SUBJECT: Orange County Comprehensive Transportation Plan Deficiency Analysis
DEPARTMENT: Planning and Inspections PUBLIC HEARING: (Y/N) No
ATTACHMENT(S): INFORMATION CONTACT:
1. Map of Future Highway Deficiencies Karen Lincoln, 245-2580
2. PowerPoint Presentation Craig Benedict, 245-2592
3. Revised Time Frame
PURPOSE: To consider endorsing assumptions and data projections used for developing the
deficiency analysis for highways.
BACKGROUND: Orange County, in June 2009, approved a resolution endorsing a
comprehensive transportation planning study for Orange County. The study is being completed
through a coordinated effort of the Orange Unified Transportation Board, Orange County
Planning, the Triangle Area Rural Planning Organization, the Durham-Chapel Hill-Carrboro
Metropolitan Planning Organization and the North Carolina Department of Transportation
(NCDOT). A Comprehensive Transportation Plan (CTP) Steering Committee, comprised of
representatives of those groups, has completed the following actions:
• Held a public workshop to kick-off the process (September 2009)
• Conducted an on-line public survey (October -November 2009);
• Collected current traffic data and projected future traffic (August 2010 -October 2010)
• Analyzed traffic growth rates to use in final data projections (November 2010)
• Prepared a highway deficiency analysis (November -December 2010)
• Held a public input meeting on the deficiency analysis (February 2011)
Although not represented in the CTP Steering Committee, the Burlington-Graham Metropolitan
Planning Organization (BGMPO) has opportunities to comment. County and NCDOT staff
apprise the BGMPO Transportation Planning Manager of any transportation plan developments.
CURRENT SITUATION: The steering committee is now ready to develop alternatives to be
considered in the Draft Transportation Plan. The committee seeks approval to develop plan
alternatives based on the deficiency analysis, i.e. the assumptions and data projections used to
develop it.
Next steps include:
1. Develop draft transportation plan for all modes;
2. Seek public input, advisory board comments; and
3. Present to BOCC for comment/direction before developing final plan for public hearing.
2
Attachment 1 is a highway deficiency map illustrating future volume-to-capacity ratios for year
2035. Attachment 2 is a copy of the presentation. Attachment 3 shows the anticipated time
frame for completing the transportation plan.
FINANCIAL IMPACT: The Comprehensive Transportation Plan will require planning staff
resources, but can be completed with existing staff.
RECOMMENDATION(S): The Manager recommends the Board:
1. Receive the presentation; and
2. Endorse the deficiency analysis to be used in developing alternatives for the draft
transportation plan.
Orange County Attachment1 3
BORN °
n ~ _..
O,p
y
~ a
'q9 ,,
P
w
c 9 3
o~ C.
~ _ q_
S
~
~ dqE~ yo A ~ ,.t ~ ~.
~ F
~ Y
F _
LAWS STORE _
mP
a
~ q^~
OLIN ~ ~ ~ -_ ,r
y~ ~ yi}
tt
~
E~
~c .
a
TEL RNER CNVR
ci
y
WM
OARR ~ ~
YEA SON[`'
l'-)
~
F
.LONESOME 3 _
-
P i '
~p
~ \ R
(
~
~
~
1
~ ,l
_
L 1 ~ 1, ~ti
7 -
u'
1
1
~ . SO
H
~. > ;.
ff~~ =:_.
2
'
~ ~ ~ ~ I. y= !
~
' ~ ~;~
y. 1
5yQ
10;N10N i
-
PS i
~Yl
~
~
1 ~ ~
~ W ~ `-~a *a.
1,
~,
_
ly
~ ~ • i
1 ^fn 'YN Y- I vd ~. I ~~1~ Ali
. l ~ ~~ ti" ~
,~ ~Vf
H
~
7° .
~.
~' ~ ~~
~f
*
~~ ~
T
OA -„~; ~~
.j
a
- ,
~ x(70 _
i - x ~ -.
~
.~sa
~..
- ~
..
.
~1 it l
_
i `~ g
~ ~+
~
oM`'
4~0 o~U ~' I ~ 4
fi
-_ , - _'
~_. ~ ,x
y m .
r
_.
r ll ~ ~ ~ i
~' - v
$ ~ MTNVR MINN~ ^{ ~;~
1. '.'=4
f' '}~`_
c
~ ~
0 ~
3 '.k
J
~
m ~ li {
o
o
~~
>F
~l t_
.,.
.. ~
W
i ~
~
~ `
~ `
-
~
T ~ `h'..
1 ,\
l
-ltlE3 15
S
Ji
~J
_ ~~ ~ .r.
-Il 4H3 , - ;
,
!
~'
r
q} ~ , t S°i ~i L
-
w
;
_
"I
~~, y~g~GQ
f +y...
Y` ~V~ 1 ~H~p ~ •~ ~'
OLD EENSBO • ^+~ 1 ~ ~ T ~ r
;~
~
~ 3 l
~ ,fir xa
~
.
z
_= ` ~
. .
,..
.~ t . -
P ' ~ ~ - ~;<
~
-;
t
~`~
_ ~
0
i1v
Capacity Deficiency Analysis ° 05 ' Z 203
5 Volume/Capacity
Mlles
Anticipated Problem Areas for 2035 (V/C) Map
Under Capacity (V/C = 0 - 0.7) N
~~`~ , cee
Near Capacity (V/C = 0.8 - 0.9) ®~
A
•
•~
W
E
Over Capacity (V/C = (1.0 +)
~
0 Municipal Boundaries s
.
e<<g `e~e~,
Municipal ETJ
COmprellenSlVe
Burlington-Graham MPO Transportation Plan
Durham-Chapel Hill-Carrboro MPO Capacity Deficiency
4
Orange County
Comprehensive Transportation Plan
*Rural Area
t~pf NORTH C1q r
Oy
h~ Y
c z
0
t
99~`~'orm1.N~0.P
May 17, 2011
®``es` ~ c°trr
A
u
°<<4 date"~ 1
Overview
• ~ Review: What is a
Comprehensive
Transportation Plan?
• What has been
accomplished so far?
- Goal: get your input
and consensus on the
data
• What are the next steps?
Slide
NCDOT Transportation
Planning Branch
5
MPO / RPO
Areas
TARPO =
Triangle Area Rural
Planning Organization
Slide
Reminder:
• This plan is for RPO area
• Encompasses no
municipalities
~,~ ,~ ~
I~' ~ ~ ~ r
~, ~,<~ ,~_r.
,~'~.
~ z i
Mebane '
~-'"` Hillsborough ~ ~~
~-
~., ~
~~
i
~~~-~.+ __ Chapel
Hill !
~~ ~ t
` ,.
Slide_ Study Area
4
2
6
What is a CTP?
(Comprehensive Transportation Plan)
• Updated process for transportation planning
- Orange County Thoroughfare Plan, 1990 (not adopted)
• Long-range (25-30 years)
• Multi-modal
• Fiscally unconstrained (no funding or priorities)
• Purpose/Objectives...
- Reduce traffic congestion and improve safety
- Identify existing and future problem areas
- Generate information decision-makers can use to guide
future transportation dec~~deons 5
What is a CTP?
• Incorporates local interests, community goals, and
statewide needs in one common plan
• Developed by steering committee with representation from
NCDOT, Orange County planning, OUTBoard, and Triangle
Area RPO
- Coordination with surrounding MPOs and counties
• Adopted/endorsed at 3 levels
- County (adoption)
- MPO/RPO (endorsement)
- State (adoption)
Slide 6
3
7
What is a CTP?
• Multi-modal
- Highway, Public Transportation,
Rail, Bicycle, Pedestrian
• Final plan is comprised of...
- A map set of recommendations for each mode
- A written report for documentation
~~
Why Develop a CTP?
• It's the law - GS 136-66.2
• Recommendations address future travel demand -not
just for vehicles, but for all modes
- Ensures that data and projections are in place to
support projects
- Informs future land use planning and corridor
protection
• Documentation is customer-friendly and easy to update
• Awell-informed public
- Public workshops are included
- Local officials are regularly updated ~ :~~'
-Plans available on NC®~T website
4
8
Typical Sequence of NCDOT Project Development
0
PLANNING PROGRAMMING DESIGN RIGHT-OF-WAY CONSTRUCTION
-CTP STUDY -:
STIP DA7A
LAND
BIDDING
---------~-~~~~ PDEA- COLLECTION PROCUREMENT PROCESS
RPO PROJECT
PRIORITIZATION EVALUATION ALIGNMENT
SELECTION
EASEMENT
NCDOT BOARD
ENVIRONMENTAL ATTAINMENT AWARDS
PROJECTS DOCUMENTS TRANSPORTATION
PUBLIC CONTRACT
PRESENTEDTO ALTERNATIVE FACILITY DESIGN ASSISTANCE CONTRACT
NCDOT BOARD STUDIES ESTIMATESB ADMINISTRATION
FOR STIP OUANITIES LEGAL ACTION
CONSIDERATION PUBLIC COMPLETED
INVOLVEMENT PROJECT
23 YEARS UP TO 7 1-2 YEARS 1-2 YEARS 1-2 YEARS
YEARS
Slide 9
CTP Progress
Roadway Network Data Collection
Public Surveys d' ~ .
Traffic Growth r
Rates
Traffic '
Projections ~~r
~..I+
Capacity
Deficiencies
J,
Public ' -'
Drop-in
We are
here
(HIGHWAY)
5
9
~T -,
~ ~ t
~ i ~ : ` .~~ -- - r
Roadwa ~':
y ~
Network
Map ~ ,~.
yr _ ;.
=All the roads chosen to v !'
study and gather data ~ -- ~ i~ _
y j
~~ ~ ~ ,~
-~ '
~~ t ~ f
cr t
D~~T gg,,, 1loatlrw, NwwoA
'Y~`
Slide Onnga County ~
.......... mror~wn
Growth Rate Map
• Begins with the roads in the studied network
• Gather historical traffic count data
- Date back to 1990
- Committee reviews the various growth rates for each
road, and decides on a final rate based on local
knowledge (usually 1-3% per year)
- Final growth rate is used to project the current traffic
counts to the horizon year (2035)
Slide
6
10
Growth
Rate
Map
i .._.^- r_ .r- - ..
L _ a :'
~
l } ~ i
'
!/
ti'
1.
~+ , ~ 1
, r ~
,
,, l
~
~~~- j'
~
l
- ~
'
~
,
~~ j
~ ~._~ .~ ~
;
` „
~
~ ~,~-- ::i
__:, ..:r~..~.
l~L/
~~de a.~. coumy
...`.. oa~«»ns~..
oa~cort.non n.n
Capacity Deficiencies Map
(Volume/Capacity Map)
• Objective: target and analyze the future problem areas
(to create solutions on the final plan)
• Capacity =how much traffic a road can hold
(Based on attributes such as speed limit, lane width,
number of lanes, etc.)
• Deficiencies =problem areas
• Projected traffic is compared to the road's existing
capacity
~ "Volume/Capacity Ratio"
~ V/C ratio = 1 when road is AT capacity
Slide 14
7
11
- ---- ; ~, --f
,, .. ~ ~. !
1 °-
~
~' P +
r--~
-~ ; i
Vol u me/ ~ ` ~ ~`~~.~~` ;
i
Capacity j - _
Map ,R
=Where the problem I~sry'~' ~ ;'
areas could be `t ~~
(just a starting point)
~ __ ..
s_~,
~~ ;
e
I
_--..!
-u.l4.cbN~Cly _ . MaP
-Qxr G~p:siryifA~)
~CauYyNa~wey
Ml~cv/WMic~
~fa~T.
44~~
~~bWy
r rrte~, ~~..
Oran9•rn•"l
5
dn+.n CaipMnsM
T'rspalNbn Nan
Street Appendix
(Spreadsheet of data for all the roads in the Network)
_. ___ _~_t_„_ _-..__.
s
,.
__~
_ _
F
n 16
8
12
How is this data used?
• Examined and reviewed by committee to ensure it is
valid, consistent, and complete
• Compared to travel demand model volumes
• OUTBoard input
• Public input
• BOCC input
- Get your endorsement of the data ~~~
Slide '
Caswell County = -;-~ ---- I _ Person County =
CTP complete ~~~ ,~ I J ~ CTP complete
~°-` 1, `~
Burlington it ~ ~ ~ f Durham-Chapel
Graham +~ r . Hill-Carrboro
Metropolitan +, `~> q~ , ~,f `r ~ Metropolitan
Planning ~' ~ ~ Planning
Organization ~ Organization
(BGMPO) _ l (DCHC MPO) _
CTP complete ~ , CTP in progress
_~;/ 1.
r~-~~ ~~
~'~~ ~' ~`
~..
Triangle _ ~ - ~
Area Rural > ~~~ ~
Planning ` i__` ;~ ___~ ;` cnatham County =
Organization ~ '--------- '---- - CTP in progress
~TARPO~ Stu~f Area
,8
9
13
Public Participation and Input
Public informational session held in Fall 2009
Public survey distributed in Fall 2009
-Nearly 500 responses
Public drop-in session ,- ., :;
held February 7, 2011 ~ ``~ ~~%
. ,~
-Attended by a number ~~ -
.j~..
of interested citizens -~--•~~~-~-~~--~~-~ °°-~-~~
Slide
19
10
14
Thank you! Questions?
Orange County CTP Website:
http://www.ncdot.org/-tpb/planning/orangecounty.html
Sarah E. Lee
Transportation Engineer
NCDOT TPB
(919) 707-0946
seleeC~ncdot.gov
Scott Walston
Triangle Unit Supervisor
NCDOT TPB
(919) 707-0941
swalston@ncdot.gov
Karen Lincoln
Transportation Planner
Orange County
(919) 245-2580
klincoln@co.orange.nc.us
Other committee contacts:
Paul Guthrie
Randy Marshall
Nancy Baker
Tina Love
(TARPO vacant)
More info at w sww ncdot.org/~tpb
21
11
DEVELOPMENT OF ORANGE COUNTY COMPREHENSIVE TRANSPORTATION PLAN (CTP)
DEVELOP CTP VISION (COMPLETED)
/ Establish Community Vision -adopted vision of Transportation Element of
Comprehensive Plan (2008)
/ Goals & Objectives -adopted Goals & Objectives of Transportation Element of Comp,
Plan (2008)
/ Trans ortation Surve -Completed November 2009
2010
2011
2012
CTP TASKS
A S 0 N D J F M A M J J A S '0 N D J F M A M J J
CONDUCT NEEDS ASSESSMENT
- Collect data and project future traffic (NCDOT)
- Develo deficient Anal sis NCDOT "~ -k
DEVELOP ALTERNATIVES ANALYSIS
- Public Workshop/Comment Period/Advisory Board input (NCDOT, TARPO, Orange Co.)
'
- BOCC endorsement of ro
ections and deficiencies, comments Oran a Coun ;~.~;:
DEVELOP RECOMMENDED ORANGE COUNTY CTP
- Develop Draft Recommended CTP for all modes (Steering Committee) ~~*
- Public Workshop/Comment Period/Advisory Board input (NCDOT, TARPO, Orange Ca ~ "'n: .,;
- BOCC comments on Draft CTP Oran a Count -; . ~
DEVLOP FINAL ORANGE COUNTY CTP
- Develop final CTP (Steering Committee)
- Public Hearin on final CTP NCDOT, TARPO, Oran a Coun ~
ADOPTIENDORSE FINAL CTP
- Orange County adopts final. CTP ~
- TARPO Endorses final CTP
- NCDOT BOT adopts final CTP
D