ACTION AGENDA ITEM ABSTRACT
Meeting Date: March 11, 1998
Action Agenda
Item No.
SUBJECT: High School Construction Standards Task Force Update
DEPARTMENT: County Manager PUBLIC HEARING: (Y/N) Ne
BUDGET AMENDMENT: (Y/N)
ATTACHMENT(S):
Resolution INFORMATION CONTACT:
Unitary Systems Approach (USA) Summary Rod Visser, ext 2300
TELEPHONE NUMBERS:
Hillsborough 732 -8181
Chapel Hill 968 -4501
Durham 688 -7331
Mebane 227 -2031
PURPOSE: To receive a report on discussions by the High School Construction Standards Task
Force.
BACKGROUND: The High School Construction Standards Task Force has met monthly since
mid - December. Major topics of discussion and activities to date include: review and comparison of
theoretical high school space profiles developed by the State Department of Public Instruction with
the space profiles of the existing high schools in Orange County; a tour of East Chapel Hill High
School; energy efficiency considerations; and construction management considerations, including
review of the Unitary Systems Approach (USA) used for the construction of several schools in
Johnston County. The task force also adopted the attached resolution encouraging pursuit of local
legislation that would allow Orange County to employ the Unitary Systems Approach to school
construction, or some similar process. That approach was approved, on a limited, trial basis in 1997
local legislation for Johnston County.
Staff and task force members will provide a brief report on discussions to date, and respond to
questions the Boards may have.
RECOMMENDATION(S): The Manager recommends that the Boards receive the report as
information.
RESOLUTION
ORANGE COUNTY HIGH SCHOOL CONSTRUCTION STANDARDS
TASK FORCE
WHEREAS, during its 1997 Session, the North Carolina General Assembly
ratified House Bill 740 entitled "AN ACT TO ASSIST THE JOHNSTON
COUNTY BOARD OF EDUCATION WITH THE EXPEDITING OF PUBLIC
SCHOOL FACILITIES ", and
WHEREAS, that legislation authorized Johnston County to enter into direct
negotiations with separate prime contractors for the construction of new school
facilities under the Unitary Systems Approach (USA) model school plan, and
WHEREAS, that legislation was intended to allow Johnston County to provide for
timely and cost - effective construction of necessary new school facilities, and
WHEREAS, reports and site visits indicate that there are potential benefits to this
approach that could be realized in Orange County and its two school systems if
authorization to use this approach, or another appropriate model, were enacted in
similar legislation applicable to Orange County,
NOW, THEREFORE, BE IT RESOLVED, BY THE ORANGE COUNTY HIGH
SCHOOL CONSTRUCTION STANDARDS TASK FORCE that it does
recommend that the Orange County Board of Commissioners contact the members
of the Orange County legislative delegation to request that they introduce and
support legislation during the 1998 Session of the General Assembly that would
permit, but not require, Orange County and its two school systems to pursue the
approach to school construction contemplated in House Bill 740.
This, the 26th day of January, 1998.
The Public Facilities Group
fAmW:e.:� !- ..., -.. ; •:.ran: n.
Ally F. D" F. E. hunt
F. 0.1w 3123
Cn Nut Udu 27519 d ( 11 934 -flit
FrAmbd jtdy I. IM The FAk Fatio1 Gnsp k a
facam m igi ft detelopmest ad mmqtmw first d iww
adaWy to w * wd phis Mies a fed andre mb dw
a da "my of pubic ham WA Ow buffing seeds,
shri kol furadd rims ad :Moog bdget F^wwK FmW
Mdrts mu fid mm dfeom ad efidw ap adws a the
dt* , - , iota isu* ad niampmest of pAk fa&iu-
14 Ddrsm hat fuq yarn experinoe is the owned"
is m7 wid IS ym kmW a pubic s "cL kq% badVmstd
isd mk wades mttattucrte. at N. C State vmireaitl►.:erne as
Sane Caaarwios Offer for Nerth Cud= ad as a member d
dw idisi towel SeW of the Natied Amwdl Cm&
irs profmioaf matsiemest and pa d immest a dw pubic
semen a what prestp W his a ants die Fubic FmfWu Greop.
ieasoe of bit broad Mot Wp of aensdecsies amd pdk- service
badromet he 's monody dW qu a assist wish spedaf
a+ mnaocdoo suites.
HrTE/MSM, P.c.
)=a G. Ifiee. Nfk htddat
IS30 Em Fwreeesth Sweet
61 etarie, NC 21353 W (111757-0333
We /MK ILL 's a d sane ud hecmm ariiseai
ad phasing fns sped"K in d dash: d idmoenal ad
pubic wbw bail u BqA is I by pmts rL Hitt.AIA. Hitt
INSM has mmesd* mrnpleted dams d pubiic sdad projects
a serval Nora Cuoiaa mumm . Wide aver vaq yarn of
OK $600 kCrq desrgtt atperince. pmts fits has aaiMW
the fun's foam on mot decd" ad bw maintenance wwmg
The Usury Syn ms Appradt mmept to sdrod bwiiags
amrperates many of dw design pradpits fGoelTfSM has rated a
put p*m but iroegnaed i m a mmprehen k :drool prototype
desrgs sys= USA is I duets regm to Hite /?Ws *Cmmiom>emt
ro Ckots" philosophy; to provide the maximum building raiue
per dater sperm
U A�-
UgCARYSYS[MAMOAGi
ftU ing Sehwh the USA way
developed �
The Public Facilities Grout
F=Wa t)se&Fmg nt
and
Hn7E/MSM, P.C.
AKMITECTURE
ENGINEERING
PLANNING
I
IITARY SYSTEMS APPROACH
HOOL DESIGNS
boil haTitia r-pie a w the no riSh A apt@&= of
woes► ad do pAk has bemwe mere red above
design. buid ad mr p them ladb s. Seen the
xd for sdhod fadik in bas ,serer been a were
s tin for efecW Ad* a eow alrhma 1 approaches
imy of sdmd fadli w The go" Sysws Approach
a alteramre se odd a deicer sdml fames that an
hafly dtd" and oaeewialy eid"L
tit Witacy Sysow App uch it bated M a simple
..a ahnpreerad q%ow Wnradoe of staadard bump
e a weds sdnol pear. The key dowent it this appradh
krdepmeit of standard Waft ink that inmrpasa
l lthhun ntatherds and wetheds, e:inO snte d the act
ir ac�.afoo. these ewe =.easi nteddid for difrM
Efar :sheer desip mist be w hire, sit eefr to
Mal prepm oeds, bolt afw a the met of opendens ad
hang Sinn so to 90% of the ace is tatepayess ova the
it lk of a sdml omQ after R is ceraarhme' The USA
;ewV dkm6W ad cadmical rpm
tea* maiiaine I
EM FEATURES
ws eadh Sdmi Sysaw a devdep their on p""
h, based on their evade needs.
#ts to Now sites withoet cosily ad him maowiq w
wades a spa approach ad edy a desip but also
atSnctioa
eshead mom phdun slew amoea aces: a meclmial,
staid, aid tadoft egeiphreit with a dpi um of iabtai0i
wa. W=ce std"
oxides safe nbge to sadenes ad staff 6* severe storm
ididaa.
utary aompooeits, as seN moained Wdia an be isolated
r use after bars, aid do cot n* apensire law boor
walls and dons.
vWes a simple, pitched roof " that will last the We d
it bt Mog.
siple desip is cost e&c&t with No sacda in polity of
tateriaii. Designs are attru " to bidders. ad bid results
n mac prtdimWe.
The Unary System Approach is mrrently beiig used and
,ned for use in Greene. Johnston, Jones. Pulko and Pitt
CASE HISTORY:
JOHNSTON COUNTY'S MODEL
K -S ELEMENTARY SCHOOL
The Ilodd IFS Elam oaq School in *M coeegr,
wing the UvitarP Sysuas App tech. vas bid in qving 1996 ad
is mtteWy hw er mamctisL Desigod for 7SO smdues ad
14959 squate feet; this sdml irides a saa of the
art te&ft sysant, a my watewenc awd symo and
a feu pipe medhari A :Phew wig castaoonhs separudy beued
ad coded.
BID SUMMARY
SITE UMPIM costs
and
.wr ko a $326.5 s414nf
u -sac onomw Co. Wba nwa
WWNG CONSiSUCTION COSTS
Genaal Cossowion $ 1,713,100 S4UYsf
hnidta low deco Cansaamiu► Co.
Medhaniad Councion
WAC Spann $ 747.700 S9,T2/Sf
Eftfu Man went System $ f IS,27S 51.50 /sf
Ctw2l Haag E Air CeneEOimg Gesorr
sKtdd Coaartct6o
lath ask lee. Greets* $ 541,100 $729/d
PTabiog Counction
9rarmo odc fftrnhing Co. Wren $ 234,000 53.04 /sf
MUL SUADING COSTS $ 5,311,115 S69.30ld
MMEN EQUIPMENT COSTS
litehen Equi vent aid Instdation $ 177,695 jZ31 /st
Noigameq Gnea / Edhrard Dos Ra/ergd
GENERAL ASSEMBLY OF NORTH CAROLINA
1997 SESSION
S.L. 1997 -37
HOUSE BILL 740
AN ACT TO 'ASSIST THE JOHNSTON COL:\.7Y BOARD OF EDUCATION
WITH THE EXPEDITING OF PUBLIC SCHOOL FACILITIES.
Whereas, Johnston County is faced with the critical need for school
facilities created by an unusual growth in student population: and
Whereas, the Johnston County Boa-z4 of Education and the Johnston
County Board of Commissioners have jointly approved and funded a School
Facilities 2000 building program; and
Whereas, the Johnston County Board of Education, faced with the critical
need for school facilities, has implemented a model facilities plan using the Unitary
System Approach (USA) to design school facilities that are educationally effective
-and economically efficient; and
Whereas, the Johnston County Board of Education has competitively bid
the USA school design under the separate prime bid laws of North Carolina and has
developed certain cost parameters based on this USA concept: and
Whereas, the Johnston Countti• Board of Education desires to explore
alternative approaches to expedite the construction of school facilities that could
assist in meeting the critical need for school facilities; and
Whereas, the General Assembly reaffirms its commitment to enhance
public education and to encourage innovation by public officials in meeting the
critical need for school facilities; Now, therefore,
The General Assembly of North Carolina enacts:
Section 1. Notwithstanding the pro ,.isions of Article 8 of Chapter 143 of
the General Statutes, the Johnston County Board of Education may select and
negotiate with separate prime coat- actors to build the Unitary System Approach
(USA) model school plan if the Johnston County Board of Education determines that
using the selection and negotiations processes instead of competitive bidding will
expedite the project, create an effective construction team, and control costs, quality,
and schedule.
Section 2. This act shall apply to construction of an elementary school at
McGee's Crossroads, an elementary school in Benson, and an elementary /middle
school in West Johnson County. The Johnson County Board of Education shall
report to the General Assembly the net price per square foot for each project at the
completion of each project.
Section 3. This act is effective when it becomes law and expires on June
30, ? CGO.
In the General Assembly read three times and ratified this the 24th day of
April, 1997.
s/ Dennis A. Wicker
President of the Senate
s/ Harold J. Brubaker
Speaker of the House of Representatives
R�6_pml
-The bmithfield Herald-JunOo
"199
Next school to cost just $68 a square -.foot
The board of education had
feared $90 -$100, but negotiated
contracts for a carbon -copy
school kept costs low.
By JENNIFER PENDER
Staff Reporter
Ray DeBruhl. building consultant to John-
ston County schools, made his point Wednes.
d "y.
Carbon -copy c+chouls built under negotiat-
ed contracts are cheaper than schools orcon-
ventional design put out to bidders. Debruhl
said after revealing the cost of a new western
Johnston elementary school.
9f we had competitively bid, we would not
have gotten the same results," DeBruhl told
school buard members, county commissioners
and state leaders.
For the new schi►ol. DeBruhl negotiated
with the contractors building the new Glen -
dale-Kenly Elementary School.
The result- Glendale- Kenly, with 76,959
square feet,- will open in August at a con-
struction cost or $69.80 per square foot. The
western Johnston school, 82,238 square feet
at McGee's Crossroads, will cost $68.37 per
squar* root.
The ogres surprised County Commis-
sioner Eleanor Creech. "You don't see many
things today where the prices actually de-
crease," she said.
Moreover, the school board had expected
the McGee's Crossroads school to cost $90 to
$100 a square root, about average in today's
building market, noted board member Dea-
con Jones.
DeBruhl was the architect or recently
passed legislation allowing Johnston schools
to negotiate building costs with contractors.
He chose the Glendale -Kenly contractors be-
cause they were building Johnston's first tru-
ly prototype school. Using the Unitary Sys-
tem Approach, or USA, they will take the
Glendale -Kenly designs for classroom, cafete-
ria and administrative spaces and arrange
them to suit the McGee's Crossroads site.
Superintendent Jim Causby said the Uni-
tary System Approach and negotiated con-
tracts will get western Johnston an olemen-
tary school sooner than the old approach to
building campuses. `It was an effort to build
more facilities economically and at a more
rapid pace," he said.
Conventional schools tAke 16.18 months to
design and build, Causby noted. The McGees
Crossroads school will open In August 1898,
less than 14 months from now, he said.
Donnie Britt is president of Britt Plumb-
ing Inc., which will install the plumbing at
McGee's Crossroads for $3.19 per square foot.
'As far as price,, they're getting a good price,"
he said.
Then again, DeBruhl and his design team,
including architect Jimmy Hite, know how to
build schools cheaply, Britt said, noting that
he will use plastic pipe instead of cast iron at
McGee's Crossroads.'Me whole organization
is a good crowd for solving problems," he said.
"USA didn't want rrills."
House Majority Leader Leo Daughtry, who
pushed DeBruhl's bill through the legislator,
said USA and negotiated contracts will save
Johnston taxpayers millions. "It was very im-
portant to the county to build schools at a
reasonable price," he snid. "When you spend
public money, you have to be responsible."
For the McGee's Crossroads school, De-
Bruhl estimates the savings at $1.5 million.
The legislation also allows him to negotiate
contracts for an elementary school in Benson
and a middle school at Cleveland.
"Hopefully we can be n model for other
counties throughout the state," said County
Commissioner Cookie Pope.
Britt. whose plumbing company is based
In Wilson, certainly hopes so. "I wish we
could do it here in Wilson County," he said.
"This is really a gem here, and its going to be
a hot item statewide."
'Britt said he hoped DeBruhl and his team
would be successfbl in negotiating contracts
for the Benson and Cleveland schools. If not,
the board of education will have to advertise
for bids,
9'd like to keep the same team," Britt
said. "The more famillar the team, the
smoother the project."
Jo:,*o&*p +ay The Public Facilities Group
and E5k-� P.C.
UNrrARY SYSTMO APPROACH
A&-g dim* The USA Wiwi
THE JOHN5TON COUNTY BOARD OF EDUCATION
KErORT OF NEGOTIATIONS BASED ON 5FECIAL LEGISLATION - F15 740
June 18.1997
• The hiitent of the special legislation was to use the experience of designing and building the
first model school and allow the USA Team to Improve the desigm to evaluate the costs and
to expedite the delvary of the second model school.
• The first USA made( school. Glendale Keny Elementary was compsrIt&* bid Jun* 13,1996 and
consists of 76.959 enclosed 94 ft. with a m mx mum student capacity of 600.
• The second USA model W a larger Amnentary school at McGas Crossroads and conalsts of
82.238 socks" set ft, (sm increase of 5,279"ft.) with a numk Hum student capacity of 913.
GENERALCON5TRUCTION
Da W"v Jaw Seen Cartroc11" Co. Raleig. NC
MECKANICAL CONSTRWTION
• Fos' rrpe HVAC 9"tan
• Ewa Mme Ohmt Conntm System
Central Heatk4 & Air Coeditwwmq. Klwca% NC
ELECTRNCAL CONSTRUCTION
rltt Electric. Ina. cmvw wu Nc
FWN VNG CONSTRUCTI0N
Britt rlwi,iny inc. mism NC
TOTAL WWNG CO5T5
FKST MODEL USA K -5
SECOW MODEL USA K-3
06ndals Keniy
76,959 g4 Ft.
Did Juw 13.1996
McGee's Crossroads
82.236 34 Fl..
Nyotiated June 16. 1997
$3,713.100 W.25/e.f.
$3.980.300 $48.401e1.
$747,700 $9.72/s.f.
$115.275 $t5o /s.f.
$769,770 49.36 /s.f.
$121.270 5147 /s.f.
$561.100 $7.29 /s.f.
$469,100 S&95/e1.
$234,000 $ 3.04/91.
$262.000 $ 3.19 /0.
$8.371.175 ET�.�Or<5.t.
35.622.44000.37%S.T.
KNTCh'EN EMIPMENT & N5TALLATION
$177,695 $ 231 191.
$173.695
Ma"Sta "V Orem / Edward Don. Kale ok NC
• 5itework is not included because the Glendale Kerry site is 25 Acres and the McGee's
Crossroads site is 52 acres and will contain both elementary and middle schools. The McGee's
Crossroads sitework is scheduled to be competitively bid June 30,1997.