HomeMy WebLinkAboutORD-2005-198 - Approval of County Capital Project Ordinances ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: November 15, 2005
Action Agenda
Item No. _
SUBJECT: Approval of County Capital Project Ordinances
DEPARTMENT: Budget PUBLIC HEARING: (Y/N) No
ATTACHMENT(S):
Attachment 1. County Capital Project INFORMATION CONTACT:
Ordinances (Under Donna Dean 245-2151
Separate Cover)
PURPOSE: To approve County capital project ordinances for fiscal year 2005-06.
BACKGROUND: On June 21, 2005, the Manager presented his recommended 2005-15
Capital Investment Plan (CIP) for the County as well as both School systems. While the Board
discussed the plans during budget deliberations throughout June, there were a number of
capital and debt related matters that the Board chose to discuss further at a fall 2005 work
session. To that end, Commissioners approved some Level 1 county and school capital
projects for fiscal year 2005-06 on June 23, 2005 and delayed action on other capital matters
until fall 2005.
Many capital project ordinances approved by the Board in June did not involve new funding
appropriations but merely extended the project timelines through June 30, 2005. Other projects
received new funding for the current fiscal year, and the County, along with each school system,
needed funding appropriations in place in order to accomplish work during summer 2005.
At their regular meeting on October 18, 2005, the Board of Commissioners approved all
remaining Chapel Hill-Carrboro and Orange County Schools' capital project ordinances for fiscal
year 2005-06. Remaining County capital project ordinances were also prepared and presented
at the October 18 meeting, but Commissioners had questions about some of the ordinances
and asked staff to review and confirm funding allocations for County projects for fiscal year
2005-06. The Budget staff has completed the review and the Budget Director has confirmed
that the County project ordinances being presented at this time accurately reflect the current
fiscal year allocations for Level 1 projects in accordance with the amounts approved by the
Board at its September 13, 2005 work session.
As a point of clarification, in accordance with the Board's adopted School Planning and Funding
Policy, Level 1 projects are those that involve a relatively small scope of work, while Level 2
projects include those projects that require several phases to complete. Staff will bring back
capital project ordinances for Level 2 school and county projects at the appropriate times over
the life of the major projects. Examples of Level 2 projects include OCS Gravelly Hill Middle
School (formerly OCS Middle School #3), CHCCS High School #3, Justice Facility and Orange
County Satellite Campus of Durham Technical Community College.
1
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: November 15, 2005
Action Agenda
Item No.
SUBJECT: Approval of County Capital Project Ordinances
DEPARTMENT: Budget PUBLIC HEARING: (Y/N) No
ATTACHMENT(S):
Attachment 1. County Capital Project INFORMATION CONTACT:
Ordinances (Under Donna Dean 245-2151
Separate Cover)
PURPOSE: To approve County capital project ordinances for fiscal year 2005-06.
BACKGROUND: On June 21, 2005, the Manager presented his recommended 2005-15
Capital Investment Plan (CIP) for the County as well as both School systems. While the Board
discussed the plans during budget deliberations throughout June, there were a number of
capital and debt related matters that the Board chose to discuss further at a fall 2005 work
session. To that end, Commissioners approved some Level 1 county and school capital
projects for fiscal year 2005-06 on June 23, 2005 and delayed action on other capital matters
until fall 2005.
Many capital project ordinances approved by the Board in June did not involve new funding
appropriations but merely extended the project timelines through June 30, 2005. Other projects
received new funding for the current fiscal year, and the County, along with each school system,
needed funding appropriations in place in order to accomplish work during summer 2005.
At their regular meeting on October 18, 2005, the Board of Commissioners approved all
remaining Chapel Hill-Carrboro and Orange County Schools' capital project ordinances for fiscal
year 2005-06. Remaining County capital project ordinances were also prepared and presented
at the October 18 meeting, but Commissioners had questions about some of the ordinances
and asked staff to review and confirm funding allocations for County projects for fiscal year
2005-06. The Budget staff has completed the review and the Budget Director has confirmed
that the County project ordinances being presented at this time accurately reflect the current
fiscal year allocations for Level 1 projects in accordance with the amounts approved by the
Board at its September 13, 2005 work session.
As a point of clarification, in accordance with the Board's adopted School Planning and Funding
Policy, Level 1 projects are those that involve a relatively small scope of work, while Level 2
projects include those projects that require several phases to complete. Staff will bring back
capital project ordinances for Level 2 school and county projects at the appropriate times over
the life of the major projects. Examples of Level 2 projects include OCS Gravelly Hill Middle
School (formerly OCS Middle School #3), CHCCS High School #3, Justice Facility and Orange
County Satellite Campus of Durham Technical Community College.
2
With regard to County owned vehicles and equipment, the County has historically funded those
through its ten year Capital Investment Plan (CIP). Examples of the types of purchases made
with annually appropriated monies include replacement of some portion of the Sheriffs vehicle
fleet and Emergency Services vehicles, including ambulances, as well as replacement of other
County department vehicles and major equipment (not including Information Technology-related
equipment).
As a complement to the County's Environmental Responsibility Goal and energy conservation
measures, staff is currently updating the Vehicle Replacement Standards to ensure that future
vehicle purchases are in accordance with Board adopted goals and policies. Over the next
months, staff will work with individual departments to explore various options for meeting
departmental equipment and vehicle needs. The Manager will approve all individual vehicle
and equipment purchases before the items are ordered. At this time, staff anticipates the
need to pursue funding arrangements that include a thirty-six month period and another for a
period of fifty-nine months. The life expectancy and cost of the equipment or vehicle would
determine the length of financing.
FINANCIAL IMPACT: The first two pages of Attachment 1 of this abstract, summarize the
annual appropriation for each Board approved capital project ordinance for the current fiscal
year. Individual capital project ordinances (included in Attachment 1) provide additional funding
details related to each project's funding source along with expenditure budget details.
RECOMMENDATION(S): The Manager recommends that the Board of County
Commissioners approve the attached County Capital Project Ordinances.
County Capital Projects
Summary of Ordinances for Fiscal Year 2005-06
BOCC Approved FY 2005-06 Project Appropriation As Approved by BOCC on
Project Ordinances Ordinances Level 2 Projects Total BOCC Total Protect
Project Name Appropriation Approved by Requested for Pending Future Approved FY Appropriation
Through FY 2005
Through FY BOCC on BOCC Approval BOCC Approval 2005-06
2004-05 ".1 c2 06
6123105 on 11/15/05 ► Appropriation
ADA Compliance $0 $12,500 $37,500 $0 $50,000 $50,000
Animal Services Facility $0 $170,000 $0 $700,000 $870,000 $870,000
Animal Shelter $0 $0 $29,000 $0 $29,000 $29,000
Assessments and Testing $0 $0 $25,000 $0 $25,000 $25,000
Automation Enhancement and Preservation Fund $578,181 $0 $50,000 $0 $50,000 $628,181
Blackwood Farm Structure Stabilization $0 $0 $75,000 $0 $75,000 $75,000
Bolin Creek Greenway $75,000 $0 $425,000 $0 $425,000 $500,000
Building Entry Access Control Systems $0 $0 $50,000 $0 $50,000 $50,000
Capital Repairs/Replacement(Emergency)Reserve Fund $0 $0 $25,000 $0 $25,000 $25,000
Carrboro Library $0 $0 $50,000 $0 $50,000 $50,000
Cate Farm Structure Stabilization $0 $0 $125,000 $0 $125,000 $125,000
Central Recreation Repairs $0 $0 $635,000 $0 $635,000 $635,000
Central/Northem Orange Senior Center $1,175,000 $0 $0 $825,000 $825,000 $2,000,000
Conservation Easements $3,795,681 $0 $950,000 $0 $950,000 $4,745,681
County Campus Development $0 $0 $0 $1,800,000 $1,800,000 $1,800,000
County Facilities Art Reserve $0 $0 $5,000 $0 $5,000 $5,000
Court Street Annex $0 $0 .$25,000 $0 $25,000 $25,000
Dickson House $0 $0 $7,500 $0 $7,500 $7,500
Elevator Repairs and Improvement $0 $0 $70,000 $0 $70,000 $70,000
Emergency Management Division Relocation $0 $0 $0 $200,000 $200,000 $200,000
Equipment and Vehicles $3,415,475 $0 $267,000 $0 $267,000 $3,682,475
Fire Alain Systems $0 $0 $15,000 $0 $15,000 $15,000
Flooring Replacements $0 $0 $241,000 $0 $241,000 $241000
Greenway Development $675,000 $0. $75,000 $0 $75,000 $750,000
Heritage Center $0 $0 $0 $112,000 $112,000 $112,000
Historic Courthouse Repairs $29,637 $0 $15,000 $0 $15,000 $44,637
Homestead A uatics Center iii $4,300,000 $0 ($3,175,000) $0 ($3,175,000) $1,125,000
HVAC Protect $150,000 $15,000 $243,000 $0 $258,000 $408,000
Information Technology $825,000 $0 $400,000 $0 $400,000 $1,225,000
Jail Renovations $0 $0 $625,000 $0 $625,000 $625,000
Justice Facility and New Courthouse Renovations Project(") $560,000 $0 $0 $9,610,000 $9,610,000 $10,170,000
Lands Legacy $12,252,577 $0 $2,050,000 $0 $2,050,000 $14,302,577
Medicald Maximization $994,661 $0 $75,0001 $0 $75,0001 $1,069,661
County Capital Projects
Summary of Ordinances for Fiscal Year 2005-06
BOCC Approved FY 2005-06 Project Appropriation As Approved by BOCC on
Total Project
Project Ordinances Ordinances Level 2 Projects Total BOCC Appropriation
Project Name Appropriation Approved by Requested for Pending Future Approved FY Through FY 2005
Through FY BOCC on SOCC Approval BOCC Approval 2005-06 06
2004-05 6123105 t'I on 11/15/05 (2) Appropriation
Northern Human Services Center Repairs $393,630 $0 $173,000 $0 $173,000 $566,630
Northern Park Development $700,000 $0 $500,000 $0 $500,000 $1,200,000
Orange Enterprises $525,000 $100,000 $0 $0 $100,000 $625,000
Orange High School Tennis Court Resurfacing $0 $0 $15,000 $0 $15,000 $15,000
Painting of County Facilities $0 $25,000 $102,000 $0 $127,000 $127,000
Parking Lot Repairs/Paving $0 $0 $140,000 $0 $140,000 $140,000
Parks Operations Base and County Storage Facility $0 $0 $0 $230,000 $230,000 $230,000
River Park Development $0 $0 $50,000 $0 $50,000 $50,000
Roofing Projects $259,832 $0 $200,000 $0 $200,000 $459,832
Signage $0 $0 $10,000 $0 $10,000 $10,000
Solid Waste Convenience Centers $0 $0 $40,000 $0 $40,000 $40,000
Sportsplex $4,140,000 $400,000 $0 $0 $400,000 $4,540,000
Utility Extenstion Development Project $40,000 $0 $25,000 $0 $25,000 $65,000
Water Demand Reduction S tems and Equipment $0 $0 $60,000 $0 $60,000 $60,000
Waterproofing and Drainage 1 $0 $0 $221,000 1 $0 1 $221,000 $221,000
West Ten Soccer Complex j5i $1,350,000 $0 $350,000 $0 $350,0001 $1,700,000
Totall $36,234,674 $722,5001 $5,301,000 1 $13,477,000 1 $19,500,500 $55,735,174
Capital project ordinances approved by the Board on June 23,2005 are not included In this agenda item
(2) Level 2 projects are major projects that require several phases to complete. For these projects the Board of County Commissioners approves a four-phase appropriation
process to Include Concept/Pre-Planning Phase,Planning Phase,Design and Construction Approval Phase,and Final Accounting Phase. Staff will bring ordinances to the
BOCC for approval as project timing necessitates.
(3) 2001 voter approved bond funds for Homestead Aquatics Center($3.5 million)were originally sold dunng fiscal year 2004-05 based on cash flow projections from the
Town of Chapel Hill;however,the project has not progressed along the timeline originally projected. As a result,the bond funds currently on hand can be redistributed to
other park bond projects that are moving more expeditiously. The reallocation of these funds approved by Commissioners in September 2004(in accordance with the
approved debt Issuance schedule)..Funds will be reallocated to the following projects: Bolin Creek Greenway Development($425,000);Lands Legacy($1,750,000);
Northern Park($500,000);and West Ten Soccer Complex($500,000 appropriated June 7,2005-see footnote 5 below). Based an most updated timelines,the Town
anticipates that funds would be needed in fiscal years 2006-07($2 million)and 2007-08($1,175,000). Capital project ordinances will be brought back for BOCC approval at
the appropriate times.
(41 Allows for addition of 38,000 square feet approved by the Board on October 17,2005.
(5)The 2001 voter approved Recreation bonds included$2 million for a Soccer Superfund to be used to construct new soccer fields as opportunties became available. On
June 7,2005,Commissioners approved capital project ordinances that allocated those funds from the Soccer Superfund capital project to Twin Creeks Park($650,000)and
West Ten Soccer Complex($1,350,000)for construction of soccer fields at those parks.
3
ADA Compliance
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to make County facilities compliant
with ADA requirements and ensure that public buildings are accessible to
all County residents and employees. Pay-as-you-go funds would finance
the project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $0 $50,000 $50,000
2001 Bonds $0 $0 $0
2004 Two-thirds Net Debt $0 $0 $0
Fees $0 $0 $0
Total Funding 50 $50,000 550,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Planning/Architect/Engineering $0 $0 $o
Construction $0 $50,000 $50,000
Other $Q $0 $0
Total Costsl 50 1 $50,000 1 $50,000
Section 5. This ordinance shall be in effect until June 30, 2006.
Adopted this 15th day of November 2005.
Animal Shelter(Current Facility)
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds for wall construction and the installation of
awnings at the Animal Shelter entrances. Pay-as-you-go funds would finance the
project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $0 $29,000 $29,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $01 $o
Grant Funds $0 $0 $0
Dedicated Property Tax $0 $0 $0
Total Funding $0 $29,000 $29,000
Section 4.The following amount is appropriated for this project:
Through FY FY 2005-06 Through FY
1004-05 2005-06
Land/Building $0 $0 $o
Design $0 $0 $0
Construction $0 $29,000 $29,000
Other
$01 $o $0
Total Bud et $0 1 $29,000 $29,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
Assessments and Testing
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds for professional studies, as needed or
required, to assess various infrastructure or mechanical systems at County
facilities. Examples would include air quality sampling, roofing or HVAC studies.
Pay-as-you-go funds would finance the project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $0 $25,000 $25,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 s0 $0
Grant Funds $0 $0 $Q
Dedicated Property Tax $0 $0 $0
Total Funding $0 525,000 $25,000
Section 4.The following amount is appropriated for this project:
Through FY FY 2005-06 Through FY
2004-05 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $0 $0
Other $0 $25,000 $25,000
Total Bud et $D 1 $25,000 $25,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
tP
Automation Enhancement and Preservation Fund
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to automate the deeds and vital records
systems in the Register of Deeds Office. As mandated by North Carolina
General Statute 161-11.3, ten percent of all General Statute 161 related fees
collected by the Register of Deeds finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $0 $0
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Financing Proceeds $1.74,276 $0 $174,276
Fees $403,905 $50,000 $453,905
Total Funding $578,181 $50,000 $628,181
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $01 $0
Other $578,181 $50,0001 $628,181
Total Costsi $578,181 S50,0001 $628,181
Section 5. This ordinance, originally adopted December 3, 2001 shall remain in effect from
January 1, 2002 until June 30, 2006.
Adopted this 15th day of November 2005.
Blackwood Farm Structure Stabilization
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to stabilize and preserve the structures
located at the Blackwood Farm. Proceeds from the 2004 Two-Thirds Net Debt
Bonds finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated Propetty
Tax $0 $0 $0
Bond Funds $0 $0 $0
2004 Two Thirds Net Debt $0 $75,000 $75,000
Grant Funds $0 $0 $0
Fees $0 $0 $0
tither . $0 $0 $0
Total Fundin $0 $75,000 $75,000
Section 4. The following amount is a ppropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Buildin $0 $0 $0
Design $0 $0 $0
Construction $0 $75,000 $75,000
HVAC SDI $0 $0
Total Costs $0 $75,000 $75,000
Section 5. This ordinance supersedes previous Blackwood Farm Structure Stabilization
Capital Project Ordinances for Orange County Government.
Section 6. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
Bolin Creek Greenway
Joint Town/County Open Space/Greenway Development
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to extend the Bolin Creek Trail
upstream of Airport Road. The extension of the existing Bolin Creek Trail
would be a step towards linking the existing trail with Carrboro, the
proposed woodland trail system of southern Orange County, Duke Forest,
the proposed Carolina North property, and the northwest areas of Chapel
Hill. Proceeds from the 2001 voter approved bond referendum via a
transfer from the Greenway Development Reserve Capital Project finance
the project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to com lete this proje ct:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $0 $0
2001 Bonds $0 $425,000 $425,000
2004 Two-thirds Net Debt $0 $0 $0
Fees $0 $0 $0
Transfer from Greenway
Development Reserve $75,000 $0 $75,000
Total Funding $75,000 $425,000 $500,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Planning/Architect/
Engineering $0 $0 $0
Contribution to Town of
Chapel Hill $75,000 $425,000 $500,000
Other $0 $0 $0
Total Costs $75,000 $425,000 $500,000
Section 5. This ordinance shall be in effect from the original date of adoption, March
24, 2003 until June 30, 2006.
Adopted this 15th day of November 2005.
Building Entry Access Control Systems
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds to install or update life safety and security
systems at County facilities. Pay-as-you-go funds would finance the project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $0 $50,000 $50,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Grant Funds $0 $0 $0
Dedicated Pmperty Property Tax $0 $0 $0
Total Funding s0 $50,000 $501000
Section 4.The following amount is appropriated for this project:
Through FY FY 2005-06 Through FY
200405 2005-06
Land/Building $0 $0 $0
Design s0 $0 $0
Construction $0 $0 $0
Other-Equipment $0 $50,000 $50,000
Total Bud et $0 $50,000 $50,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
10
Capital Repairs/Replacement(Emergency) Reserve Fund
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted_
Section 1.The project authorized provides reserve funds that would be used to address major
system/component needs, abatement, etc. that may arise after the budget is
adopted. Pay-as-you-go funds would finance the project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $0 $25,000 $25,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Grant Funds $0 $0 $0
Dedicated Property Tax $0 $0 $0
Total Funding $0 $25,000 $25,000
Section 4.The following amount is appropriated for this project:
Through FY FY 2005-06 Through FY
2004-05 2005-06
Land/Building $0 $0 To-
Design $0 $0 $0
Construction $0 $0 $0
Reserve $0 $25,0001 $25,000
Total Bud et $0 $25,000 1 525,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
Carrboro Library
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds to address property to be acquired at a yet to
be determined location and to some extent, the subsequent planning for the new
facility. Pay-as-you-go funds would finance the project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $0 $50,000 $50,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $01 $0
Grant Funds $0 $0 $0
Dedicated Property Tax $0 $0 $0
Total Funding $0 $50,000 $50,000
Section 4.The following amount is appropriated for this project:
Through FY FY 2005-06 Through FY
2004-05 2005-06
Land/Buiidin $0 $0 $0
Design $0 $0 $0
Construction $0 $0 $0
Other $0 $50,000 $50,000
Total Budget $01 $50,000 I $50,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
� a
Cate Farm Structure Stabilization
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to stabilize and restore the structures
located at the Cate Farm. Proceeds from the 2004 Two-Thirds Net Debt
Reduction Bonds finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY 2005-
2004-05 FY 2005-06 06
Sales Tax and Dedicated Property
Tax $0 $0 $0
Bond Funds $0 $0 $0
2004 Two Thirds Net Debt $0 $125,000 $125,000
Grant Funds $0 $0 $0
Fees $0 $0 $0
pffier $0 $0 $0
Total Fundi $0 $125,0001 $1251000
Section 4. The following amount is appropriated for this prooje ct:
Through FY Through FY 200
2004-05 FY 2005-06 06
LandBuildin $0 $0 $0
Design $0 $0 $0
Constmction. $0 $125,000 $125,000
HVAC -Sol $0 $0
Total Costsl Sol 5125,000 $125,000
Section 5. This ordinance supersedes previous Cate Farm Structure Stabilization Capital
Project Ordinances for Orange County Govdmment.
Section 6. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
Central Recreation Repairs
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to renovate and repair the Central
Recreation facility located at the Whiffed Human Services Center in Hillsborough.
Proceeds from the 2004 Two-Thirds Net Debt Reduction Bonds finance this
project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY 2
2004-05 FY 2005-06 06
Sales Tax and Dedicated Property
Tax $0 $0 $0
Bond Funds $0 $0 $0
2004 Two Thirds Net Debt $0 $635,000 $635,000
Grant Funds $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Fund' $0 $635,000 $635,000
Section 4. The following amount is appropriated for this projec t:
Through FY Through FY 2005-
2004-05 FY 2005-06 06
Land/Building $0 $0 $0
Desi $0 $65,000 $65,000
Construction $0 $570,000 $570,000
HVAC $D $0 $0
Total Costs $01 S635,0001 $635,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
Conservation Easements
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for the acquisition of conservation
easements to help preserve County farmland. Financing for the project includes
proceeds from private placement loans and federal grant funds from the USDA
Natural Resource Conservation Service.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY 2004- Through FY 20
05 FY 2005-06 06
Sales Tae and Dedicated Property -
Tax $0 $200,000 $200,000
Bond Funds $0 $0 $0
Private Placement $1,500,000 $750,000 $2,250,000
Grant Funds $2,268,681 $0 $2,268,681
Fees $0 $0 $0
Transfer from Lands Legacy
Ca ital Project $27,000 $0 $27,000
Total Fundingl $3,795,681 S950,0001 $4,745,681
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building:
Walters Easement $725,000 $0 $725,000
Volpe Easement $73,100 $0 $73,100
Cheek Easement $580,000 $0 $580,000
McPherson Easement $68,000 $0 $68,000
Ward Easement $444,750 $0 $444,750
Lloyd Easement $219,000 $0 $219,000
Laws Easement $0 $0 $0
Unallocated $1,685,831 $950,000 $2,635,83I
Total Land/Building $3,795,681 $950,000 $4,745,681
Design $o $0 $0
Construction $01 $0 $0
Total Costsl S3,795,6811 $950,000 $4,745,681
Section 5. This ordinance supersedes all previous Conservation Easements Capital Project
Ordinances for Orange County.
Section 6. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
1 �
County Facilities Art Reserve
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides reserve funds to allocate monies to construction
and renovation projects for approved art projects in County facilities, Pay-as-you-go
funds would finance the project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $0 $5,000 $5,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $o $0 $0
Grant Funds $0 $0 $0
Dedicated Property Tax $0 $0 $0
Total Funding $0 $5,000 $5,000
Section 4.The following amount is appropriated for this project:
Through FY FY 2005-06 Through FY
2004-05 2005-06
Land/Building $0 $o $0
Design $0 $0 $0
Construction $0 $0 $0
Other $0 $5,000 1 $5,000
Total Bud et $0 I $5,OOD 1 . $5,000
Section 5. This ordinance shall remain in effect until June 30, 2006..
Adopted this 15th day of November 2005.
ClJ
Court Street Annex
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds for building renovations at the Court Street
Annex in Hillsborough. Proceeds from the County's portion of the one-half cent
sales taxes and dedicated property taxes finance this project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $0 $25,000 $25,000
Bond Funds $0 $0 $o
2004 Two Thirds Net Debt $o $0 $0
Grant Funds $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Fundin $0 $25,000 $25,000
Section 4.The following amount is appropriated for this project:
Through FY Through FY
20" FY 2005-06 2005.06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $0 $0
Od= $0 $25,000 $251000
Total Costs $0 $25,0001 $25,000
Section 5. This ordinance supersedes all previous Court Street Annex Capital Project
Ordinances for Orange County.
Section 6. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
Dickson House
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds to continue the refurbishment and upkeep of
the Dickson House, such as re-glazing of the windows and realignment of the
gutters. Pay-as-you-go funds would finance the project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $0 $7,500 $7,500
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Grant Funds $0 $0 $0
Dedicated Property Tax $0 $0 $0
Total Funding $0 $7,500 $7,500
Section 4.The following amount is appropriated for this project:
Through FY FY 2005-06 Through FY
2004-05 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $7,500 $7,500
Other $0 I $0 I $0
Total Bud et $0 1 $7,500 1 $7,500
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
Elevator Repairs and Improvement
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds for upgrading/replacing elevator equipment.
Funds for fiscal year 2005-06 provide for improvements at the Whitted Human
Services Center, and funding in future years would allow for repairs at other County
facilities including the Historic Courthouse and Jail. Pay-as-you-go funds would
finance the project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $0 $70,000 $70,000
Bond Funds $o $0 $0
2004 Two-Thirds Net Debt $o $01 $0
Grant Funds $0 $o $0
Dedicated Property Tax $0 $o $0
Total Funding $0 $70,000 $70,000
Section 4.The following amount is appropriated for this project:
Through FY FY 2005-06 Through FY
2004-05 2005-06
Land/Building $0 $0 $o
Design $0 $o $0
Construction $0 $0 $0
Other $o $70,000 $70,000
Total Bud et $0 1 $70,000 1 $70,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
19
Equipment and Vehicles Project
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds to purchase County-owned vehicles and
major equipment. The project will be financed with proceeds from the County's
portion of the one half-cent sales taxes, dedicated property taxes, and proceeds
from private placement financing arrangements.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 1005-06
Sales Tax and Dedicated
Property Tax $548,295 $267,000 $815,295
Bond Funds $0 $0 $0
Alternative Financing $2,199,806 $0 $2,199,806
Grant Funds $667,374 $0 $667,374
Other $0 $0 $0
Total Funding $3,415,475 $267,000 $3,682,475
Section 4.The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 1005-06 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $0 $0
Equipment&Vehicles $3,415,475 $267,000 $3,682,475
Total Costs $3,415,475 $267,000 $3,682,475
Section 5. This ordinance supersedes all previous Equipment and Vehicle Capital Project
Ordinances.
Section 6. This ordinance shall remain in effect from July 1, 1998 until June 30, 2006.
Adopted this 15th day of November 2005,
Fire Alarm Systems
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds for the installation of fire alarm systems in
buildings that are not currently equipped with ones, as funding allows. Pay-as-you-
go funds would finance the project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Pmperty Tax $0 $15,000 $15,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Grant Funds $0 $0 $0
Dedicated Property Tax $0 $0 $0
Total Funding $0 $15,000 $15,000
Section 4.The following amount is appropriated for this project:
Through FY FY 2005-06 Through FY
2004-05 2005-06
Land/Building $0 $0 To—
Design $0 $0 $0
Construction $0 $15,000 $15,000
Other $0 $0 $0
Total Budgeti $0 1 $15,000 1 $15,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
a�
Flooring Replacements
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds for the replacements of floor coverings in
County facilities with specific projects to be determined each year based on
available funding. Pay-as-you-go funds would finance the project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $0 $241,000 $241,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Grant Funds $0 $0 $0
Dedicated Property Tax $0 $0 $0
Total Funding $0 $241,000 $241,000
Section 4.The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $241,000 $241,000
Other $0 $0 $0
Total Bud et $0 1 $241,000 $241,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
�a
Greenway Development Reserve
Joint Town/County Open Space/Greenway Development
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General'Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to extend un-built portions of the
Chapel Hill and Carrboro greenway systems in a fashion to provide future
connections to Town and County parks and other open space networks.
Funds would be used specifically for trail construction and some land
acquisition, as needed. Proceeds from the 2001 voter approved bond
referendum finance the project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $0 $0
2001 Bonds $750,000 $75,000 $825,000
2004 Two-thirds Net Debt $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Fundiniz $750,000 $75,000 $825,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Planning/Architect/
Engineering $0 $0 $0
Contribution to Carrboro $675,000 $75,000 $750,000
Transfer to Bolin Creek
Greenway Project $75,000 $0 $75,000
Total Costs $750,000 $75,000 $825,000
�3
Section 5. The following amount has been transferred from this project to the Bolin
Creek Greenway Project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Transfer to Bolin Creek
Greenway Project(2004-05) $75,000 $0 $75,000
Total Costs $75,000 $0 $75,000
Section 6. The following budget remains in the project:
Original Budget(see section 4 above) $825,000
Less Transfer to Other Funds(see section 5 above) $75,000
Total Project Budget $750,000
Section 7. This ordinance shall be in effect from the original date of adoption, March
24, 2003 until June 30, 2006.
Adopted this 15th day of November 2005.
Historic Courthouse Repairs
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to make repairs to the Orange County
Historic Courthouse. Pay-as-you-go funds will finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $29,637 $15,000 $44,637
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Unfunded $01 Sol $0
Total Fundi $29,637 $15,000 $44,637
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $29,6371 $15,0001 $44,637
Other $01 $0 $0
Total Costs $29,6371 $15,0001 $44,637
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
Homestead Aquatics Center
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds to assist the Town of Chapel Hill with
construction of an indoor aquatic center at Homestead Park on Homestead Road.
Proceeds from the 1997 and 2001 bond funds and Town bond funds will finance
this project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 1005-06
Sales Tax $0 $0 $0
1997 Bond Funds $800,000 $0 $800,000
2004 Two-Thirds Net Debt $3,500,000 $0 $3,500,000
Grunt Funds $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Funding, $4,300,000 $0 $4,300,000
Section 4.The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY2005-06 2005-06
L%%ML lding $0 $0 $0
Design $0 $0 $0
Construction $0 $0 $0
Contribution to Chapel HII $4,300,000 $0 $4,300,000
Total Costs $4,3W,000 $0 $4,300,000
aco
Section 5. The following amounts have been transferred to other County Capital Projects:
Through FY Through FY
20U4-05 FY 2005-06 20054)6•
Transfer to Bolin Cb=k Greenway
Development(2005-06) $0 $425,000 $425,000
Transfer to Lards Le (2005-06) so $1,750,000 $1,750,000
Transfer to Nm*m Park(2005-06) $0 $500,000 $500,000
Transfer to West Ten Soccer(2004-05) $500,000 $0 $500,000
Total Costs $500, $2,675,000 $3,175,000
Section 6. The following budget remains in the project:
Original Bud (see section 4 a)ove)
Less Transfer to Other Projects(see section 5 above) ($3,175,000)
Total Project Bucket $11125,000
Section 7. This ordinance shall remain in effect from July 1, 2000 until June 30, 2006.
Adopted this 15th day of November 2005.
J7
HVAC Project
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds for the replacement of heating, venting and
air conditioning (HVAC) systems at County facilities. Proceeds from the County's
portion of the one half-cent sales taxes and dedicated portion of property taxes
finance this project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $150,000 $258,000 $408,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Grant Funds $0 $0 $0
Dedicated Property Tax $0 $0 $0
Total Funding, $150,000 $258,000 $408,000
Section 4.The following amount is appropriated for this project:
Through FY FY 2005-06 Through FY
2004-05 2005-06
Land/Building $0 $0 $0
Design $15,000 $25,000 $40,000
Construction $0 $0 $0
Other $135,000 $233,0001 $368,000
Total Budgetl $150,000 1 $258,000 $408,000
Section 5. This ordinance supersedes all previous HVAC Project Ordinances for Orange
County.
Section 6. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
Information Technology
Capital. Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to implement the phases of the
County's Information Technology Plan. Proceeds from the County's
portion of the one-half cent sales taxes and dedicated property taxes
finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $825,000 $400,000 $1,225,000
Bond Funds $0 $0 $0
2004 Two-thirds Net Debt $0 $0 $0
Grant Funds $0 $0 $0
Other $0 $0 $0
Total Funding $825,000 $400,000 $1,225,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY Through FY
2004-05 2005-06 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $0 $0
Other $92:5,0001 $400,0001 $1,225,000
Total Costsi S825,0001 $400,0001 $1,225,000
Section 5. No funds allocated for public access initiatives will be expended from this
project without recommendations from the Information Technology
Committee and approval from the Board of County Commissioners.
Section 6. This ordinance supersedes all previous Information Technology Capital
Project Ordinances for Orange County.
Section 7. This ordinance, originally adopted December 1, 1997, shall be in effect
until June 30, 2006,
Adopted this 15th day of November 2005.
Jail Renovations
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to complete renovations to the
Orange County Jail. Pay-as-you-go funds and proceeds from the 2004
Two-thirds net debt reduction bonds will finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax and Dedicated
Property Tax $0 $25,000 $25,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $600,000 $600,000
Grant Funds $0 $0 $0
Other $0 $0 $0
Total Funding $0 $6251000 $625,000
Section 4. The following amount,is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $Q $0
Design $0 $60,000 $60,000
Construction $0 $540,000 $540,000
Other $0 $25,0001 $25,000
Total Costs Sol S625,0001 $625,000
Section 5. This ordinance supersedes all previous Jail Renovations Capital Project
Ordinances for Orange County.
Section 6. This ordinance shall be in effect until June 30, 2006.
Adopted this 15th day of November 2005.
3
Lands Legacy
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to protect identified natural areas
and prime forestlands, and preserve critical cultural and archaeological
sites. In addition funds may be used to acquire lands for future park sites,
farmland conservation easements, and nature preserves. Proceeds from
the 2001 voter approved bonds, 2004 Two-thirds net debt reduction
bonds, half-cent sales tax, Subdivision Payment-in-Lieu funds, Grant
Funds, and alternative financing finance the project.
Section 2. The officers of the County are hereby directed to proceed with the project
Within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $3,939,016 $0 $3,939,016
1997 Bonds $2,700,000 $0 $2,700,000
2001 Bonds $3,000,000 $1,750,000 $4,750,000
2004 Two-Thirds Net Debt s0 $300,000 $300,000
Grant Funds $421,950 $0 $421,950
Fees $o $o $0
Other(Transfer from Other
Funds) $2,191,611 $0 $2,I91,611
Total Fundingi $12,252,577 $2,050,000 $14,302,577
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $12,279,577 $2,050,000 $14,329,577
Design $0 $0 $0
Construction $0 $0 so
Transfer to Conservation
Easements Capital Project ($27,000) $0 ($27,000)
Total Costs 512,252,577 $2,050,000 1 $14,302,577
Section 5. This ordinance shall be in effect from the original date of adoption, March
24, 2003 until June 30, 2006.
Adopted this 15th day of November 2005.
3(
Medicaid Maximization
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds for the Health Department to
purchase capital items and make minor renovations to clinic space.
Medicaid maximization funds received by the Health Department finance
this project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $0 $0
Bond Funds $0 $0 $0
2004 Two-thirds Net Debt $0 $0 $0
Grant Funds $0 $0 $0
Other $994,661 $75,000 $1,069,661
Total Funding $994,661 $75,000 $1,069,661
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 'SO
Design $0 $0 $0
Construction $0 $0 $0
Other $994,661 1 $75,000 $1,069,661
Total Costsl $994,661 I $75,000 $1,069,661
Section 5. This ordinance supersedes all previous Medicaid Maximization Capital
Project Ordinances for Orange County.
Section 6. This ordinance, originally adopted February 16, 1999, shall be in effect
until June 30,2006.
Adopted this 15th day of November 2005.
Northern Human Services Center Repairs
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for major renovations, including roof repair
and septic and HVAC systems upgrades, at the Northern Human Services
Center. Financing for the project includes proceeds from the County's portion of
the one-half cent sales taxes and the two-thirds net debt reduction bonds finance
this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $393,630 $0 $393,630
Bond Funds $0 $0 $0
2004 Two-thirds Net Debt $0 $173,000 $I73,000
Grant Funds $0 $0 $0
Transfers $0 $0 $0
Other $0 $0 $0
Total Funding $393,630 x173,000 $566,630
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $60,000 $0 $60,000
Desi $0 $0 $0
Construction $190,000 $0 $190,000
Septic System $143,630 $173,0001 $316,630
Total Costs $393,630 $173,000 $566,630
Section 5. This ordinance supersedes all previous Northern Human Services Center Capital
Project Ordinances for Orange County.
Section 6. This ordinance shall remain in effect from July 1, 1998 until June 30, 2006.
Adopted this 15th day of November 2005.
33
Northern Park Development
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for the planning, design, and construction
of the Northern Human Services Center Park. Proceeds from the 2001 Bond
Funds finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $0 $0
2001 Bond Funds $700,000 $500,000 $1,200,000
2004 Two-thirds Net Debt $0 $0 $0
Grant Funds $0 $0 $0
Transfers $0 $0 $0
Other $0 $0 $0
Total Funding $700,000 1 $500,000 1 $1,200,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $35,000 $0 $35,000
Construction $665,000 1 $500,0001 $1,165,000
Other $0 $0 $0
Total Costs $700,000 $500,000 $1,200,000
Section 5. This ordinance supersedes all previous Northern Park Development Capital
Project Ordinances for Orange County.
Section 6. This ordinance shall remain in effect from July 1, 1998 until June 30, 2006.
Adopted this 15th day of November 2005.
Orange High School Tennis Court Resurfacing
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to resurface eight full size tennis courts on
the grounds of Orange High School. The County has had a long standing
contractual arrangement for use of these courts by the public, which stipulates
that the County will provide half of the funding required for capital repairs to the
facility. The courts are in severe need of repair. These courts experience heavy
use by members of the public, both in formal, programmed settings as well as
informal use. They are the only tennis courts available for public use in northern
Orange County. The Orange County School District has prioritized this project in
the CIP request the have submitted. Pay-as-you-go funds will finance this
project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $15,000 $15,000,
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Other ' $0 $0 $0
Total Funding $0 $15,000 $15,000
Section 4. The following amount is appropriated for this project.
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $0 $0
Other-Contribution to OCS $0 $15,0001 $15,000
Total Costs $0 $15,0001 $15,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
35
Painting of County Facilities
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds for the interior and exterior painting
of County facilities. Pay-as-you-go funds would finance the project:
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $127,000 $127,000
2001 Bonds $0 $0 $0
2004 Two-thirds Net Debt $0 $0 $0
Fees $0 $0 $0
Other $0 $0 $0
Total Funding S0 $127,000 $127,000
Section 4. The following amount is appropriated.for this project:
I
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Planning/Architect/
Engineering $Q $0 $0
Construction $0 $0 $0
Other $0 $127,000 $127,000
Total Costs $0 $127,000 $127,000
Section 5. This ordinance shall be in effect until June 30, 2006.
Adopted this 15th day of November 2005.
Parking Lot Repairs/Paving
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for parking lot improvements (including
paving) at County facilities. Funds in fiscal year 2005-06 will address parking lot
improvements at Whitted Human Services Center. Pay-as-you-go funds will
finance this project.
Section 2. The officers of the County are hereby directed to.proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $140,000 $140,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Other $0 $0 $0
Total Funding $0 $140,000 .$140,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $0 $14,000 $0
Construction $0 $126,000 $126,000
Other $0 $01 $0
Total Costs $0 $140,0001 $140,000
Section S. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
River Park Development
Capital Project Ordinance
Be it ordained by the drange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for the development of the open area
between the Eno River and the County government campus. Proceeds from
sales and property taxes finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is-anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $50,000 $50,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Grant Funds $0 I $0 $0
Fees $0 1 $01 $0
Total Funding $0 1 $50,000 1 $50,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0 '
Construction $0 $50,000 $50,000
Other $0 $0 $0
Total Costs $0 1 $50,000 $50,000
Section 5. This ordinance shall remain in effect from until June 30, 2006.
Adopted this 15th day of November 2005.
3�
Roofing Projects
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to conduct a study on the maintenance
and replacement schedule including cost estimates on the roofs of all County
Buildings, along with actual repairs and replacement of county facility roofs
identified in the study as high priority. For fiscal year 2005-06, those roofs
identified as high priority are Orange Enterprises (current facility), Planning and
Agriculture Building, Northern Human Services Center, Skills Development
Center and 501 West Franklin Street. This project will be financed by proceeds
from the County's portion of the one-half cent sales taxes.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $259,832 $200,000 $459,832
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $a
Dedicated Property Tax $0 $0 $0
Transfer from Other Capital
Projects $0 $0 $0
County Capital Fund
Appropriated Fund Balance $0 $0 $0
Total Fundingl $259,832 S200,0001 $459,832
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $20,000 $o $20,000
Construction $239,832 $200,000 $439,832
Other $0 Sol $0
Total Costs $259,832 $200,000 $459,832
Section 5. This ordinance supersedes all previous County .Facilities Roofing Projects
Capital Project Ordinances.
Section 6. This ordinance shall remain in effect from July 1, 1998 until June 30, 2006.
Adopted this 15th day of November 2005.
29
Signage
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for repairs and replacements of exterior
and interior signs located at County facilities. Pay-as-you-go funds will finance
this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $10,000 $10,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Other $0 $0 $0
Total Funding $0 $10,0001 $10,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $0 $0
Other $0 $10,000 $10,000
Total Costs $0 $10,000 $10,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
IL."
Solid Waste Convenience Centers
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for the replacement of waste containers,
fencing and signage at convenience center sites and for the installation of
concrete pads, barriers and driveways at the County's six sites. Pay-as-you-go
funds will finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $40,000 $40,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $01 $0
Other $0 $0 $0
Total Funding $0 $40,000 $40,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $0 $0
Other $0 $40,0001 $40,000
Total Costs $0 $40,0001 $40,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
4-I
Utility Extension Development Project
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds to assist with the extension of water
and/or sewer lines for economic development projects, particularly in the
Economic Development Districts. Pay-as-you-go funds will finance this
project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $25,000 $25,000
Bond Funds $0 $o s0
Private Placement $0 s0 $0
Fees $0 $o $0
Transfer from General Fund
(property taxes) $205,000 $0 $205,000
Total Funding 5205,000 $25,000 $230,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $o
Design $0 $0 $0
Construction $0 $0 s0
Other $205,0001 $25,0001 $230,000
Total Costsi $205,0001 S25,0001 $230,000
Section 5. The following amount has been transferred from this project to the
General Fund:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Transfer to General Fund(2002-
03) $165,000 $0 $165,000
Total Costs $165,000 $0 $165,000
Section 6. The following budget remains in the project:
Original Budget(see section 4 above) $230,000
Less Transfer to Other Funds(see section 5 above) $165,000
Total Project Budget 565,000
Section 7. This ordinance supersedes all previous Utility Extension Development
Capital Project Ordinances for Orange County.
Section 8. This ordinance originally adopted June 29, 1993 and subsequently
amended shall be in effect until June 30, 2006.
Adopted this 15th day of November 2005.
4-3
Water Demand Reduction Systems and Equipment
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to upfit appropriate County facilities with
water reduction demand fixtures and apparatuses. Pay-as-you-go funds will
finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $60,000 $60,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Other $0 $0 $0
Total Funding SO $60,000 $60,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY
200405 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $0 $0
Other $0 $60,0001 $60,000
Total Costs $0 $60,0001 $60,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
Waterproofing and Drainage
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to waterproof below grade foundations and
correct drainage problems in county facilities. For fiscal year 2005-06, facilities
identified as high priority are Court Street Annex and Purchasing and Central
Services. Pay-as-you-go funds will finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
200405 FY 2005-06 2005-06
Sales Tax $0 $221,000 $221,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Other- $0 $0 $0
Total Funding $0 $221,000 $221,000
Section 4. The following amount is appropriated for this project.
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $0 $0
Other $0 V-21,0001 $221,000
Total Costs $01 , $221,0001 $221,000
Section 5. This ordinance shall remain in effect until June 30, 2006_
Adopted this 15th day of November 2005.
�-s
West Ten Soccer Complex
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to
Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
capital project is hereby adopted.
Section 1. The project authorized provides funds for the development of a six-field
soccer complex adjacent to the Orange County Middle School #3 site
through a collaborative effort between Orange County and Orange County
Schools. Proceeds from the 2001 voter approved Soccer Superfund
bonds and 2004 Two-thirds net debt reduction bonds will finance this
project.
Section 2. The officers of the County are hereby directed to proceed with the project
within the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $0 $0
2001 Bonds $0 $0 $0
2004 Two-Thirds Net Debt $0 $350,000 $350,000
Fees $0 $0 $0
Transfer From Soccer
Superfund 2001 Bonds $1,350,000 $0 $1,350,000
Total Funding $1,350,000 $350,000 $1,700,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land Acquisition $508,500 $o $508,500
Planning/Arch/Engineering $119,000 $0 $119,000
Construction $722,500 $350,000 $1,072,500
Other $0 $0 $0
Total Costsi $1,350,0001 $350,000 $1,700,000
Section 5. This ordinance shall be in effect until June 30, 2006.
Adopted this 15th day of November 2005.