ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date:
August 21, 2012
Action Agenda
Item No.
7-c
SUBJECT:
Southern Orange County Government Services CampusMaster PlanUpdate,
BOCC Recommendation of Concept Master Plan
DEPARTMENT:Manager’s Office, Asset PUBLIC HEARING: (Y/N)No
Management Services
ATTACHMENT(S):INFORMATION CONTACT:
1)Master Planning PrinciplesFrank Clifton, 919-245-2306
2)Context and Background InformationGwen Harvey, 919-245-2307
3)Concept Master PlanAlternativesand Michael Talbert, 919-235-2308
ComparisonJeff Thompson, 919-245-2658
PURPOSE:
To receivean update on the status of the Southern OrangeCounty Government
Services Campus master planning process;
To providefeedback to staff on the merits of its two prepared concept master plan
designalternatives;
To consider recommending a single concept master planfor staff to 1) take to a Public
Information Session on September 4, and 2) develop into a final plan to be presented to
the Board forapproval in October of 2012.
BACKGROUND:
In 1992 the County purchased 34.1acres at 2500 Homestead Road on
which to develop a County campus for service offerings in southern Orange County for the
foreseeable future. To date, two buildings have been built on the site: the Southern Human
Services Center and the Seymour Senior Center. The site also supports Project HomeStart on
northwest sector of the property.
The Board of Commissioners approved a conceptual site master plan in 2006 and included
funding for a formal master plan of the Campus in the current year Capital Investment Plan
(CIP).
On May 15, 2012the Board of County Commissioners approved a Professional Services
Agreement with Clarion Associates of Chapel Hill (“Clarion”) to develop the formal master plan
andSpecial Use Permit Modification for the Southern OrangeCampus.
The overall intent of the master plan and the subsequentSpecial Use Permit modification with
the Town of Chapel Hill is to secure the most comprehensive and flexible set of development
rights for a significant period of time into the future to serve Orange County’s needs. The
objective is to prepare an application to submit to the Townto secure this comprehensive set of
development rights for a 25 year period. The plan will outline development areas and specific
design guidelines for County planning and construction for both building expansion and new
building construction.
002
The Clarion team has worked closely with County staff and a comprehensive set of stakeholder
groups in moving the project forward. The team’s design effort is grounded in both the BOCC-
adopted planning principles and the Chapel Hill 2020 plan as noted in Attachment 1,and the
team continues to meet with these various stakeholders of the project, including County
Departments, Advisory Boards, Utilities, and other regulatory officials.
The team has also assembled contextual, background, and technical informationrelevant to the
project in the form of meeting presentation slides as noted in Attachment 2.A current survey
has been prepared to validate many of the design opportunities and constraints. This survey
also includes significant tree specimens on the site.
The project outcomes have been based on this principled framework andthe extensive primary
feedback from the stakeholders as well as the technical information available on the site. Based
upon the feedback from the Board, the team will alsoconduct two public information sessions
on September 4, 2012 to provide information onthe status of this project.
The following table highlights key milestones for the project:
TASKPROPOSED END BY
BEGINNING DATE
DATE
Concept master plan presentation to the BOCC8/21/128/21/12
Public information sessions to provide information on the status of the 9/4/129/4/12
project
Project overview presented to the Town Board of Chapel Hill9/12/129/12/12
Final master plandrafting9/13/1210/15/12
Final master Plan approval by BOCC10/16/1210/16/12
Chapel Hill Special Use Permit Modification Process11/1/1212/31/13
(est.)
Members of the Clarion team will make a formal presentation on the progress of the project to
the Board and will be available to answer questions and respond toBoard discussion.
FINANCIAL IMPACT:
There is no financial impact associated with receiving the update and
providing feedback to staff and Clarion.
RECOMMENDATION(S):
The Manager recommends the Board:
receive the update on the status of the Southern Orange County Government Services
Campus master planning process;
provide feedback to staff on the merits of its alternative concept master plan designs;
and
recommend a single concept master plan for staffto 1) take to a Public Information
Session on September 4,and 2) develop into a final plan to be presented to the Board
for approval in October of 2012.
003
ATTACHMENT 1
MASTER PLANNING PRINCIPLES
FOC2030CP:
ROM RANGE OUNTY OMPREHENSIVE LAN
BOCC Planning Principles
Efficient and Fiscally Responsible Public Facilities
Sustainable Growth and Development
Energy Efficiency, Reduced Consumption, Air Quality Protection
Natural Area Resource Preservation
Preservation of Rural Land Pattern
Water Resources Preservation
Promotion of Economic Prosperity and Diversity
Preservation of Community Character
Key Land Use Goals
Coordinating new development with public service capacity
Development that supports non-auto modes of travel
Patterns of development that mix uses, limit sprawl, and protect
Promoting clustered, walkable developments
Supporting green design of public facilities
Land uses that protect natural and cultural resources
FCH2020CP:
ROM HAPEL ILL OMPREHENSIVE LAN
Plan Ideas Relevant To This Site:
Vibrant center of culture, academia, diversity, and ideas
Compact community; population growth expected
Promote environmentally-friendly modes of transportation
Focus on green infrastructure , emphasis on connections
Focus on hubs of activity, with multiple destinations
Support and encourage community engagement
Be clear about preservation areas and development zones
Tree canopy, greenways, and open space
Allocation of scarce public resources
This site in one of six
00
Context Attachment 2
and Background
Southern Orange Campus
Master Plan
Background Information and Draft Concept Plans
August 21,2012
Orange County Board of County Commissioners
i
Presentation Objectives
• Project Fundamentals
• Background and Existing Information for Site
• Concept Plan Options
• BOCC Discussion and Direction
z
Project Fundamentals:
Purpose
• Develop and Adopt Master Plan
—Supportive of County government services
• In Southern Orange County
•Centralized,convenient,accessible,co-located
—Phased Plan
—Design Guidelines
• Obtain Development Approval from TOCH
—Special Use Permit Modification
3
Context Attachment 2
and Background
Project Fundamentals:
Schedule
Tonight: Presentation of Project,Principles,Options
September 4: Public Information Meeting
September 12: Chapel Hill Town Council Meeting(Introduction/Briefing)
October 16: BOCC meeting,approval of Master Plan
October,2012:Start Chapel Hill Process-Concept Plan Review Application
November,2013:Target for approval of Special Use Permit-Modification
a
IBackground and Existing Information for Site:
Area Map
.o.o..n.,.,o...,f.�..R• li i fSG:K1k o
f 1 o I h
Background and Existing Information for Site:
Regulatory History of Site
• 1992: County Purchased Site
• Consolidation of human services in southern Orange County
• 1994:Special Use Permit(SUP)Approved by Chapel Hill
• Orange County Southern Human Services Center
• 1995:SUP Modification Approved by Chapel Hill
• Project Homestart facility
• 2005:SUP Modification Approved by Chapel Hill
• Robert and Pearl Seymour Senior Center
• 2007:County Adoption of Concept Plan
• For Internal Staff Working Purposes I'll• Several assessments:cultural,archaeological,environmental
s
0 .
Context Attachment 2
and Background
OWHE%�OF%,GE CAMPUS
50-year Development Plan
Carolina North Plan
Background and Existing Information for Site:
Site Conditions and Constraints
tii s
I 1
N �
Background and Existing Information for Site:
Carolina North
f' y
A.
a
Concept Plan Options:
Key Factors to Consider in Concept Plan
General Polity Objectives
Site Design Objectives
Maximize Buildable Area Within Polity Context
Maximize Floor Area for Flexibility
Provide for Undisturbed Areas
Use of Existing Stormwater Ponds
Minimize Infrastructure Cost
Minimize Impact to Hardwoods in Southwest Corner
Minimize Need for Future Land Acquisition
Minimize Operational Costs
Potential for Accommodating CouM�/s Future Needs
e
Context Attachment 2
and Background
-CONCEPT SITE OPTION A AND B SHOWA TAN-COLORED A EA NOTED AS THE'VE VELOPM ENT AREA"
-THE DEVELOP ME NT AREA IS WHERE THE FOLLOWING WILL BE LOCATED:
BUILDING
/PAR ING
LANDSCAPING
HE
Key Definitions for Concept Plan
• What"Development Area" means-A place for:
—Buildings
—Parking
—Landscaping,Open Space
—Roads,Paths
—Infrastructure(e.g.,stormwater facilities)
• What"Undisturbed Area" means:
—No land disturbance,protected during/after construction
io
Definition of Development Area
C RE
UTIL TY CONNECTIONS AND
ITY
STORMr�TER FACILITIES AS
REQUIRED BY FINAL DESIGN Thi.lid
Option A
e w
f '
0 :
Context Attachment 2
and Background
Option B
k—.
r,
i Alilr,.z I_.
i t
w I g
I
N I
Evaluation
Concept Plan Variable Concept Plan A 0 Concept Plan B
220,000 sf 310,000 sf
quisillon
Mullipl.buildings on-Ilpl. C--d,..nIr.k.d buildings
Distinguishing Characteristics
Common to Both
Development Area
Undisturbed Area
Ponds Relocated
Infrastructure Cost
Impact Hardwoods in Southwest Corner
Future Land Acquisition
Operational Costs
Potential for Accommodating County's Future
Needs
Chapel Hill Process
• Concept Plan Application
• Community Design Commission Review
• Town Council Review
• SUP-Modification Application
• Staff Review,Advisory Board Review
• Town Council Public Hearing,Subsequent Action
• Estimated Time Frame: January 2013-November 2013
• Individual Buildings Application
• Subsequent to SUP-M Approval.Estimate 6-months for each.
• May include most of site infrastructure with first building
• Estimated Application Fees
• September 12 Briefing to Town Council
�s
0 •
Context Attachment 2
and Background
Discussion
• Board Feedback on Plan Alternatives
• Take to Public Information Meeting September 4
• Develop into Full Master Plan with Design
Guidelines to Present October 16
�6
Southern Orange Campus
Master Plan
010
ATTACHMENT 3
CONCEPT MASTER PLAN ALTERNATIVES AND COMPARISON
Sheet#1: Principles and Variables to Consider in Preparing Concept Plan
Sheet#2: Area Map with Existing Conditions
Sheet#3: Draft Concept Plan—Option A
Sheet#4: Draft Concept Plan—Option B
Sheet#5: Comparison of Options to Principles
Oil
Sheet#1: Principles and Variables to Consider in Preparing Concept Plan
Principles Concept Plan �Mllllllll
Variable • Consider in Developing • -
• Coordinate locations of development and public services
• Support non-auto modes of travel
General Policy • Protect rural lands, promote clustered,walkable developments
Objectives • Efficient and fiscally responsible public facilities
• Protect natural resources, promote sustainable development
• Compact community, hubs of activity
• Be clear about preservation areas and development areas
• Promote green design of public facilities
• Promote energy efficiency, reduced consumption of resources
Site Design • Emphasis on connections
Objectives • Attention to tree canopies,greenways,open space
• Coordinate building locations and parking locations
• Design road and pedestrian networks to achieve safety,connectivity
• Develop a walkable campus of clustered County services
OIL-
• Focus development on most buildable areas of site
• Maximize potential buildable areas while considering other objectives
Buildable Area • Buildable Area=buildings, parking, landscaping, roads, paths,and open space
in area to be developed
• Maximize potential floor area available for public facilities,while considering
other policy and site design objectives
• Be clear about designating preservation areas
• Minimize land disturbance in most sensitive areas of site
• Take advantage of existing stormwater management facilities on the site if
possible
• Minimize infrastructure costs for ultimate site development,while
considering other objectives
• Avoid land disturbance in southwest corner of site if possible
• Minimize need for future land acquisitions to provide needed services
• Minimize costs of operating buildings and facilities
Potential for • Maximize potential for and flexibility in accommodating Orange County's
Accommodating needs for buildings to provide needed services
County's Future
Needs
40 �� }
C >I t TO
ROAD-' m
' I I SOUTHERN ORANGE
�-
CAMPUS I CHAPEL VIEW • _.'
I I 33.24 ACRES
I APARTMENTS
CAROLINA NORTH GREENWAY
CONNECTION TO HOMESTEAD ' t 'BROOKST .� � �•••
(NO ROAD CONNECTIONS ARE PLANNED I APARTIGISI
TO HOMESTEAD RD.OR CAMPUS SITE) , ' �.•.-
t
CAROLINA NORTH PROPERTY 1'" _`_ t_.. r• fir- _ ix
r
Ow
013
Sheet#3: Concept Plan: Option A
r`ETpgCK BUFFER
•,R [ INTER' COUN
1 PROJE OME STA
ROBERT A PEARL
SEYMOUR TE - r
3 STORMWATER
AREA
D
c DEVELOPMENT ARE
IMPROVED 85,000 SF
rfn ROADWAY
ALIGNMENT \ d
ISTING DEVELOPMENT AREA
,T ONO 135.000 SF
�. 40
S UTHERN HUMA m
. HARDWOODS RVICES CERN� > •k' '�
tN SOUTHEAST f� 1\ U Y
CORNER i� \PROPOSED ADDITION TO
_ EXISTING BUILDING IS
ANTICIPATED. SIZE AND
LOCATION TO BE
' a 30'SETBACK DET -s
014
Sheet#4: Concept Plan: Option B
D'BETBAC BUFFER
• INTER- 13 COUN N
R PROJECT HOME START �f..
ROBERT A PEARL +
SEYMOUR TE -
i
D VELOPME DEVELOPMENT AREA
AREA 260.000 SF
•000 SF
S THERN HUMAN
HARDWOODS S VICES CEN DEVELOPMENT
IN SOUTHEAST AREA
CORNER 80,000 SF
PROP EO ADDITION TO I
EXISTING BUILDING IS
ANTICIPATED. SIZE AND
LOOATION TO BE DETERMIND
30'SETBACK BUFFER:
015
Sheet#5: Comparison of Options
Concept Plan Variable Concept Plan A Concept Plan B
• Improved road alignment • Improved entrance intersection and
Distinguishing Characteristics • Maintain existing internal circulation
stormwater ponds • Largest area of development
• Improved traffic circulation for vehicles and pedestrians
• Proposed road along east side of site(dedicated right of way)
• • • : . • Additions to existing buildings with associated parking
• Maintain undisturbed southwest area
• An additional 350,000 sf of floor area available per Town's ordinance
- - • • - 220,000 sf 390,000 sf
Undisturbed - 7 acres 10 acres
Ponds R- • - • no yes
Infrastructure Cost moderate high
Impact Hardwoods in Southwest . no no
Good potential for meeting future Highest potential for eliminating need for
Future • Acquisition space needs on this site,without
additional land acquisition future land acquisition
Operational Costs Multiple buildings on multiple Co-located, centralized buildings
sites increases operational costs potentially lowers operational costs
• •
)F ACEUMMUDW •
high highest
Needs