HomeMy WebLinkAbout2006 NS Contract - Process and Facilitation Consultant Contract for Comprehensive PlanORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: November 14, 2006
Agenda
Item No. Q -
SUBJECT: Process and Facilitation Consultant Contract for Comprehensive Plan
DEPARTMENT: Planning & Inspections/ PUBLIC HEARING: (Y /N) No
County Manager
ATTACHMENT(S):
1) Comprehensive Plan Update Timetable
2) Proposed Contract
INFORMATION CONTACT:
Tom Altieri, Comprehensive Planning
Supervisor, (919) 245 -2579
Rod Visser, Interim County Manager, 245 -2308
PURPOSE: To approve a contract between the Orange County Dispute Settlement Center
(DSC) and Orange County for the provision of process and facilitation services related to the
Comprehensive Plan update.
BACKGROUND: At its October 3, 2006 meeting, the Board of County Commissioners (BOCC)
approved, with minor revisions, the Planning Board's proposed process for updating the
Comprehensive Plan as well as the various roles of County staff, advisory boards, and elected
officials during the update. Furthermore, County Administration and the Planning Board were
asked to compress the proposed timetable for completion of the update and to consider the use
of a consultant, if necessary to complete the project.
On October 23, 2006, County Administration met with the Chairs of the Planning Board and
BOCC to discuss an accelerated schedule and the use of consulting services to complete the
Plan update. In summary, the major outcomes of this meeting were twofold.
First, the Comprehensive Plan would be completed by August 2008. This timeline (see
Attachment 1) would take approximately 2 years, concluding 6 months earlier than the October
3`d proposal.
Second, the idea is to use a combination of two different "types" of consultants to complete the
Comprehensive Plan:
1. A consultant to provide process and meeting facilitation services (proposed Contract
attached); and
2. A consultant to "synthesize" the existing reports and studies that have been completed by
various county departments, advisory boards, and in some cases consultants; identify
any missing components; and repackage into a Draft Comprehensive Plan.
The recommended approach will permit an additional joint meeting of advisory , boards involved
in the Comprehensive Plan, to occur in January 2007, as outlined in the accelerated process
timetable. The underlying premise of the proposed approach is that to a great extent the
2
updated Comprehensive Plan already exists in various County documents and in a variety of
formats, shouldn't require the generation of a lot of new material, and can be completed by
pulling together all of the good work that has already been done by the various County
departments and advisory boards.
The Planning Board will be holding a special meeting on November 15, 2006 to discuss the
timetable, the idea for a "synthesizing consultant ", and potential scope of services. Mr. Andy
Sachs of the DSC will be attending this meeting to introduce himself, review the services he
offers, and participate in discussion.
RELATION TO BOCC PRIORITIES At the work session on September 14, the BOCC
discussed previously identified priorities and directed staff to proceed and develop a set of
written goal statements and timelines associated with its top priorities for the remainder of 2006.
The six emerging issues the BOCC considered as its top priorities, in no rank order, included
continuation of the process for updating the County's Comprehensive Plan. This contract
constitutes a step in the act of moving forward with one priority issue before the BOCC in this
calendar year.
FINANCIAL IMPACT: The services of the DSC will be provided on an as needed basis as
requested by Orange County throughout the course of the Comprehensive Plan update process.
The DSC offers their services at the following rates:
Through June 2007: (a) $85.00 per hour for all necessary time provided to this project by
Program Coordinator Andrew M. Sachs; (b) $40.00 per hour for all necessary time provided
to this project by each DSC facilitator other than Mr. Sachs (e.g., small group facilitators, co-
facilitator, temporary substitution for Sachs where that is necessary).
July 2007 through May 2008: (a) $90.00 per hour for all necessary time provided to this
project by Program Coordinator Andrew M. Sachs; (b) $45.00 per hour for all necessary time
provided to this project by each DSC facilitator other than Mr. Sachs (e.g., small group
facilitators, co- facilitator, temporary substitution for Sachs where that is necessary).
Planning Staff estimates approximately 170 hours of DSC time may be required for process
consultation and meeting facilitation during the course of the Comprehensive Plan Update
process. Funding for DSC services will be drawn from appropriations already approved in the
2006 -07 operating budget and from funds to be included in the 2007 -08 Manager's
Recommended Budget. Planning Staff will keep the BOCC apprised of DSC hours spent on the
project through regular staff reports as provided by the BOCC approved process for updating
the Comprehensive Plan.
RECOMMENDATION(S): The Manager recommends that the Board authorize staff to prepare
a contract with the Dispute Settlement Center (DSC) that incorporates the scope of work
outlined under the "Cost and Contracting" section of the proposal, and authorize the Chair to
sign the contract.
Comprehensive Plan Update Timetable ATTACHMENT 1
Revised 11/06/06 (D3
*To include BOCC and Advisory Boards
0=1 MW
,Adoption of Process
Contract with Consultant
("Meeting Facilitator')
�and Guidelines
Public Information M
Planning Board Evaluation
and Appraisal of 1981 Plan
Contract with Consultant
'Preparation of County
Profile Element
Public Information Mtg.
Preparation of Goals
Outreach (not defined)
Approval of Legal Ad for
Public Hearing
'Evaluation &Appraisal of
1981 Plan, Goals, and
County Profile Element
lAdvisory Board(s)
Recommendation (s)
BOCC Adoption
Comprehensive Plan
Advisory Boards Receive
Outreach (not defined)
Planning Board develops
recommendations on any
reconciliation
Approvalof Legal Ad for
Public Hearing
Expanded Advertisement—immommmmmmmmmmmmmmmEMENEENNEEM
lQtr. Public Hearing
Advisory Board(s)
BOCC Adoption
Qtr. Public Hearing to
Adopt Regulatory Policies
and Programs
*To include BOCC and Advisory Boards
Attachment 2
(4)
Proposal by the Dispute Settlement Center (DSC) to Provide Consultation and Meeting
Facilitation in Support of Orange County's Comprehensive Plan Update Process
November 1, 2006
This proposal is based on discussions between DSC, Craig Benedict, and Tom Altieri in
which they shared the Comprehensive Plan Update Process (approved by BOCC 10/03/06)
and the Draft Comprehensive Plan Update Timetable (revised 10/09/06). According to
Benedict and Altieri, the material they shared with DSC was based on direction from the
County Commissioners and subsequent meetings with County Administration, Planning
Board Chair and Planning Staff as the Commissioners had suggested.
DSC proposes to support the County's efforts at updating the Comprehensive Plan by
providing consultation and facilitation services to the Project Management Team (County
Manager, Planning Director, Comprehensive Planning Supervisor, and Planning Board
Chair), so that the Comprehensive Plan Update Process will be well understood and
acceptable to all interested or affected stakeholders.
At a minimum, the stakeholders appear to be the Board of County Commissioners, the
Planning Director and his staff, the Planning Board, the Directors of Contributing (County)
Departments and their staff who participate in the process, the Element Lead Advisory
Boards, other County advisory boards and commissions that might or should participate in
the process, the Advisory Board Liaisons, the county's municipalities, neighboring counties,
major institutions located within Orange County (e.g., UNC), civic associations and private
sector interests that might or should participate in the process, and the public at large from
within Orange County.
The Project Management Team appears to be the primary steward of the process. It has
ultimate responsibility for ensuring that the key events within the Comprehensive Plan
update process will be well planned and well managed. DSC proposes to begin its process
consultation with the Project Management Team because the Team is accountable for the big
picture.
Andrew M. Sachs, Coordinator of DSC's Public Disputes Program, will be the lead
consultant and facilitator on this project. A statement of qualifications is appended to this
proposal. Other DSC personnel might be available as needed by the Project Management
Team, depending upon the schedules of the other personnel and resources (see proposed
budget, below).
Sachs will meet with the Project Management Team for as many times as is needed to
accomplish the following:
• To ensure that he and all Team members are well informed and aligned on all important
aspects of the Update Process, including the sequence of events, the timeframe, their own
roles, the roles of others, and the internal process by which the Team itself will operate
50
(set its agenda, stay focused, make decisions, resolve conflict, and link with groups and
individuals outside of the Team),
To consider how well individuals and groups holding leadership roles in the Update
Process other than the members of the Project Management Team (e.g., staff from
County departments other than Planning and Inspections; the Board of County
Commissioners; and advisory boards, members and liaisons) are informed and aligned on
the important aspects of the process, and what interventions if any are needed by the
Team or process consultant to explore or address any problems.
• To consider what if anything will be needed from the municipalities, other jurisdictions in
the region, regional organizations, and the State.
To set goals for a successful Update Process, including consideration of how the process
overall and key events within it (e.g., Joint Advisory Board meetings, Public Hearings,
Outreach efforts, -and substantive reviews by the Planning Board and the Board of County
Commissioners) will be coordinated, planned, managed and facilitated to ensure that they
are:
• Inclusive — Effectively involving the voices of all affected interests.
• Practical - Having a concrete and important purpose.
• Self- organizing - Allowing participants to set their own purposes, objectives,
procedures, tasks, and topics.
• Civil - Supporting discourse in which all participants are respected, listened
to, have equal access to information, and learn about each other's interests.
• Informative - Adapting and incorporating high - quality information.
• Creative - Allowing participants to challenge assumptions.
• Engaging - Keeping participants at the table, interested, and learning.
• Open - Seeking closure only after discussions have fully explored the issues,
interests, and opportunities for resolving differences.
• The point immediately above might include consideration, as Mr. Benedict suggested, of
the development of a "Compact" that communicates the Project Management Team's
values for the Update Process, and invites others (Planning staff, advisory boards, other
Department heads and their staff, the BOCC, the public at large) to "sign onto" working
consistently with those values.
Decisions regarding the Update Process that are made during Sachs's meetings with the
Project Management Team will be documented by Sachs (and reviewed/corrected by the
Team) and used by Sachs in the development of written plans for each event that DSC
facilitates. The record of the Project Management Team might also be used by the Team
itself or others to plan events that DSC does not facilitate (e.g., Planning Board meetings,
Board of County Commissioner meetings).
I
Costs and Contracting
1. The timeframe for the services described herein will extend from the date of contract approval
through May 31, 2008. The contract may be extended upon written consent of both parties.
2. In consideration for DSC's services described herein, the County will pay DSC as follows:
(i) Through June 2007: (a) $85.00 per hour for all necessary time provided to this project by
Program Coordinator Andrew M. Sachs; (b) $40.00 per hour for all necessary time provided to
this project by each DSC facilitator other than Mr. Sachs (e.g., small group facilitators, co-
facilitator, temporary substitution for Sachs where that is necessary).
(ii) July 2007 through May 2008: (a) $90.00 per hour for all necessary time provided to this
project by Program Coordinator Andrew M. Sachs; (b) $45.00 per hour for all necessary time
provided to this project by each DSC facilitator other than Mr. Sachs (e.g., small group
facilitators, co- facilitator, temporary substitution for Sachs where that is necessary).
3. The County will provide for all project logistics and materials, including adequate meeting
facilities, audio - visual equipment, advance and follow -up communications with meeting invitees
or attendees, handouts, flip chart paper, masking tape, magic markers, maps and renderings,
sticky dots, refreshments, nametags, and photocopying.
4. The County will reimburse DSC for all necessary automobile travel incurred to conduct the tasks
specified herein at the IRS rate in effect at the time of travel, which is currently $ 0.405 /mile.
Reasonable and necessary out of pocket expenses will be reimbursed to DSC by the County
following the submission of valid receipts for those expenses.
5. DSC will invoice the County no more frequently than once per month. Each invoice will include
a summary of the tasks /meetings /deliverables completed during the time period covered by the
invoice.
6. The County will pay DSC's invoices within 10 days of receipt. Checks will be made payable to
the order of the Dispute Settlement Center, and mailed or delivered to DSC, 302 Weaver Street,
Carrboro, NC 27510. DSC federal tax identification number is F56-1216584
7. DSC agrees to designate Public Disputes Program Coordinator Andrew M. Sachs as the lead
contact for this project. Planning and Inspections Department Director Craig Benedict will serve
as the County's project liaison with DSC upon signing of this agreement.
8. Both DSC and the County agree that if disputes related to this contract emerge between them
during or after the period of this agreement, each will first seek resolution by face -to -face
problem- solving, facilitated by a mutually agreeable third party if necessary, before taking the
grievance for resolution to any outside authority.
9. Any modification to this agreement must be written and signed by both parties.
I
PUBLIC DISPUTES PROGRAM
Dispute Settlement Center of Orange County
Since 1987, the Public Disputes Program has been helping communities,
jurisdictions and organizations discuss difficult topics, resolve multi -parry conflict,
and develop consensus - building skills by designing collaborative processes,
providing mediation and facilitation, and conducting training and education
programs. For more information, contact Andrew M. Sachs, Program Coordinator,
302 Weaver Street, Carrboro, NC 27510, (919) 929-8800, ext. 23,
asaschs(@disputesettlement.org.
Representative Project Experience
Design and facilitation of a year long community consensus building process on the
Town of Carrboro's Northern Transition Area Small Area Plan. The result of
this intervention, the "Facilitated Small Area Plan for Carrboro's Northern Study Area"
was selected in 200o by the NC Carolina Chapter of the American Planning Association
as the recipient of the Brian Benson Award for Small Community Comprehensive
Planning.
• Facilitation of public forum through which parks and recreation advocates,
environmental advocates, affordable housing advocates, neighbors of the
"Greene tract," and officials from Chapel Hill, Carrboro and Orange County met to clarify
options for future uses of a log acre parcel jointly owned by the three local
governments.
• Mediation for residents living near the Orange County regional landfill and
representatives of three local governments. The parties negotiated an agreement
through which the governments would acquire soil from adjoining tracts for use in
landfill operations while minimizing adverse impacts on residents and the
environment.
Facilitation of a work group composed of people from neighborhoods near the
University of North Carolina at Chapel Hill (UNC) power plant and UNC administrators.
The group evaluated UNC's plans for demolishing and reconstructing the power
plant's coal silos. After a seven -month process, work group members signed an
"outcome document" that recorded areas of understanding and agreement, clarified
issues that were not yet resolved, and set forth methods for future consultations between
UNC and the neighbors.
• Design and facilitation of process through which twenty seven residents of Chapel Hill,
Carrboro, Hillsborough and the unincorporated areas of Orange County appointed by
their respective jurisdictions to the Shaping Orange County's Future Task Force reached
consensus on a set of values and goals for guiding the community's future and on a
draft set of recommendations for achieving those ideals.
• Facilitation for 60 local elected officials, non -profit housing development and
advocacy organizations, government staff, and advisory board members convened
by a local Department of Housing and Community Development for a three -hour
"strategic housing session." Participants learned about different types of public funding
V
available for affordable housing and generated ideas for improving how those funds
are allocated and used. A task force was then formed to continue the collaboration and
develop ideas further.
• Facilitation of five community dialogue sessions on racism, poverty and inequality
in partnership with the University of North Carolina at Chapel Hill (UNC) Center for the
Study of the American South, the UNC Sonja Haynes Stone Black Cultural Center, and
the Orange County Human Rights and Relations Commission.
Co- facilitator with George Mason University's Conflict Clinic and the Winston -
Salem /Forsyth County Neighborhood Justice Center for an innovative year -long
community problem solving process convened by the Winston -Salem /Forsyth County
Coalition on Drug and Alcohol Problems. Over 60 organizations in the public, private
and civic sectors reached consensus on improvements to local substance abuse
treatment services.
Mediated among sponsors of a proposed group home for people living with AIDS and
residents of four surrounding neighborhoods in opposition to the proposal. The
parties jointly organized a public forum at which the proposal and neighborhood
concerns were discussed. Opposition to the group home dissipated after information
was shared, relationships were established, and lines of communication opened across
the groups.
• Co- Mediator (with Dr. David Godschalk) for multiple parties (Neighborhood Coalition
for Responsible Development in Raleigh, the Oberlin Village community, First Colony
Property Company, City of Raleigh) in conflict over First Colony Properties' proposal to
develop 15 acres as mixed -use infill at Wade Avenue and Oberlin Roads in Raleigh,
NC.
Facilitation of the County /Schools "Collaboration Work Group," composed of the Chairs,
Vice Chairs, and Executive staff persons from the Orange County Board of
Commissioners and the Boards of Education for Orange County and Chapel
Hill /Carrboro. Since January 2004, the Work Group has identified, clarified, planned,
and /or evaluated cross jurisdiction issues such as revisions to local school
construction standards, community use of school recreation facilities, and "new
paradigm" funding for school -based human services.
Consultation to Dr. David Salvesen, Director, UNC -CH Program on Smart Growth and
the New Economy, Center for Urban and Regional Studies, for projects in North Carolina
and in the Atlanta metropolitan region relating to collaborative planning across
school districts and county and municipal governments in public school siting
processes, including design and facilitation of the May 2006 Summit on School Facility
Siting convened by CURS for over 30 municipal, county, and schools officials from
Cabarrus, Guilford, Johnston and Union counties.
I
Andrew M. Sachs
Sachs initiated the Public Disputes Program at DSC in 1987 with a grant from the
Mary Reynolds Babcock Foundation. He has served as a mediator, group facilitator,
and conflict resolution trainer since 1980.
He earned a Masters in City Planning from the M.I.T. (1986) and a B.A. in
Environmental Studies from the State University of New York at Binghamton (1979)
He is a member of the National Association for Community Mediation (since 1994),
the Society of Professionals in Dispute Resolution /Association for Conflict
Resolution (since 1993), and the National Roster of Environmental Dispute
Resolution and Consensus Building Professionals (since 2000).
He was a Lecturer in the Department of Psychology, University of North Carolina at
Chapel Hill from 1994 — 2oo1, a position through which he co- developed and co-
taught an upper -level undergraduate course, "Non- Violent Conflict Resolution" with
Professor John H. Schopler.
His publications in the field include:
Contributions to the chapters on History and on Procedure in Alternative
Dispute Resolution in North Carolina: A New Civil Procedure, Jacqueline R.
Clare, editor. Raleigh, NC: North Carolina Bar Foundation and the North
Carolina Dispute Resolution Commission (2003)
"Understanding Public Disputes Resolution in Community Mediation,"
Mediation Quarterly, v.17, no. 4, Summer 2000.
"Resolving Disputes the Kinder, Gentler Way: The North Carolina Way."
Planning, American Planning Association (Chicago, IL), Volume 61, Number
5, May 1995•
"Local Dispute Settlement Centers: Helping Planners to Build Consensus."
Carolina Planning, University of North Carolina at Chapel Hill, Volume 16,
Number 1. Spring 199o.
"The Patuxent River Clean -up Agreement" with Peter Schneider. The
Environmental Forum, 2:1, May 1983•
"Policy Dialogue for Environmental Dispute Resolution" with Sam Gusman.
Program on Negotiation Working Paper Series, 87 -1. Cambridge,
Massachusetts: Harvard Law School (1987).