g `? 9- d '�i�Z 15
RESOLUTION
OF THE
ORANGE COUNTY BOARD OF COUNTY COMMISSIONERS
TO APPROVE A
CLASS A SPECIAL USE PERMIT
FOR
LAWRENCE PARK PLANNED DEVELOPMENT
Date June 1, 1999
Owner/Applicant Meadowmont Farms, LLC
The Change County Board of County Commissioners hereby approves an
application submitted by Meadowmont Farms, LLC, for Lawrence Park Planned
Development Class A Special Use Permit and the preliminary plat dated
September 28, 1998, and last revised November13, 1998, subject to the
following conditions:
1. Existing and proposed vegetation shall be installed and/or maintained as
indicated on the Landscape Plan.
2. The submitted draft homeowners association documents and restrictive
covenants to address use and maintenance of the recreation and open
space areas shall be reviewed and approved by the County Attorney.
3. Security shall be submitted by the applicant and approved by the County
Attorney guaranteeing the construction of all improvements. Security may
be posted on a Phase by Phase basis. However, all improvements in each
phase must be complete before construction may begin on a new phase.
The amount of the security shall be 110 percent of the estimate.
4. Water and Sewer improvements shall be constructed to Town of
Hillsborough standards.
g:\plandev\pd398\app_sup.res\5-26-99\kI
16
5. All road improvements shall be constructed to NCDOT standards.
Improvements proposed for Lawrence Road shall be constructed in Phase
One. Improvements proposed for US 70A shall be constructed in Phase
Two. The extension of Lori Drive shall be constructed from Dunston Way to
Lannie Drive in Phase Three.
6. Stringent erosion control measures shall tie installed where soil is disturbed
and maintained until project completion.
7. A stormwater management plan must be developed and approved by the
Division of Water Quality before construction activities begin.
8. A minimum 25 foot riparian buffer zone should be maintained along any
small streams or wetlands identified on the site.
9. Unavoidable impacts to any wetlands or streams on the sight must be
coordinated with the US Army Corps of Engineers and NC Division of Water
Quality. Mitigation might be required for impacts to these areas.
10. The developer shall notify Planning staff when construction is to
commence.
11. The Special Use Permit will automatically expire within 12 months from the
date of approval if the use has not commenced or construction has not
commenced or proceeded unless a timely application for extension of this
time limit is approved by the Board of County Commissioners as provided in
8.4.11 of the Orange County Zoning Ordinance.
12. If any condition of this Special Use Permit shall be held invalid or void, then
this Special Use Permit shall be void in its entirety and of no effect.
g:\plandev\pd398\app_su p.res\5-26-99Vd