HomeMy WebLinkAboutAgenda - 06-05-2012 - 7aORANGE COUNTY BOARD OF COMMISSIONERS ACTION AGENDA ITEM ABSTRACT Meeting Date: June 5, 2012 SUBJECT: Orange County Transit Plan and Related Agreement DEPARTMENT: Manager, Planning & Inspections, Financial Services and Attorney ATTACHMENTS: (UNDER SEPARATE COVER) 1. Final Draft Bus and Rail Investment Plan (includes Financial Plan) 2. Orange County/Triangle Transit DRAFT Implementing Agreement Action Agenda Item No. -7-0, PUBLIC HEARING: (Y /N) No INFORMATION CONTACT: Frank W. Clifton, Jr., Manager, 245 -2300 David King, General Manager, Triangle Transit, 485 -7424 Wib Gulley, General Counsel, Triangle Transit, 485 -7418 PURPOSE: To consider adoption of the Orange County Transit Plan and approval of the Implementing Agreement. BACKGROUND: Staff from Triangle Transit (TT) will lead the Board through discussion and consideration of the attachments. At its May 3, 2012 work session, the Board reviewed the public input on The Orange County Transit Plan (also referred to as the Bus and Rail Investment Plan in Orange County) from the following events: o Public hearing held on April 3, 2012 o Public hearing on April 17, 2012 o Open House at Extraordinary Ventures, Chapel Hill, on April 23, 2012 o Open House at the West Campus office building, Hillsborough, on April 30, 2012 The Board also received and discussed the draft OCTP at the May P work session, and at its regular meeting on May 15, 2012. Attachment 1 is the final draft Bus and Rail Investment Plan in Orange County, which incorporates BOCC direction received on May 15. The OCTP will describe Orange County's plans to utilize revenue from the Y percent sales tax, if the Board establishes a referendum on the tax and if it is approved by Orange County voters, in addition to how funds are spent from a possible $7.00 county tag fee, a $3.00 increase to the current Triangle Transit tag fee, and triangle regional rental car fee revenues. The Plan includes elements such as: • Fixed guideway transit (Light Rail Transit) o Orange County's transit partnership with Durham County • Expanded or new bus service (local, rural and regional) • Martin Luther King Jr. Blvd. bus lanes • Small capital transit facilities (park and ride lots, train stations) The Draft Orange County/Triangle Transit Implementing Agreement (Attachment 2) describes how Triangle Transit will utilize the funds received through the % percent sales tax and other revenue sources. Input from Triangle Transit legal counsel is pending. The BOCC has already adopted a Durham /Orange Cost Share Agreement and a Do Not Levy Agreement between Orange County and Triangle Transit that confirms that Triangle Transit will not levy the '/ percent sales tax in Orange County until certain conditions have been met if and when an associated referendum is approved by Orange County voters. A public hearing will be conducted at this same meeting as a separate agenda item to collect any input the public may have to offer to the BOCC prior to its decision whether or not to place the 'h percent sales tax referendum on the November 2012 ballot. FINANCIAL IMPACT: None at this time. The Bus and Rail Investment Plan in Orange County includes information on future commitments. RECOMMENDATIONS: The Manager recommends that the Board: 1) Consider and take appropriate action on the Orange County Transit Plan; and 2) Consider and take appropriate action on the Orange County/Triangle Transit Implementing Agreement, and if approved, authorize the Chair to sign the Agreement. The DRAFT ' Bus Rail Investment Plan in Orange County m _ M ChHill °`a'"� �•"`�- HII M �o r. ORANGE BUS Of 1111;17 ROPOLITAN Planning Organization 5/23/2012 The Bus and Rail Investment Plan in Orange County 2 I. INTRODUCTION 3 II. TRANSIT STEPS LEADING UP TO THIS PLAN 4 III. PLAN ELEMENTS 5 A. PUBLIC TRANSIT PROVIDERS B. NEW BUS SERVICE C. NEW BUS CAPITAL INVESTMENTS D. HILLSBOROUGH AMTRAK STATION E. NEW LIGHT RAIL SERVICE F. MARTIN LUTHER KING JR. BOULEVARD BUS LANES IV. MAPS 11 V. ORANGE COUNTY REVENUES 20 A. ONE -HALF CENT TRANSIT SALES TAX B. $7 COUNTY VEHICLE REGISTRATION FEE C. $3 REGIONAL VEHICLE REGISTRATION FEE D. REVENUE FROM REGIONAL RENTAL CAR TAX E. STATE GOVERNMENT FUNDING F. FEDERAL GOVERNMENT FUNDING VI. ORANGE FINANCIAL PLAN DATA 23 VII. AGREEMENTS 23 VIII. NEW STARTS PROCESS 24 IX. ALTERNATIVE PLAN 26 X. CLOSING SUMMARY 26 XI. APPENDIX 28 5/23/2012 - Page 12 The Bus and Rail Investment Plan in Orange County I. INTRODUCTION 41 Orange County has achieved an enviable quality of life at the end of the first decade of the 21St century. Recent accolades include its ranking as the one of the best place to live by Money Magazine, July 2010, one of the best places to start a business by Entrepreneur Magazine, August 2009 and one of the best places in the nation to raise children by Business Week, December 2010. Orange County is nationally known for its excellent public education systems. Two districts serve the residents of Orange County: The Chapel Hill - Carrboro City School System and the Orange County School System. The University of North Carolina at Chapel Hill consistently ranks among the great institutions of higher education in the nation, most recently honored by US News & World Report. With these successes comes growth in population and increased pressure on our roads and highways. Since 2004, the Triangle has moved from 46th largest metro area in the nation to 40th in 2009, and our vehicle demand on freeways is up by 28% over those five years. Recently, our region was named the P most sprawling urban area in the country among the 83 areas studied. In 2009, the Joint Long Range Transportation Plan for 2035, by the Durham - Chapel Hill - Carrboro Metropolitan Planning Organization (DCHC MPO) noted that the region's population would more than double over the 25 -year period. For the last two decades, the demand on our roads has grown significantly faster than our population. Even with planned highway improvements and likely additional revenues for new roads, it is clear that Orange County and the region will see declining levels of service on major roads in the next 25 years. Orange County population grew by 1.6% a year since 2000 and is projected to grow from the countywide 2010 census of 133,801 to approximately 173,000 by 2030. The economic costs for increasingly congested roads are significant. In its 2010 Annual Urban Mobility Report, the Texas Transportation Institute estimated that our region has "congestion costs" of almost one -half billion dollars a year. Recently, a May 10, 2011 study cited in Forbes magazine found that the Triangle was the urban region in the nation that is most vulnerable to rising gasoline prices. Enhanced transportation options need to be created to ensure that Orange County's residents of all income levels have access to job centers and commerce. Orange County residents and their regional neighbors are aware of the growth in clogged roads, as well as the accompanying air quality problems, negative economic impacts and the loss of the quality of life we enjoy if these transportation challenges are not met. Local citizens and elected leaders have responded to these challenges, with some assistance from state government, as described in this investment plan. 5/23/2012 - Page 13 II. TRANSIT PLANNING STEPS LEADING UP TO THIS PLAN 0 Beginning in 2007, a blue- ribbon group of Triangle leaders (the Special Transit Advisory Commission, or STAC) met for over a year and in 2008 unanimously recommended a regional vision for bus and rail investments. One year later, the region's two Metropolitan Planning Organizations (MPOs) fully incorporated the STAC recommendations into a long -range (25- year) transportation plan. In August 2009, Governor Beverly Perdue signed into law the Congestion Relief and Intermodal Transport Fund Act (HB 148), legislation that allows Orange, Durham and Wake counties to generate new revenues for public transportation. These new revenues can include a one -half cent sales tax, if approved by the public through a referendum, as well as an additional $10 in local and regional vehicle registration fees. Over the last two years, Triangle Transit staff has worked with municipal, Orange County, the MPO and other regional transportation staff to develop a detailed, 25 -year plan for new bus and rail investments designed to provide greater transportation options for residents and employers. These investments would positively impact traffic congestion and air quality, and support local land use policies. This plan is the culmination of that collaboration and proposes crucial public investments and services to maintain our quality of life and economic vitality for the next 25 years. Extensive public engagement has occurred over the two years in the development of the bus and rail elements of this plan. In 2010 and 2011 Triangle Transit and local transportation staff members from municipalities, counties and MPOs conducted a series of 19 public workshops, at various locations throughout the Triangle, on the process and substance of the plan's development. A total of over 1,100 participants attended the meetings and they provided over 500 comments on the plan. Since that time, the project Web site, www.ourtransitfuture.com, was viewed by over 73,000 unique individuals. The Web site houses all of the presentation materials and proposed plan elements. Additionally, the DCHC MPO held five public workshops to receive input on the proposed plan in 2011. In spring 2012, the Orange County Board of Commissioners held two public hearings and two public workshops to provide opportunities for the public to ask questions and provide feedback on the proposed plan. There have been dozens of meetings with citizens, local elected officials, staff and members of the region's MPOs, community stakeholders and business leaders, allowing extensive feedback on the proposed bus and rail elements of the plan. The financial and service elements of this plan are coordinated with the adopted Durham County Bus and Rail Investment Plan. Additionally, this bus and rail investment plan builds on existing transit services and therefore does not eliminate or reduce the current financial and service commitments. 5/23/2012 - Page 14 III. PLAN ELEMENTS A. Public Transit Providers The Triangle has a number of public transit providers that have been involved in the development of this plan and will have responsibility to implement the recommendations of the plan upon its approval. Below is a brief description of the transit agencies: Chapel Hill Transit is a multijurisdictional agency formed by a partnership of the Towns of Chapel Hill, Carrboro and the University of North Carolina at Chapel Hill. Chapel Hill Transit is responsible for regular and express route and demand response service in the Chapel Hill, Carrboro, and University area. Chapel Hill Transit also provides regional express bus service, in cooperation with Triangle Transit to Hillsborough. Orange County Public Transportation is a county agency that provides community transportation in unincorporated Orange County consisting of demand response service and circulator service within Hillsborough in cooperation with the Town of Hillsborough. Orange County Public Transportation is responsible for providing transportation services to all residents of unincorporated Orange County, the Town of Hillsborough and a portion of the City of Mebane with destinations within and beyond Orange County's borders. Triangle Transit is a regional transit agency serving Wake, Durham and Orange counties. Triangle Transit is responsible for providing regional commuter express and demand response service connecting Wake, Durham and Orange counties B. New Bus Service Representatives from Orange County, Chapel Hill, Carrboro, Hillsborough, The University of North Carolina at Chapel Hill, and Triangle Transit have worked collaboratively to develop a comprehensive bus service improvement plan that supports the effort to improve public transit in Orange County. The group identified a range of services that would address county- wide transit service needs. Identified services were ranked and prioritized based on a set of goals and strategies. Goals include: • Improve overall mobility and transportation options in the region • Provide geographic equity • Support improved capital facilities • Support transit supportive land use • Provide positive impact on air quality Strategies to accomplish these goals include: • Improve connectivity • Increase frequency in peak hours • Improve weekend, night services (off peak) 5/23/2012 - Page 15 5 • Enhance existing service 0 • Maintain existing services • Maintain level of local funding at no less than the August 1, 2009 spending level Over the course of the plan, a new half -cent sales tax would enable delivery of a total of 40,950 additional bus hours in Orange County. By comparison, Chapel Hill Transit currently provides 190,000 annual bus hours and Orange Public Transportation provides approximately 13,000 annual bus hours. The projects will provide benefits to all areas of the county by enhancing urban and rural transit services. Bus improvement projects were classified by type of service: • Local bus service - service operating within Orange County boundaries • Rural or Non -urban service- new or supplemented bus service in northern and western portions of the County. • Regional service - service operating in more than one county or between separate urban areas. Note: Costs and expenses for regional bus services traveling between Durham and Orange counties are shared on a 50 -50 basis by Durham and Orange counties in this Plan. First Five Years following successful sales tax referendum An investment that equals about 34,650 bus service hours will be provided during the first five years. Improvements will include: Improve connectivity • New regional service connecting Carrboro, Chapel Hill, and Durham • New regional express service connecting Mebane, Hillsborough and Durham Increase frequency in peak hours • Enhanced services in the US 15/501 corridor between Durham and Chapel Hill for Chapel Hill Transit, Triangle Transit, and DATA • Improvements in the NC 54 corridor transit service • Increased peak hour service on Triangle Transit Route 800 between Research Triangle Park and Chapel Hill • Increased peak hour service on Triangle Transit Route 420 between Hillsborough and Chapel Hill Improve weekend, night services (off peak) • New Saturday service on the in -town Hillsborough circulator • Expanded local Saturday service in Chapel Hill, Carrboro and UNC • Expanded regional Saturday service on existing Triangle Transit Route 405 between Durham and Chapel Hill and Triangle Transit Route 800 between Chapel Hill and the Research Triangle Park • Expanded regional Sunday service on existing Triangle Transit Route 405 between Durham and Chapel Hill and Triangle Transit Route 800 between Chapel Hill and the Research Triangle Park • New local Sunday service in Chapel Hill, Carrboro and UNC • Expanded local evening service in Chapel Hill, Carrboro and UNC 5/23/2012 - Page 16 Bus Service Enhancements 7 • Enhanced rural transit service in unincorporated Orange County Maintain existing services Revenues from the County vehicle registration fee of $7.00 as identified in the plan (see page 21) will be used to support existing bus service Continue weekday hourly service on the in -town Hillsborough circulator ❖ Routes provided by Chapel Hill Transit, may or may not, be included in the plan. Chapel Hill Transit and its partners will determine which of the improvements will be included after further public involvement and analysis. Year six and beyond following successful sales tax referendum An additional 6,300 new bus service hours will be provided between year six of the plan implementation through the end of the program (year 2035) bringing the total to 40,950 total new bus hours. Improvements include: Increase frequency in peak hours Increased peak hour service on Pittsboro — Chapel Hill Express Increased peak hour service on the existing Triangle Transit Route 800 between Research Triangle Park and Chapel Hill • Increased peak hour service in Chapel Hill, Carrboro and UNC Service Enhancements Continued enhancements to rural transit service in unincorporated Orange County 5/23/2012 - Page 1 7 8 The following chart depicts how revenue will be appropriated initially to the various transit providers—Chapel Hill Transit, Orange Public Transit, and Triangle Transit. 8,200 CHT 24% OPT 4,118 12% 22,332 TT 64% Provider Hours % Share of Revenue CHT 22,332 64% OPT 4,118* 12% TTA 8,200 24% Total 34,650 100% Operating Cost for TT/CHT is$97 1hr; OPT cost is$58 1hr `The above chart uses a blended formula for operating costs.Since operating cost for OPT are currently$58/hr,the 4,118 hours will result in 6,887 hours at that $58/hr rate. ❖ See Appendix for more detailed information about specific bus routes and proposals 5/23/2012-Page 18 C. New Bus Capital Investments • Park and Ride lots • Bus shelters in both rural and urban areas of the County • Real -time passenger information signs and technology • Bus stop access improvements such as sidewalks �61 ❖ For financial information about these proposed investments please see the Appendix. D. Hillsborough Amtrak Station The plan will provide local funding to support the creation of a passenger rail station in the Town of Hillsborough. The Rail Station Small Area Plan is a conceptual site and land use plan for the 20- acre tract of land owned by the Town located off of Orange Grove Street. The proposed land uses include a rail station building with space for municipal meetings and a police station; a fire station, and space for a civic arts center. On the eastern portion of the site, high- density commercial and residential land uses are suggested. Phasing options have been considered as well. In addition to the conceptual site plan for the Hillsborough tract, a general transportation network and set of land uses is proposed for the adjacent Collins property. ❖ For financial information about this proposed investment please see the Appendix. 5/23/2012 - Page 19 1 ` $�i 3$��3 t (den t42iH!. •�k3 iF } � �i hs�v r s M I L L S O O R O U G H - O R A N G C C O U N T Y R A I L STATION TASK PO R C C } w 1 � i H I L L S B O R O U G H - O R A N G E C O U N T Y R A I L S T A T I 0 N T A S K F O R C E �!� E. New Light Rail Service 11 The Orange County Bus and Rail Investment plan provides funding for a fixed guideway transit system that would connect Durham and Orange counties using Light Rail technology (LRT). The 17.3 -mile alignment extends from the University of North Carolina (UNC) Hospitals to Alston Avenue /NCCU in East Durham. A total of 17 stations have been proposed including a station at Mason Farm Road, Hamilton Road, the UNC Friday Center, as well as a potential station at Woodmont /Hillmont or Meadowmont in Chapel Hill. Stations in Durham include Patterson Place along US 15 -501, the South Square area, at Duke Medical Center, Ninth Street, and downtown Durham, with convenient access to nearby bus and Amtrak intercity rail connections. Due to the light rail vehicle's capabilities and the requirements of the activity centers and neighborhoods being served along the corridor, light rail stations are routinely spaced between % mile and 2 miles apart. Light Rail vehicles are electrically powered and travel at speeds up to 55 mph. The total travel time for the 17.3 -mile alignment is about 35 minutes, including stops. The vehicles are approximately 90 feet long and can operate in both directions. Additional cars can be added as the demand increases. Recent 2035 projections indicate that ridership will exceed approximately 14,000 boardings per day. These projections are subject to change as the demand model is refined and as development, population and employment changes are recognized. Light rail vehicles can operate in exclusive right of way, as well as along urban streets, and characteristically serve accessible low platforms (14 inches high) at each station. The operations plan for the 17.3 -mile alignment includes train frequencies (headways/ e.g. time between each train) of 10 minutes during the morning and evening peak and 20 minutes during the off -peak hours and on weekends. Vehicles will operate on an 18 -hour schedule each weekday. Several potential light rail vehicle maintenance facility locations are being evaluated. Detailed alignment and station location decisions will be made at the end of Preliminary Engineering. The total capital cost for the Durham and Orange Light Rail Project is approximately $1.378 billion (2011 dollars). Orange County's share is $316.2 million in 2011 dollars, which is the same as $418.3 million in Year -Of- Expenditure (YOE) dollars. Operations and Maintenance costs are estimated at $14.44 million /year (2011 dollars). Orange County's share of the Operations and Maintenance costs are $3.46 million /year (2011 dollars). For Orange County's share of the capital cost of the Light Rail project the total cost allocation is Orange County 25 %, and an assumed State participation of 25% and Federal Participation of 50 %. Cost estimates for the light rail project have been developed with multiple conservative assumptions. Included in the $1.378 billion total project cost are the following contingencies: • 30% contingency on all civil engineering construction costs (stations, sitework, track, yard & shop) • 20% contingency on systems (signals, electricity, communications) 5/23/2012 - Page 111 12 10% contingency on vehicles Additional contingency on all soft costs ( Design /Architectural /Engineering) Beyond these line -item specific contingencies, there are also two general contingency line items, one that is equal to 5% of construction cost and another that is equal to 5% of the entire project cost. For financial information about this proposed investment please see the Appendix. F. Martin Luther King Boulevard Bus Lanes and Corridor Improvements This investment provides for corridor improvements for buses on Martin Luther King (MLK) Boulevard from Interstate 40 to UNC, using a combination of exclusive lanes and other forms of preferential treatment. It will make bus travel times more reliable in peak periods. Existing buses operating in the MLK corridor will be re- routed to take advantage of the enhanced facilities. Orange County's cost for the bus lanes is anticipated to be $22 million in $2011 dollars, which is the same as $24.5 in YOE dollars — according to staff at Chapel Hill Transit. This project assumes 25% of the funding will come from the State and 50% of the funding will come from the Federal Government. Since the bus lanes will be used by existing services, they do not generate any additional operational costs within the plan. For financial information about this proposed investment please see the Appendix. IV. MAPS: The series of maps listed below articulate proposed investments in both bus and rail throughout Orange County. a. Chapel Hill Transit Weekday Service Improvements b. Chapel Hill /Carrboro: Saturday Service Improvements c. Chapel Hill /Carrboro: Sunday Service Improvements d. Improved Bus Service in US 15/ 501 and NC 54 Corridors e. Orange County Transit Plan: Proposed Regional Bus Service Improvements f. Proposed Hillsborough and Rural Bus Service Improvements g. Durham - Orange Light Rail Transit Project h. Improved Bus service on MLK i. Regional Integration of Orange, Durham, and Wake Transit Plans 5/23/2012 - Page 1 12 13 Created by Chapel Hill Transit Weekday Improvements L ._ p ;f� CD ai t Z pS a Estes Dr Eastgate CO University Mall jf UNC � Rd.� 'ti ��. • a - 7 I Carr MITI �A Route Route + �CWRoute ®D Route - N FRoute - -�-G Route W' E �HSRoute �HU Route 41111111111111111PJ Route `S a N Route _- - DNS Route •Improve evening service(A,CM,CW, D,F,G,HS, 411111111111111INIJ Route HU,J,N,NS,NU,S,U,V, T) I11111111111111iSRoute }� -Extend the hours i11111111111111ITRoute -Make the schedules more consistent G2111111I Route -Improve frequency v Route •Utilize a portion of the funds to sustain the financial stability of the system. . .weekday Route sotz •Increase peak-hour service G• Park and Ride Lots -Add service frequency on routes that experience Carrboro Town Dmts overloading during the rush hour O Chapel Hill Tawn Limits 5/23/2012- Page 1 13 14 Chapel Hill/Carrboro: Saturday Service Improvements Existing Service Characteristics: •Operates 8:00am-6:30pm •80 daily service hours Proposed Improvements: -Re-design routes •Double the existing service •Expand operating hours •Improve service frequency •Add up to 70 daily service hours astgate t: niversity Mali �d 5 Car i w C ® Saturday Improvements Q p Tnangle Counties Chapel Hill Carrboro Streets —Existing CHT Saturday Routes Landmarks QParkand Rido Lots Created by Chapel Hill Transit Mlles 5/23/2012-Page 14 15 Chapel Hill/Carrboro: Sunday Service Improvements Existing Service Characteristics: •Operates 10:30am-11:30pm when UNC is in session •22 daily service hours Proposed Improvements: I •Design and implement new routes •Adjust existing routes •Add up to 98 daily service hours -t ,Easfgate i E ,University Mall i Carr MiU- C i _-- 1 f _ Sunday Improvements �. _ _,,•` • Triangle Counties Chapel Hill Carrboro 1 str•.rc -J °---Existing CHT Sat -Existing Sunday U -Existing Sunday NU `Landmarks Park and Ride Lots Created by Chapel Hill Transit D o s 1 1.5 Mlles 5/23/2012-Page 115 16 Improved Bus Service in US 15/501 and NC 54 Corridors US 151501 Corridor Improvements: Q- •Re-design CL and D •Extend service to connect to Durham •Establish connections with regional service i •Improve frequency in service hours Carol(rla North �lEastgate ~' �, • University I Carr Mill �� r SRT on MILK NC 54 Corridor Improvements: rr • Triangle Comities •Add vehicles in the corridor ` , Chapel Hill Carrboro to meet Park-and-Ride demand streets • Identify additional satellite parking ----CHT Weekday Service (utilize existing lots) #Landmarks Park and Ride Lots Created by Chapel HIII Transit 9 r Milos 5/23/2012-Page 1 16 17 Orange County Transit Plan: Proposed Regional Bus Service Improvements LEGEND Triangle Counties ' - _ Orange Townships e _ Hillsborough IV/, Hillsborough d ,rt E. t.n.-- 4 $ [Chapel Hill S arrboro 5 _ y � Streets ch � ------ «� Cha el Hill-Raleigh Express ;Durham Te Downtown _ �Carrboro-Chapel Hill-Durham Oran a Cam us Durham —Mebane-Hillsborough-Duke-Durham (Duke,''- i chapel Hill-South Durham-RTP NCCU i�iillsborough-Chapel Hill 0 [Park-Ride Catchment Area /40 v55 e Q Existing P-R Lots JytsP Potential P-R Lots Other 2010 Residents Per Sq.Mile 0 to 250 �. 250 to 500 UNC t _ ti ' -s0o to 1,000 ti �41 ®1,000 to 2,000 �9h -2,000 to 3,500 RT s 3,500 to 5,000 _5,000 to 10,000 =10,000 and above 0 2.5 5 7.5 �t-------------�- Miles Created by Ttianek Tiansa Stair April 23,2012 I 5/23/2012-Page 117 i 18 Orange County Transit Plan:Proposed Hillsborough and Rural Bus Service Improvements v.. . /85 it NCS4 LEGEND Hiifs6orouc�r i � QChapel Hill 7 �I�anboro Streets hanced OPT Dial-A-Ride Servic Created by Triangle Transit o z a s Miles 5/23/2012-Page 118 19 t ,.. i h s* t , =e- • • / Duke University Light Rail Route Routes to be Studied Further � Railroad Corridor Light Rail Stations North Carolina • Central University Durham Technical • Altercate Community College Light Rail Stations a miles co • connection to station • 2 miles floc bike .~•' connection to station •�•• .. *,—"—l12 mile for � •• mlkxceess Note:NotTo Scale University of North Carolina .•�• at Chapel Hill ,•' • Our Transit Future 5/23/2012- Page 1 19 20 Improved Bus Service on Martin Luther King Jr. Boulevard BRT is a flexible,high performance Eubanks . bus service that combines many characteristics of light rail including physical,�o operating,and system elements into a permanently integrated bus system w with a quality image and unique identity, a.. r Characteristics: • High capacity buses • High frequency service • Dedicated lanes • Upgraded shelters Carolina North r f East ate y l •Technology �� < /� • Easy fare payment _s tag EL ✓ • Unique identity �y University 11, iR Carr Mill A - J BRT on MILK + Q Triangle Counties Chapci Nall •MLK is a prime corridor to introduce BRT_ Carrboro •CHT has funding in place to begin Alternatives Ana sis(AA) streets ---CHT Weekday Serwise •AA process will be guided by Chapel Hill 202Rjj co mendations A Landmarks �', Park and Rids Lots D 7 Created by Chapel Hill Transit ,S Wes es 1,5 5/23/2012- Page 120 21 Y Dufiam 1r. � Wake Forest G70'' Chapel Nifl{ Regional Integration of Orange, Durharn, and Wake Transit Plans o Cary i @Raleig Created by Triangle Transit 5/23/2012- Page 21 V. ORANGE COUNTY REVENUES 22 A variety of revenue sources provide the funding for the Orange County Bus and Rail Investment Plan. Those revenues include: • A new one - half -cent sales tax in Orange County • A new $7 vehicle registration fee levied by Orange County • An increase of $3 to the existing $5 vehicle registration fee currently levied by Triangle Transit in Orange County • Revenue from Triangle Transit's rental car tax • NC State Government contributions • Federal Government contributions In addition, local funding of current transit services will remain in place. The initial proceeds for a FULL YEAR of each local revenue stream for Orange County in 2013 for transit are assumed to be: • Y -cent sales tax: $5.0 million • $7 vehicle registration fee: $788,000 • $3 vehicle registration fee increase: $338,000 • Rental car tax revenue: $582,000 Growth rates assumed for each revenue source: • Y -cent sales tax: • Growth rate from 2011 through 2014: 1.0% • Growth rate from 2015 through 2035: 3.6% • $7 vehicle registration fee: 2.0% • $3 vehicle registration fee increase: 2.0% • Rental car tax revenue: 4.0% A total of $25 million would be borrowed over the life of the plan. This borrowing would cover for the large capital expenditures which occur for 3 to 4 years of construction of the light rail component of the plan. Any borrowing would be from capital markets through government bonds, would require approval by the NC Local Government Commission, and would have to meet debt to revenue ratios required by the capital markets for bond issuance. Further details for each revenue source follow. A. One -half cent sales tax in Orange County A one half -cent sales tax in Orange County means that when individuals spend $10.00 on certain goods and services, an additional five cents ($0.05) is added to the transaction to support the development of the Bus and Rail Investment Plan. Purchases of food, gasoline, medicine, health care and housing are excluded from the tax. A one half -cent sales tax in Orange County is estimated to generate $5.0 million in 2013 if active for the full year. Discussions with the NC Dept of Revenue indicate that in the first year 5/23/2012 - Page 122 of the plan, the revenue streams may not be active until April 1St instead of January 1St. The 23 figures in Appendix G: Revenue reflect the partial first -year levy of both a % -cent sales tax and a $10 vehicle registration fee increase. Over the life of the plan to 2035, the sales taxis expected to generate approximately $163 million in Year -Of- Expenditure (YOE) dollars. This tax can only be levied subsequent to a referendum by the Orange Board of County Commissioners and approval by the voters. Revenue from the % -cent sales tax identified in the Bus and Rail Investment Plan for Orange County can be used for financing, constructing, operating and maintain local public transportation systems. The funds can be used to supplement but not supplant or replace existing funds or resources for public transit systems. B. $7 Vehicle Registration Fee in Orange County A seven dollar ($7) vehicle registration fee in Orange County means that when an individual registers a new vehicle or renews the registration for an existing vehicle in Orange County, an additional $7 per year is added to the cost above the other required registration fees for that vehicle. The seven dollar fee in Orange County is expected to bring in $782,000 in 2013 if implemented for a full year. Discussions with the NC Dept of Revenue indicate that in the first year of the plan, the revenue streams may not be active until April 1St instead of January 1st. The figures in Appendix G: Revenue reflect the partial first -year levy of both a % -cent sales tax and a $10 vehicle registration fee increase. Over the life of the plan to 2035, the seven dollar fee is expected to generate $22.5 million in Year -Of- Expenditure (YOE) dollars. The implementation agreement will articulate how this revenue can be utilized. C. $3 Vehicle Registration Fee Increase for Triangle Transit in Orange County A three dollar ($3) vehicle registration fee increase in Orange County means that when an individual registers a new vehicle or renews the registration for an existing vehicle in Orange County, an additional $3 per year is added to the cost above the other required registration fees for that vehicle. An existing $5 fee for vehicle registration supports activities of Triangle Transit, including bus operations and long -term planning. This fee would be increased to $8 when the $3 increase is implemented. The three dollar ($3) fee in Orange County is projected to generate $330,000 in 2013 if implemented for a full year. Discussions with the NC Dept of Revenue indicate that in the first year of the plan, the revenue streams may not be active until April 1St instead of January 1St. The figures in Appendix G: Revenue reflect the partial first -year levy of both a % -cent sales tax and a $10 vehicle registration fee increase. Over the life of the plan to 2035, the three dollar ($3) fee is expected to generate $9.7 million in Year -of- Expenditure (YOE) dollars. The implementation agreement will articulate how this revenue can be utilized. D. Revenue from Triangle Transit's Rental Car Tax 5/23/2012 - Page 123 Triangle Transit operations are partially funded by a five percent (5 %) tax on car rentals in Wake, Durham, and Orange Counties. Under existing policy adopted by the TTA Board, 50% of the rental car tax revenues are dedicated to advancing long -range bus and rail transit. Since a significant portion of all cars rented and driven in the three counties are rented at the RDU International Airport, it is difficult to determine which rentals are driven primarily in one county or another. Therefore, the 50% rental revenues dedicated to long -term transit were allocated by county according to the percentage of population in the Triangle Region, which is: Wake (68 %); Durham (21.5%); Orange (10.5 %). The Triangle Transit rental car tax proceeds directed to project development in Orange County are estimated to be $582,000 in 2013. Over the life of the plan to 2035, the rental car tax is expected to generate $21.3 million in Year -of- Expenditure (YOE) dollars for Orange County. E. NC State Government Funding The plan includes a 25% capital cost contribution by the NC Department of Transportation ( NCDOT) for both light rail and commuter rail projects in Orange County. This level of participation was established by the State in Charlotte's Lynx Blue Line light rail project in 2003. The plan assumes that NCDOT also pays for 10% of bus capital costs (replacement buses, new buses, park and ride lots, etc) consistent with its current practices. Over the life of the plan to 2035, the contributions of NCDOT are expected to total $130.6 million in Year -of- Expenditure (YOE) dollars in Orange County. F. Federal Government Funding The plan assumes that the Federal Government contributes 50% of the capital cost for the light rail project in Orange County. This was the federal level of participation in the Charlotte Lynx Blue Line light rail project and is consistent with federal funding outcomes for most rail projects in the Federal Transit Administration's New Starts program in recent years. The plan assumes that the Federal Government also pays for 80% of bus capital costs, consistent with its current practices, and continues to provide operating appropriations consistent with present Federal Transit Administration operating grant formulas. Over the life of the plan to 2035, the contributions of the Federal Government are expected to total $248 million in Year -of- Expenditure (YOE) dollars in Orange County. G. Transit Fares The plan assumes fares for all operating agencies remain unchanged from the existing fare structures. • Light Rail farebox recovery ratio: 20% • Triangle Transit bus farebox recovery ratio: 15% • Chapel Hill Transit bus farebox recovery ratio: 0% • Orange Public Transportation bus farebox recovery ratio: 3.5% 5/23/2012 - Page 124 24 H. FTA Formula Funds 25 The plan assumes that new bus services will receive partial operating and capital cost contributions through existing formula programs established by the Federal Transit Administration (FTA), and that transit agencies in Orange County will receive those contributions in accordance with historical patterns of funding that existing transit services have received. Over the life of the plan to 2035, FTA Formula funds are expected to total $70.9 million in Year -Of- Expenditure (YOE) dollars in Orange County. I. Additional Revenue Sources This draft Bus and Rail Investment Plan does not rely on additional municipal contributions, public or private third party contributions or value capture forms of revenue. VI. ORANGE FINANCIAL PLAN DATA The following is a list of the total spending for each technology and category identified in the Orange County Bus and Rail Investment Plan to 2035. All figures are in Year of Expenditure dollars (YOE) unless otherwise noted. • Light Rail Capital: $418.3 million ($316.2 million in 2011 dollars) • Light Rail Operations: $59.1 million • Bus Capital: o MLK Bus Lanes - $24.5 million o Miscellaneous Bus Capital Projects- $6.7 million • Bus Operations: $107 million • Amount borrowed by Triangle Transit to execute the plan: $25 million • Amount of debt service payments made by Triangle Transit through 2035: $19.2 million • Hillsborough Intercity Rail Station: $8.9 million Additional specific financial information on each of these plan elements can be found in the Appendices. VII. AGREEMENTS IMPLEMENTATION AGREEMENT: ANNUAL REVIEW AND CHANGES TO THE PLAN The Bus and Rail Investment Plan in Orange County details the specific elements of local and regional bus service, and Light Rail service to be added in Orange County over a 23 -year period. Because of the long time frame for implementation of the Plan and its major capital projects, over time there will be changes and revisions made to the Plan. As the statutory implementation agency, Triangle Transit will work with Orange County, the DCHC Metropolitan Planning Organization (MPO), and the towns of Chapel Hill, Carrboro, Hillsborough, the University of North Carolina at Chapel Hill and Chapel Hill Transit, and the public transit provider in Orange County, to develop and execute an Implementation agreement which details the following aspects of implementation of the Plan: 5/23/2012 - Page 125 (a) Annual review presentations of the activities and progress made in implementation 26 of the Plan by Triangle Transit to the County and the MPO; (b) The process for review and vote by the County, the MPO and Triangle Transit's Board of Trustees or the role of the operating agency regarding on any significant or substantial revisions to the Plan required by changes experienced in revenues received, capital costs, operating expenses, or other substantial issues affecting the Plan; (c) A recognition and preservation of decision making responsibilities of the operating agencies; (d) Responsibility of Triangle Transit for direct disbursement of funds from the revenues received per Section V (above) to the public agency responsible for implementing the bus services set forth in the Plan; and (d) Other necessary provisions regarding implementation of this Plan as agreed to by the County, the MPO, and Triangle Transit. COST SHARING AGREEMENT The capital and operating costs for the 17.3 -mile LRT line will be shared by Orange and Durham counties. Accordingly, a separate cost sharing agreement between Orange County, Durham County and Triangle Transit has been developed. The cost sharing agreement sets forth the respective shares of the capital and operating costs that will be paid by each county for this project that cross both county and municipal borders. TAX LEVY AGREEMENT One additional agreement has been developed by Orange County and Triangle Transit relevant to the plan. In this tax levy agreement Triangle Transit agrees not to levy the half -cent transit sales tax for Orange County in the event of a successful referendum vote on the sales tax until after receiving a Resolution from the Orange County Board of County Commissioners requesting that the tax be levied. VIII. NEW STARTS PROCESS Federal New Starts Funding Process It is anticipated that Federal funds assisting in the planning and implementation of the Durham - Orange Light Rail Transit Project would be secured through the Federal Transit Administration's (FTA) discretionary New Starts program. New Starts is the federal government's primary financial resource for funding transit "guideway" capital investments. Projects seeking New Starts funding — like all federally - funded transportation investments in metropolitan areas — must emerge from a locally - driven, multimodal corridor planning process, as depicted graphically in this chart: 5/23/2012 - Page 126 Alternatives Analysis Selection of Preliminary Locally Preferred Alternatives P U 0000. Scoping L L C Preliminary Engineering/ Draft Environmental impact Statement (PEIDEIS) I N Final Selection o V Locally Preferred Alternative O L Preliminary Engineering/ V Final Environmental Impact Statement E M E Environmental Record of Decision Final Design Construction I 27 Through the jointly adopted 2035 Long Range Transportation plan by the Durham - Chapel Hill - Carrboro MPO (DCHC MPO) and the Capital Area MPO (CAMPO), transportation corridors in greatest need of more detailed planning and analysis were identified. The Alternatives Analysis (AA), completed in 2011, focused on a set of needs and alternative actions to address these needs, and generated information needed to select an option for further engineering and implementation. In February 2012, the DCHC MPO selected a 17.3 -mile light rail corridor from East Durham to UNC Hospitals as the locally preferred alternative (LPA). Triangle Transit, as the local project sponsor, will submit to FTA the New Starts project justification and local financial commitment and request FTA's approval to enter into the preliminary engineering (PE) phase of project development. 5/23/2012 - Page 127 28 During the preliminary engineering phase of project development, local project sponsors refine the design of the proposal, taking into consideration all reasonable design alternatives. Preliminary engineering results in estimates of project costs, benefits, and impacts at a level of detail necessary to complete the federal environmental process. Preliminary engineering for a New Starts project is considered complete when the FTA has issued a Record of Decision (ROD) as required by the National Environmental Policy Act (NEPA). Projects which complete preliminary engineering and whose sponsors are determined by the FTA to have the technical capability to advance further in the project development process must request FTA approval to enter final design and submit updated New Starts information for evaluation. Final design is the last phase of project development, and includes right -of -way acquisition, utility relocation, and the preparation of final construction plans, detailed specifications, construction cost estimates, and bid documents. The FTA typically considers a Full Funding Grant Agreement (FFGA) for a New Starts project during the final design phase of the New Starts project development process. A State FFGA will also be requested by the local project sponsor to supplement federal and local funding sources. With all funding secured, construction on the project will begin. IX. ALTERNATIVE PLAN If it is determined that Federal or State funding for the proposed projects are not available, an alternative plan must be developed. Upon this determination, Triangle Transit will work in collaboration with the citizens, elected officials, and stakeholders from Orange County, Chapel Hill Transit, DCHC MPO and Durham County to identify next steps toward the development of a revised plan. X. CLOSING SUMMARY The Bus and Rail Investment Plan in Orange County is the result of years of collaborative work among Orange County elected officials and civic leaders, regional stakeholders, municipal and county staff and Triangle Transit. The plan consists of a balance of bus improvements and rail investment to help accommodate the population and employment growth that the region is expected to experience in the next 25 years. The proposed plan addresses the ongoing need to provide more options to transit riders with improved and expanded bus and rail connections. Once implemented, the residents of Orange County will be able to have greater access to jobs, shopping, and activity centers such as downtown Chapel Hill and Carrboro, the University, or UNC Hospital. Additionally, the plan will provide core infrastructure investment that will help support the goals and objectives of local land use plans in Orange County and its municipalities. In 5/23/2012 - Page 128 particular, as evidenced in communities across the country, investment in light rail has proven to be a great motivator for private companies to build transit - oriented development at station locations along the rail corridor. This kind of more intense development generally consists of a mixed -use, walkable environment that can provide a more sustainable alternative to the suburban growth pattern that exists today, while allowing more open space to be preserved. All the elements listed in the Draft Bus and Rail Investment Plan of Orange County are fiscally constrained. At every turn, the Plan is conservative in revenue assumptions and incorporates contingencies for capital and operating expenditures. The draft plan has been shared with the general public, Carrboro Board of Aldermen, Chapel Hill Town Council, the Hillsborough Town Commissioners, the DCHC MPO, the Burlington - Graham MPO and the Orange County Commission. The draft plan will be considered for approval by the DCHC MPO, the Burlington— Graham MPO, the Triangle Transit Board of Trustees, and the Orange County Board of Commissioners. The Orange County Board of Commissioners will determine if and when to set a referendum date. Once a referendum passes, work can begin on implementation of the Bus and Rail Investment Plan. ❖ As directed by NCGS 105 - 510.6, Triangle Transit drafted and developed this Plan, working in collaboration with the citizens, elected officials, and stakeholders from Orange County, the DCHC MPO, and Chapel Hill Transit. 5/23/2012 - Page 129 30 DRAFT Bus and Rail Plan In Orange County Appendix A: Master Assumption List Assumptions in Orange County and Durham County Financial Plans for Bus and Rail Transit May 21,2012 ASSUMPTIONS Sales Tax Growth Rate to 2015 ORANGE DURHAM Sales Tax Growth Rate 2016 and Beyond 1.00% 2.00% Light Rail Capital Cost Responsibility(Percentage) 3.60% 3.50% Light Rail Operating Cost Responsibility(Percentage) 22.95% 77.05% Light Rail Capital Cost Share Based on Current Cost Estimates ($2011 millions) $ 23.95%316.2 76.05% Light Rail Operating Cost Share Based on Current Cost Estimates($2011 millions) L $ 3.46 $ -._____1 10.98 MLK Bus Lanes Capital Cost ($2011 millions) MLK Bus Lanes Operating Cost* $ 22.1 NA p g ($2011 millions) _ $ NA Hillsborough Intercity Train Station Capital Cost ($2011 millions) Hillsborough Intercity Train Station Operations Cost ''' $4.0 $8.0 NA Amount borrowed by Triangle Transit to execute the plan ($2011 millions) Not part of f p plan Plan Minimum Cash Balance ($2011 millions) $25 $165 $4.1 $12.9 OUTCOMES New Bus Hours in First Five Years of Plan Total Cumulative New Bus Hours by End of Plan (Year 2035) 34,650 87, 00 40,950 87,5500 Opening Year for Hillsborough Intercity Train Station 2015 Opening Year for MLK Bus Lanes NA Opening Year for Light Rail 2019 NA "Rail Dividend" Bus Hours that can be re-directed when Light Rail Opens 2026 2026 g p 30,000 45,000 12,000 35,000 Plan Cash Balance in 2035 ($2035 millions) r $4 Plan Cash Balance in 2035 ($2011 millions) $45 $ *MLK Bus Lanes have no operating costs because existing, already-paid-for bus services will be-re-organized to use the bus lanes **Operations cost of Intercity Rail Station assumed to be covered in existing station plans by NCDOT Rail Division and Town of Hillsborough. Capital Cost contribution of the Orange County plan is 10% of total capital cost for Hillsborough train station. Light green indicates updated cell or figure since previous draft i CO 32 TOTAL Plan Revenues and Costs to 2035, and LOCAL Costs to 2035: All Numbers Are in Year-Of-Expenditure (YOE) Dollars Orange County Plan Revenue, All Sources to 2035: Total Revenue $706.0m 2.2%�3.5% ®Sales Tax($162.9m) 10.0%, El Vehicle Registration Fees($32.2m) %,\ El Rental Tax($21.3m) IN 23. Federal Share($247.9m) 8.5% i 4.6% 11 State Share ($130.6m) 3.0% FTA Formula Funds($70.9m) 35.1°% Fares($15.6m) Bonds($24.5m) How ALL Dollars Are Spent to 2035: Total Cost $659.9m 2.7% 1'®%X2.9% ®LRT Capital ($418.3m) A-41 D LRT Operations($59.1m) 16.2% El Hillsborough Train Station ($8.9m) M MLK Bus Lanes($24.5m) 1.4% 11 Bus Operations ($106.8m) 8.9% Buses ($17.6m) Bus Capital Projects($6.7m) Debt Service($19.2m) How LOCAL Orange County Dollars Are Spent to 2035: $268.7m 7.1% ®LRT Capital ($104.6m) 0.7% F-1 LRT Operations ($29.6m) Hillsborough Train Station ($0.9m) a MLK Bus Lanes($6.1m) la Bus Operations ($82.7m) ►_i Buses($1.8m) LJ Bus Capital Projects ($24.5m) 2.3% �0.3% Debt Service($19.2m) Note:small differences and percentages not adding exactly to 100.0%may be due to rounding 33 DRAFT Bus and Rail Plan In Orange County Appendix B: Proposed Bus Service Enhancements ORANGE COUNTY DRAFT BUS PLAN -FUNDED AND FUTURE COMPONENTS REGIONAL SERVICES-FUNDED FIRST FIVE YEARS Service Type PROJECTS Enhanced or Cumulative New New Service Hours Service Description Increase peak-hour frequency of the express route between Durham and Chapel Hill to Regional Exp Carrboro-Chapel Hill-Durham Express(Route 405) Enhanced 1,506 15 minutes during the peak commute,directly serve Downtown Carrboro with rush hour service to Durham. Regional Exp Mebane-Hillsborough-Durham Express Introduce Service New 2,510 Introduce a new express route serving Mebane,Hillsborough,and Durham. Regional Exp Carrboro-Chapel Hill-Durham Express(Route 405)-mid-day Enhanced 4,016 Increase frequency of the express route between Durham and Chapel Hill or Carrboro to 30 minutes during the mid-day. Regional Exp Carrboro-Chapel Hill-Durham Express(Route 405)-Sundays New 4,640 Introduce Sunday service on route between Durham and Chapel Hill or Carrboro. Regional Chapel Hill-Regional Transit Center via Southpoint(Route 800)-Sundays New 5,264 Introduce new Sunday service to the existing TTA route 800. Regional Exp Carrboro-Chapel Hill-Durham Express(Route 405)-Saturday Enhanced 5,484 Extend service between Durham and Chapel Hill or Carrboro to 11pm on Saturdays. Regional Chapel Hill-Regional Transit Center via Southpoint(Route 800)-Saturdays Enhanced 5,704 Extend service between RTP and Chapel Hill(via Southpoint)to 11pm on Saturdays. Regional Route 800-SW Durham(Southpoint)-Chapel Hill peak Enhanced 7,210 Phase 1 service improvement-increase peak hour frequency on the existing TTA Route 800.Currently the route operates at 30-minute frequency. Regional Exp Chapel Hill-Raleigh Express(Route CRX)-peak Enhanced 7,963 Introduce mid-day service on the express route between Chapel Hill and Raleigh. Regional Hillsborough-Chapel Hill(Route 420)-peak:IMPLEMENTED In 2012 Enhanced 7,963 Increase frequency of the regional route between Hillsborough and Chapel Hill to 30 minutes during the peak commute. Re.ional Additional service Hours TBD Enhanced 8 200 237 additional hours that ma au!ment an of the services above REGIONAL SERVICES-UNFUNDED,FUTURE PRIORITIES AFTER YEAR 2020 Service Type PROJECTS EnhNe`ed or Cumulative Service Description Regional Exp Mebane-Hillsborough-Durham Express Expansion New g Y04 Increase the frequency on an express route serving Mebane,Hillsborough,and Durham to 30 minutes at peak. Regional Hillsborough-Chapel Hill(Route 420)-mid-day Enhanced 13,722 Increase frequency of the regional route between Hillsborough and Chapel Hill to 30 minutes during the mid-day. Regional Exp White Cross to Carrboro to Chapel Hill Express New 15,228 Phase I-Introduce a new express route serving Alamance County and Chapel Hill(via NC-54)at an hourly frequency. Regional Exp White Cross to Carrboro to Chapel Hill Express New 16,734 Phase II -Introduce a new express route serving Alamance County and Chapel Hill(via NC-54)at a 30-minute frequency. Regional Exp Chapel Hill-Raleigh Express(Route CRX)-mid-day Enhanced 18,366 Introduce mid-day service on the express route between Chapel Hill and Raleigh. Regional Chapel Hill-Regional Transit Center via Southpoint(Route 800)-mid-day Enhanced 19,997 Increase frequency of the regional route between RTP and Chapel Hill(via Southpoint) to 30 minutes during the mid-day. Regional Route 800-RTC via SW Durham(Southpoint)-Chapel Hill peak Enhanced 20,813 Phase 2 service improvement-increase frequency of the existing Route 800 between RTP and Chapel Hill(via Southpoint)to 15 minutes during the peak commute. Regional Chapel Hill-Regional Transit Center via Woodcroft(Route 805)-mid-day Enhanced 21,691 Introduce added mid-day trips to regional route between Woodcroft and Chapel Hill. Prepared by Triangle Transit April 23,2012 CO Orange County Transit Plan: Proposed Regional Bus Service Improvements ® ir' 7----------- )-- , , ,,i Ala , — —,r t 1 ow -if . �x LEGEND ' `�;# { :Triangle Counties ;, 8s F`" '?C. r ; ' <, ��Orange Townships N��4p � �' � �" r I_—!Hillsborough •Rq 6u . r I'Chapel Hill �r.f li ,� c� Carrboro p e; y� * y° Streets j Durham Tech ' - sv' r! ••Chapel Hill-Raleigh Express Oran u am Cam•us •' •" Downtown ; /IPA,- �.Carrboro-Chapel Hill-Durham . � �, Durham , �`' Mebane-Hillsborough-Duke-Durham r Duke wx � '� +YtiP . Chapel Hill-South Durham-RTP t'� q 1 NCCU 4 ' ��� �° `�" 'N•mwHillsborough-Chapel Hill C .4 -,";',,:.s,,, i ° f Park-Ride Catchment Area D - Std ' c'Y ' * /� r I .. 4` .,,,, ;°' P' Existing P-R Lots {4q '8 rcP Potential P-R Lots - ' Other bra ( ; 2010 Residents Per Sq. Mile r • � I / 0 to 250 P i 250 to 500 ~ ' .. ,ti' ,A 1500 to 1,000 -- •-•___ ° �-' �/�� 1,000 to 2,000 °"• 9yA -2,000 to 3,500 TC JJ -3,500 to 5,000 I -5,000 to 10,000 -10,000 and above r 0 2.5 5 7.5 Created by Triangle Transit Staff Miles cri April 23,2012 CA) ORANGE COUNTY DRAFT BUS PLAN -FUNDED AND FUTURE COMPONENTS HILLSBOROUGH LOCAL AND RURAL ORANGE COUNTY SERVICES-FUNDED FIRST FIVE YEARS Service Type PROJECTS Enhanced or Cumulative New Service Description New Service Hours Local Hillsborough Circulator Enhanced 2,008 Operate Hillsborough Circulator Mon-Fri,B hours per day Local Improve Service in Unincorporated Orange County Enhanced 4,200 _Improve capacity of demand response service to rural areas Local Hillsborough Circulator Phase 2 Enhanced 4,702 Add Saturday Service to Hillsborough Circulator Local Improve Service in Unincorporated Orange County Enhanced 6,887 Further improve capacty of demand response service to rural areas HILLSBOROUGH LOCAL AND RURAL ORANGE COUNTY SERVICES -UNFUNDED,FUTURE PRIORITIES AFTER YEAR 2020 I I I I NA-All identified needs funded in first five years. Prepared by Triangle Transit Apnl 23,2012 W Cr) , . Orange County Transit Plan: Proposed Hillsborough and Rural Bus Service Improvements OR tp, k LI rl c-1 ,wo.'.- 5Iall^o Oco Pocbte : CS' \ 1 Oranqo CI, > ,, ----■ _ - ----------____ ----..., /as DURHAM ma /iTO -(0\ , NC3 LEGEND AlC 54 r Hillsborough I Chapel Hill tkl 1---learrboro 1 Streets .,‘. ........A, =Enhanced OPT Dial-A-Ride Servic 1 0 2 4 6 .V110111•■ MIME watimato Miles co --J ORANGE COUNTY DRAFT PLAN-FUNDED AND FUTURE COMPONENTS CHAPEL HILL TRANSIT BUS SERVICE OPTIONS Service Type Project Enhanced or New Cumulative New Service Hours Local Service Improvements Chapel Hill,Carrboro,UNC in the 15/501 corridor Enhanced 7,279 Local 54 Corridor Improvements(Orange and Durham Counties Enhanced 4,016 Local Support existing services Enhanced 6,000 Local Chapel Hill-Carrboro-UNC Saturday Service New 5,096 Sub-Total 22,391 Local Chapel Hill-Carrboro-UNC Sunday Service New 3,640 Local Extend evening service in Chapel Hill Carrboro UNC Enhanced 4,080 Regional Pittsboro-Chapel Hill Express Enhanced 816 Local Improve peak hour frequency Chapel Hill Carrboro UNC Enhanced 2,209 Total 33,136 This list of service priorities supplied by Chapel Hill Transit exceeds the 22,332 bus hour budget currently expected to be available in the plan for Chapel Hill Transit.Roughly a third of the proposed service hours will not be funded in the plan.Chapel Hill Transit and its partners will make a final determination of service priorities based on extensive public involvement and analysis in order to fit within the approximately 22,000 hour limit called for in the financially constrained plan. CO Co Bus Operations Total Bus Operations and Maintenance Costs by Year Year 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Bus Hours 9,000 15,750 24,750 34,650 34,650 34,650 34,650 34,650 34,650 34,650 34,650 34,650 Cost($YOE thousands) $ 905 $ 1,608 $ 2,565 $ 3,702 $ 3,817 $ 3,935 $ 4,057 $ 4,183 $ 4,313 $ 4,447 $ 4,584 $ 4,727 Year 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Bus Hours 34,650 34,650 34,650 34,650 34,650 34,650 34,650 34,650 34,650 34,650 40,950 Cost($YOE thousands) $ 4,873 $ 5,024 $ 5,180 $ 5,341 $ 5,506 $ 5,677 $ 5,853 $ 6,034 $ 6,221 $ 6,414 $ 7,815 Total Bus Operations$YOE Cost to Year 2035 $ 106,782,735 Bus Operations Costs assumed to be split according to following percentages: Federal 8.9% State 10.0% Local 77.6% Fares 3.5% ca co 40 DRAFT Bus and Rail Plan In Orange County Appendix C: Bus Capital Enhancements Bus Capital and Vehicle (Bus) Purchases/Replacements Total Bus Purchases(New and Replacement Buses) Year 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 New Buses Purchased 4 3 4 4 - - - - - - - _ Replacement Buses Purchased Cost($YOE thousands) 1,606 1,222 1,654 1,876 - - - - - - - Year 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 New Buses Purchased - - - - - - - - - - 3 Replacement Buses Purchased 4 3 4 4 - - - - - - - Cost($YOE thousands) 2,245 1,736 2,386 2,706 - - - - - - 2,132 Total Bus Purchases$YOE Cost to Year 2035 $ 17,564,162 Total Bus Capital Project Spending(Amenities,Transit Centers, Park/Ride Lots,Sidewalks,etc) Year 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Cost($YOE thousands) 656 2,664 3,379 - - - - - - - - Year 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Cost($YOE thousands) - - - - - - - - - - - Total Bus Capital Projects$YOE Cost to Year 2035 $ 6,699,000 Bus Purchases and Bus Capital projects assumed to be split according to current trend: Federal 80% State 10% Local 10% 42 DRAFT Bus and Rail Plan In Orange County Appendix D: Hillsborough Train Station Expenditures Hillsborough Intercity Rail Station Total Rail Station Construction Costs by Year Year 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Cost($YOE thousands) $ 875 $ 3,552 $ 4,506 $ - $ - $ - $ - $ - $ - $ - $ - $ Year 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Cost($YOE thousands) $ - $ - $ - $ - $ - $ - $ - $ - $ - $ $ Total Hillsborough Intercity Rail Station$YOE Cost to Year 2035 $ 8,932,229 Hillsborough Rail Station assumed to be split according to pattern for other NCDOT Rail Division-approved stations Federal 80% State 10% Local 10% NCDOT Rail Division has studied two possible station designs.The option in the plan includes a permanent station. A modular, temporary station can be built for less money,approximately$4 million in.$2011 dollars. Examples of the type of station the$8.9 million YOE dollar investment projected above would build can be found in Cary and Kannapolis. co 44 DRAFT Bus and Rail Plan In Orange County Appendix E: MLK Bus Lanes Expenditures MLK Bus Lane Project Total MLK Bus Lane Project Costs by Year Year 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Cost($YOE thousands) $ 694 $ 704 $ 4,007 $ 7,456 $ 7,892 $ 3,703 $ - $ - $ - $ - $ - $ - Year 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Cost($YOE thousands) $ - $ - $ - $ - $ - $ - $ - $ - $ _ $ _ $ _ Total MLK Bus Lane$YOE Cost to Year 2035 $ 24,456,259 Project Costs are anticipated to follow the percentages below within the FTA Small Starts program Federal 50% State 25% Local 25% .A 01 46 DRAFT Bus and Rail Plan In Orange County Appendix F: Light Rail Expenditures Durham-Orange Light Rail Expenditures: Capital & Operating to 2035 Total Light Rail Capital Spending Year 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Cost($YOE thousands) $ 3,258 $ 3,306 $ 5,034 $ 3,460 $ 3,567 $ 5,517 $ 16,757 $ 28,530 $ 31,211 $ 68,984 $ 120,898 $ 96,797 Year 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Cost($YOE thousands) $ 31,009 - - - - Total Bus Purchases$YOE Cost to Year 2035 $ 418,327,293 Total Light Rail Operations Spending Year 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Cost($YOE thousands) - - - - - - - - Year 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Cost($YOE thousands) - $ 5,135 $ 5,294 $ 5,458 $ 5,627 $ 5,802 $ 5,982 $ 6,167 $ 6,358 $ 6,555 $ 6,759 Total Light Rail Operations$YOE Cost to Year 2035 $ 59,136,705 The capital cost of the Durham-Orange Light Rail project is anticipated to be split as follows: Federal 50% State 25% Local 25% The operating cost of the Durham-Orange Light Rail project is anticipated to be split as follows: Federal 20% State 10% Local 50% Fares 20% v 48 DRAFT Bus and Rail Plan In Orange County Appendix G: Revenues by Year Orange County Plan Revenues Total Orange County Revenues by Year($YOE millions) Year 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 1/2-Cent Sales Tax* $ 3.9 $ 5.0 $ 5.0 $ 5.2 $ 5.4 $ 5.6 $ 5.8 $ 6.0 $ 6.2 $ 6.5 $ 6.7 $ 6.9 $7 Vehicle Registration Fee* $ 0.6 $ 0.8 $ 0.8 $ 0.8 $ 0.9 $ 0.9 $ 0.9 $ 0.9 $ 0.9 $ 0.9 $ 1.0 $ 1.0 $3 Vehicle Registration Fee* $ 0.3 $ 0.3 $ 0.4 $ 0.4 $ 0.4 $ 0.4 $ 0.4 $ 0.4 $ 0.4 $ 0.4 $ 0.4 $ 0.4 Car Rental Tax(existing) $ 0.6 $ 0.6 $ 0.6 $ 0.7 $ 0.7 $ 0.7 $ 0.7 $ 0.8 $ 0.8 $ 0.8 $ 0.9 $ 0.9 FTA Formula Funds $ 2.3 $ 2.4 $ 2.4 $ 2.5 $ 2.6 $ 2.6 $ 2.7 $ 2.8 $ 2.8 $ 2.9 $ 3.0 $ 3.0 Federal Projects Share $ 4.5 $ 8.0 $ 12.2 $ 7.0 $ 5.7 $ 4.6 $ 8.4 $ 14.3 $ 15.6 $ 34.5 $ 60.4 $ 48.4 State Projects Share $ 1.4 $ 1.9 $ 3.5 $ 3.3 $ 3.2 $ 2.7 $ 4.6 $ 7.6 $ 8.2 $ 17.7 $ 30.7 $ 24.7 Fares $ 0.0 $ 0.1 $ 0.1 $ 0.1 $ 0.1 $ 0.1 $ 0.1 $ 0.1 $ 0.2 $ 0.2 $ 0.2 $ 0.2 Bond Proceeds $ - $ - $ - $ - $ $ $ $ $ $ Total Revenue By Year $ 14.4 $ 20.2 $ 26.2 $ 21.1 $ 20.2 $ 18.9 $ 24.9 $ 34.1 $ 36.5 $ 65.2 $ 110.4 $ 104.5 Year 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 TOTAL 1/2-Cent Sales Tax $ 7.2 $ 7.4 $ 7.7 $ 8.0 $ 8.3 $ 8.6 $ 8.9 $ 9.2 $ 9.5 $ 9.9 $ 10.2 $ 162.9 $7 Vehicle Registration Fee $ 1.0 $ 1.0 $ 1.0 $ 1.1 $ 1.1 $ 1.1 $ 1.1 $ 1.1 $ 1.2 $ 1.2 $ 1.2 $ 22.5 $3 Vehicle Registration Fee $ 0.4 $ 0.4 $ 0.4 $ 0.5 $ 0.5 $ 0.5 $ 0.5 $ 0.5 $ 0.5 $ 0.5 $ 0.5 $ 9.7 Car Rental Tax(existing) $ 0.9 $ 1.0 $ 1.0 $ 1.0 $ 1.1 $ 1.1 $ 1.2 $ 1.2 $ 1.3 $ 1.3 $ 1.4 $ 21.3 FTA Formula Funds $ 3.1 $ 3.2 $ 3.3 $ 3.4 $ 3.4 $ 3.5 $ 3.6 $ 3.7 $ 3.8 $ 3.9 $ 4.0 $ 70.9 Federal Projects Share $ 17.3 $ 1.4 $ 1.9 $ 2.2 $ - $ - $ - $ State Projects Share $ 8.5 $ 1.2 $ 1.3 $ 1.4 $ 1.1 $ 1.1 $ 1.2 $ 1.2 $ 1.3 $ 1.3 $ 1.7 $ 130.6 Fares $ 0.2 $ 1.2 $ 1.2 $ 1.3 $ 1.3 $ 1.4 $ 1.4 $ 1.4 $ 1.5 $ 1.5 $ 1.6 $ 15.6 Bond Proceeds $ 1.2 $ - $ - $ - $ - $ $ $ $ Total Revenue By Year $ 41.2 $ 18.3 $ 19.4 $ 20.2 $ 18.3 $ 18.9 $ 19.5 $ 20.1 $ 20.7 $ 21.3 $ 24.1 $ 706.0 Total Orange County Transit Plan$YOE Revenue to Year 2035 $ 706,000,000 *Revenue in first year is 75%of full value because revenue source is anticipated to be active on 4/1/2013,not 1/1/2013 Co Ame,.�- ,a INTERLOCAL IMPLEMENTING AGREEMENT ON TRANSIT FUNDING FOR ORANGE COUNTY BETWEEN ORANGE COUNTY BOARD OF COMMISSIONERS AND TRIANGLE TRANSIT AUTHORITY This Interlocal Agreement ( "Agreement ") dated 1 2012 is entered into by and between Orange County ( "Orange "), a North Carolina County, and Research Triangle Regional Public Transportation Authority, d /b /a Triangle Transit ( "TTA "). Orange and TTA may be referred to individually as "Party" and collectively as "Parties ". This Agreement is made pursuant to Article 20 of Chapter 160A of the North Carolina General Statutes. Whereas, the Parties each desire to provide for the future transportation needs of Durham and Orange, understanding that enhanced mobility options will support a high quality of life, strengthen economic development, and enhance sustainability; and Whereas, the Parties, together witti - Durham County, Durham County and Research Triangle , Interlocal Agreement for Cost Sharing for LRT Rail` F outlining the provision of costs related to the plann;: maintenance of a 17.3 mile passenger rail service run! having 17 stations, four of which are located in Orange unty entered into the Orange gional Public Transportation ect ( "Cost Share Agreement ") construction, operation, and g from Durham to Orange and wri y (the "LRT Project "); and Whereas, the Par#isacknowledge that the LRT'Project will be managed, planned, constructed," maintained and operated by the TTA according to Orange County's Bus and Rail. Invesli" Plan ( "BRI Plan ") as adopted or subsequently modified by the Parties, which plan; shall be modified and amended as provided in this Agreement. Now therefore, in light of the mutual 'covenants contained herein the Parties hereby agree as follows: 1. APPROVAL OF THE TRANSIT PLAN: Orange has previously approved the BRI Plan subject to the Parties' entry into and approval of this Agreement. The BRI Plan details funding sources and use, governance, local rail priorities, bus service expansion strategy, structure, and financial implementation. 2. TRANSIT SPECIFIC FUNDING SOURCES: The parties agree that additional funds for transit are needed locally and that new local tax sources of revenue, as allowed by the North Carolina General Assembly, should be pursued. The taxes or fees that should be considered are: a. An additional Y cent sales tax for all non - exempted goods sold within Orange County. This source shall require the approval of over 50% of the voters in a referendum to be enacted. Page 1 of 10 b. A new $7.00 vehicle registration fee on all vehicles registered within Orange County, as decided by the Orange County Board of County Commissioners ( "BOCC "). c. A $3.00 increase in the existing vehicle registration fee on all vehicles registered within Orange County. This fee would only go into effect if the TTA Board of Trustees approves the increase. This Agreement incorporates the BRI Plan in full by reference (Attachment 1). The BRI Plan sets forth the sources of revenue, expected amounts of revenue received over the term of the BRI Plan, the allocation of revenue for bus and rail projects and services, and the lead provider of each ";service. 3. GOVERNANCE: Future decision - making authority regarding the BRI Plan shall lie with the BOCC. The parties agree tv ,abide by the final decisions of the BOCC subject to the terms of this Section. a. The parties agree that the BOCC will receive annual reports by August 1 regarding the status of the plan and may evaluate the;effectiveness of this Agreement and efficiency and effectiveness of the BRI Plan. The BOCC evaluation will be based on municipal input, public input, financial health of the BRI Plan, including revenues, expenditures and timing, and the status of transit project implementation. If issues are identified, the Parties to this Agreement grant the BOCC the power to request special reporting from the service district, the Orange County Transit Plan Partnership, or any transit provider. Once special reporting is.requested the BOCC may, with a supermajority vote, prohibit_the -;use of Grange County generated local funds until such time as the identified issue(s) is satisfactorily addressed. Any'..':,. route that is funded with aforesaid revenues between cities or betweem counties (excepting that portion of Chapel Hill in Durham County and between Chapel Hill and Carrboro) is a decision of the BOCC since the effect of that route has regional significance and the impact on inter - county or intra= county agreements. C. Higher revenues than those projected in the financial model shall be held by TTA in reseiiie in a separate account for a period of at a minimum two years. The ":�BdCC may by majority vote, authorize the allocation of additional monies for buses, small capital, or continue to hold the funds in reserve for future larger capital programs such as Small Starts or Very Small Starts applications. d. An advisory board will be created to be known as the Orange County Transit Plan Partnership. The five member board will consist of one member from each of the entities (Chapel Hill Transit, Hillsborough, and Mebane) and two members from the BOCC. Advisory Board members shall be appointed by the BOCC and the board and its members shall be subject to the terms of the Orange County Board of County Page 2 of 10 Commissioners Advisory Board Policy document and any associated board specific policy document. Information on major recommendations related to the BRI Plan and/ or the Orange County local transit tax revenue shall be distributed to the Parties at least 30 days prior to the advisory board's recommendation. Recommendations related to funding sources, investment priorities, and financial bonding shall be considered major recommendations. 2. Elected officials representing any of the advisory board member entities may request a "directed vote" from their board representative. When this type of vote is requested the representative may only vote as directed by a majority vote of the elected body. 3. All proposed changes to,the Orange County Area Transit Plan shall be routed through the i6rham Chapel Hill Carrboro Metropolitan Planning Organization ( "MPO ") standard plan modification procedure if and when required This procedure shall include review by the Transportation" Coo rdinating Committee, applicable public outreach, a public comment period, and public hearing. 4. The MPO and Orange County shall review and have the statutory authority to approve the initial BRI Plan".,. The BOCC shall review end may "approve all amendments to the BRI Plan as provided in 4. LOCAL FUNDING FOR FIXED GUIDEWAY SERVICE: Orange approved a Locally'Preferred Alternative in February of 2012 that noted a corridor alignment and'- end points '(i.e. length), as well as, a fixed guideway technology chosen to be ;Light Rail. ' The use of funds noted herein to be implemented will be in accordance with the BRI Plan and the Cost Share Agreement. 5. LOCAL FUNDING FOR BUS SERVICE: a. 1. In accordance with the non - supplantation mandate set out in NCGS 105 -510 the parties to this Agreement agree to maintain the equivalent hourly service and associated dollar amount of non -sales tax local transit investment at or above the level budgeted on August 1, 2009. To meet this expectation, a financial report (detailing the amount of non -sales local tax money spent and verifying that at least hours and $ was spent) will be produced annually by TTA. Through separate agreement TTA shall require Chapel Hill Transit to produce such annual financial report. Orange shall require Orange Public Transportation to produce such annual financial report. Page 3 of 10 3 2. The Parties acknowledge that the majority of service and non -sales tax funds will come from existing sources as detailed in Table 1 during the initial years of BRI Plan implementation. 3. A full description of each transit provider's fixed bus route summary is required to establish baseline existing services. Associated services and capital (i.e. bus stops, etc.) should be included as well as funding sources. New and expanded routes will either develop a new bus route description and /or note the expansion of existing route and the associated bus hours. 4. The Parties acknowledge that in future years of BRI Plan implementation the use of new funds as authorized in Articles 43, 50 and 51 of NCGS Chapter 105 will be initialized as formulated in the BRI Plan but may be reapportioned, through an amendment to this Agreement, based on population and as determined by the BOCC and advised by the Advisory Board of the Orange County Transit Plan Partnership. See Table 2 and 3. Entity -."Au �ust 1, 2009 Funding Level Chapel Hill Transit Hours Dollars • Town of Chapel Hill • Town of Carrboro uran a L;oupty Hours Dollars Irian le Transit Hours Dollars 5. Each provider ret'ams- authority to modify existing routes within these parameters. Minor motlifications to existing routes, including but not limited to alterations of stop.` "locations, roads travelled between stop locations, or route extensions consisting of less than one mile in distance, shall not entitle any provider to utilize Article 43 revenues for those routes. Page 4 of 10 4 5 b. Apportionment of County Vehicle Tag Fee Monies for Existing Service Apportionment of funds for existing services will be as follows: Orange County Population Distribution (Census 2010) Table 2 Areas Population Percenta a Hours Dollars Chapel Hill 54,397 40.66% Carrboro 19,582 14.64% Chapel Hill - Carrboro Subtotal 73,979 55.29% 3,317 $321,749 Unincorporated Orange Coun 51,942 38.82% Hillsborough 6,087 Mebane 1,793 1.34% Rural /Central Orange Area Subtotal 59,882 44.71% -2`682 $260,212 Orange County ." Total Po ulation 133,801 100% 1. The Parties acknowledge that 75 6 percent of vehicle tax revenues will be used to support existing service This percentage is equivalent to approximately 6000 hours arts /or $582,UU0 (@ $97 /hour). The remaining vehicle tag revenueequates to approximately 1938 hours and /or $187,986 which wil} be, used for new and expanded service. The BOCC may distribute its share of monies to other transit providers as t',determines by resolution. If more than 6,000 hours or 75.6% is used, then . monies for new and expanded service will be reduced. The monies ($260,212) noted to fund approximately 2,682 hours are calculated at $97 /hour operating cost, which is the rate used for the vast majority of the providers (CHT and TTA) in the bus service plan, `however OPT operated at approximately $58 /hour in FY2011/12. For those existing services provided by OPT or future contractual provider, the allocation of monies will be based on the effective hourly operations rate of that provider. Monies saved from the difference in $97 /hour vs $58 /hour (FY2011 -12) will be employed in the Rural /Central Orange Area or the associated regional connectivity of the above area as decided by the BOCC by resolution. NOTE: A full description of each fixed bus route summary is required to establish baseline existing services. Description should include, but not be limited to, service provider, service type, route name and description, map and days and hours of service. Associated services and capital (i.e. bus stops, etc.) should be included as well as funding sources. New and expanded Page 5 of 10 routes will either develop a new bus route description and /or note the expansion of existing route and the associated bus hours. If more than 6,000 hours or 75.6% is used, then monies for new and expanded service will be reduced. C. Apportionment of % cent transit sales tax and other revenue sources not outlined in 5(a) and 5(b) above to support new and expanded services This referenced system is used in the levy of the "Local Government Sales Use Tax" to allocate monies from the Secretary of State to TTA as shown to support new and expanded transit services in an area and region to the service provider of the specific route. The BOCC will be responsible to designate providers or prioritize routes for regional (multi - county), or intercity (e.g. Hillsborough to CHT area) route decisions. Page 6 of 10 1.1 7 Table 3 (2012 Estimate Entity Hours $ Amount ** 2035 Total Less Support Existing Service Remaining 40,950 6,000 34,950 $3,972,150 $582,000 $3,390,150 Orange Count R, H, M/D Triangle Transit - Regional and intercity OC/TTA Subtotal Chapel Hill Transit CH,C,UNC CHT Subtotal . 2018 Total 34,650 $3,361,050 Less Support ExistingService 6,000 $582,000 Remaining 28,650 $2,779,050 Orange Count R, H, M/D Triangle Transit - Regional and intercity OC/TTA Subtotal Chapel HiILTtansit CH,C,UNC CHT Subtotal 2016 Total,; 28, 350 $2,749,950 Less Su ort, Existing Service $582,000 Remaining 22,350 1 $2,167,950 e County (R, le Transi#. regional and i 'A Subtotal Chapel Hill Transit (CH,C,UNC) CHT Subtotal ** Assumed at $97 /hour - Hourly costs operated at lower than assumed can accrue to similar service areas and /or service function (i.e. rural, regional, local CH = Chapel Hill, C = Carrboro, H = Hillsborough, M = Mebane, D = Durham, R = Rural, UNC = University of North Carolina Page 7 of 10 6. PERFORMANCE OF TRANSIT: The Parties agree that every effort will be made to ensure that provided transit services are safe, reliable, and efficient. TTA, as the implementing agency, shall report annually to the Commissioners and the MPO on progress towards implementation of the BRI Plan. At a minimum, transit services will be evaluated annually by transit. providers and reported to the BOCC and the Orange County Transit Plan Partnership Advisory Board. These periodic evaluations will be a collaborative and cooperative process between the jurisdictions receiving transit service and the transit service providers with a goal of making services successful from both a coverage and market objective. The Parties will make available to the public an annual report detailing costs, expenditures, and the status of the implementation of the BRI Plan. a. The BOCC, with an advisory recommendation from the Orange County Transit Plan Partnership Advisory Board, ' may°. utilize the transit service performance standard guidelines (urban;" rural ands „demand response) and ridership trend data to make a determination as to , whether any changes to transit services are warranted from monies related to .,new and expanded service. Performance guidelines will be jointly developed acid agreed to by the BOCC and transit providers. Such guidelines shall be developed within two years of the effective date; of this Agreement. b. Transit providers sha described in the BRI Plan. for providing transit services as b. If the New Starts application for the LRT Project in accordance with the Locally Preferred Alternative Js unsuccessful then a re- analysis of the cost -share agreement and, new,-proposal must be accomplished before a new initiative is undertaken. The timeframe to determine success is five years from the effective date of this Agreement. This provision shall be reviewed annually. 8. TERM AND TERMINATION a. The term of this Agreement shall be from the date first above recorded to and including June 30, 2035. Upon its expiration the Agreement may be renewed upon mutual agreement of the Parties for successive three -year terms. b. The Agreement may be terminated upon mutual agreement of the Parties or by either of the Parties upon a material breach by the other Party. Page 8 of 10 9. OPERATION OF THIS AGREEMENT: Except to the extent provided otherwise in 9 this Agreement, it is agreed that the Orange County Manager shall designate persons to carry out Orange County's obligations under this Agreement and the General Manager of TTA shall designate persons to carry out TTA's obligations under this Agreement. 10. AMENDMENTS AND OTHER ASPECTS FOR THE IMPLEMENTATION OF THE BRI PLAN a. The BRI Plan shall be reviewed and amended as may be necessary subject to the following provisions: 1. Review of the BRI Plan for efficiency and effectiveness by transportation staff for Orange shall occur every two years. 2. Orange transportation staff and /or the Orange County Transit Plan Partnership may recommend amendments to the BRI Plan as they deem appropriate. r 3. The Parties shall review such recommendations and take such action as may be needed to amend the BRI Plan. 4. Review may, but is not required Jlgo, be- based upon material changes in revenues such as an increase .For decrease greater than three percent (3 %), material changes m "costs such as an increase or decrease greater than three percent (3 °Jo), or material changes in bus service priprities or bus services funded by "the BRI Plan. 611 a b. Neither this .`Y referendum re the voters of regarding the i 1. This Agreement or renewal of this Agreement must be in the form of ,nt approved by the governing Boards of the Parties. t " nor the BRI Plan shall be effective until a ie imposition of the % cent transit tax is passed by County. Upon such passage of a referendum of the % cent transit tax: effective. 2. The BRI Plan becomes effective. 3. The BOCC may vote to impose the seven dollar County Tag Fee. 4. The governing Board of TTA may vote to increase the TTA based tag fee by three dollars. 5. The BOCC may by resolution "authorize TTA to proceed with the cent tax levy as set forth in the Orange County Tax Levy Agreement and as provided in Chapter 105, Article 43 of the North Carolina General Statutes. Page 9 of 10 11. GOVERNING LAW 10 This Agreement shall be governed by and in accordance with the laws of the State of North Carolina. All actions relating in any way to this Agreement shall be brought in the General Court of Justice in the County of Durham and the State of North Carolina. IN WITNESS WHEREOF, the Parties have approved this Agreement and have caused it to be signed by the Chair of the Orange County Board of County Commissioners, attested to by the Clerk of the Orange County Board and by the General Manager of TTA and is effective as provided in Section 10(b) herein. Orange County Bernadette Pelissier, Chair Board of County Commissioners Research Triangle Regional Public Tra David nager Approved as to,,legal form: Wib Gulley, Gene Page 10 of 10