A BILL TO BE ENTITLED
AN ACT TO ALLOW THE BOARDS OF EDUCATION
IN THE COUNTIES OF JOHNSTON, ORANGE AND PITT
TO USE ALTERNATIVE DELIVERY SYSTEMS
FOR PUBLIC SCHOOL FACILITIES
WHEREAS, education is the energy that drives economic growth and
development; and
WHEREAS, facilities are an integral part of the educational equation and vital
to the educational learning process; and.
WHEREAS, North Carolina is faced with a crisis in providing adequate public
school facilities, estimated to exceed six billion dollars over five years; and
WHEREAS, local government is faced with serious budget challenges due to
increased demands for public service, shrinking financial resources and shifting
budget priorities; and
WHEREAS, bold and creative leadership is required by public officials to
meet the challenge of "adequate school facilities for every learner in North Carolina";
and
WHEREAS, the counties of Johnston, Orange, and Pitt are committed to
creativity in the development and delivery of public school facilities and believe that
the public investment in capital assets should be properly managed; and
WHEREAS, the Boards of Education in the counties of Johnston, Orange and
Pitt have agreed to join together in a unique creative and collaborative venture of
sharing educational programming and facilities technology to their mutual benefit;
and
`WHEREAS, the Board of Education and County Commissioners in each
county have joined together in a cooperative effort to deliver schools that are
educationally effective and economically efficient.
WHEREAS, the General Assembly reaffirms its commitment to enhance
public education, to encourage innovative development of school facilities and
explore alternative delivery systems.
NOW THEREFORE, the General Assembly of North Carolina enacts:
Section 1. Notwithstanding the provisions of any general statute or
administrative rule to the contrary, the Boards of Education in the counties of
Johnston, Orange and Pitt are authorized to jointly develop and implement afive-
year pilot program for the delivery of public school facilities that includes:
(a) Qualifications Based Contractor Selection Process: The contractor
selection criteria may be based on: organizational information; financial status and
bonding capacity; experience of office and field personnel; experience on school
projects; experience with the separate prime contract delivery system; cooperation
and coordination with other contractors; quality, cost and timely performance on
completed school projects; references of public owners and other factors deemed
appropriate. Based upon the qualifications criteria, each Board of Education may
select, in their sole discretion and determination, a minimum of three of the best-
qualified contractors in each of the categories of work to be bid.
(b) Separate-Prime Contract Delivery System: Based on the public
bidding of the specified work by the selected contractors, as provided in Section 1(a)
above, each Board of Education may choose to award contracts based on the
separate-prime contract delivery system. If the Board chooses to use the separate-
prime contract delivery system, the provisions of G.S.143-128(a) and 143-129 shall
apply.
(c) Single-Prime Contract Delivery System: Based on the public bidding of
the specified work by the selected contractors, as provided in Section 1(a) above,
each Board of Education may choose to award contracts based on the single-prime
contract delivery system. If the Board chooses to use the single-prime contract
delivery system, the provisions of G.S. 143-129 shall apply. However, the
mechanical, electrical and plumbing construction, as specified, must be publicly bid
at least one day prior to the general construction and each single-prime bidder must
incorporate the bids and contract with the successful mechanical, electrical and
plumbing. contractor.
(d) Professional Construction Management Delivery System: Based upon
the provisions of G.S.143-64.31 each Board of Education shall select the best
qualified designer, who for a negotiated fee based on scope of work, will be Liable
and responsible to the Board for the delivery and management of all project design
services; and based upon the provisions of Section 1(a) above, each Board of
Education shall select the best qualified contractor (hereafter called construction
manager), who for a negotiated fee based on scope of work, will be liable and
responsible to the Board for the delivery and management of all project construction
services. Working together as a professional team, the designer and the construction
manager will use their unique skills and experiences to design, publicly bid and
deliver a school facility that serves the best interest of the Board and the public.
Based on Section 1(a) above the designer and contractor will jointly select a
minimum of three mechanical, electrical, plumbing, general or other specialty
contractors and publicly bid the specified work packages consistent with the
provisions of G.S. 143-129. The lowest bids of the successful subcontractors will be
combined into alump-sum single contract with the selected construction manager
who will deliver and manage all construction services for the negotiated fee.
(e) Design-Build Delivery System: Each Board of Education may accept
proposals and award a contract to deliver school facilities based on single liability for
the design and construction services for a guaranteed maximum price. If the Board
chooses the design-build delivery system, the design-build teams, selected to submit
proposals, must be selected based on criteria similar and consistent with the intent of
G.S. 143.64.31 and Section 1(a) above.
(f) Design/Buiid/Finance Delivery System: The Boards of County
Commissioners in the counties of Johnston, Orange and Pitt, in agreement with each
Board of Education, may accept proposals and award a contract to deliver school
facilities on a design/buildlfinance basis; provided however, that the proposed facility
meets the educational program needs and is approved by the respective Board of
Education; and further provided that the financing of the school project is approved
by the North Carolina Local Government Commission.
If the County Commissioners, in agreement with the Board of Education,
choose the design/buildlfinance delivery system, the design-build teams selected to
submit proposals must be selected based on criteria similar and consistent with the
intent of G.S.143.64.31 and Section 1(a) above.
Section 2. Consistent with the authority to develop and implement afive-year
pilot program for the delivery of public school facilities, the Boards of Education in
Johnston, Orange and Pitt will jointly develop a common set of guidelines and
procedures to administer and evaluate the program. During the development and
implementation of this program, the Boards of Education will seek input from and
share information with appropriate education, industry and government groups.
Section 3. The Boards of Education in the counties of Johnston, Orange and
Pitt shall present a joint report annually to the Joint Legislative Committee on
Governmental Operations.