HomeMy WebLinkAboutORD-2000-108 County Facilities Roofing Projects Capital Project Ordinance t� �t ,o - Z000 - JOB oao .
County Facilities Roofing Projects Y b
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section 13.2
of Chapter 159 of the General Statutes of North Carolina,the following capital project is hereby adopted.
Section 1. The project authorized provides funds to conduct a study on the maintenance and
replacement schedule including cost estimates on the roofs of all County Buildings.
The money appropriated will address high priority projects like Whiffed Human Services,
Animal Control Building, The Jail and the house located on the Southern Human Services
Campus. This project will be financed by proceeds from the County's portion of the one-half
cent sales taxes and an appropriation from the County Capital Fund Balance.
Section 2. The officers of the County are hereby directed to proceed with the project within the budget
contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
1999-00 FY 2000-01 2000-01
Sales Tax $583,000 $0 $583,000
Bond Funds $0 $0 $0
Private Placement $0 $0 $0
Fees $0 $0 $0
County Capital Fund Appropriated
Fund Balance $0 $100,100 $100,100
Total Funding, $583,000 $100,100 $683,100
Section 4. The following amount is appropriated for this project:
Through FY Through FY
1999-00 FY 2000-01 2000-01
Land/Building $0 $0 $0
Design $53,000 $15,000 $68,000
Construction $0 $0 $0
Roofing Construction $530,000 $85,100 $615,100
Total Costs $583,000 $100,100 $683,100
Section 5. This ordinance supersedes all previous County Facilities Roofing Projects Capital Project
Ordinances.
Section 6. This ordinance shall remain in effect from July 1, 1998 until June 30, 2001.
Adopted this 29h day of June 2000.
The Board approved a lease for Suite 105 at 501 West Franklin Street, Chapel Hill, NC to
ebb
Brokerage Resource, Inc. for$1,100.00 per month and taxes-in-lieu of$100 per month.
Y. Bid Award—Leachate Collection Piping
The Board awarded a bid for Leachate Collection Piping for$26,241.33.
Z. Bid Award—Orange Coun Landfill Phase 4 Construction Geosynthetics
The Board awarded a bid for Phase 4 Construction - Geosynthetics at the Orange County
Landfill to Clary Hood, Inc. of Kissimmee, Florida in the amount of$346,000 and authorized the
Purchasing Director to execute the necessary paperwork, and authorized the County Manager to
execute change orders as may be necessary during the course of the installation, to the extent project
funds are available for this work.
Other bids received are listed below:
Reynolds - $432,500
Clary Hood - $346,000
Plastic Fusion - $450,479
Serrot International, Inc. - $457,906.60
aa. Bud-get Amendment#13
The Board approved budget ordinance amendments, grant project ordinance, and a capital
project ordinance for fiscal year 1999-2000.
bb. Adoption of 2000-2001 Grant and Capital Proaect Ordinances
The Board approved grant project ordinances and selected capital project ordinances in
accordance with the actions taken by the Board of Commissioners at the June 20, 2000 budget work
session.
cc. Chance in Board of Commissioners' Meeting Schedule
The Board approved a change in the Board of Commissioners' meeting schedule to change
the joint meeting with the two school boards from September 21, 2000 to September 25, 2000.
VOTE ON THE CONSENT AGENDA: UNANIMOUS
ITEMS REMOVED FROM THE CONSENT AGENDA
b. Minutes
motion was made by Commissioner Gordon, seconded by Commissioner Jacobs to
approve the highlighted draft of the minutes for March 21st and the minutes for March 23`d with the
changes as shown on the green sheet.
VOTE: UNANIMOUS
m. Contract for Orange County Video Production
The Board considered approving a contract with Horizon Video Productions, Inc. to produce a
10-12 minute video about Orange County's departments and services to be presented at new employee
and board and commission orientation sessions, to citizens on cable access television, and to
community, civic, and educational groups.
Commissioner Brown said that her interest in this was that the Commissioners have not had
any opportunity to discuss it and what it would be like. She would either like to hold this item and the
next item to have a presentation on it, or to put some very specific language in the contract specifying
when the Commissioners would be part of the review process.
Commissioner Jacobs said that there were three separate communication efforts going on —a
message to the people, an update of the web site, and this video. He does not see that these three are
in any way coordinated and he would like to see it be a coherent message.
Commissioner Gordon said that there could be some language added to say that the video,
the web site, and the message to the people would articulate a common and coherent theme and
message. Also, the Board of Commissioners would approve the effort at key intervals to be identified by
the Commissioners. This common theme is specified in the Strategic Communications Plan.
Commissioner Brown suggested having a presentation on both of the project concepts—the
web site design and the video— by the proposed companies so that the Commissioners could see what