ORANGE COUNTY
BOARD OF COMMISSIONERS
• ACTION AGENDA ITEM ABSTRACT
Meeting Date: April 24, 2012
Action Agenda
Item No.
SUBJECT: Follow-up Discussion of the Manager's Recommended 2012-2017 Capital
Investment Plan (CIP).
DEPARTMENT: Finance and Administrative PUBLIC HEARING: (Y/N) No
Services
ATTACHMENT(S): INFORMATION CONTACT:
Attachment 1. McGowan Creek Outfall Frank Clifton, County Manager
Project (Stand-alone CIP (919) 245-2306
project, page 54-a) Clarence Grier, Financial Services,
Attachment 2. Central Efland/North (919) 245-2453
Buckhorn Sewer Paul Laughton, Financial Services,
Expansion Project (919) 245-2152
(Revised, pages 53-54)
Attachment 3. Communication System
• Improvements Project
(Revised, pages 33-34)
Attachment 4. Sportsplex Project
(Revised, page 68)
PURPOSE: To provide updates to the Manager's Recommended 2012-2017 Capital
Investment Plan (CIP) during the budget work session.
BACKGROUND: The FY 2012-17 Manager's Recommended Orange County Capital
Investment Plan (CIP) was presented to the Board of County Commissioners during work
sessions on March 1, 2012 and March 15, 2012, and follow-up discussion occurred as part of
the April 19, 2012 work session.
Tonight's meeting provides revised CIP pages for the following projects:
McGowan Creek Outtall
This project was originally included within the Central Efland/North Buckhorn Sewer Expansion
Project (page 53 of the CIP document). Since then, staff has been notified by the State that the
. McGowan Creek Outfall project is eligible to receive State Revolving Loan funds in the amount
of $755,450. See Attachment 1 for a stand-alone McGowan Creek Outfall CIP project.
2
Central Efland/North Buckhorn Sewer Expansion
Attachment 2 is a revised Central Efland/North Buckhorn Sewer Expansion project (pages 53- •
54) page to reflect the removal of the McGowan Creek Outfall project from this project.
Communications System Improvements
Attachment 3 is a revised Communications System Improvements project (pages 33-34)
reflecting a funding plan for the replacement of 800 MHz radios for the Emergency Services and
Sheriff's departments only. This project, as well as the Viper Radio System and Future EMS
Stations projects, continues to be reviewed as part of the charge to the Emergency Services
Work Group.
Sportsplex
Attachment 4 is a revised Sportsplex project (page 68) recommending the shifting of funding for
Lobby Renovations, estimated at $125,000, from Year 2 to Year 1 of the CIP, due to a
prominent need for renovations to enhance the appearance and appeal of the facility.
FINANCIAL IMPACT: There is no immediate financial impact associated with the FY 2012-17
Capital Investment Plan. It is a long-range financial planning tool with a financial impact in FY
12-13, if the first year of the CIP is approved by the Board of County Commissioners with the
adoption of the Annual Budget.
EDUCATION: Further work is needed to determine the future impacts on the county's debt •
capacity due to proposals advanced by the Orange County School System to expedite building
projects as previously discussed.
RECOMMENDATION(S): The Manager recommends the Board of County Commissioners
continue their discussion of the FY 2012-17 County's Capital Investment Plan and provide
direction to staff.
•
Water&Sewer Utilities Capital Projects - REVISED
Fiscal Years 2012-17
Project Name McGowan Creek Outfa/l Project Status Approved
Functional Service Area Community and Environment Starting Date 81112012
Department Planning Completion Date 513112013
Current Year 1 Year 2 Year 3 Year 4 Year 5 Five Year 6
Prior Years Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Year to
Project Budget Funding 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 Total Year 10
Appropriation
Professional Design Services 75,000 75,000
LandBuilding 50,000 50,000
Construction/Repairs/Renovations 630,450 630,450
Equipment/Furnishings
Total Project Budget - - 755,450 - - - - 755,450
General Fund Related Operating Costs
Personnel Services -
Operations -
New Debt Service 45,432 45,432 45,432 45,432 181,728 227,160
Total Operating Costs - 45,432 45,432 45,432 45,432 181,728 1 227,160
Revenues/Funding Source
Transfer from General Fund 45,432 45,432 45,432 45,432 181,728 227,160
Debt Financing 755,450 755,450
Total - 755,450 45,432 45,432 45,432 45,432 937,178 227,160
Project Description/Justification
The McGowan Creek Pump Station(MCPS) is the main pump station of the Efland Sewer System. The pumps,generator and electrical controls were installed and put
into operation in 1988,so they are now roughly 23 years old. According to Orange Water and Sewer Authority(OWASA),who perform our routine maintenance,all of
these components of the system have been in service longer than OWASA's standard duty schedule of 10 years for pumps and controls and 20 years for generators.
The construction-phase engineering consultant for the ongoing Central Efland-2/North Buckhorn sewer expansion has determined that the existing MCPS can be taken
out of service by installing a new gravity outfall between the MCPS and the proposed, but upsized, Brookhollow sewer lift station located on Brookhollow Road. Work is
currently being done to design this project in time to make it a part of the ongoing Central Efland-2/North Buckhorn sewer expansion.The County has recently been
notified by NCDENR of approval of Clean Water State Revolving Loan funds in the amount of$755,450 for this project. This project will also facilitate the eventual
transfer to the City of Mebane by removing an antiquated lift station leaving a new sole source pump station origin that handles all Efland sewer flow.
W
.p
Water&Sewer Utilities Capital Projects - REVISED
Fiscal Years 2012-17
Project Name Central Efland/North Buckhorn Sewer Expansion Project Status Approved
Functional Service Area Community and Environment Starting Date 71112010
Department Planning Completion Date 313112013
Current Year 1 Year 2 Year 3 Year 4 Year 5 Five Year 6
Prior Years Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Year to
Project Budget Funding 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 Total Year 10
Appropriation
Professional Services 34,000 -
Land/Building 59,900 -
Construction/Repairs/Renovations 4,693,101 Equipment/Furnishings
Total Project Budget 4,727,101 - - - - - -
General Fund Related Operating Costs
Personnel Services
Operations
New Debt Service 225,000 225,000 225,000 225,000 225,000 1,125,000 1,125,000
Total Operating Costs 1 225,000 225,000 225,000 225,000 225,000 1,125,000 1 1,125,000
Revenues/Funding Source
Transfers from General Fund 59,900 33,701 225,000 225,000 225,000 225,000 225,000 1,125,000 1,125,000
EPA Special Appropriations Grant 1,348,400 -
State Revolving Loan Funds 3,345,000 -
Debt Financing -
Total 4,727,101 225,000 225,000 225,000 225,000 225,000 1,125,000 1 1,125,000
Project Description/Justification
In the mid-1980s,the decision was made to construct public sewer service in the Efland Community. The County's funding ran out before the entire community could be
served, but there were approximately 80 residents remaining who had signed up to receive sewer and never did. The Central Efland portion of this project will provide
sewer service availability to the majority of those properties that requested service 25 years ago, in addition to providing sewer availability to most of the rest of the Efland
Community. The Northern Buckhorn project will be an extension of the City of Mebane's sewer system and will serve residents in the area along Buckhorn Road
between the Interstate and the railroad tracks. This portion of the project is made possible by EPA Special Appropriations Grants that were earmarked by Congressman
David Price and applied for by the County. The vast majority of the Central Efland project will be paid for by the remainder of the EPA grant and by a DENR State
Revolving Loan Fund. An estimate of the debt service is shown above, based on the full loan amount of$3,500,000, an interest rate of 2.445%and the maximum term of
20 years. The full loan amount of$3,500,000 is a maximum line of credit. The debt service payments would be based on the actual amount used. Orange County will
not be using the full$3,500,000 line of credit since contracts were bid lower. When Orange County closes the project,the remaining monies will return to DENR and be n
'reallocated'to an associated project known as McGowan Creek Outfall shown in a separate CIP project. Therefore,there will likely not be new debt above the original J(,>
project noted herein.
County Capital Projects-REVISED
Fiscal Years 2012-17
Project Name Communication System Improvements Project Status New
Functional Service Area Public Safety Starting Date 7/1/2012
Department Emergency Services Completion Date 613012017
Available Year 1 Year 2 Year 3 Year 4 Year 5 Five Year 6
Prior Years Balances Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Year to
Project Budget Funding 1/3112012 2012-13 2013-14 2014-16 2015-16 2016-17 Total Year 10
OSSI-CAD Replacement 128,000 128,000 128,000 128,000 128,000 640,000
800 Mhz Radios 620,000 620,000 920,000
NextGen Phone System 400,000 400,000
9-1-1 Call Taker and Dispatch Software:
*Emergency Police Dispatch 80,000 80,000
*Emergency Fire Dispatch 80,000 80,000
*Smart9-1-1 30,000 30,000
Paging Hardware 150,000 150,000
Total Project Budget - 748,000 528,000 128,000 468,000 128,000 2,000,000 920,000
General Fund Related Operating Costs
Personnel Services
Operations
New Debt Service 135,328 222,652 222,652 222,652 803,284 1,113,304
Total Operating Costs - 135,328 222,652 222,652 222,652 803,284 1,113,304
Revenues/Funding Source
Transfer from General Fund 28,000 163,328 250,652 430,652 250,652 1,123,284 1,113,304
9-1-1 Funds 100,000 100,000 100,000 260,000 100,000 660,000
Capital Projects Fund Balance
Debt Financing 620,000 400,000 1,020,000 920,000
Total - 7489000 663,328 350,652 690,652 350,652 2,803,284 1 2,033,304
Project Description/Justification
Note: This Communications System Improvements project is being reviewed as part of the charge to the Emergency Services Work Group.
OSSI:Since 1992 Orange County has utilized a Computer Aided Dispatch system from the current vendor,Logysis.The system is outdated,unable to meet current
demands and should be replaced in order to accommodate system needs.OSSI has a complete package that will provide a more robust and efficient system with
needed modules already interfaced.This system supports data sharing between agencies and across jurisdictions;improves employee productivity by simplifying
repetitive tasks;delivers real-time information across the entire Emergency Services spectrum including law enforcement,fire and EMS.OSSI is offering a five-year
payment plan which includes equal payments over the five years with 0%interest.This proposal includes a turnkey hardware,software and services solution.$500,000
can be funded by 9-1-1 funds contingent upon the approval of the NC 9-1-1 Board.
800 MHz Radios: Portable and mobile 800 MHz radios for all Public Safety Departments County-Wide have or will be reaching seven-years of age. Replacement is
necessary to ensure reliability for emergency responders. Only the Emergency Services and Sheriffs departments are included in the CIP.It will be up to each
individual municipal or rural department to fund their repalacment radios.It is important to establish standard features and specifications for 800 MHz radios(portables
and mobiles)to ensure system reliability,optimal integration with new platforms(P25)which will be placed in service by NCSHP/VIPER starting in 2013. Regardless of
funding source or user,it is critical that units purchased be standardized to ensure integration,reliability and reduce potential for field failure. Year 1 funding includes
Emergency Services radios and two mobile digital repeaters to assist field units with reception and reliable communications throughout the county. Years 6-10 includes
funding of$920,000 for replacement of Sheriff radios. /`1,
NextGen Phone System:Replacement of the main 9-1-1 switch,which is necessary to gain access to Internet(Next Generation)based services.The current switch W
will have reached the end of its useful life and will no longer be supported by the vendor.If the switch is not replaced,the cost of repairs/maintenance/parts will become
very expensive.There is a risk that parts for this equipment will not be available in the coming years. Based on the most current vendor consultation, the request is
being made in year 2-FY 2013-2014.
tr
rn
9-1-1 Call Taker and Dispatch Software:
EPD:ProQA Dispatch Software integrates the National Academy Protocols with today's critical computer technologies and assists telecommunicators in quickly
determining the appropriate response specifically configured by local agency authorities.ProQA guides dispatchers in providing relevant Post-Dispatch and Pre-
Arrival instructions prior to units arriving on scene.
EFD:Fire Priority Dispatch system will allow all the benefits and safety features of a unified fire protocol system based on fire department approved parameters to
combine with the latest in caller integration and response prioritization.
Smart 9-1-1: Allows citizens to enter information through a secure website that would be available in the event they need to call 9-1-1.When the citizen calls 9-1-1 the
data automatically displays on the 9-1-1 operators work station.The same information is also available via the web to police,fire and EMS units in the field which helps
them respond more quickly and effectively.It works seamlessly in today's infrastructure as well as future Next Generation solutions.
Paging Hardware: Will provide a reliable station notification system for all County Fire and EMS stations.Can not be funded through 9-1-1 funds.
i
•
RECOMMENDED- Sportsplex Capital Projects Summary-REVISED
Fiscal Years 2012-17
Current Year 1 Year 2 Year 3 Year 4 Year 5 Five Year 6
Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Year to
Project Budget 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 Total Year 10
Appropriations
Land/Building
Design 30,000 30,000
Construction/Repairs/Renovations 20,000
Locker Room Improvements 165,000
Parking Lot Repair/Repave 125,000 150,000 150,000
Pool Roof repair 180,000 180,000
Pool wall reglaze 125,000 125,000
Mezzanine(Pool) 950,000 950,000
Mezzanine(Ice),Phase 2;Children's Activity Center(Phase 3) 1,000,000 1,000,000
Tilt up Panel(exterior wall system) 100,000 100,000
Equipment/Fumishings
Fitness Equipment Repl-Seniors 36,000 100,000 100,000
New UV System for Pool 100,000 100,000
Bleachers
Pool Dectron 217,000
Pool pump/boiler#2 20,500
Cooling Tower Replacement 100,000 100,000
Major upgrade of Servers, Telephones 75,000
75,000
Lobby-Renovations 125,000 125,000
Rink concrete ice floor repair 150,000 150,000
Rink de-humidication/Ice Rink Munters 125,000 125,000
Zamboni 100,000 100,000
Major rebuild-compressors/chiller barrel 100,000 100,000
Lobby-HVAC Replacement 80,000 80,000
Climbing Wall(outside-fee based) 100,000 100,000
Total 683,5001 660,000 505,000 1,175,000 1,150,000 200,000 3,690,000
Revenues/Funding Source
Sportsplex Fund Balance 583,500 660,000 505,000 225,000 150,000 200,000 1,740,000
Transfer from General Fund
Debt Financing 950,000 1,000,000 1,950,000
Total 583,500 660,000 505,000 1,175,000 1,150,000 200,000 3,690,000
The Sportsplex Fund is a self supporting Proprietary Fund that is used to account for revenues and expenses related to the operations of all Sportsplex
Programs for the residents of Orange County. In FY 2014-15,the Mezzanine(Pool)will consist of dedicated fitness member change areas and lockers,
and workout rooms for Zumba,high and low impact aerobics,and Yoga/Pilates. In FY 2015-16,the Mezzanine(Ice)-Phase 2 will provide additional
fitness space to support the additional equipment required for member growth with particular focus on specialized units designed for seniors.
Additionally,there will be a dedicated group cycling area for this high growth program and an advanced training center to handle group training
programs. The appearance and function will be similar to the existing ice mezzanine. Also in FY 2015-16,the Children's Activity Center(Phase 3)will
not only facilitate a 50%growth in After School and Summer Camp programs,but will facilitate programs focused on children's obesity through mini-
gym based programs,children's martial arts,gymnastics,tumbling,and child appropriate dance classes.
v