HomeMy WebLinkAboutORD-2000-019 Equipment and Vehicles Project Capital Project Ordinance Equipment and Vehicles Project
Capital Project Ordinance
Project Number 61-412
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section 13.2
of Chapter 159 of the General Statutes of North Carolina, the following capital project is hereby
adopted.
Section 1. The project authorized provides funds to purchase County-owned vehicles and major
equipment. The project will be financed with proceeds from the County's portion of the one
half cent sales taxes, appropriated fund balance from the County Capital Projects Fund, and
grant funds from the North Carolina Department of Transportation.
Section 2. The officers of the County are hereby directed to proceed with the project within the budget
contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY.
1998-99 FY 1999-00 Through FY 1999-00
Sales Tax $3,144,589 $956,850 $4,101,439
Bond Funds $o $0 $0
Private Placement $0 $0 $0
Grant Funds $631,938 $45,000 $676,938
Other $20,000 $0 . $20,000
Total Funding $3,796,S27 $1,001,850 $4,798,377
Section 4. A portion of the funds available for this project have been expended. The following
amendment is anticipated to close these amounts:
Through FY 1995-
99 FY 1999-00 Through FY 1999-00
Transfer from County
Capital Reserve(1992-93) $239,583 $0 $239,583
Transfer from County
Capital Reserve(1993-94) $348,384 $0 $348,384
Transfer from County
Capital Reserve(1994-95) $351,954 $0 $351,954
Intergovernmental(1992-
93) $32,935 $0 $32,935
Intergovernmental(1993-
94) $4,688 $0 $4,688
Intergovernmental(1994-
95) $128,822 $0 $1282822
Total $1,106,366 $0 $1,106,366
23
Section 5. The following amount is appropriated for this project:
Through FY 1998-99 FY 1999-00 Through FY 1999-00
Land/Building $o $0 $0
Design $o $0 $o
Construction $0 - $0 $0
Equipment and
Vehicles $2,690,161 $1,001,850 $3,692,011
Total Costs $2,690,161 $1,001,850 $3,692,011
Section 6. This ordinance supersedes all previous Equipment and Vehicle Capital Project
Ordinances.
Section 7. This ordinance shall remain in effect from July 1, 1998 until June 30,2000.
Adopted this fourth day of April 2000.
�� '�1999-2000 Capital Profects; Update and Approval of Ordinances, � ��
d.
The Board received an update on the funding status of approved capital projects for the County
and the school systems, and considered approval of capital project ordinances for the Chapel Hill-Carrboro
schools and Orange County.
Assistant County Manager Rod Visser said that the staff is asking the Board to take two specific
sets of actions. The first action relates to funding for Chapel Hill-Carrboro City School projects, specifically
providing an appropriation so that the Glenwood Elementary renovation project can get into full swing. The
Chapel Hill-Carrboro Board of Education has approved construction contracts for this project,and there was
already$950,000 worth of 1997 bonds that were programmed with the understanding that the Chapel Hill-
Carrboro Board of Education would have to look at some of its other projects and come up with some savings
to fund the full construction costs. The Chapel Hill-Carrboro Board of Education has identified some savings
and is proposing to transfer$277,000+ in savings from the Scroggs Elementary project to cover the
renovation. The action for the Board is to adopt the project ordinance to appropriate the funds for the
Glenwood Elementary renovations and adopt the project ordinance that would reallocate funds and reduce
the project aUocaionfnrthaS Elementary project.
The second set of actions kmtn implement the County capital projects thst were approved inthe
C|P last summer.
Commissioner Brown questioned the costs on Scroggs Elementary and Pathways Elementary.
She said that it was important to keep track of the new schools and the full cost. She also asked for ofinal
figure on East Chapel Hill High Schno| Rod Viayar will provide this information.
Commissioner Gordon wants the 1,000 student figure to be included in the materials giving the
final costs for East Chapel Hill High School.
Commissioner Jacobs asked for final figures on some of the schools built in both systems. He
made reference to page three and asked if the County owned the animal shelter. Rod Visser said that the
County owns the building and the land is leased.
Commissioner Jacobs asked about the Equipment and Record Storage item.
Budget Director Donna Dean said that the first allocation of$69,975 would be for the outside
storage facility for Public Works. The funds left over would be used for record storage for departments that
have not been specified.
Commissioner Jacobs asked if the space study group would look at record storage and John
Link said that they would
Commissioner Jacobs made reference to page 4 and the protective ground covers at existing
parks and suggested that the County coordinate with the Solid Waste Department to do this in-house.
Commissioner Brown asked for figures on school technology and how much has been spent by
each school system.
Commissioner Gordon made reference to page three and corrected"Environmental Resources
Conservation"to"Environment and Resource Conservation." In regards to the Equipment and Vehicles she
suggested that it be underscored that they be energy efficient and/or alternative fueled vehicles. She said
that she would like some basic information about the schools(i.e.,the sizes, how many students,the
capacities, comparisons of new schools and old schools,etc.). She will submit her requests for this
information in writing.
John Link said that he would send the material that has been developed to the Board of County
A motion was made by Commissioner Gordon,seconded by Commissioner Jacobs to adopt the
capital project ordinances for Chapel Hill-Carrboro City Schools and Orange County.
VOTE: UNANIMOUS
e. Proposed Contract for Student Generation Rate and Impact F2e Studies
The Board was to consider awarding a contract to Tischler and Associates Inc. in an amount not
to exceed$53,400 for student generation rate and impact fee studies. However,this item was postponed.
f. N.C. Health Choice Coordinator Position—Conversion from Time-limited to Permanen
Status
The Board was to consider converting the existing Health Choice coordinator position to a regular
permanent position. However,this item was postponed.
10. REPORTS
a. �eport on Travel and Tourism/Economic Development Promotional Event
The Board received a report on possible support of a North Carolina travel and tourism/economic
development promotional event on July 4,2000 in Ottawa, Ontario,Canada.