HomeMy WebLinkAboutORD-2003-074 Handicapped Accissibility Orange County Schools Capital Project Ordinance' ~- ~G - .~- od3 ~ ~'
Handicapped Accessibility
Orange County Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section 13.2
of Chapter 159 of the General Statutes of North Carolina, the following capital project is hereby adopted.
Section 1. The project authorized provides fixnds to modify and improve the handicapped accessibility
throughout all buildings, playing fields, and parking lots on seven campuses. Proceeds from
the Schools' portion of the one-half cent sales taxes and the 1997 bond referendum finance
this project.
Section 2. The officers of the County are hexeby directed to proceed with the project within the budget
contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2002-03
FY 2003-04 Through FY
2003-04
Sales Tax 434,017 434,017
Impact Fees 0 0
PSBF 0 0
1997 Bond Funds 235,983 235,983
Other 0 0
Total Project Funding 670, 000 0 670, 000
Section 4. The following amount is appropriated for this project:
Through FY
2002-03
FY 2003-04 Through FY
2003-04
Plannin Arch/En ' 0 0
Land/Assoc Fees 0 0
Construction 670,000 670,000
E ui ment/Furnishin s 0 0
Other 0 0
Contin enc 0 0
Total Appropriation 670,000 0 670,000
Section 5. This ordinance supersedes all previous Handicapped Accessibility Capital Project
Ordinances for the Orange County School System.
Section 6. This ordinance shall remain in effect from July 1, 1993 until June 30, 2004.
Adopted this 26th day of June 2003.
c~ oQfJ ~ ~ ~'U~3- d ~~l
~~
r. Approval of Fiscal Year 2003-2004 Capital Proiect Ordinances and Grant
Proiect Ordinances
The Board considered adopting the capital project ordinances and grant project
ordinances for FY 2003-2004.
Commissioner Jacobs made reference to page 16, Central Northern Orange Senior
Center Capital Project Ordinance, and that there was some discussion about trying
to treat both senior centers equally and spend a relatively equal rate. One center
has $400,000 and one center has $100,000, and he was trying to remember if they
were going to catch up next year. Rod Visser said that they are going to catch up
eventually. He will write it up and reiterate the timeline for this and the explanation
for the difference.
A motion was made by Commissioner Jacobs, seconded by Commissioner
Halkiotis to adopt the accompanying capital project ordinances and grant project
ordinances.
VOTE: UNANIMOUS