HomeMy WebLinkAboutAgenda - 11-20-2012 - 5h ORD-2012-053
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: November 20, 2012
Action Agenda
Item No. 5-h
SUBJECT: Proposal to Upgrade Audio Visual Equipment at Southern Human Services
Center, and Approval of Budget Amendment#4-B
DEPARTMENT: Clerk, Information PUBLIC HEARING: (YIN) No
Technologies, Financial
Services
ATTACHMENT(S): INFORMATION CONTACT:
Sound Advice of Eastern NC, Inc. Donna Baker, 919-245-2130
Proposals for Replacement of Clarence Grier, 919-245-2453
Audio\Visual Equipment at Southern Carla Banks, 919-245-2302
Human Services Board Meeting Room Jim Northrup, 919-245-2276
PURPOSE: To receive information on the need to upgrade existing audio/visual (AV)
equipment at the Southern Human Services Center Meeting Room in Chapel Hill; to approve a
proposal by Sound Advice of Eastern NC, Inc. to upgrade AV equipment; and to approve
Budget Amendment#4-B.
BACKGROUND: As part of the FY2012-13 Approved Budget, South Advice of Eastern NC, Inc.
was hired to operate the AV equipment for all regular Board meetings and work sessions.
Additionally, Sound Advice has been evaluating the County's AV equipment and has
recommended the upgrading of a large portion of the AV equipment used for meetings.
Over the past 5 years, the AV equipment in the Southern Human Services Center (SHSC)
Meeting Room has required repair and/or replacement. The current AV equipment in the
meeting room is out of date and too costly to repair. Several components of the AV equipment
are also obsolete, out of date, and/or at a critical point of failure. Sound Advice has
recommended that the County upgrade existing AV equipment as soon as possible.
The recommended options to upgrade the equipment are:
1) Upgrading the projection system at SHSC —This would include the full replacement of all
the display equipment, including projector, wiring for the podium, LCD panels and
necessary interconnections. This would bring everything up to a high quality, HDMI
based standard. The total estimated cost is$46,260.62
2) Implementing a video server that supports live streaming from two locations —This would
include a video server and necessary equipment for managing programming for the
2
Public, Educational, Governmental (PEG) channel and supporting live streaming (with a
two minute delay) of meetings at either SHSC or the Department of Social Services
Meeting Room at Hillsborough Commons in Hillsborough. The total estimated cost is
$29,000.54.
Total estimated cost to upgrade the proposed AV equipment at SHSC would be $75,261.16.
The estimated timeframe for installation of the proposed equipment upgrades is approximately
two to three weeks.
FINANCIAL IMPACT: The financial impact is expected to be $75,261.16. Budget Amendment
#4-B approves an appropriation of $75,261 from the General Fund's unassigned fund balance
for the above mentioned AV equipment costs.
RECOMMENDATION(S): The Manager recommends that the Board approve the proposal by
Sound Advice, Inc. to upgrade the proposed AV equipment at SHSC, and approve Budget
Amendment#4-B.
3
Sound Advice of Eastern NC Inc PROPOSAL
657-B Worthington Road
PO Box 270 DATE QUOTATION...
Winterville,NC 28590 -
�� 9/28/2
252 355-1111 012 4600
`:
, .
NAME/ADDRESS
Orange County
PO Box 8181
131 W.Margaret Lane
Hillsborough,NC 27278
TERMS REP PROJECT
Due on receipt DER 4600 Projector u.:.
QTY ITEM DESCRIPTION COST Total
1 112-204 E-Vision WXGA 7000(NO LENS) 5,875.80 5,875.80T
1 112-501 E-Vision Lens(1.72-2.27:1) 1,361.10 1,361.10T
1 SA82 8 amp surge protection for monitors and 240.50 240.50T
projectors
1 111-182 E-Vision Adjustable Ceiling Mount Kit 451.10 451.10T
1 MISC Hardware to mount projector 170.00 170.00T
3 PN-E602 60"LCD Display, 1080P,RS232 3,760.90 11,282.70T
3 SA82 8 amp surge protection for monitors and 240.50 721.50T
projectors
3 RLT2 Large universal Tilt Mount 116.10 348.30T
1 DM-MD8x8 DM Series Switcher 2,795.00 2,795.00T
2 DMC-C DigitalMedia 8G+input card for DM Switchers 715.00 1,430.00T
1 DMCO-55 4 DM 8G+w/2 HDMI Output Cards 1,820.00 1,820.00T
4 DM-RMC-SCALE... DigitalMedia 8G+Receiver&Room 910.00 3,640.00T
Controller with Scaler
1 VP-438 Scaler/Switcher 4 HDMI 2 PC(Rack Mount) 925.60 925.60T
1 MC3 Master w/2-RS232,5-IR,IP&Wireless 1,120.00 1,120.00T
1 DM-TX-201-C DigitalMedia 8G+Transmitter 201 845.00 845.00T
1 DM-TX-200-C-2G... Wall Plate DigitalMedia 8G+Transmitter 200, 910.00 910.00T
black textured,includes 2407WUL
2 TSW-750-B-S 7" Surface mount TP Core3,Black(POE) 980.00 1,960.00T
1 MIS C HDMI to Composite video converter 450.00 450.00T
Thank you for the opportunity to quote
Sales Tax (7.0%)
The information herein constitutes a design.Any unauthorized use or dissemination of the
contents is prohibited. Total
Page 1
4 /
Sound Advice of Eastern NC Inc PROPOSAL
657-B Worthington Road
PO Box 270 DATE QUOTATION...
Winterville,NC 28590
252 355-1111 9!28/2012 4600
NAME/ADDRESS
Orange County
PO Box 8181
131 W.Margaret Lane
Hillsborough,NC 27278
TERMS REP PROJECT
Due on receipt DER 4600 Projector u:..
QTY ITEM DESCRIPTION COST Total
1 CEN-SW-POE-5 5 Port PoE Switch 260.00 260.00T
4 CBL-HD-3 HDMI 3'Certified 1080p 16bit 30.00 120.00T
1 CBL-HD-6 HDMI 6'Certified 1080p 16bit 37.50 37.50T
1 SX-AX15 I RU,8 Outlet, 15A w11P Control 1,207.70 1,207.70T
1 ERK-2725 27 Space Economy rack 25" deep with rear door 502.31 502.31 T
1 DM-CBL-8G-P-SP... DM 8G Cable Plenum(500') 420.00 420.00T
0.1 DM-8G-CONN-100 DM 8G Cable Connector(100) 375.00 37.50T
1 W&C Wire and connectors 350.00 350.00T
1 SHIPJ AND Shipping charges 311.65 311.65T
1 LABOR Labor to install projection,displays and control. 3,895.83 3,895.83
Program control
***NOTE-While this sytem fully supports
HDCP content protection,this feature will be
disabled so signal can pass to the video switcher
for recording.When the video system gets
upgraded,we can turn this feature back on
which will allow full blu-ray and content
protection sources to be available everywhere.
Sent 9-28-12 DBE
Thank you for the opportunity to quote Sales Tax (7.0%) $2,771.53
The information herein constitutes a design.Any unauthorized use or dissemination of the
contents is prohibited. Total $46,260.62
Page 2
r
5
Sound Advice of Eastern NC Inc PROPOSAL
657-B Worthington Road
PO Box 270 DATE QUOTATION...
Winterville,NC 28590
252 355-1111 10/9/2012 4608
NAME/ADDRESS
Orange County
PO Box 8181
131 W.Margaret Lane
Hillsborough,NC 27278
TERMS REP PROJECT
Due on receipt DER
QTY ITEM DESCRIPTION COST Total
LEIGHTRONICS HEAD END
1 UltraNexus 2 Channel Video Player with Internet Streaming 12,701.98 12,701.98T
Encoder
2 LGX-ITBR-D 1 Terabyte USB RAID External Hard Disc 999.00 1,998.00T
Array(Rack Mountable)for Use with NEXUS,
U1traNEXUS,U1traNEXUS-SDI,and
EMINENCE-HD2
1 DV-DOlU 1-rackspace DVD Player w/RS-232 Control 558.99 558.99T
Port•Defeatable on-screen guide icons•HDMI
Out•Optical out
1 LGX-DVply Interface cable for Tascam DV-DO IU 58.50 58.50T
1 Total Info Video Content Service Annual Fee(Included 0.00 O.00T
free of Charge 1 st year)
1 W&C Wire and connectors 250.00 250.00T
1 LABOR Installation 1,926.67 1,926.67
1 LABOR Training&Programming 1,341.21 1,341.21
1 SHIP/HAND Shipping charges 250.00 250.00T
Subtotal of above: 19,085.35
Sales Tax (7.0%)
The information herein constitutes a design.Any unauthorized use or dissemination of the
contents is prohibited. Total
Pagel
6 /
Sound Advice of Eastern NC Inc PROPOSAL
657-B Worthington Road
PO Box 270 DATE QUOTATION ...
Winterville,NC 28590 -
10/9/2012 '4608
� ^ 252 355-1111
NAME/ADDRESS
Orange County
PO Box 8181
131 W.Margaret Lane
Hillsborough,NC 27278
TERMS REP PROJECT
Due on receipt DER
QTY ITEM DESCRIPTION COST Total
OPTIONAL PROGRAMMING
1 Total Info Video Content Service Annual Fee 995.00 995.00T
STREAMING ON DEMAND
1 Peg Central Streaming VOD Service Annual Fee 2,988.00 2,988.00T
REMOTE RECORDER/TRANSFERRED TO
ULTRANEXUS AS LIVE....with 2 minute
delay
1 PEGvaultSD Digital Video Encoder 3,407.63 3,407.63T
(Requires 6-10 MBPS)
This device would be installed at Hillsboro
Commons to allow"near live"feed from there
back to U1traNexus unit at Southern Human
Services Head End. The PegVault has a 1
minute buffer and the U1traNexus has a 1
minute delay which combine in an effort to
avoid transmission delays causing interruption
of programming.
1 LABOR Installation and Programming 900.00 900.00
Sales Tax (7.0%) $1,624.56
The information herein constitutes a design.Any unauthorized use or dissemination of the
contents is prohibited. Total $29,000.54
Page 2