HomeMy WebLinkAboutORD-2003-079 Playground Protective Surfaces Orange County Schools Capital Project Ordinance6~4><ly ~-~°~o~
G a- ~, ~
Playground Protective Surfacing
Orange County Schools
Capital Project Ordinance
~-10
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section 13.2
of Chapter 159 of the General Statutes of North Carolina, the following capital project is hereby adopted.
Section 1. The project authorized provides funds to install protective materials under and around all
playgrounds in the district. Proceeds from the Schools' portion of the one-half cent sales tax
finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within the budget
contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2002-03 ~ 2003-04 Through FY
2003-04
Sales Tax $140,000 $140,000
act Fees $0 $0
PSBF $0 $0
1997 Bond Funds $0 $0
Other $0 $0
Total Pro'ect Fundin $140,000 $0 $140,000
Section 4. The following amount is appropriated for this project:
Through FY
2002-03 FY 2003-04 Through FY
2003-04
Plannin Arch/En in $0 $0
Land/Assoc Fees $0 $0
Construction $140,000 $140,000
E ui ment/Furnishin s $0 $0
Other $0 $0
Contin enc $0 $0
$0 $0
Total A ro riation $140,000 $0 $140,000
Section 5. This ordinance supersedes previous Playground Protective Surfacing Capital Project
Ordinances for the Orange County Schools.
Section 6. This ordinance shall remain in effect from July 1, 1998 until June 30, 2004.
Adopted this 26th day of June 2003.
d o~sJ ~ ~dU3- v ~9
~~
r. Approval of Fiscal Year 2003-2004 Capital Proiect Ordinances and Grant
Proiect Ordinances
The Board considered adopting the capital project ordinances and grant project
ordinances for FY 2003-2004.
Commissioner Jacobs made reference to page 16, Central Northern Orange Senior
Center Capital Project Ordinance, and that there was some discussion about trying
to treat both senior centers equally and spend a relatively equal rate. One center
has $400,000 and one center has $100,000, and he was trying to remember if they
were going to catch up next year. Rod Visser said that they are going to catch up
eventually. He will write it up and reiterate the timeline for this and the explanation
for the difference.
A motion was made by Commissioner Jacobs, seconded by Commissioner
Halkiotis to adopt. the accompanying capital project ordinances and grant project
ordinances.
VOTE: UNANIMOUS