MEMORANDUM
To: Michael Talbert, Interim County Manager
Through: Craig Benedict, Planning Director n
From: Kevin Lindley, PE, Staff Engineer
Date: January 6, 2014
RE: Buckhorn Mebane Phase 2 Utility Project Change Order#2
This change order combines two change order requests submitted by the
Contractor to the County's engineering consultant in late August and mid-
September. The first of these two requests asked for 8 extra days due to inclement
weather, as shown on the supporting documentation. The second request was for
extra cost required to resurvey/layout the sewer line across the Rohl property north
of West Ten Road. This was a County-initiated shift in sewer alignment made
necessary based on the results of the Cultural and Archaelogical Survey performed
pursuant to County Policy. This cost can be covered by the existing project
budget. It will be paid out of a portion of the budget set aside as an easement
resolution contingency.
The costs of this change order have been summarized below, along with the
summary for Change Order#1. Going forward, new change orders can be added
to the summary so that all the change order information will be available in one
document.
Original Contract Price: $4,016,545.74
- Original rock contingency for water line: $ 67,500.00 (included)
CO#1 $ 15,328.00
. . z
- Extra work to avoid an unmarked 16" force main
- Reroute a 4" water main
- Delays due to easement dispute
- Revised rock contingency for water line: $ 52,172.00
Net Contract Price Change for CO#1: $ 0.00
CO#2 $ 2,242.50
- Cost due to resurveying/relayout of sewer S-1
- Done to avoid a potentially significant
cultural/archaeological site on the Rohl
property
Revised Contract Price after Change Orders: $49,0189788.24
SCHEDULE
The project start date was 4/16/2013. Based on the original schedule the allowed
substantial completion date would have been 4/16/2014, or 365 days. C0#1 added
an additional 57 days due to delays in obtaining easements and the time to
complete the extra work. This extended the contractually allowed substantial
completion date to 6/12/2014.
CO#2 requests an additional .8 days due to inclement weather, which would push
the allowed substantial completion date out to 6/20/2014.
Please call or email with any questions.
Change Order
No. 2
Date of Issuance: 12/10/13 Effective Date: 12/15/13
Project:Buckhorn-Mebane EDD Water and Owner: Orange County owner's Contract No.:
Sewer Improvements
Contract: Date of Contract:
contractor:JF Wilkerson Contracting Co., Inc. Engineers Project No.: OC1 O01
The Contract Documents are modified as follows upon execution of this Change Order:
Description:Cost reflects charges for delays due to surveying change on realignment due to
archaeological survey and additional time for easement delays and weather conditions
Attachments: (List documents supporting change):
Funds for change order are available in contract.All quantities at cost will be balanced
on the final adjusting change order.
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price: Original Contract Times: ❑ Working days X Calendar days
Substantial completion(days or date):365
$4,016,545.74 Ready for final payment(days or date):395
[Increase][Decrease]from previously approved Change [Increase][Decrease] from previously approved Change Orders
Orders No.-011 to No-01 No. to No.
Substantial completion(days):422
$0.00 Ready for final payment(days):452
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial completion(days or date):422
$4,016,545.74 Ready for final payment(days or date):452
Increase [Decrease]of this Change Order: Increase [Decrease]of this Change Order:
Substantial completion(days or date):8
$2,242.50 Ready for final payment(days or date):8
Contract Price incorporating this Change Order: Contract Times with all approved Change Orders:
Substantial completion(days or date):430
$4,018,788.24 Ready for final payment(days or date):460
RECOMMENDED ACCEPT CEPTED:
By: By: By
Engineer(Authorized Signature) Owner uthori d Sig lure) Contra r(Authorized Signature)
Date: Z Date: Date:
This instrumerihas b4en pre-audited in the
Approved by Funding Agency(if applicabli?anner required by the Local Government Date:
/j/&Budget an I Control Act
EJCDC No.C-941(2002 Edition) Clarence G. Grier,Assistant Co. Manager& Page 1 of 2
Prepared by the Engineers'Joint CoWQt Documents Committee and endorsed by the
Associated General Contractors of America and the Construction Specifications Institute.
Change Order
Instructions
A. GENERAL INFORMATION
This document was developed to provide a uniform format for handling contract changes that affect
Contract Price or Contract Times. Changes that have been initiated by a Work Change Directive must be
incorporated into a subsequent Change Order if they affect Price or Times.
Changes that affect Contract Price or Contract Times should be promptly covered by a Change Order.
The practice of accumulating Change Orders to reduce the administrative burden may lead to
unnecessary disputes.
If Milestones have been listed in the Agreement, any effect of a Change Order thereon should be
addressed.
For supplemental instructions and minor changes not involving a change in the Contract Price or Contract
Times, a Field Order should be used.
B. COMPLETING THE CHANGE ORDER FORM
Engineer normally initiates the form, including a description of the changes involved and attachments
based upon documents and proposals submitted by Contractor, or requests from Owner, or both.
Once Engineer has completed and signed the form, all copies should be sent to Owner or Contractor for
approval, depending on whether the Change Order is a true order to the Contractor or the formalization of
a negotiated agreement for a previously performed change. After approval by one contracting party, all
copies should be sent to the other party for approval. Engineer should make distribution of executed
copies after approval by both parties.
If a change only applies to price or to times, cross out the part of the tabulation that does not apply.
EJCDC No.C-941(2002 Edition) Page 2 of 2
Prepared by the Engineers'Joint Contract Documents Committee and endorsed by the
Associated General Contractors of America and the Construction Specifications Institute.
J.F. Wilkerson Contracting Co., Inc.
PO Box 183
Morrisville, NC 27560
CHANGE ORDER REQUEST
Engineer: Hobbs Upchurch Associates
Owner: Orange County
Contractor: J.F. Wilkerson
Job: Buckhorn—Mebane EDD Phase 2
Project Manager: Michael Coates
Request number: 4
Date: May 6,2013 through August 21,2013
Description of extra work/materials:
No extra compensation on this request,only lost days due to inclimate weather
Rain days as follows:
Date Time Request
5/6/13 9:30 AM(Heavy) 1 Day
5/20/13 1:30 PM (T Storm) %Day
6/3/13 7:00 AM (Steady) 1 Day
6/6/13 12:30 PM (Hard rain) %a Day
6/7/13 7:00 AM(Steady) 1 Day
6/10/13 7:00 AM (Steady) 1 Day
7/1/13 7:00 AM (Heavy) 1 Day
7/3/13 1:45 PM (T Storm) % Day
7/9/13 2:45 PM (T Storm) '/e Day
8/19/13 7 AM (Intermittent) 1 Day
8/21/13 2:00 PM(4"Storm) % Day
Total Time Lost due to weather: 8 Days
Total additional days added to the contract request: 8 Days
• + s
J.F. Wilkerson Contracting Co., Inc.
PO Box 183
Morrisville,NC 27560
CHANGE ORDER REQUEST
Engineer: Hobbs Upchurch Associates
Owner: Orange County
Contractor: J.F. Wilkerson
Job: Buckhom—Mebane EDD Phase 2
Project Manager: Michael Coates
Request number: 5
Date: September 17, 2013
Description of extra work:
Meeting,planning,surveying Sewer Line S-1 re-alignment from MH 14 to MH 18
because of archeological survey
Request for compensation:
Labor
Project Manager V4 Day(office&field)@ 1000 250
Travel time %day @ 1000 250
Foreman Jimmy Gray%2 Day @ 500 250
Surveying new alignment LS 1,200
Total of all labor,surveying,etc. 1,950
15% Overhead/profit allowed 292.50
Total Change Order this request $2,242.50
Request for additional Days: 0 day