HomeMy WebLinkAboutAgenda - 01-26-2012 - 1ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: January 26, 2012
1
Action Agenda
Item No. _~_
SUBJECT: Municipal Solid Waste Closure Decision and Update
DEPARTMENT: Solid Waste Management
PUBLIC HEARING: (Y/N) No
ATTACHMENT(S):
INFORMATION CONTACT:
Frank Clifton, County Manager, 245-
2306
Michael Talbert, Asst. County Manager,
245-2308
Gayle Wilson, Director, Solid Waste
Management, 968-2885
PURPOSE: To provide an update on the closure and post-closure of the Orange County
Municipal Solid Waste Landfill, landfill utilization by local governments, and updates on
transition to single stream recycling and solid waste convenience center
improvements/modernization.
BACKGROUND: The Board of Commissioners (BOCC) has previously stated, subsequent to
the unsuccessful search for a Transfer Station site, that following the closure of the MSW landfill
Orange County would deliver its waste to the City of Durham Transfer Station for an interim
period until a more permanent waste management solution is established. Discussions with the
City of Durham have indicated a willingness of Durham to receive wastes delivered from Orange
County, although no written agreement is currently in place.
Landfill Closure
Staff has presented the BOCC with options for the timing of the closure of the landfill that
ranged from closure according to its current permit capacity that would indicate a closure
sometime in late 2013. With a minor permit amendment disposal capacity could be extended to
mid- 2017 and to mid- 2018 with a major permit amendment (based on recent incoming
tonnages). These types of landfill permit amendments are generally considered routine from a
regulatory perspective. On October 4, 2011 the Board instructed the staff not to seek an
extension past the projected useful life of the landfill, which is anticipated in the spring of 2013,
and inform the municipalities that the County intends to close the landfill no later than June 30,
2013.
The suggested timetable for closure:
• Final BOCC Closure Decision
• Development of construction documents, contractor bidding and award process and
execution of closure construction contract/notice to proceed - 245 days
• Mobilization - 84 days
2
• Landfill Closes (June 30, 2013?)
• Construction - 182 days (regulations require closure construction to be completed within
6 months from last day of receiving waste)
Engineering estimates indicate a Municipal Solid Waste Landfill closure cost of about
$3,116,720. A minimum 30-year post-closure period would result in post-closure monitoring,
maintenance and reporting cost of about $4,824,555. Additional closure and post-closure cost
for the Construction & Demolition (C&D) Landfill is estimated at about $4,025,326, for a total
closure and post-closure estimate of $11,966,601. As of June 30, 2011 the total liabilities of
solid waste fund was $16,999,996, including capital lease and debt obligations, post-
employment health care obligations, and compensated absences. As of June 30, 2011 total
Solid Waste Fund cash reserves are $12,941,892. The Solid Waste enterprise fund, without
considering the sale of any assets, is about $4,058,104 short of meeting all long-term liabilities.
Landfill Utilization by Towns & County - FY 2010/11
The proportional use of the landfill (tons of municipal solid waste) by the Towns and County are
as follows:
Carrboro - 6,650 19
Chapel Hill - 15,008 42
Hillsborough - 3,185 9
County - 10,497 30
Total 35,340
Single Stream Rec~/clina
County and Town elected officials have for several years expressed interest in moving to single
stream recycling collection. The Solid Waste Planning Work Group, the Solid Waste Advisory
Board and various individual county residents have also advocated this change.
Consistent with the adopted Fiscal 2011/12 Solid Waste Budget, Orange County recycling
programs are now planned to transition to single stream recycling by July 2012. This change
will be implemented for all county recycling programs -Rural Curbside, Urban Curbside, Solid
Waste Convenience Centers, Multi-family, Commercial, Schools, etc.
Single stream recycling is the practice of comingling all recyclable materials (paper and
containers) together for collection rather than separating containers from paper (normally
referred to as dual stream). There may be some slight variations among programs as discussed
in the attached memorandum to the County Manager.
An example of the efficiencies gained by the switch to single stream is best illustrated by the
expected reduction in contract cost in the Urban Curbside program. The current cost to the
County for this collection is $4.17 per household per month resulting in a Fiscal Year 2011-12
budget of $931,395 for this service. Once the landfill switches to single stream collection, the
costs is expected to be between $3.00 and $3.75 per household per month. Using the current
population, if the cost is as high as $3.75 per household per month, the contract cost could be
as low as $823,500 per year. Roll carts may be incorporated into the collection cost or bid
separately, depending on which is most economical.
It is anticipated that roll-carts will be utilized for the Urban Curbside Program (contracted
service) and that the Rural Curbside Program (county staff provided service) will continue to
utilize 18-gallon bins, at least for the near term. It is currently understood from resident
comments that portions of the Rural Program may not be suitable for roll-carts and staff will,
over the next year or two, assess areas where roll-carts can be reasonably used with the
expectation that eventually roll-carts can be provided for certain select rural areas.
The Town of Chapel Hill is currently evaluating solid waste alternatives for all facets of solid
waste management within the Town. Therefore, it is questionable as to whether Orange County
should commit to acquisition for recycling roll carts for distribution within the Town at this time.
Orange County will need a formal commitment from all of the Towns prior to making the
investment in roll-carts and executing an agreement with a contract service .provider that
includes the Town. The existing urban curbside collection agreement expires June 30, 2012.
Solid Waste Convenience Centers (SWCC)
Based on recommendations from the Solid Waste Planning Work Group, consisting of
representatives from the Towns and County and the Solid Waste Advisory Board, the BOCC
has decided to begin implementation of the first convenience center in a longer term objective
for upgrading and modernizing all five county convenience centers. The Walnut Grove Road
Solid Waste Convenience Center site design and construction bidding is currently underway.
Staff expects to return for a construction bid award in March, 2012 with completion of
construction in July, 2012. Other sites will be considered for upgrades through the annual
budget process, with the potential for one center to be modernized each year.
The Work Group recommended aDistrict/Neighborhood Center approach with District Centers
more centrally located having expanded hours of operation and more services. Neighborhood
Centers would have somewhat reduced hours of operation and reduced services available.
Walnut Grove Church Road and Eubanks Road were recommended as District Centers.
Convenience centers received 457,632 total visits in 2010/11 and are considered a core county
service. Improvements include:
• increasing hauling and waste handling efficiencies by using compaction and larger
containers
preparing for landfill closure as SWCC's will be the primary waste infrastructure in the
County
• facilitating enhanced services such as adding new materials for recycling and expanding
salvage opportunities
• addressing current site issues such as improving traffic flow, reducing container loading
height, paving to enable better cleanup of spills/reducing dust reducing maintenance,
reducing noise and odor, etc.
• reducing labor and collection costs
• improving safety
FINANCIAL IMPACT: Decisions with regard to the landfill closure will have considerable
financial impacts which include funding of closure and post-closure, the additional costs related
to the delivery of local waste to the Durham Transfer Station (or other disposal destination) and
for significantly reduced future enterprise fund tipping fee revenue. There is an unknown
financial impact if the Towns choose to contract separately for their own recycling services.
4
RECOMMENDATION(S): The Manager recommends that the Board, along with the elected
Boards of the Towns of Carrboro, Chapel Hill and Hillsborough, discuss the various issues
related to local solid waste management, including landfill closure in 2013, decisions regarding
utilization of alternative disposal facilities and the transition to single stream recycling.