HomeMy WebLinkAbout2000 S Solid Waste - Quality Assurance Technical Assistance Contract for Landfill Cell #4 Liner STATE OF NORTH CAROLINA AGREEMENT FOR
COUNTY OF ORANGE CONSTRUCTION QUALITY
ASSURANCE SERVICES
This Agreement made and entered into by and between the County of Orange herein
"County", acting in its capacity as administrator of the Orange Regional Landfill, and
Draper Aden Associates, herein"Consultant" for services as hereinafter described for the
County of Orange County.
WITNESSETH
That for and in consideration of the mutual promises and conditions set forth below, the
Consultant and County agree:
1. Duties of Consultant: Consultant agrees to provide services as described in Exhibit A
attached hereto and incorporated herein by reference.
2. Duties of the County: The County shall pay for Consultant's services as set forth in
Exhibit A and incorporated herein by reference.
3. Billing and Payment: Consultant shall submit regular invoices for work performed and
shall be paid.for completion of the work performed during that period under the terms
of this Agreement. Consultant shall bill and County shall pay at the rate and frequency
set forth herein Exhibit A. Payment shall be made by the County within thirty(30)
days of receipt of an accurate invoice. The value of this contract is not to exceed
$56,652, except as agreed by the parties.
4. Amendment : This agreement may be amended or cancelled by mutual agreement of
the County and the Consultant. Either the County or the Consultant may terminate
this Agreement at any time with or without cause upon giving the other party 21
calendar days prior written notice. The County shall within sixty calendar days of
termination pay the Consultant for all services rendered and all costs incurred up to
the date of termination, in accordance with the compensation provisions of this
contract.
Any amendments to the contract are not valid unless signed by the Chairman of the
Board of County Commissioners.
5. Insurance Provisions
a. Worker's Compensation: Coverage to apply for all employees for statutory limits
in compliance with the state and federal laws. The policy must include employer's
liability with a limit of$100,000 each accident, $100,000 bodily injury by disease
each employee and$500,000 bodily injury by disease policy limit.
b. Comprehensive General Liability: Shall have minimum limits of$1,000,000 per
occurrence combined single limit for bodily injury, liability and property damage
liability. This shall include premises and/or operations, independent contractors,
products, and/or completed operations,broad form property damage and
explosion, collapse and underground damage coverage and a contractual liability
endorsement.
c. Professional Errors and Omissions Liability: Coverage shall have minimum limits
of$1,000,000 per claim and $1,000,000 aggregate.
d. Additional Insured: The County of Orange is to be included as an additional
insured on the Comprehensive, General Liability. This requirement is to be stated
on the Certificate of Insurance.
e. Insurance Policies: Current, valid insurance policies meeting the requirements
herein identified shall be maintained during the duration of the named project.
Renewal certificates shall be sent to the Town thirty(30) days prior to any
expiration dates. There shall also be a 30 day notification to the Town in the event
of a cancellation or modification of any stipulated insurance coverage. Certificate
of insurance meeting the required insurance provisions shall be forwarded to
the County of Orange. Wording on the certificate which states that no
liability shall be imposed upon the company for failure to provide such notice
is not acceptable and should be deleted. Original policies or certified copies of
policies may be required by the County at any time.
f. Certificates of Insurance for all the insurance coverages described herein shall be
submitted to the County upon execution of a contract by Consultant.
g. All insurance required under this agreement shall be written with a company
licensed to do business in North Carolina. Certified copies insurance policies may
be requested by the County.
6. Hold Harmless: Consultant agrees,to indemnify and hold the County harmless from
any damage, liability or cost(including reasonable attorneys'fees and costs of
defense)to the extent caused by the Consultant's negligent acts, errors or omissions
in the performance of professional services under this Agreement and those of his or
her subconsultants or anyone for whom the Consultant is legally liable.
The Consultant is not obligated to indemnify the County in any manner whatsoever
for the County's own negligence.
7. Claims_The parties agree to attempt to resolve any dispute without resort to
litigation. However, in the event a claim is made that results in litigation, and the
claimant fails to prevail,then the claimanLshall pay all costs incurred in defending
the claim, including reasonable attorney's fees. The claimant will be considered to `
have prevailed if the judgement obtained and retained through any applicable appeal
is at least ten percent greater than the sum offered to resolve the matter prior to the
commencement of trial. Any litigation between the County and Consultant under
this agreement shall be filed and tried only in a court of competent jurisdiction within
Orange County,North Carolina.
8. Term: This Agreement, unless amended as provided herein, shall be in effect from
June 6, 2000 through November 30, 2000.
IN WITNESS WFMREOF,the parties acting hereto have set their hands as this 6th day of June,2000.
County of Orange,a NC
Cipal Corpor n
County Co
Draper Aden Associates mmr
B
Ti ie-
Address:
8090 Villa Park Drive
Richmond,Virginia 23228
Witne
Section IV.1 QA Team Organization
x
JEFFREY T. CRATE, P.G. Draper Aden Associates QA Team will be led by Mr. Jeffrey T. Crate,
P.G. Jeff is Vice President of Solid Waste Management Services and will
serve as the Principal-in-Charge for this project.
Jeff has served in the capacity of Project Engineer, Chief Hydrogeologist
and Project Manager for more than 200 solid waste management,
hazardous waste and environmental projects over the past 25 years. His
work experience encompasses the eastern United States and abroad. He is
currently responsible for the coordination and oversight of solid waste
management planning and design, groundwater monitoring, site
characterizations and remediation projects. He plays a significant role in
corporate strategic planning, staffing and project resource allocation as it
relates to these fields.
Mr. Crate will ensure that all necessary resources of the firm are allocated
to the Town of Chapel Hill for the duration of this project.
KENNETH M. PIAZZA, JR., The Senior Project Engineer (QAE) for this project is Mr. Kenneth
P.E. M. Piazza, Jr., P.E. Ken is an Associate in the firm and is the
Director of Geotechnical/Construction Administration as well as
the Geoteclmical Team Leader.
Ken is responsible for managing geotechnical and environmental
aspects of projects and for preparing technical reports. He provides
construction management, inspection and QA/QC review services
for a wide variety of landfill building and infrastructure
construction projects. Ken serves as the director of Draper Aden
Associates' in-house soils laboratory, whim provides soil testing
services to evaluate soil strength and other physical properties.
GREG DAUPHIN Draper Aden Associates' Project Manager for this project is Mr.
Greg Dauphin. Greg is responsible for technical performance of
both construction management and geotechnical engineering
services. He is responsible for performance of subsurface
explorations, field and laboratory test programs, data reduction and
analysis and design recommendations. In addition to project
management responsibilities. Greg also prepares and present
technical presentations.
The following page contains an organization chart for'this
project..
Detailed resumes of all team members are found in Section H.
Section IV.2 Communications
a
CA
Draper Aden Associates anticipates that there will be frequent
communication and interaction between Draper Aden Associates'
project personnel and the owner. The goal will be to listen, and
then listen some more, to completely understand the needs and
the desires of the Town of Chapel Hill as they relate to the
design,operation,and economic issues of the project.
The CQA services which Draper Aden Associates will provide
include the performance of QA Engmeeting, Construction
Management and QC soils testing in accordance with the project
plans and specifications.
In order to improve communication, and provide potential savings
to the Town of Chapel Hill. Draper Aden Associates can provide a
highly qualified QA Officer (QAO) on site full time to provide
both general CM Services and QC soils testing services for the
contractor during.the placing of the soil component of the liner
system. Draper Aden Associates' QA Engineer will perform
weekly site visits with routine attendance at job site meetings to
update progress, provide testing clarification and monitor the
performance of the contractor. As part of this scope of work,
Draper Aden Associates construction administration services will
include items such as coordinating job site meetings, processing of
submittals, maintaining submittal review files, updating
construction schedules, interpreting construction documentation,
processing change orders and reviewing contractor pay requests.
The QA Officer (QAO) will provide on-site monitoring of the
construction operations and perform soils and aggregate quality
control sampling, monitor synthetic conformance testing, and
additional testing and reporting mandated by the specifications. He
will maintain daily logs, test records and certificates in a well-
organized, tabulated mazmer. The QAO will notify the contractor
immediately of non-complying test results and will be available to
verify remediation and retesting of non-complying work. He will
maintain an awareness of the project in order to detect conditions,
which may directty or indirectly jeopardize the integrity of the
project.
Upon completion of the project,the QAE, CM, and QAO will work
in direct communication with Chapel Hill personnel to prepare the
Section IV.2 Communications
Page 2
Final CQA Permit documentation. These are the Certificate
Documents that must be submitted to the DEQ. The final
documentation will be organized and indexed to enable easy access
and retrieval of original inspection, testing data sheets, material
certifications,reports and the record drawings.
i
r Section IV.3 The QA Role for This Project
PART I GENERAL The Quality Assurance (QA) program shall be maintained for all
REQUIREMENTS Soil Liner (SL) construction activities. A Quality Assurance
Officer (QAO) shall be responsible for the implementation of the
quality control program.
The QA program shall consist of all construction and
administrative activities related to the SL to control the overall
quality of the SL. The program shall be implemented by Draper
Aden Associates. See Section II of this proposal personnel
resumes. Quality shall be defined as the level of effort, materials,
means or methods used which meet the minimum requirements as
specified in the Project Documents. Administrative items included
in the QC program include project QC submittals, field logs, and
record drawings.
All soils testing shall be performed in-house by our qualified
testing laboratory. The soils testing laboratory has participated in
an inspection program conducted by the National Institute for
Science and Technology or the U.S. Army Corps of Engineers
within the past 2 years. A soils testing laboratory representative
shall be present on site during all construction operations which
require quality control testing or observation as per the project
specifications.
Time schedules for Quality Control testing will closely follow the
Contractor's proposed schedule, and will be adjusted during
construction as per the Contractor's schedule.
The CQA services which Draper Aden Associates will provide
include the performance of QA Engineering, Construction
Management and QC soils testing in accordance with the project
plans and specifications.
In order to improve communication, and provide potential savings
to the Town of Chapel FE11. Draper Aden Associates can provide a
highly qualified QA Officer (QAO) on site full time to provide
both general CM Services and QC soils testing services for the
contractor during the placing of the soil component of the liner
system. Draper Aden Associates' QA Engineer will perform
weekly site visits with routine attendance at job site meetings to
update Progress, Provide testing clarification and monitor the
performance of the contractor. As part of this scope of work,
Draper Aden Associates construction administration services will
include items such as coordinating job site meetings, processing of
Section IV.3 The QA Role for This Project
PART GENERAL The Quality Assurance (QA) program shall be maintained for all
REQUIREMENTS Soil Liner (SL) construction activities. A Quality Assurance
Officer (QAO) shall be responsible for the implementation of the
quality control program.
The QA program shall consist of all construction and
administrative activities related to the SL to control the overall
quality of the SL. The program shall be implemented by Draper
Aden Associates. See Section 11 of this proposal personnel
resumes. Quality shall be defined as the level of effort, materials,
means or methods used which meet the minimum requirements as
specified in the Project Documents. Administrative items included
in the QC program include project QC submittals, field logs, and
record drawings.
All soils testing shall be performed in-house by our qualified
testing laboratory. The soils testing laboratory has participated in
an inspection program conducted by the National Institute for
Science and Technology or the U.S. Army Corps of Engineers
within the past 2 years. A soils testing laboratory representative
shall be present on site during all construction operations which
require quality control testing or observation as per the project
specifications.
Time schedules for Quality Control testing will closely follow the
Contractor's proposed schedule, and will be adjusted during
construction as per the Contractor's schedule.
The CQA services which Draper Aden Associates will provide
include the performance of QA Engineering, Construction
Management and QC soils testing in accordance with the project
plans and specifications.
kill
In order to improve communication, and provide potential savings
to the Town of Chapel Hill. Draper Aden Associates can provide a
highly qualified QA Officer (QAO) on site M time to provide
both general CM Services and QC soils testing services for the
contractor during the placing of the sod component of the liner
system. Draper Aden Associates' QA Engineer will perform
weekly site visits--with routine attendance at job site meeiiM to
update progress, provide testing clarification and monitor the
performance of the contractor. As part of this scope of work,
Draper Aden Associates construction administration services will
include items such as coordinating job site meetings, processimg of
■
Section IV.3 The QA Role for This Project
Page 2
submittals, maintaining submittal review files, updating
construction schedules, interpreting construction documentation,
1 processing change orders and reviewing contractor pay requests.
The QA Officer (QAO) will provide on-site monitoring of the
construction operations and perform soils and aggregate quality
control sampling, monitor synthetic conformance testing, and
additional testing and reporting mandated by the specifications. He
will maintain daily logs, test records and certificates in a well-
organized, tabulated manner. The QAO will notify the contractor
immediately of non-complying test results and will be available to
verify remedwhon and retesting of non-complying work. He will
maintain an awareness of the project in order to detect conditions,
which may directly or indirectly jeopardize the integrity of the
project.
Upon completion of the Project,the QAE, CM, and QAO will work
in direct communication with Chapel Hill personnel to prepare the
Final CQA Permit documentation. These are the Certificate
Documents that must be submitted to the DEQ. The final
documentation will be organized and indexed to enable easy access
and retrieval of original inspection, testing data sheets, material
certifications,reports and the record drawings.
Inspection and testing of the Test Pad, Soil Subgra4 and Soil
Liner are outlined in the sealed bid
I {
tw `tA Section 1VA Quality Control Testing
4
w4�`
jThe Quality Control program will include all construction and
administrative activities related to the soil liner to control the overall
quality of the soil liner. Time schedules for Quality Control testing will
closely follow the Contractor's proposed schedule and will be adjusted
during construction as per the Contractor's schedule.
All soils testing will be performed in-house by our qualified testing
laboratory. Inspection of the structural fill, low permeability soil, GCL,
drainage layer, diversion berms, slope drains, rip-rap ditches, access
roadways and seeding and mulching will be performed on a full time
schedule, as required Inspection of erosion control will be performed
throughout the project to ensure compliance with the approved Erosion
and Sediment Control Plan..
If applicable, material for the borrow study will be sampled from the
borrow site or taken from stockpiles. The borrow source will be
documented and approved by the Engineer prior to use.
Prior to the low permeability soil and GCL placement, the base will be
prepared--smooth,free of surface defects and proof rolled
The Contractor will construct a test pad to determine if the required
permeability can be obtained using the specified compaction equipment
and lift thickness. The test pad will be used to check if the methods used
to reduce clods in the soil (if applicable), interconnect lifts and compact
the soil liner are sufficient to remold the soil and achieve the required
Permeability.
At the completion of phases of the project, Quality Control Reports and
testing will be compiled and certified by the Quality Control Engineer.
The reports will present all test results and test locations;both horizontal
and vertical.
,s
We will use the services of the following testing laboratory:
Precision GwMrthetic Laboratories
11817 Watercr+ea"Court
Austin,Texas 78733
4/28/00
QA/QC Non-Binding Fee Estimate
Orange Regional Landfill, Phase 4
Minimum frequency based on Permit Documentation
by: TAM
Work Item Quantity Units Rate Total
Borrow Area Investigation
Soil Liner
Moisture Content 18 each $ -
Sieve Analysis 18 each $ 45.00 $ 810.00
Atterberg Limits 4 each $ 45.00 $ 180.00
Specific Gravity 2 each $ 45.00 $ 90.00
Standard Proctor 4 each $ 110.00 $ 440.00
Recompacted Flexwall Permeability 12 each $ 200.00 $ 2,400.00
Total $ 3,920.00
Structural Fill
Moisture Content 1 each $ -
Atterberg Limits 1 each $ 45.00 $ 45.00
Sieve Analysis 1 each $ 45.00 $ 45.00
Standard Proctor I each $ 110.00 $ 110.00
Total $ 200.00
Aggregates
Sieve Analysis 3 each $ 35.00 $ 105.00
Aggregate Permeability 3 each $ 100.00 $ 300.00
Total $ 405.00
Total Borrow Testing Costs $ 4,525.00
Laboratory Construction Testing
Test Pad
Flexwall Permeability 6 each $ 200.00 $ 1,200.00
Recompacted Permeability 3 each $ 250.00 $ 750.00
Moisure Content . 3 each $ - $ -
Sieve Analysis 3 each $ 45.00 $ 135.00
Atterberg Limits 3 each $ 45.00 $ 135.00
Standard Proctor 3 each $ 110.00 $ 330.00
Total $ 2,550.00
Soil Liner Placement
Sieve Analysis 27 each $ 45.00 $ 1,215.00
Atterberg Limits 27 each $ 45.00 $ 1,215.00
Flexwall Permeability 27 each $ 200.00 $ 5,400.00
Total $ 7,830.00
Composite Drainage Net
Transmissivity 4 each $ 102.00 $ 408.00
Ply Adhesion 4 each $ 102.00 $ 408.00
Tensile Strength 4 each $ 65.00 $ 260.00
$ 1,076.00
Orange Regional Landfill, Phase 4 Constructlon.)ds
Proposal
Page 1
4/28/00
GCL
Grab Strength and Elongation 5 each $ 65.00 $ 325.00
Permeability 5 each $ 20.00 $ 325.00
$ 650.00
60 mil HDPE
Testing As Per Section 13303, 2.01 5 each $ 5.00 $ 560.00
$ 560.00
60 mil HDPE Destructive Seam Testing
Approximate Based on 22'wide roils
Fusion Weld 55 each $ 35.00 $ 1,925.00
Extrusion Weld 10 each $ 35.00 $ 350.00
$ 2,275.00
Total Conformance Testing Costs $ 14,941.00
Field Construction/Observation
Baser!on Time schedules noted in the RFP
Soil Liner Placement
Senior Soil Technician 60 hours $ 27.00 $ 1,620.00
Mileage 800 miles $ 0.32 $ 256.00
Subtotal Per Week $ 1,876.00
Total 6 weeks $ 1,876.00 $ 110,256.00
Protective Cover
Senior Soil Technician 50 hours $ 27.00 $ 1,350.00
Mileage 800 miles $ 0.32 $ 256.00
Subtotal Per Week $ 1,606.00
Total 3 weeks $ 1,606.00 $ 4,818.00
Leachate Piping
Senior Soil Technician 40 hours $ 27.00 $ 1,080.00
Mileage 800 miles $ 0.32 $ 256.00
Subtotal Per Week $ 1,336.00
Total 3 weeks $ 1,336.00 $ 4,008.00
Geosynthetic Installation
Senior Soil Technician 60 hours $ 27.00 $ 1,620.00
Mileage 800 miles $ 0.32 $ 256.00
Subtotal Per Week $ 1,876.00
Total 4 weeks $ 1,876 00 $ 7,504.00
Total Fiel"bservation Costs $ 27,586.00 1
Orange Regional Landfill, Phase 4 Construction.xls
Proposal
Page 2
4/28/00
QA/QC Management / Meetings / Reporting
Project Manager 80 hours $ 62.00 $ 4,960.00
Project Engineer 40 hours $ 92.00 $ 3,680.00
Mileage 3000 miles $ 0.32 $ 960.00
Total $ 9,600.00
Total Project Management Costs $ 9,600.00
Total Costs Of QA/QC $ 56,652.00
Orange Regional Landfill, Phase 4 Constructionxls
Proposal
Page 3