HomeMy WebLinkAboutAgenda - 03-24-2003 - 8e1
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: March 24, 2003
Action Agenda
Item No. ~ _L
SUBJECT: Budget Amendment #9
DEPARTMENT: Budget PUBLIC HEARING: (Y/N) No
ATTACHMENT(S): INFORMATION CONTACT:
Attachment 1. Budget as Amended Donna Dean 245-2151
Spreadsheet
Attachment 2. Affordable Housing Capital TELEPHONE NUMBERS:
Project Ordinance Hillsborough 732-8181
Attachment 3. FY 2002-03 Issues - 2001 Chapel Hill 968-4501
Bonds & Alternative Financing Durham 688-7331
Attachment 4. County and School Capital Mebane 336-227-2031
Project Ordinances
PURPOSE: To approve budget ordinance amendments and capital project ordinances for fiscal year
2002-03.
BACKGROUND:
Register of Deeds
1. The Register of Deeds Office has experienced a significant increase in the number of land
related transactions that are processed. While the increased volume in work has resulted in
higher than anticipated expenditures for items such as supplies and temporary personnel, it has
also resulted in revenue collections that are well beyond the current year budget. Staff estimates
the department will generate approximately $50,000 in additional unbudgeted revenue for the
remainder of fiscal year 2002-03. This. budget amendment increases the budgeted revenues to
be more in line with current year receipts and allows for the expenditures related to the increased
departmental activity. (See Attachment 1, column #1)
Department of Social Services
2. The Department of Social Services recently received a reimbursement related to a Medicaid
overpayment case. While the settlement totaled $100,000, Orange County's share is equivalent
to the County's Medicaid match of 5.66 percent of the total or $5,660. The County will forward
the remaining $94,340 to the State as reimbursement of its share of the settlement.. This budget
amendment provides for the receipt of the settlement funds and allows for reimbursement to the
State for its respective share of the settlement. (See Attachment 1, column #2).
Department on Aging
3. On August 20, 2002, the Board of County Commissioners renewed the County's agreement with
Manley Estates, a senior housing complex in Chapel Hill: In accordance with the agreement,
Department on Aging social work interns assess residents' needs at the complex and make
referrals to community resources. Manley Estates reimburses the Department on Aging at the
rate of $15 per resident per month. Based on revenues received to date, projected receipts
associated with the agreement total $7,500. This budget amendment provides for the receipt of
the additional funds related to the agreement. (See Attachment, column #3).
Library Services
4. In accordance with the Federal Telecommunications Act of 1996, schools and libraries receive
discounts for telecommunication services, Internet access, -and internal connections. The
discounts are based on economic need (as determined by the National School Lunch Program)
and location, such as rural or urban. This year, the Orange County Library has received a-rate
discount funds totaling $3,137. The department will use the funds to install an outdoor book drop
and purchase additional computer terminal supplies for patron access at the Hillsborough main
library. There is no County match for the receipt of these funds. (See Attachment 1, column #4).
Non-Departmental
5. Last spring during the County's budget development process, it was not clear if there would be
State-funding cuts for the Orange Chatham Alternative Sentencing Program (OCAS). The Board
of County Commissioners approved funding fora $15,000 reserve account that would be
combined with $15,000 from Chatham County to offset potential State-funding cuts. Based on
the funding cuts approved by the State in fall 2002,. Commissioners released the reserve funds
so that Orange County, in partnership with Chatham County, could maintain pre-trial services for
at least the first six months of the fiscal year.
In order to continue operations beyond the first six-month of the fiscal year, OCAS recently
requested additional appropriations of $5,000 from both Orange and Chatham counties. The
attached budget amendment. allocates $10,000 to OCAS with $5,000 funded from Orange
County's Social Safety Net and the remaining $5,000 with a contribution from Chatham County.
(See Attachment 1, column #5)
6. On December 10, 2002, the Board of County Commissioners accepted State pass-through funds
for several organizations that provide services for high-risk youth. Included in this funding
package was the Orange-Chatham Justice Partnership recommendation to fund an additional
agency, Volunteer Families for Children, in the amount of $5,000 for the current fiscal year. In
order for the agency to receive the pass-through funds, Orange County is required to provide a
30 percent match ($1,500). The attached budget amendment appropriates $1,500 from Orange
County's Social Safety Net for the required match. (See Attachment 1, column #6)
Health Department
7. State funds totaling $7,300 is available to the Orange County Health Department to offset costs
associated with public awareness campaigns related to bioterrorism. Examples of how the
Health Department would use the funds include media campaigns such as informational public
service announcements, flyers, and pamphlets and extensive training for staff. The department
plans to cover such topics as how and who to contact in matters associated with an actual or
suspected biological attack or an unusual outbreak of disease and steps that can be taken to
prepare for a biological attack. This budget amendment provides for the receipt of these funds.
(See Attachment 1, column #7).
Cooperative Extension
8. Cooperative Extension has received a $1,000 grant from the North Carolina Division of Public
Health. Through .the grant, Orange County would partner with Wake County to offer a new
program, Eat Smart, Move More. The purpose goal of the project is to assist youth and their
families develop good nutrition and physical activity as lifelong behaviors. The funds would
offset the cost of promotional materials project. This budget amendment provides for the receipt
of the funds (See Attachment 1, column #8)
Housing and Community Development
9. On December 10, 2002, the Board of County Commissioners approved a $250,000 funding
request from Habitat for Humanity of Orange County. Habitat plans to use these funds to offset
costs associated with purchasing a 16-acre parcel of land on Sunrise Road in Chapel Hill for the
future development of affordable housing. The purchase price of the land totals $400,000. The
chart below outlines the funding sources that Habitat has obtained to fund the purchase:
Orange County $250,000
Town of Chapel Hill $50,000
Habitat for Humanity $100,000
Total $400,000
Orange County's contribution towards the purchase price is comprised of the following sources:
Community Development
Program Income $126,432
County Housing Loan Trust
Fund $123,568
Total $250,000
This budget amendment appropriates $250,000 from the above-mentioned sources for the
County's contribution towards purchase of the property. (See Attachment 2, Affordable Housing
Capital Project Ordinance)
Bond and Alternative Financing Capital Project Ordinances
10.On September 3, 2002, the Board approved a schedule for issuing 2001 voter approved bonds
and alternative financing for County and School capital projects. Attachment 3 of this abstract
outlines specific projects that were approved by the Board for issuance this fiscal year. In
accordance with the approved schedule, the County issued $3.475 million in private placement
debt in December 2002. Accordingly, by the end of March 2003, a total of $19.175 million in
2001 voter approved bonds will be issued.
The Commissioners have not approved capital project ordinances for the projects receiving
funds this fiscal year due to the fact that the actual issuance is just now occurring. The attached
capital project ordinances (Attachment 4 of this abstract) provide budgets for the approved
projects and allow for expenditures for County projects and for those school-related projects that
are not considered "Level 2" projects as defined by the Board approved Policy on Planning and
Funding School Capital Projects. A capital project ordinance is not included for Orange County
Schools Hillsborough Elementary School because the Board of Commissioners approved that
ordinance on September 11, 2002.
By definition, "Level 2" projects are considered "major projects that require several phases to
complete". There are two school related. projects that fall into the "Level 2" category -Chapel
Hill High School Rashkis Elementary and Orange County Schools Middle School #3. The most
recent Commissioners approval for Rashkis Elementary occurred on June 27, 2002. In
accordance with the Board approved policy, the next step for the planned middle school in the
Orange County School district is for the OCS Board of Education to request funding for the initial
planning phase of the project. Once that step occurs, staff plans to follow the guidelines outlined
in the planning and funding policy.
FINANCIAL IMPACT: Financial impacts are included in the background information above.
RECOMMENDATION (S): The Manager recommends that the Board of County Commissioners
approve the attached budget and capital project ordinances.
C
E~
o~
G ~
O1 a
~ c
m E
ee
w
0 8
N ~
0
O
O m
M1 5S.
m
C
7 ~.
U O
o,U
~ ~
O ~
'cq
• N
u g
m
6~
~~ y nry '$m, Q~Q' np~p syy(S ~
' ~S F~y{SS{ eZ e{ g w3
1p ~S ~:d ~ •
P'i
~~g'`.
m§~ 3
~ $~
ri~ ~a
.~Mi a i~
ee~ n
e ~ 3iS n~ S
.r$ :a,e F(e w
d
E
~~cm ~~
o
"
Q~i
~
Q
c ~F 4cd
y 3
~w
.~ «
«
u.
g
€
~
~
~
~~
i~ ~~
~~~~
T~ ~W~
~~
M
N
ug ~~a8
5.2~~g pg~~
~ ~ ~ ~ i °c ~ ~ ~
~
SS
~ ~ G S
~~~~
~~ ~~~~
~
Yr
o€
~
~
E E
CC Q q
2y57
„S
~g~~~~~
~y
~~ ;;
-~_a~E~s
~ ~ ~ .~
2gg~
~o~~
~.
$$~
H $~ ~
s~~ $~
~~ g~~
e $ •~
8 ~
8 .~
8 ~
8
~ES~=
~
~a ~
s na.~ S p~ sg
0
. qq
S
R QQ
E
9 q
.~
S gQ
a
d
.
77~~
d ~ ~ ~ ~ ~ d
SS
~
~ YY~ n~S R. p~g~ ~gng R ~~y ~SiS ~e~ ~
R g ~~ ~ n •
_~
Y~Q
m0 3~
~H ~~
~~-~ ~
H ~~ H'it n v _i i id H~
f
0 1 ~~ 5
N
m=
e l_n
~e na
~'~ K f
?~ : 7{
~~ S'~~'
~~ n~' q'~•
~~ y~
~s K~
~~ gt
~ Rl
a ~~
~~ ~ $
g
m ~YI ~~ p ~ Y Of $ ~~ ~
S
O
~Q$
B
F'
=
$
a
~ i
~
e ~ G
r
y
d d
~
`z
~
a
~
3
.
g~a
o
o~ S
dm
a_ =
~~ ~
se ~
g m
dS E
u~
o'~ E ~i
~x~ V 3
;~ s d
wz 9
o' ~ 8
~d e O
~
Y~
Attachment 2
Affordable Housing Program
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to fund housing activities in the following
categories: land acquisition, housing development, and homeownership. The project is
financed by proceeds from the 1997 voter approved bond referendum and from Affordable
Housing Trust funds.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The followin revenue is antici ated to com lete this ro'ect:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
Bond Funds $1,287,500 $345,000 $1,632,500
Grant Funds $0 $15,000 $15,000
Private Placement $0 $0 $0
Fees $0 $0 $0
Transfer from Community
Development (Program
Income
$0
$126,432
$126,432
Transfer from Community
Development (Housing
Trust Funds)
$50,000
$123,568
$173,568
Total Fundin $1,337,500 $610,000 $1,947,500
Section 4.The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Land
EmPOWERment $90,000 $0 $90,000
Habitat for Humani $460,000 $0 $460,000
Total Land $550,000 $0 $550,000
Desi $0 $0 $0
Construction $0 $0 $0
Scarlett Drive $140,000 $0 $140,000
EmPOWERment $247,500 $0 $247,500
Meadowmont
Condominiums
$400,000
$0
$400,000
Continuin Care Center $0 $275,000 $275,000
Total Construction $787,500 $275,000 $1,062,500
Pine Knolls Community
House Relocation
$0
$85,000
$85,000
Sunrise Road Pro'ect $0 $250,000 $250,000
Total Costs $1,337,500 $610,000 $1,947,500
Attachment 2
Section 5.This ordinance supersedes previous Affordable Housing Capital Project Ordinances
for Orange County Government.
Section 6.This ordinance shall remain in effect until June 30, 2003.
Adopted this 24th day of March 2003.
Proposed Projects by Fiscal Year (AS Approved by BOCC on September 3, 2002) 012°3
Information below reflects approved timetable for issuing November 2001 voter approved bonds and alternative financing for fiscal years 2002-
03 and 2003-04.
FY 20 02-03 FY 20 03-04
Bond Alternative Bond Alternative
A -< B C D
Schools
CHCCS - Cha el Hill Hi h
$750,000
$0
$1,250,000
$0
CHCCS Elementa #9 $11,100,000 $0 ` $1,700,000 $0
OCS - Hillsborou h Elementa $900,000 $0 $0 $0
OCS Middle School #3 $1,000,000 $0 $4,500,000
OCS Oran a Hi h Renovations $0 $950,000 $0 $0
Total Schools $13,750,000 $950,000 $7,450,000 $0
Parks, Recreation ~ Open S ace
Cedar Grove District Park $200,000 $0 $500,000 $0
Chapel Hill District Park $200,000 $0 $500,000 $0
Efland Cheeks Park (Phase 2) $125,000 $0 $125,000 $0
Fairview Park $200,000 $0 $500,000 $0
Greenway Development $400 000 $0 $200,000 $0
Homestead Aquatics Center $0 $0 ...:$3,500,000 $0
Lands Legacy (including priority projects identified during Capifa/ Needs
Adviso Task Force process
$1;750,000
$0'
$.1,750,000
$0
Smith Middle School Park $250,000 $0 $0 $0
Soccer Super Fund $500,000 $0 $600,000 $0
Total Parks, Recreation and O en S ace $3,625,000 $0 $7,675,000 $0
Affordable Housin $1 300,000 $0 $1,300,000 $0
Conservation Easements $0 $1,000.,000 $0 $0
Senior Centers
Chapel Hill Center $400,000 $0 $1,000,000 $0
Northern/Central Orange Center $100,000 $0 $500,000 $0
Total Senior Centers $500,000 $0 $1,500,000 $0
Other Count Facilities
Community College Satellite Campus County Match) $0 $1,000,000 $0 $0
Orange Enterprises $0 $525,000. $0 $0
Total Other Coun Facilities $0 $1,525,000. $0 $0
Total $19,175,000 $3,475,000 $17,925,D00 $0
t
fiscal Year 2002-03
Budget Amendment #9
Attachment 4
County and School Capital Project
Ordinances
i
Chapel HiI1 High School -Indoor Air Quality
Chapel Hill Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to replace heating, ventilation and air
conditioning systems along with boilers, chillers and cooling towers at Chapel Hill
High School. Proceeds from the 2001 voter approved bonds finance this project.
Section 2, The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
02-03
Sales Tax $0 $0 $0
2001 Bonds $0 $750,000 $750,000
act Fees $0 $0 $0
Private Placement $0 $0 $0
Other $0 $0 $0
Total Fundin $0 $750,000 $750,000
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
02-03
Land/Buildin $0 $0 $0
Desi $0 $0 $0
Construction $0 $0 $0
Mechanical S stems $0 $750,000 $750,000
Total Costs $0 $750,000 $750,000
Section 5. This ordinance shall be in effect from the original date of adoption, March 24,
2003, until June 30, 2005.
Adopted this 24th day of March 2003.
Orange High School Renovations
Orange County Schools
Capital. Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to renovate Orange High School. Planned
renovations include improvements to the auditorium, science laboratories, tennis
courts and athletic fields along with flooring replacement in the main gymnasium
and construction of an athletic field house. Proceeds from a private placement
loan finance the project...
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
02-03
Sales Tax $0 $0 $0
Bonds 2001 $0 $0 $0
act Fees $0 $0 $0
Private Placement $0 $950,000 $950,000
Other $0 $0 $0
Total Fundin $0 $950,000 $950,000
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
02-03
LandBuildin $0 $50,000 $50,000
Desi $0 $0 $0
Construction $0 $900,000 $900,000
Other $0 $0 $0
Total Costs $0 $950,000 $950,000
Section 5. This ordinance shall be in effect from the original date of adoption, March 24,
2003, until June 30, 2005.
Adopted this 24~' day of March 2003.
I (~
Recreation and Parks Facilities -Cedar Grove District Park
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to construct a park on County-
owned lands at the Northern Human Services Center located in Cedar
Grove. Components of the park include lighted multi-purpose playing
fields, nature trails and a picnic shelter. Proceeds from the 2001 voter
approved bonds finance the project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
2001 Bond Funds $0 $200,000 $200,000
Private Placement $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Fundin $0 $200,000 $200,000
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
LandBuildin $0 $0 $0
Planning/Architect/En
gineerin
$0
$35,000
$35,000
Construction $0 $165,000 $165,000
Other $0 $0 $0
Total Costs $0 $200,000 $200,000
Section 7. This ordinance shall be in effect from the original date of adoption, March
24, 2003, until June 30, 2005.
Adopted this 24~' day of March 2003.
(~
Recreation and Parks Facilities -Chapel Hill District Park
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to construct a district park located
on County-owned property near the intersection of Old Highway 86 and
Eubanks Road in Chapel Hill. Plans include renovations to the house and
barn located on the property; installation of water and sewer
infrastructure; and construction of playing fields, nature trails and a picnic
area surrounding an existing pond. Proceeds from the 2001 voter
approved bond finance the project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
2001 Bonds $0 $200,000 $200,000
Private Placement $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Fundin $0 $200,000 $200,000
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
l.andBuildin $0 $0 $0
P lanning/ArchitectlEn
ineerin
$0
$55,000
$55,000
Construction $0 $145,000 $145,000
Other $0 $0 $0
Total Costs $0 $200,000 $200,000
Section 7. This ordinance shall be in effect from the original date of adoption, March
24, 2003, until June 30,2005.
Adopted this 24th day of March 2003.
~~
Recreation and Parks Facilities -Efland Cheeks Park (Phase 2)
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to construct the second phase of
the Efland Cheeks Park. The park, located on land owned by the Orange
County Schools, is co-located with the Efland Cheeks Community Center
and Efland Cheeks Elementary School. This phase of the park includes
construction of a lighted playing field and nature trails as well as
restoration and landscaping of a pond located on site. Funds from the
2001 voter approved bond referendum finance the project..
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
2001 Bonds $0 $125,000 $125,000
Private Placement $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Fundin $0 $125,000 $125,000
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Land/Buildin $0 $0 $0
Planning/ArchitectlEn
ineerin
$0
$10,250
$ i 0,250
Construction $0 $114,750 $114,750
Other $0 $0 $0
Total Costs $0 $125,000 $125,000
Section 7. This ordinance shall be in effect from the original date of adoption, March
24, 2003, until June 30, 2005.
Adopted this 24th day of March 2003.
i~
Recreation and Parks Facilities -Fairview Park
Capital Project Ordinance
Be it ordained by the Orange County Board of County.Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to develop a concept plan and
construct a park facility on a 40-acre site located in the Fairview
community in northern Hillsborough. Proceeds from the 2001 voter
approved bonds finance the project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
2001 Bonds $0 $200,000 $200,000
Private Placement $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Fundin $0 $200,000 $200,000
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
I.,and/Buildin $0 $0 $0
Planning/Architect/En
ineerin
$0
$52,000
$52,000
Construction $0 $148,000 $148,000
Other $0 $0 $0
Total Costs $0 $200,000 $200,000
Section 7. This ordinance shall be in effect from the original date of adoption, March
24, 2003, until June 30, 2005.
Adopted this 24~' day of March 2003.
1(~
Recreation and Parks Facilities - Greenway Development
Capital Project Ordinance
Be it ordained by the Orange County Board of County;Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to extend un-built portions of the
Chapel Hill and Carrboro greenway systems in a fashion to provide future
connections to Town and County parks and other open space networks.
Funds would be used specifically for trail construction and some land
acquisition, as needed. Proceeds from the 2001 voter approved bond
referendum finance the project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
2001 Bonds $0 $400,000 $400,000
Private Placement $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Fundin $0 $400,000 $400,000
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Land/Buildin $0 $0 $0
P lanning/Architect/En
ineerin
$0
$0
$0
Construction $0 $400,000 $400,000
Other $0 $0 $0
Total Costs $0 $400,000 $400,000
Section 7. This ordinance shall be in effect from the original date of adoption, March
24, 2003 until June 30, 2005.
Adopted this 24th day of March 2003.
!~
Recreation and Parks Facilities -Lands Legacy
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to protect and preserve identified
natural areas, prime forestlands, and critical cultural/archaeological sites.
In addition funds may be used to acquire lands for future park sites,
farmland conservation easements, and nature preserves. Proceeds from
the 2001 voter approved bonds finance the project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
2001 Bonds $0 $1,750,000 $1,750,000
Private Placement $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Fundin $0 $1,750,000 $1,750,000
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Land Ac uisition $0 $1,750,000 $1,750,000
Planning/Architect/En
ineering
$0
$0
$0
Construction $0 $0 $0
Other $0 $0 $0
Total Costs $0 $1,750,000 $1,750,000
Section 7. This ordinance shall be in effect from the original date of adoption, March
24, 2003 until June 30, 2005.
Adopted this 24th day of March 2003.
~~,
Recreation and Parks Facilities -Smith Middle School
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to install lighting and bleachers at
the playing fields located at Smith Middle School in Carrboro. Proceeds
from the 2001 voter approved bonds finance the project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
2001 Bonds $0 $250,00 $250,000
Private Placement $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Fundin $0 ..$250,000 $250,000
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Land Ac uisition $0 $0 $0
Planning/Architect/Engin
eerie
$0
$0
$0
Construction $0 $0 $0
Li tin & Bleachers $0 $250,000 $250,000
Total Costs $0 $250,000 $250,000
Section 7. This ordinance shall be in effect from the original date of adoption, March
24, 2003, until June 30, 2005.
Adopted this 24~' day of March 2003.
C~
Recreation and Parks Facilities -Soccer Superfund
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2. of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to construct soccer fields at both
existing and future park sites located throughout the County. Proceeds
from the 2001 voter approved bonds finance the project.
Section 2.
Section 3.
Section 4.
Section 7.
The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
2001 Bonds $0 $500,000 $500,000
Private Placement $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Fundin $0 $500,000 $500,000
The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Land Ac uisition $0 $0 $0
Planning/Architect/En
ineerin
$0
$0
$0
Construction $0 $500,000 $500,000
Other $0 $0 $0
Total Costs $0 $500,000 $500,000
This ordinance shall be in' effect from the original date of adoption, March
24, 2003 until June 30, 2005.
Adopted this 24th day of March 2003.
~~
Affordable Housing Program
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to fund housing activities in the following
categories: land acquisition, housing development, and homeownership.
Proceeds from the 1997 and 2001 voter approved bond referenda, Affordable
Housing Trust funds and Community Development Program Income finance the
project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The followin revenue is antici ated to com lete this ro'ect:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
1997 Bond Funds $1,287,500 $345,000 $1,632,500
2001 Bond Funds $0 $1,300,000 $1,300,000
Grant Funds $0 $15,000 $15,000
Private Placement $0 $0 $0
Fees $0 $0 $0
Transfer from Commutrity
Development (Program
Income
$0
$126,432
$126,432
Transfer from Community
Development (Housing
Trust Funds)
$50,000
$123,568
$173,568
Total Fundin $2,625,000 $1,910,000 $3,247,500
al
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Land
EmPOWERment $90,000 $0 $90,000
Habitat for Humani $460,000 $0 $460,000
Total Land $550,000 $0 $550,000
Desi $0 $0 $0
construction $o $o $o
Scarlett Drive $140,000 $0 $140,000
EmPOWERment $247,500 $0 $247,500
Meadowmont
Condominiums
$400,000
$0
$400,000
Continuin Care Center $0 $275,000 $275,000
Total Construction $787,500 $275,000 $1,062,500
Pine Knolls Community
House Relocation
$0
$85,000
$85,000
Sunrise Road Pro'ect $0 $250,000 $250,000
2001 Unallocated Bond
Funds
$0
$1,300,000
$1,300,000
Total Costs $1,337,500 $1,660,000 $2,997,500
Section 5. This ordinance supersedes previous Affordable Housing Capital Project
Ordinances for Orange County Government.
Section 6. This ordinance shall remain in effect until June 30, 2003.
Adopted this 24th day of March 2003.
`='~~
Conservation Easements
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for the acquisition of agricultural
conservation easements to help preserve County farmland with a priority placed
on farms with a strong conservation track record in water supply watersheds.
Financing for the project includes proceeds from private placement loans and
federal grant funds from the USDA Natural Resource Conservation Service.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
Bond Funds $0 $0 $0
Private Placement $0 $1,000,000 $1,000,000
Grant Funds $0 $784,155 $784,155
Fees $0 $0 $0
Other $0 $0 $0
Total Fundin $0 $1,784,155 $1,784,155
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY2002-03 Through FY
2002-03
LarxllBuildi $0 $1,784,155 $1,784,155
Desi $0 $0 $0
CAr~stnxtion $0 $0 $0
Other $0 $0 $0
Total Costs $0 $1,784155 $1,784y155
Section 5. This ordinance supersedes all previous Conservation Easement Capital Project
Ordinances for Orange County.
Section 6. This ordinance shall be in effect from the date of adoption until June 30,
2005.
Adopted this 24~' day of March 2003.
:~ .5
Chapel Hill Senior Center
Capital Project Ordinance
Be it ordained by the Orange County Board of County; Commissioners that pursuant to
Section 13.2. of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to plan and construct a new twenty-
five thousand square foot Senior Center located at the Southern Human
Service Center site on Homestead Road in Chapel Hill. The planned new
facility will replace the current Chapel Hill Senior Center located in leased
space in the Galleria on Elliott Road in Chapel Hill. Proceeds from the
2001 voter approved bond referendum and a private placement loan
finance the project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
2001 Bonds $0 $400,000 $400,000
Private Placement $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Fundin $0 $400,000 $400,000
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Land Ac uisition $0 $0 $0
Planning/Architect/En
ineerin
$0
$325,000
$325,000
Construction $0 $75,000 $75,000
Other $0 $0 $0
Total Costs $0 $400,000 $400,000
Section. 7. This ordinance shall be in effect from the original date of adoption, March
24, 2003, until June 30, 2005.
Adopted this 24th day of March 2003.
a~-~
Central/Northern Orange Senior Center
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of .North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to acquire land and construct a
fifteen thousand square feet Central/Northern Orange Senior Center in or
around the Hillsborough area. The planned center will replace the Central
Orange Senior Center currently located in leased space at the
Meadowlands in Hillsborough. Proceeds from the 2001 voter approved
bonds and a private placement loan finance the project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
2001 Bonds $0 $100,000 $100,000
Private Placement $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Fundin $0 $100,000 $100,000
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Land Ac uisition $0 $0 $0
Planning/Architect/En
ineerin
$0
$100,000
$100,000
Constnzction $0 $0 $0
Other $0 $0 $0
Total Costs $0 $100,000 $100,000
Section 7. This ordinance shall be in effect from the original date of adoption, March
24, 2003, until June 30, 2005.
Adopted this 24th day of March 2003.
-~ S
Orange County Satellite Campus of Durham Technical Community College
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds for the County's portion of land and
construction costs for an Orange County satellite campus for Durham Technical
Community College. Proceeds from a private placement loan finance the project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
02-03
Sales Tax $0 $0 $0
Bonds 2001 $0 $0 $0
act Fees $0 $0 $0
Private Placement $0 $1,000,000 $1,000,000
Other $0 $0 $0
Total Fundin $0 $1,000,000 $1,000,000
Section 4.The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
02-03
Land $0 $1,000,000 $1,000,000
Desi $0 $0 $0
Construction $0 $0 $0
Other $0 $0 $0
Total Costs $0 $1,000,000 $1,000,000
Section 5. This ordinance shall be in effect from the original date of adoption, March 24,
2003, until June 30, 2005.
Adopted this 24th day of March 2003.
~~
Orange Enterprises Capital Project
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to construct a building addition at
Orange Enterprises. facility on Valley Forge Road in Hillsborough.
Proceeds from a private placement loan finance the project.
Section 2. The officers of the County are hereby directed to proceed with the project
within budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
Sales Tax $0 $0 $0
Bond Funds $0 $0 $0
Private Placement $0 $0 $0
Fees $0 $0 $0
Other $0 $525,000 $525,000
Total Fundin $0 $525,000 $525,000
Section 4. The following amount is appropriated for this project:
Through FY
2001-02
FY 2002-03 Through FY
2002-03
l.andBuildin $0 $0 $0
Desi $0 $50,000 $50,000
Construction $0 $475,000 $475,000
Other $0 $0 $0
Total Costs $0 $525,000 $525,000
Section 5. This ordinance shall be in effect from the original date of adoption, March
24, 2003, until June 30, 2005.
Adopted this 24th day of March 2003.