $0
Other $0 $0 $0
Contingency $0 $0 $0
Total Costs $745,000 $0 $745,000
Section 5. This ordinance remains in effect from July 1, 2002 until June 30, 2007.
Adapted this 17th day of October 2006.
~P
Doors, Hardware and Canopies.
Chapel Hill-Garrboro Gity Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Comrnissianers that pursuant to 5ectian
13,.2 of Chapter 159 of the General Statu#es of North Carolina, the following capital project is
hereby adapted_
Section 1. The project authorized provides funds for interior and exterior doors, frames, and
hardware replacements of Culbreth Middle Sch~~~, Estes Hills Elementary
School, Phillips Middle School, and Chapel Hill High School. Proceeds from the
Schools' portion of the one-half cent sales taxes and alternative financing fund
this project.
Section 2. The officers of the County are hereby directed to proceed with the praject within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2005-06
FY 2006.07 Through FY
2006-07
Sales Tax $315,000 $32,563 $347,563
lm act Fees $0 $0 $t)
PSBF $0 $0 $0
1992 Bond Funds $0 $0 $0
1997 Bond Funds $0 $0 $0
Alternative Financin $120,000 $67,437 $987,437
Tota{ Funding $435,000 $700,000 $535,000
Section 4. The following amount is appropriated for this project:
Through FY
2005-06
FY 2006-07 Through FY
20.06»07
Plannin /ArchlEn in $0 $0 $0
Land/Assoc Fees $0 $0 $0
Construction $435,000 $100,000 $535,000
E ui ment/Furnishin s $0 $0 $0
Other $0 $0 $0
Contin enc $0 $0 $0
Total Costs $435,000 $100,000 $535,000
Section 5. This ordinance supersedes all CHCCS Doors, Hardware and Canopies Capital
Project Ordinances.
Section 8. This ordinance remains in effect from July 1, 2002 until June 30, 2007.
Adopted this 17th day of October 2006.
Electrical Systems
Chapel Hill-Carrboro City Schaots
Capital Rroject Ordinance
Se it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for the installation of additional electrical
outlets in the classrooms at Carrboro Elementary School. Funding far the project
comes from a transfer from CHCCS Elementary School #9 and proceeds from
alternative financing.
Section 2. The officers of the County are hereby directed to proceed with the praject within
the budget contained herein.
Section 3. The fallowing revenue is anticipated to complete this praject:
Through FY
200506
FY 2006.07 Through FY
2006-07
Sales Tax $0 ~ $0 $0
Im act Fees $0 $0 $0
PSBF $0 $0 $0
1992 Bond Funds $0 $0 $0
1997 Bond Funds $0 $0 $0
Transfer from Elementary
#~g
$125,000
$0
$125,000
Alternative Financing $0 $20,000 $20,000
Total Funding $125,000 $20,000 $145,000
Section 4, The following amount is appropriated far this project:
Through FY
2005-06
FY 2006-07 Through FY
2006-07
Planning/ArchlEngin $12,000 $0 $12,000
Land/Assac Fees $0 $0 $0
Construction $713,000 $20,000 $133,000
E uipmenflFurnishings $0 $0 $0
Other $0 $0 $0
Contingent $0 $0 $0
Total Costs $125,000 $20,000 $145,000
Section 5. This ordinance remains in effect from July 1, 2002 until June 30, 2007.
Adapted this 17th day of October 2006.
FirelSafety/Security Renovations
Chapel Hili-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13,2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adapted.
Section 1. The project authorized provides funds to replace the Fire Safety Systems at
various schools throughout the district. Proceeds from the Schools' portion of
the one-half cent sales taxes and alternative financing fund this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein,
Section 3. The following revenue is anticipated to complete this project;
Through FY
2005-06
FY 2006-07 Through FY
2006.07
Sales Tax $1,131,665 $0 $1,131,665
Impact Fees . $a $0 $0
PSBF $0 $0 $0
1997 Bond Funds $0 $0' $0
Savings an Construction
Gontracts
$90,235
$0
$90,235
Alternative Financin $d $264;659 $264,659
TotaE Project Funding $1,221,900 $264,659 $1,486,559
Section 4. The following amount is appropriated for this project:
Through FY
20D5-06
FY 2006-07 Through FY
2046-07
Plannin !Arch/En in $60,000 $0 $60,000
Land/Assoc Fees $0 $D $4
Construction $1,140,140 $264,659 $1,444,759
E ui ment/Furnishin s $21,84D $0 $21,8D0
Other $0 $0 $4
Cantin enc $4 $4 $0
.Total $9,221,900 $264,659 $1,486,559
Section 5. This ordinance supersedes ail .previous Fire/Safety/Security Capita{ .Project
Ordinances far the Chapel Hill-Carrboro City Schools.
Section 6. This ordinance, originally adopted June 30, 1997, shall remain in effect until
June 3Q, 2007. .
Adapted this 17th day of October 2006,
Indoor Air Quality Improvements
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Ghapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds for the specialized cleaning of old HVAC
equipment, classrooms, offices, and air ducts. Exterior brick painting and building
facade repairs are also included. Proceeds from the Schools' portion of the one-
half cent sales taxes finance and alternative financing fund this project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Secfian 3.The following revenue is anticipated to complete this project:
raug
2005-06
FY 2006-07 roug
2006-07
Sales Tax $95;782 $25,000 $120,782
Irn act Fees $0 $0 $0
PSBF $0 $0 $0
1992 Bond Funds $0 $0 $0
1997 Bond Funds $0 $0 $0
Alternative
Financin ,
$134,218
$60,000
$194,218
Total Funding $230,000 $85,000 $395,000
Section 4.The following amount is appropriated for this project:
Through FY
2005»06
FY 200607 Through FY
2006-07
Piannin /ArchlEn in $35,000 $0 $35,000
LandlAssac Fees $0 $0 $0
Construction $195,000 $85,000 $280,000
E ui ment/Fumishin s $0 $0 $0
Other $0 $0 $0
Contin enc $0 $0 $0
Total Costs $230,000 $85,000 $315,000
Section 5, This ordinance supersedes all CHCCS Fire/Safety/Security Systems Capital Project
Ordinances.
Section 6. This ordinance remains in effect from July 1, 2002 until June 30, 2007.
Adopted this 17~' day of October 2006.
1~
Mechanical Systems
Chapel Hill-Carrboro City Schools
Capifial Project Qrdinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to 5ectian
93.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.,
Section 'I. The project authorized provides funds to replace obsolete mechanical equipment
including bailers and electric heating and coaling systems. Proceeds from the
Schools' portion of the one-half cent sales taxes, alternative financing, and
transfers from completed projects within the District finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The follawing revenue is anticipated to complete this project:
Through FY
2005-06
FY 2006-07 Through FY
2005-06
Sales Tax $1,540,490 $p .$9,540,490
lm act Fees $0 $0 $0
PSBF $0 $0 $0
Transfers from Completed
Projects
$29 0,000
$0
$210,000
Alternative Financin $1,930,000 $900,000 $2,030,000
Total P'ro'ect Fun~din $3,680,490 $900,000 $3,780,490
Section 4. The follawing amount is appropriated for this project:
Through FY
2005-06
FY 2006-07 Through FY
2006-07
Plannin /Arch/En in $ S 12,000 $0 $912,000
Land/Assoc Fees $25,000 $0 $25,000
Construction $2,895,000 $100,000 $2,995,000
E ui ment/Furnishings $648,490 $0 $648,490
Other $0 $0 $0
Canon enc $0 $0 $0
Total $3,6$0,490 $100,000 $3,780,490
Section 5. This ordinance supersedes all previous Mechanical Systems Capital Project
Ordinances far the Chapel Hill-Carrboro City Schools.
Section G. This ordinance, originally adopted May 21, 1997, shall remain in effect until June
30, 2Q07.
Adopted this 17~h day of October 2006,
Mobile Classrooms
Chapel Hill-Garrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for the purchase of mobile classrvorns.
Proceeds from impact fees, pay-as-you-go funds and alternative financing fund
this project,
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The fallowing revenue is anticipated to complete this project:
Through FY
2005-06
FY 2006-07 Through FY
2006-D7
Sales Tax $280,000 $0 $280,000
Impact Fees $1,170,000 $0 $1,170,000
PSBF ~ $0 $D $0
1982 Bond Funds $D $0 $0
1997 Bond Funds $0 $.0 $0
Alternative Financing $0 $110,000 $110,040 .
To#al Funding $1,450,000 $110,OOD $1,560,000
Section 4. The following amount is appropriated for this project:
Through FY
2005-06
FY 2006-D7 Through FY
2006-07
Plannln !Arch/En in $0 $0 $0
LandlAssocFees $0 $0 $0
Construe#ion $i,45D,000 $0 $1,450,000
E ui ment/Furnishin s $0 $0 $0
Other. $0 $110,ODD $110,004
Contin eno $D $0 $0
To#al Costs $1,450,000 $110,000 $1,560,000
Section 5. This ordinance remains in effect from July 1, 2001 until June 30, 2007.
Adapted this 17~' day of October 2006.
lz
Paving and Parking Lot Renovations
Chapel Hill-Ca-°rboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to 5ectian I.3.2
of Chapter 159 of the General Statutes of North Carolina, the following capital project is hereby adopted.
Section 1. The project authorized provides funds to repair and pave existing driveways and parking..
Proceeds from Schools' portion of'the one-half cent sales tax and alternative financing fund
this project.
Section 2. The officers of the County are hereby directed to proceed with the project within the budget
contained herein.
Section .3. The following revenue is antici aced to complete this project:
TI-rougli FY
1005-OG FY 2006-07 TGraugIj FY 2006
07
Sales Tact $9GI,590 $0 $9GI,S90
Im act Fees $0 $0 $0
PSBF $0 $0 $0
I'997 Bond Funds $0 $0 $0
Alternative Financin $65,000 $0 $65,000
Total Fundin $I,OZG,590 $0 $1,02G,590
Section 4. The following amount is a propriated for this project:
Through FY
1005-OG FY 100G-07 Througi~ FY 200G-
07
Plannin lArcl~/En in $50,000 $0 $50,000
Land/Assoc Fees $0 $0 $0
Constriction $97G,S90 $0 $97G,S90
1; ui ment/Furnishings $0 $0 $U
Other $0 $0 $0
Contin enc $0 $0 $0
Tat11 Costs $1,02G,590 $0 $y,02G,590
Section 5. This ordinance supersedes all previous Paving and Parking L,ot Renovations Capital Project
Ordinances.
Section 5. This ordinance, originally adopted June 22, 1998, s11a11 remain in effect until June 30, 2007_
Adopted this 17`i' day of October 200G.
t3
Roofing Projects
Chapel Hill-Garrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the fallowing capital project is
hereby adapted..
Section 1. The project authorized provides funds to repair and replace roofs at many of the
schools in the district, Proceeds from the Schools' portion of the one-half cent
sales taxes, alternative financing, and transfers from completed projects within
the District finance this project.
Section 2. The.afficers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The fallowing revenue is anticipated to complete this project:
Through FY
2005-06
FY 2006-07 Through FY
2006.07
Sales Tax $683,626 $0 $883,626
Im act Fees $0 $0 $0
Alternative Financin $1,495,000 $9,520,000 $3,015,000
1992 Bond Funds $0 $0 $0
9997 Bond Funds $0 $0 $0
Transfers from Completed
Pro'ects
$488,500
$0
$488,500
Total Pro ect Funding $2,867,126 $1,520,000 $4,387,126
Section 4. The following amount is appropriated for this project:
Through FY
2005-D6
FY 2006-07 Through FY
2006-07
Plannin tArchlEn in $85,000 $120,000 $205,ODD
Land/AssocFees $0 $0 $0
Construction $2,782,126 $1',400,000 $4,182,126
E ui rrient/Furnishin s $0 $0 $0
Other $0 $0 $0
Conlin enc $0 $0 $0
Total $2,867.126 $1,520,000 $4,387,126.
Section 5. This ordinance supersedes all previous Renovations -Roofing Capital Projects
far the Chapel Hill-Carrboro City Schools.
Section 6. This ordinance, originally adopted July 1, 1998, shall remain in .effect until June
30, 2007.
Adopted this 17th day of October 2005.
~~
Technology
Chapel Hill-Carrboro City Schools
Capital Praject Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital Praject is
hereby adopted.
Section 1.The Praject authorized provides funds to upgrade instructional technology and other
systems throughout the district. Proceeds from the Schools' Portion of the one-half
cent sales taxes, alternative financing.and transfers from completed projects within
the District finance this Praject.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Thraugh FY
2005-06
FY 2006-07 Thraugh FY
2006-07
Sales Tax $9,823,816 $9,010,000 $10,833,816
Im act Fees $0 $0 $0
PSBF $0 $0 $0
rans er rom omp e e
Projects
$960,000
$0
$960,000
Transfer from East Chapel
Hill High Addition Savings
$0
$0
$0
Alternative Financing $223,686 $0 $223,686
Total Pro'ect Funding $11,007,502 $1,010,000 $12,017,502
Section 4.The following amount is appropriated for this project:
rang
2005-06
FY 2006-07 roug
2006-07
Plannin !Arch/En in $0 $0 $0
LandlAssoc Fees $0 $0 $0
Construction $0 $0 $0
E ui mentlFurnishings $11,007,502 $1,090,000 $12,017,502
Other $0 $0 $0
Contingency $0 $0 $0
Total $11,007,502 $9,010,000 $12,017,502
Section 5. This ordinance supersedes all previous Technology Capital Project Ordinances for
the Chapel Hill-Carrboro Gity Schools.
Section 6. This ordinance, originally adapted June 29, 1992, shalt remain in effect until June
30, 2007.
Adopted this 27th day of June 2006.
t'S
Window Replacements
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter # 59 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for the replacement of old and inoperable
windows at various elementary, middle, and high schools. Funding far the
project camas from savings from Public School Building Funds, savings from
other projects within the District and alternative financing.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The fallowing revenue is anticipated to complete this project:
Through FY
2005-06
FY 2006-07 Through FY
2006-07
Sales Tax $870,DDD $0 $87D,DD0
Im act Fees a0 $0 ~w0
PSBF $D• SO $0
1992 Bond Funds 5D $D $0
1997 Bond Funds $D $0 $D
Prc acts $D $0 $D
Alternative Financin $350,000 $345,DDD $655,000
Total Funding $1,220,000 $305,000 $1,525,000
Section 4. The following amount is appropriated for this project:
Through FY
2005-06
FY 2006-07 Through FY
2006-0?
Plannin /Arch/En in $a $25,DOa $25,aaa
Land/Assoc Fees $a $a $0
Construction $9,22a,aaa $28a,a00 $1,5aa,aa0
E ui rnentlFurnishin s $a $0 $0
Other $a $D $0
Contin enc $a $a $a
Total Costs $1,220,000 $305,000 $9,525,000
Section 5, This ordinance remains in effect from July 1, 2002 until June 30, 2007,
Adapted this 17h day of October 2006.