Mechanical Systems
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds to replace obsolete mechanical equipment
including boilers and electric heating and cooling systems. Proceeds from the
Schools' portion of the one-half cent sales taxes finance this project and transfers
from completed projects within the District.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY
2002-03
FY 2003-04 Through FY
2003-04
Sales Tax $995,490 $995,490
Im ct Fees 0 0
PSBF $0 0
Transfers from Completed Projects $650,000 50,000
Total Pro ect Fundin $1,645,490 $0 $1,645,490
Section 4.The following amount is appropriated for this project:
Through FY
2002-03
FY 2003-04 Through FY
2003-04
Plannin /Arch/En in $112,000 $112,000
Land/Assoc Fees $25,000 $25,000
Construction $860,000 $860,000
E ui ment/Furnishin s 648,490 648,490
Other $0 0
Contin enc $0 0
Total 1,645,490 0 1,645,490
Section 5.This ordinance supersedes all previous Mechanical Systems Capital Project
Ordinances for the Chapel Hill-Carrboro City Schools.
Section 6. This ordinance, originally adopted May 21, 1997, shall remain in effect until June
30, 2004.
Adopted this 26th day of June 2003.
d o~~ ~ ~d~~- o ~a
~~
r. Approval of Fiscal Year 2003-2004 Capital Proiect Ordinances and Grant
Proiect Ordinances
The Board considered adopting the capital project ordinances and grant project
ordinances for FY 2003-2004.
Commissioner Jacobs made reference to page 16, Central Northern Orange Senior
Center Capital Project Ordinance, and that there was some discussion about trying
to treat both senior centers equally and spend a relatively equal rate. One center
has $400,000 and one center has $100,000, and he was trying to remember if they
were going to catch up next year. Rod Visser said that they are going to catch up
eventually. He will write it up and reiterate the timeline for this and the explanation
for the difference.
A motion was made by Commissioner Jacobs, seconded by Commissioner
Halkiotis to adopt the accompanying capital project ordinances and grant project
ordinances.
VOTE: UNANIMOUS