HomeMy WebLinkAboutORD-2005-193 - Waterproofing and Drainage Capital Project Ordinance Waterproofing and Drainage
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to waterproof below grade foundations and
correct drainage problems in county facilities. For fiscal year 2005-06, facilities
identified as high priority are Court Street Annex and Purchasing and Central
Services. Pay-as-you-go funds will finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Sales Tax $0 $221,000 $221,000
Bond Funds $0 $0 $0
2004 Two-Tturds Net Debt $0 $0 $0
Other $0 $0 $0
Total Funding $0 $221,0001 $221,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY
2004-05 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $0 $0
Other $0 $221,000 $221,000
Total Costs $0 $221,0001 $221,000
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 15th day of November 2005.
Sa
Waterproofing and Drainage
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to waterproof below grade foundations and
correct drainage problems in county facilities. Pay-as-you-go funds will finance
this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY Through FY
200405 FY 2005-06 2005-06
Sales Tax $0 $221,000 $221,000
Bond Funds $0 $0 $0
2004 Two-Thirds Net Debt $0 $0 $0
Other $0 $0 $0
Total Funding $0 $221,000 $221,000
Section 4. The following amount is appropriated for this project:
Through FY Through FY
200405 FY 2005-06 2005-06
Land/Building $0 $0 $0
Design $0 $0 $0
Construction $0 $0 $0
Other $0 $221,000 $221,000
Total Costs $0 $221,000 , $221,000.
Section 5. This ordinance shall remain in effect until June 30, 2006.
Adopted this 18th day of October 2005.