HomeMy WebLinkAboutAgenda - 06-19-2012-13 (2) Information Item
Department of Environment,
Agriculture, Parks&Recreation
To: Frank Clifton, County Manager
Michael Talbert, Assistant County Manager
From: David Stancil, Environment, Agriculture, Parks and Recreation Director
Date: June 1, 2012
Re: Parks and Recreation Master Plan Status
The Parks and Recreation Master Plan is now fully engaged, and staff, our
consultants and the Parks and Recreation Council have begun work that will
continue through the fall, winter and spring, to solicit community input (via a
scientific survey, youth survey, and input sessions) and develop a plan for the
year 2030.
Two staff teams have been formed to work on the project, a Master Plan Group
and a Staff Resources Team (which comprises representatives from a number of
other departments and the Manager's office). Professors at UNC-Greensboro
have been hired to conduct the community needs assessment (scientific random-
sample) survey, and produce documents for the plan on economic development
linkages with parks and recreation, and tourism opportunities. An intern from
UNC's Master of Public Administration program is working with staff on
demographics and other background materials.
Attached is a timetable for planned activities associated with the project. The
most ambitious portion of the project is a random-sample survey of 4,100 county
households on parks and recreation program usage and experiences and
preferences for future needs, among other topics. A draft of the community
needs assessment survey instrument will be completed and shared in upcoming
weeks (well prior to distribution). This survey would be administered in
September and completed in October, with evaluation and analysis received prior
to the end of the year.
Orange County Department of Environment, Agriculture, Parks &Recreation
PO Box 8181
Hillsborough, NC 27278
Phone: (919) 245-2510
Fax: (919) 644-3351
A Youth Survey will also be administered to participants in summer recreation
programs, and distributed to other camps and venues during the summer to gain
the perspective of young people on the facilities and programs offered, and their
needs and interests.
While subject to change as needed, three public input sessions are planned (in
addition to a public hearing once the draft plan is completed). This document,
when completed, will provide a blueprint for the future of parks and recreation
facilities and programs that will build on the 1988 plan and the many reports,
plans and facility accomplishments since that date, and complement and add to
the goals and objectives identified in the Parks and Recreation Element of the
Orange County Comprehensive Plan 2030, adopted in November 2008.
The document will also explore partnership opportunities (current and future),
linkages to municipal plans, conservation and open space contiguity, economic
development, tourism, and many other topics.
Staff and the Parks and Recreation Council are excited about gaining new
information on our parks and recreation offerings and the exploration of future
options and paths that will help provide healthy lifestyles and the opportunity to
recreate, learn team-building and life lessons through recreation, and enjoy our
quality of life. At this point, existing resources appropriated as part of the FY
2011-12 budget will be sufficient to complete the task, with no additional funds
requested for FY 2012-13,
Please let me know if I can provide any additional information. Our next projected
check-in to the Board (other than providing advance copy of the survey) would be
in October, although more frequent informational reports could be generated if
desired.
Copies: Keith Bagby and Denise Dickinson, PRC Co-Chairs
Master Plan Group
Staff Resources Team
Orange County Department of Environment, Agriculture, Parks&Recreation
PO Box 8181
Hillsborough, NC 27278
Phone: (919) 245-2510
Fax: (919) 644-3351
Parks and Recreation Master Plan 2030 - Timetable of Activities
June 2011 Approval of Project,Funds NA
August 2011 Project Scope Discussion P&R Master Plan Team(Team)
September 2011 RFP Prepared, Refined Team,Stancil
November 2011 RFP Solicited Financial Services(FS)
December 2011 Proposals Received(0) FS
January/February 2012 Review Status,Status memo to BOCC,Re-engage and plan for action Team
March May Hire Research Consultant(s),complete timeline Team/Stancil
June-August Community Needs Assessment survey instrument created, refined and Consultant, Team, Parks and
completed, sampling techniques finalized. Companion "Youth Survey" Rec Council (PRC), Staff
prepared and administered. Background sections of plan drafted, Resources Group (SRG)
annotated Table of Contents completed. Informational item update to
BOCC June 19.
July-September Survey prepared, random sample identified and ready for dissemination. Team, Consultant, SRG
Youth Survey' results evaluated, report created. Demographic,
socioeconomic and service area (transportation) data collected, and other
Master Plan sections drafted.
September Survey distributed to random sample (4,100 households). Follow-up Consultant, Team, PRC
postcards. Municipal & School Coordination sections drafted.
October Public Input Session#1 held. Status Report to BOCC. Survey results to Consultant, Team, PRC, SRG
consultant by end of month, analysis of survey data.
November-Dec Survey results/analysis received. Draft Plan. Meet with Mgmt Consultant, Team, PRC, SRG
January 2013 Consultant report on survey findings/recommendations. Public Input Consultant, Team, PRC, SRG
Session#2 on results of CNA and Draft Sections of Plan. Complete
remaining data collection, and receive final reports on standards,
tourism/parks and economic impacts from consultant.
February 2013 Full Draft Plan, BOCC update. Present draft at Input Session#3. Team, PRC, SRG
March 2013 Revisions to Draft Plan as needed. Status Report to BOCC. Team, PRC
April-May 2013 Review BOCC and public comments, create Plan Final Draft. Public Team, PRC
Hearing. Advisory Board review (PRC recommendation)
June 2013 BOCC Considers for Approval. Team, PRC
July-August If needed.PRO Final Review and refinement(if remanded).Return for action by BOCC for BOCC(PRC)
formal adoption of Parks and Recreation Master Plan(if needed)
The Youth Survey will be administered through surveys and focus groups during summer camps and programs,and also administered via the schools in September.