HomeMy WebLinkAboutAgenda - 10-06-1998 - 10a1
ORANGE COUNTY
BOARD OF COMMISSIONERS
AGENDA ITEM ABSTRACT
Meeting Date: October 6,1998
Action Agenda
Item # ~ D~Q
SUBJECT: REPORT -ENVIRONMENT AND RESOURCE CONSERVATION DEPARTMENT
DEPARTMENT: ` MANAGER: BUDGET AMENDMENT REQUIRED: Yes X No
ATTACHMENT(S):=_ INFORMATION CONTACT:
John Link, Extension 2300
• Report -Recommendations for En~iranment
and Resource Conservation. Department
• Draft June 22 Board minutes TELEPHONE NUMBERS:
Hillsborough -.732-8181
Durham - 6%8=7331
Mebane = 227-2031
Chapel Hill - 967-9251
PURPOSE: To receive a report on formation of the new Environment and Resource
Conservation Department.
BACKGROUND: On June 22, the Board approved the creation of a new Environment and Resource
Conservation Department (ERCD), and asked the Manager to respond back with
specific recommendations on formation of the new department.
Please find attached my recommendations for the new department. These
recommendations are the result of a staff work group convened to develop a plan
for implementing the new ERCD.
In developing this report, the work group used Dr. Gordon's May 26 memoranda
as a basis for defining a mission and charge for the department. Using this mission
statement and the adopted Commissioners' goals, proposals for departmental
tasks and responsibilities, work plans, personnel and equipment needs have been
generated -based on our understanding to date. As such, we recognize that all
points of emphasis may not yet be addressed.
The report recommends that the new department use a mixture of existing and
new resources to accomplish its tasks. Two permanent, full-time positions in the
Planning Department would be re-assigned to the new department, and a third
position would be split between Planning and the ERCD. Two time-limited
positions (scheduled to end June 30, 1998) would also be transferred to the
ERCD. Two new positions would be added, an Administrative Assistant and a
Natural Resource Conservation Manager. Start-up costs for the new department
are anticipated to be $52,000, and are recommended to be covered from the Board
contingency.
Comments have been received from the Orange Soil and Water District
(previously distributed under separate cover, along with new material attached as
Appendix D to the report). In addition, comments from the Orange County Board
of Health were received on Thursday, October 1. Staff has not had an opportunity
to review the Board of Health comments, but has enclosed them as Appendix F to
the report.
RECOMMENDATION: Receive as information. The Administration will use feedback from the Board to
refine the report, and bring the report back as a recommended decision item on
October 20. There has been discussion with regard to establishing a Public
Hearing for citizen comment on the new department. The Board may wish to
consider the regular meeting of November 4th as the date for the Public Hearing.
The recommended effective date for the new department would be November 23,
1998.
3
Memorandum
To: Board of Commissioners
From: John Link, County Manager
Date: October 6, 1998
Re: Environment and Resource Conservation Department (ERCD)
On June 22, the Board approved the creation of a new Environment and
Resource Conservation Department (abbreviated herein as ERCD). Please find
attached the results of a staff work group which has worked over the past two
months to develop a plan for implementing the new department. The attached
report summarizes my recommendations for the new department. I am
recommending that the Board consider this proposal on October 6, with an
action item for October 20, 1998. The effective date for the new department
would be November 23, 1998.
In developing this report, the staff work group has used Dr. Cordon's May 25
memoranda as a basis for defining a mission and charge for the department.
Using this mission statement and the adopted Commissioners' goals, proposals
for departmental tasks and responsibilities, work plans, personnel and equipment
needs have been generated -based on our understanding to date. As such, we
recognize that all points of emphasis may not yet be addressed.
To summarize, after evaluating the mission, tasks and needs of the new
department, I am recommending that it include four permanent positions, one
shared position with the Planning Department, plus one and one-half time-limited
positions (scheduled to end 6/30/99) currently filled for specific projects. Existing
staff will be utilized to fill these positions, with the exception of a new Natural
Resources Conservation Manager and Administrative Assistant to be hired
(please see Attachment B). Short-term space arrangements are proposed that
will not require any current additional funding, but long-term needs may require
alterations to the Planning and Agricultural Center beyond FY 2000.
The estimated expenses for start-up of the department are approximately
$52,000 for the current fiscal year (including half-year salaries and benefits for
the Natural Resource Conservation Manager and Administrative Assistant). I am
recommending that funding for these current year needs be taken from the
$250,000 contingency set aside when the FY 99 budget ordinance was adopted.
4
RECOMMENDATIONS FOR ESTABLISHMENT OF AN
ENVIRONMENT AND RESOURCE CONSERVATION
DEPARTMENT
1. Mission of the Environment and Resource Conservation
Department (ERCD)
The May 25 memoranda from Dr. Gordon lay out a number of concepts that
would easily translate into a mission for the new department. Based on the staff
work group's reading, this mission statement would include:
A. Overseeing, implementing, and coordinating County goals for
environmental protection and resource conservation.
An important key for the County's future quality of fife is 'staying green
while we grow'. The concept of "green infrastructure" has become popular
in other counties and regions as a means of providing reasonable access
to nature and establishing a Countywide system of natural areas, parks
and trails to support wildlife populations. The preservation of our skeletal
framework of natural areas and important resources has been identified
as a crucial component of how livable Orange County will be in the future.
A number of the existing Commissioners goals are directly related to this
concept, and the creation of this department. While future goals may be
added to address new initiatives that the Board wishes to address, the
following goals represent examples of ways that the County is already
working to build and maintain "green infrastructure." The following goals
appear to be a good fit with the new department, and responsibility for
them should be transferred to the Environment and Resource
Conservation Department:
1. Natural Resource Preservation
2. Water Resources (ground water)
3. Historic Preservation
4. Farmland Preservation
5. Watershed Protection
6. Shaping Orange County's Future
7. Sustainability
This department will have primary responsibility for these areas (e.g.,
natural resources). In addition, it will coordinate the acquisition programs
and the records for other areas, as outlined below.
B. Developing a plan and program for the acquisition of land for
resource conservation, and implementing that program.
One of the new department's most significant tasks will be to elevate
planning for resource protection to a new level through the voluntary
acquisition of the County's most critical land resources. While some
planning and prioritization of important resource lands has occurred to
date, a comprehensive program to evaluate the County's most important
resources will need to be developed so that the County can begin
systematic acquisition of land through conservation easements, fee
simple ownership, or other agreements. This department will take the lead
in identifying and recommending natural and other resources to be
protected and conserved, as outlined in Section A above, and will also
coordinate the conservation of resources recommended by other
departments, such as Recreation and Parks. This program will be of a
voluntary nature and will be subject to review and approval by the
Board of Commissioners, before the County can begin acquiring lands
through conservation easements, fee simple ownership, or other
agreements.
It should be noted that development of this area of emphasis will be a
stepwise process involving check-in points with the Board of
Commissioners at every step. The major elements of a land acquisition
program might include:
1.Organizational Structure. The County may wish to consider a
process for establishing a land trust, or developing a partnership with
an existing land trust, such as the Triangle Land Conservancy.
2. Land Conservation Criteria. Deciding what resources to protect
and acquire is fundamental. The County has the following plans and
programs in place for ranking priority resources:
Inventory of Natural Areas and ~Idlife Habitats. Orange County's
most significant natural areas and wildlife habitat were described in
the Inventory of the Natural Areas and Wildlife Habitats completed
in 1988 by the Triangle Land Conservancy. In the next few months,
the TLC is scheduled to complete a Wildlife Habitat Study ranking
prime wildlife habitat areas.
Comprehensive Resources Map. Developed as part of the Rural
Character Study and Flexible Development process, this map is
incorporated into the Comprehensive Plan and identifies important
natural resources in the County identified to date.
2
6
Farmland. For farmland resources, the Agricultural Districts
Advisory Board has developed a program to use the Land
Evaluation and Site Assessment (LESA) system for ranking prime
farmland.
Parkland and Recreation Lands. The County is currently pursuing
an update to the Master Parks and Recreation Plan, through the
Master Parks and Recreation Committee. This effort to identify
current and future resources is being held in conjunction with the
Towns of Chapel Hill, Carrboro and Hillsborough (who have their
own parks and greenways programs).
Historic Sites and Landscapes. The Historic Preservation Element
of the Comprehensive Plan describes an evaluation and ranking
system for historic resources.
3. Land Resources Database. A GIS database of prioritized land
resources will be created for use in evaluating acquisition options. This
database will include data previously generated by the County and the
Triangle Land Conservancy, along with new research. Upon
completion of the Comprehensive Resource Acquisition Program, the
ERCD will coordinate the compilation of a records and mapping
database that contains prioritized areas that will be maintained and
augmented over time.
4. Land Acquisition Mechanism. The County will have the
mechanism and expertise to acquire desired land or sites, and to
manage those sites as appropriate. Implementation of the
Comprehensive Resource Acquisition Program will be instituted using
the current and new personnel resources, as well as seed or matching
money from the County, augmented with grant funding from a variety
of possible sources, such as the Natural Heritage and Clean Water
Trust Funds.
While the development of a comprehensive acquisition program will be
ongoing, there will be options on an interim basis to enable the County to
work with voluntary conservation easements and donations, or to develop
school/park sites. There may also be opportunities to purchase desirable
properties before the comprehensive program is completely developed
(e.g., the recent purchase of property at the Northern Human Services
Center). These options are shown in Attachment A.
3
7
C. Integrating current and future data into a comprehensive resource
database.
In order to accomplish the above initiative, department staff must
coordinate previous work with new inventories of natural, cultural and
recreational resources to develop a Comprehensive Resource Database.
This will involve amulti-level coordinated Geographic Information System
database that encompasses all of the County's land preservation
activities, with records and mapping capabilities of all activities. This
database will be used not only by ERCD staff, but will also help many
County departments that are also involved in resource conservation -
such as Recreation and Parks, the Soil and Water District office, and the
Use Value program under the direction of the Tax Assessor's office.
D. Providing staff support to boards and commissions.
There are a number of standing and ad hoc commissions or boards that
are working on active Commissioners goals listed in Section I.A. Based on
the May 25 memo and the expected work duties, ERCD staff members
will provide support to the following boards:
Board or Commission Status
Commission for the Standing commission
Environment
Historic Preservation Standing commission
Commission
Agricultural Districts Standing board
Advisory Board
Water Resources Committee Ad Hoc committee, scheduled to
merge efforts into Commission for the
Environment in 2000
Shaping Orange County's Joint ad hoc task force with County as
Future Task Force lead entity, scheduled to conclude
6/1999
Master Parks and Recreation Joint ad hoc task force with County as
Work Group lead entity, with recommendations
and priorities to be developed by 1/99
E. Working with other departments/agencies.
With the nature of its duties, the ERCD will be a department with strong
linkages to several other departments. Due to shared data and other
considerations, astrong relationship will be required with the Planning
Department. Developing this level of coordination will be enhanced by the
4
8
fact that some members of the recommended ERCD staff have been in
the Planning Department for years, and currently have a strong
relationship with staff in Planning. Additionally, one position is proposed to
be shared between Planning and the ERCD (please see page 11 and
Appendix B). There may also be shared duties with Planning in
developing implementing ordinances, due to the fact that the
implementing ordinances for Flexible Development/open space/rural
character are in the Subdivision Regulations and to a lesser degree the
Zoning Ordinance. Responsibility for the Environmental Impact Ordinance
must also be defined. As such, these two departments should meet in the
near future to work out details of ordinances and plans with overlapping
issues and plans for coordination.
The Soil and Water District is another department with which the ERCD
will need to coordinate closely, especially in terms of possible roles for
farmland conservation easements. Other departments that will require
coordination might include Environmental Health, the County Engineer,
Cooperative Extension, Recreation and Parks, Tax Assessor's office, and
Economic Development.
Planning Flexible Development and. open space
issues, Environmental Impact Ordinance,
protection of watersheds and natural
resource sites through ordinances; GIS
data sharing; other operational
coordination
Soil and Water / NRCS Possible acquisition of farmland
conservation easements/land resources,
farmland preservation, surface water
resource protection (for agricultural
operations), other conservation programs
Environmental Health Water Resources (ground water)
programs, watershed protection
County Engineer Water Resources (ground water)
programs, watershed protection
Cooperative Extension Service Farmland preservation
Recreation and Parks Coordination on parkland acquisition,
passive recreation (open space) lands
Economic Development Sustainability
5
Tax Assessor _ Coordination of Use Value program with
other conservation initiatives, such as
farmland preservation and property
appraisals necessary for buying
conservation easements
The department may also coordinate its work with other groups such as the
Schools and Land Use Councils and the Master Recreation and Parks Work
Group.
I1. Tasks for the ERCD
To a degree, the tasks and workplan for the department will evolve along with
the goals and changes to the mission statement over time. There appear to be
eight areas of tasks and duties for the ERCD staff, based on the mission and
the May 25 memos.
A. Water Resources (ground water) Project. The Water Resources project
involves a 10-person Committee, a public education campaign and a
significant Ground Water Resource Investigation in conjunction with
USGS. The USGS resource investigation is entering the second of three
years and will wrap up in June, 2000. After final recommendations in year
2000, the work of this Committee is planned to merge into the
Commission for the Environment, and that group would begin to develop
implementation programs for ground water, and synthesize surface water
and ground water protection into an integrated program. This is the final
step of the Water Resources goal, and all of this would become the Water
Resources Element of the Comprehensive Plan.
B. Land acquisition plan/program for resource conservation and
parkland ("Comprehensive Resource Acquisition Program"). The
Comprehensive Resource Acquisition Program is outlined in some detail
by Dr. Gordon in her second memo, and includes an assessment of the
loss of resources that has occurred to date, an inventory of resources at
present, and development of a program of easements and purchase for
the future that involve a number of approaches. Fortunately, some of the
preliminary GIS work in this area has been accomplished -but additional
efforts will be needed to complete the task, including the collation of data
from inventories previously compiled. This program will coordinate the
acquisition of land for historic sites, natural resources, parks and
recreation, and farmland -using matching funds and seed money from
the County. Initiatives already underway include the Schools/Land Use
Councils' efforts and the Master Recreation and Parks Plan.
C. Initiatives from the Commission for the Environment. As a new group,
the Commission has yet to identify many of its programs or plans, but
6
10
clearly the efforts in water (linked with the Water Resources project), air
quality, biological and other natural resources, environmental indicators
and sustainability would fall into this realm and be coordinated with the
other tasks outlined here.
D. Development of Comprehensive Resource Inventory/Database. As
part of the Comprehensive Resource program, we will need to develop a
process for maintaining records and a database of natural, cultural, and
recreational resources. Much of this would be GIS-based and related to
the above.
E. Staff Boards/Commissions. As previously mentioned, staff members in
this department will be responsible for staffing the Commission for the
Environment, Agricultural Districts Advisory Board, and Historic
Preservation Commission -along with the Shaping Orange County's
Future Task Force and Water Resources Committee until their completion
in 1999/2000. Coordinating the agendas and initiatives from these boards
will be a significant part of the staff work load, as all of the boards and
commissions have ambitious and challenging projects.
F. Developing Elements of the Comprehensive Plan. The County's
Comprehensive Plan has several elements which have not been
completed or undertaken. Chief among these would be the eventual
Water Resources Element (coordinating surface and ground water
programs) and the Natural Areas Element, both of which would fall into
the realm of the Commission for the Environment. Preliminary plans to
combine the work of the Rural Character Study and Flexible Development
for the Open Space/Rural Character element were developed several
years ago, but have not been finalized. Given the nature of the
department's duties, staff would need to coordinate with the Master Parks
and Recreation effort on finalizing that element of the plan. Given the
strong relationship of resource conservation in the Land Use Element,
ERCD staff could also assist the Planning Department in preparing the
planned 2001 update of that element, as well.
G. Farmland Preservation. The department will work with the Agricultural
Districts Advisory Board on current and future goals and initiatives related
to farmland preservation, including enhancing and promoting the
Voluntary Agricultural Districts program.
H. Historic Preservation. The department will work with the Historic
Preservation Commission on current and future goals and initiatives
related to historic preservation, including local landmark designations and
National Register nominations.
I. Shaping Orange County's Future / Sustainability. A multi-year joint
initiative, Shaping Orange County's Future is nearly two-thirds completed.
Orange County serves as the lead coordinating .entity of the project, and
David Stancil, the project coordinator will be moving into the ERCD
department (please see Attachment B). Assigning another planner to
coordinate completion of this project would be difficult given the
7
11
complexity of this project, and the May 25 memo on the new department
indicated that Shaping Orange County's Future coordination could move
to the ERCD pending its completion next year. This would make sense,
especially given the fact that many of the issues and goals of Shaping
Orange County's Future have a strong linkage to environment and
resource conservation. Related to this is the Commissioners goal on
sustainability, which uses Shaping Orange County's Future as a
springboard for launching a County program to integrate sustainability into
County policies and programs. Since these issues are intertwined, and
much of the underpinnings of sustainability lie in the environmental area,
ERCD staff could continue to coordinate efforts in this regard working
closely with the Commission for the Environment, Economic Development
and other County departments.
III. Evaluating Resource Needs for the New Department
Using the mission and tasks outlined above, the staff work group has evaluated
and assessed the resource needs of the new department (personnel, equipment,
budgetary and space).
One method to adequately accomplish this evaluation is through adual-modal
approach -with two trains of thought.
In the first approach, the ERCD is looked at as if it were a new department
"starting from scratch", with no available resources to call on. Once needs are
assessed using this approach, the second model is a parallel assessment of the
new department, given known resources and opportunities that exist within the
County.
Review of these two models together enables a clearer picture of the necessary
resources for the new department, and might point up any gaps between needs
and available resources.
A. Evaluation Model #1 - "Starting from Scratch"
1. Personnel
Personnel needs for a new department would be based around the
mission and tasks, as previously noted. Using this a base, these would
appear to include:
a) Background and knowledge of surface and ground water planning and
management
b) Background and knowledge in biological resources, air quality,
sustainability and general environmental issues
8
12
c) Background and knowledge in identifying and prioritizing natural and
cultural resources, including natural areas, wildlife habitats, historic
preservation, archaeological sites and farmland preservation
d) Experience and knowledge in land acquisition for resource
conservation and recreation
e) Experience in working with citizen boards and other
agencies/departments to accomplish multi-task objectives
f) Background and knowledge in working with geographic and other
databases (including GIS and tabular database record systems)
g) Background and experience in working with community visioning
initiatives, including sustainability and community-building
h) Background and experience in providing administrative support to
citizen boards and commissions
2. Equipment
If personnel should have the above qualifications and experience needs,
equipment for acompletely-new department to accomplish the tasks
outlined would appear to include:
a) adequate ofFce space
b) furniture and file storage for staff members,
c) networked personal computers and a printer,
d) telephones, and
e) at least one GIS workstation and digitizing table with linkages to other
departments, a plotter, and the internal network.
B. Evaluation Model #2 -Using Existing Resources to Meet Needs
1. Personnel
Having assessed the needs for a new ERCD built "from scratch",
personnel requirements for such a department might translate into the
following positions:
a) One position to provide administrative support to department staff and
develop board/commission meeting minutes.
b) One position to provide GIS and database support for resource
inventories and records, as well as developing new coverages as part
of board/commission initiatives. This position should have strong
working knowledge of ARC-Info GIS systems and database programs.
c) One position with a combined background of environmental science
and resource acquisition, with knowledge of natural and cultural
resource identification and planning, and substantial expertise in land
acquisition for resource conservation and recreational purposes. This
position should also have knowledge of inventory/database systems
and strong presentation skills.
9
13
d) One position to coordinate the work of boards in historic preservation
and agricultural districts.
e) One position to serve as department head, with supervisory and
budgetary experience, along with a broad background in open space,
water resources, natural and cultural resources, other environmental
areas, as well as strong interpersonal and presentation skills.
In evaluating current resources, it is apparent that, with one notable
exception, all of the tasks for the new department are currently housed in
the Planning Department to the degree that they are dealt with. Transfer
of the duties and work tasks outlined above would involve shifting relevant
personnel and equipment to the new ERCD.
Fortunately, because many of these tasks are currently being addressed,
there are staff members in the Planning Department that have sufficient
background and experience in many of the areas listed above. One
Administrative Assistant in the Planning Department has experience
providing support to existing staff members working on these projects,
and with advisory boards that deal with the new department's subject
areas. Two GIS Project Coordinators are currently on staff that are
knowledgeable about environment and resource-related coverages, and
have strong knowledge of the ARC-Info system. The current Special
Projects Planner position has significant expertise with historic
preservation and farmland issues, as well as previous background in
natural resources. Finally, the current Land Use and Environmental
Planner has significant expertise in water resources, open space,
sustainability and other environmental issues - as well as supervisory and
budgetary experience.
2. Equipment
Similarly, the equipment needed for the new department is currently
located with the personnel listed above. All of the staff members have
personal computers and existing office furniture and storage space. Three
GIS workstations and three digitizing tables are currently in the Planning
Department. Existing telephones and computer networking arrangements
are in place, if the new department stays in the Planning and Agricultural
Center.
3. Space
Space needs constitute an area that would need to be addressed. No
available space in other buildings exists at this time. Reconfigured space
in the Planning and Agricultural Center would be the recommended short-
term solution to space needs.
10
14
If existing staff were transferred from the Planning Department, the
Planning budget would need to be adjusted to reflect the personnel,
operating and capital expenses that would be shifted to the new ERCD.
C. Gaps between "Starting from Scratch" and Existing Resources
Combining the theoretical and existing resource assessments, a large
majority of the department's needs could be met from Planning Department
staff. Even so, there are a few possible "gaps" for the new department that
may need to be addressed:
1. The one area where existing resources do not cover department needs is
in the area of resource acquisition and environmental science background
for the identification and prioritization of resources. Meeting these needs
will require a new position with land acquisition and environmental science
background.
2. Further information will be developed for an interim and long-term
acquisition program, as specified in Section I.B and Appendix A, so that a
program with the ability to meet specific needs for resource land
acquisition can be implemented. Questions regarding the entity to serve
as a "land trust" (County, Triangle Land Conservancy, Soil and Water
District) will need to be addressed.
3. The Planning Department has an existing Administrative Assistant that
provides board and staff support, but re-assignment of this position to the
ERCD would leave the Planning Department without support for the
boards that it would retain, not to mention daily administrative functions.
4. In terms of equipment needs, most could be acquired through the transfer
of resources from Planning. However, a new printer and ARC-View
software will be needed (not available for detachment from Planning), and
office equipment for any new positions would also need to be acquired.
11
15
IV. Recommended Personnel and Equipment Needs
Upon completion of the evaluation of the mission, tasks and resource needs of
the new department, the Administration recommends the following program to
initiate an Environment and Resource Conservation Department.
A. Personnel
As previously stated, a considerable proportion of the mission and tasks for
the new department are a reconfiguration and expansion of efforts and
projects currently handled by existing staff in the Planning Department.
Based on the assessment of resources, the Administration recommends a
combination of existing and new personnel for the new department. Two
permanent positions and 1.5 project-funded permanent time-limited positions
are recommended for re-assignment from the Planning Department to the
new Environment and Resource Conservation Department. Two new
permanent positions (a Natural Resource Conservation Manager and an
Administrative Assistant position) would be created to meet needs not
available from current Planning personnel. Finally, one current position
(retitled Land Use and Preservation Planner) is recommended to be shared
between the Planning Department and the ERCD -with reconfigured job
duties to meet needs in both departments (please see Section C below, and
Appendix B).
The recommended personnel and related costs for the new department are
shown in Attachment B, Recommended Personnel and Costs for the
Environment and Resource Conservation Department.
B. Equipment Needs
Likewise, equipment needs for the new department can largely be met using
existing resources. It is recommended that each of the re-assigned staff keep
their existing personal computers, office furniture and storage space in the
new configuration. One existing GIS workstation would be dedicated to the
new department, with a temporary shared arrangement with Planning for the
second workstation/digitizing table. A new printer and furniture/PC's for the
new Natural Resource Conservation Manager and Administrative Assistant
would be purchased. Existing network linkages between Planning and the
department would be retained, for both personal computers and GIS
workstations.
12
16
C. Space Needs
In the immediate short-term, no changes to existing office arrangements are
recommended through the end of calendar year 1998. In the meantime, staff
will continue to explore two alternative configurations in the Planning
Department and/or a portion of the Planning/Agricultural Center breezeway.
One of these two options would be undertaken in 1999 to provide a distinct
space for the new department utilizing existing building resources.
D. Budgetary and Other Recommendations
1. Since a re-assignment of personnel and tasks would occur from Planning
to the ERCD, a concurrent transfer of related funds to a new budget would
be needed. The administration and staff will work with the Budget Director
to transfer relevant funds from the Planning Department budget to a new
ERCD budget.
2. While a significant portion of the existing Land Use and Environmental
Planner's current duties would be transferred to the new department
(please see Appendix B), responsibilities related to the Land Use Element
of the Plan, demographics and Township Advisory Councils will remain in
Planning. As such, I am recommending that the existing Special Projects
Planner II position be retitled Land Use and Preservation Planner, and be
split between the new ERCD and Planning. This position would be re-
assigned to the Comprehensive Planning Division to cover the functions
not transferring to the ERCD, with a substantial portion of job duties
staying in Planning and a smaller portion in the ERCD.
3. The Orange Soil and Water District Commissioners have provided a
proposal for their involvement in some of the duties listed herein (please
see Attachment D). The Soil and Water District, in conjunction with the
Natural Resource Conservation Service, offers a number of programs and
opportunities for County partnership efforts and funding possibilities. The
Soil and Water District has recently hired a Neuse River Basin Technician,
who will begin working on the possible purchase of riparian buffer areas in
the Neuse basin. In addition, opportunities through the USDA
Conservation Reserve Program offer additional opportunities for
cooperation with Soil and Water in voluntary conservation for agricultural
erosion control or water quality. A summary of some of these programs
can be found in Appendix D. With a clear need to build a strong tie with
this department, it is recommended that the administration and staff meet
to pursue the nature of this relationship over the next several months.
4. In the event that land or easement acquisition becomes available during
this fiscal year, money from the contingency fund could be utilized if the
13
17
land is deemed important for resource acquisition. Attachment A
summarizes the options for short-term land/easement acquisition on a
temporary basis while the Comprehensive Resource Acquisition Program
is developed.
5. Comments from the Orange County Board of Health were received on
Thursday, October 1. Because of this, staff has not had an opportunity to
review the comments. The Board of Health comments are attached as
Appendix F.
V. Proposed Effective Date and Cost
If the Board agrees with the recommendations herein, the Manager recommends
an effective date of November 23, 1998 for the new department to take effect.
Due to the fact that no physical change in location is required and that most of
the initial duties will involve workplan items already underway, this timeframe for
startup should be feasible.
Since the majority of the department's work will use existing resources, most of
the funding needs for FY 99 can be transferred from the Planning budget. An
additional estimated $52,000 would be needed as start-up costs for the new
department. It is recommended that this funding be appropriated from the
Board's $250,000 contingency for FY 99.
Erc10-1.doc
14
18
Appendix A
Options for Interim Acceptance of
Conservation Easements and Other Land
Donations
1 ~J
Possible Interim Program for Land Acquisition
During the interim period when the necessary process, prioritization and program
for the Comprehensive Resource Acquisition Program is being developed, there
may be occasions where the County will be approached about voluntary
donation of land, either through conservation easement orfee-simple dedication.
The County has, for several years, promoted voluntary donations of land, and
has sponsored conservation easement workshops for the public and created
incentives for land conservation within its Flexible Development standards in the
Subdivision Regulations. By working with existing State and Federal agencies to
promote programs such as the Forest Stewardship Program, the Conservation
Reserve Program, and the Wildlife Habitat Incentive Program, among others, the
County can enhance voluntary land conservation initiatives.
Interim Acquisition Of Conservation Easements and Purchase of Land
Prior to developing a Comprehensive Resources Acquisition Program, the
County may desire to acquire conservation easements from willing property
owners, when such proposed acquisitions are consistent with resource
preservation goals. Such proposed acquisitions may be motivated by a
landowner's estate plans, or by other initiatives. The County may also be
presented with the opportunity to purchase desirable parcels of land.
In order to move quickly in such instances, the County should acquire the ability
to negotiate an acquisition, execute the necessary documentation, and accept
the donation or obtain title to the land. In these cases, the County would provide
stewardship and/or acquisition funds at the outset. To facilitate these activities,
the County will hire a Natural Resources Conservation Manager. Among the
abilities of this new position will be significant expertise in identification and
prioritization of natural resources, and substantial experience in the negotiation
of land acquisition.
It is recommended that the County begin to develop an interim program based
on the above, and report back to the Board with a proposed interim acquisition
program.
20
Appendix B
Recommended Personnel and Costs for the
Environment and Resource Conservation
Department
1. Administrative Assistant II -Proposed new permanent full-time position
Because there are no existing administrative assistants in Planning that could
be re-assigned without dramatically affecting the ability of Planning to
address the boards and staff it retains, it is recommended that a new
Administrative Assistant position be established for this department. The
Administrative Assistant would be needed due to the responsibilities of
supporting staff and developing commission/board minutes for several
boards.
Associated Costs: $18,000 (half-year salary and benefits)
Impact on Planning Department Projects: None.
2. GIS Project Coordinator -Proposed reassignment of existing permanent
full-time position.
This position would be responsible for coordinating GIS products and the land
records database for staff and the commissions/boards that the department
supports. It is recommended that current GIS Project Coordinator Beth
Young be re-assigned to the ERCD. As one of two existing Planning GIS
members, Beth has had many occasions to produce coverages of an
environmental and resource conservation nature, including recent work with
the Triangle Land Conservancy on the "Landscape wth Wildlife" report.
Associated Costs: None
Impact on Planning Department Projects: A substantial portion (perhaps
over 50%) of recent duties for Planning GIS personnel has been related to
environmental or resource-oriented projects. As this position becomes part of
the new department, existing Planning GIS projects in this field will be
accordingly reassigned to the ERCD. One GIS workstation and access to a
second would be shifted to the new department, consistent with the shift in
workload and projects.
21
3. Land Use and Preservation Planner (split position between Planning
and ERCD) - Proposed reassignment of existing permanent full-time
Special Projects Planner II position.
This position would have duties split between the Planning Department and
the ERCD, with the majority of duties in the Planning Department. Duties and
responsibilities with the ERCD would include staff support to the Historic
Preservation Commission and the Agricultural Districts Advisory Board. The
remainder of the position's duties would be in the Comprehensive Division of
the Planning Department, related to long-range land use and preservation
planning. A position outline that illustrates the duties with both departments is
attached (please see Appendix C). The duties related to the new ERCD are
currently performed by Special Projects Planner Don Belk. In four years
with the County, Don has served as staff resource person for the Historic
Preservation Commission and the Agricultural Districts Advisory Board. He
has also worked with the County's Flexible Development program, and has
previous experience in resource conservation assessment and land
acquisition.
Associated Costs: None
Impact on Planning Department Projects: The shared nature of this
position would allow Planning to meet needs left by the transfer of other staff,
while also meeting needs of the ERCD by allowing this position to continue
work and experience with Historic Preservation and Agricultural Districts.
4. Natural Resource Conservation Manager -Proposed new permanent
full-time position.
This new position would be the primary staff person responsible for
identification of the County's natural resources and prioritization of natural
resource acquisition needs. In assessing the land conservation needs and
acquisition priorities, this position will apply a knowledge of environmental
science in developing recommendations.
The Natural Resources Conservation Manager will be responsible for
obtaining appraisals and negotiating the purchase and/or donation of land,
and will work with other department staff to develop and evaluate a
comprehensive resource database that prioritizes and targets the County's
natural resource preservation efforts.
Associated Costs:. $25,000 (half-year salary and benefits)
Impact on Planning Department Projects: None.
22
5. Environment and Resource Conservation Director -Proposed
reassignment of existing permanent full-time position.
This position would serve as department head, planning and directing the
department's activities, supervising staff and administering the department
budget, personnel and related matters. The position would also serve as
primary staff resource to the Commission for the Environment and the Water
Resources Committee. Current Land Use and Environmental Planner
David Stancil has almost 10 years of experience with the County, and
currently serves as staff resource for the Water Resources Committee,
among others. David has three years of project budget experience, and
developed much of the FY99 Planning Department budget. He also has
supervisory experience, currently supervising two permanent (time-limited)
positions and two intern positions, and has substantial background in surface
and ground water resources, sustainable development and open space
issues. With the Shaping Orange County's Future project nearing completion
in mid-1999, transition to new staff coordination would be difficult. It is
therefore recommended that David Stancil continue his work as Shaping
Orange County's Future project coordinator in addition to his other duties.
Because of the change in duties for this re-assigned position, Personnel
would conduct a classification and pay study of the position after the new
duties are assumed. Based on this, Personnel would recommend a
reclassification of the position to an appropriate classification and salary
grade to recognize the new duties. This would occur within the first six
months of the new department.
Associated Costs: None at present (classification study pending)
Impact on Planning Department Projects: Many of the existing duties of
the Land Use and Environmental Planner would be re-assigned with the
position, but some duties would remain in Planning, including work with the
Land Use Element of the Comprehensive Plan and demographic analysis. To
address this need, the existing Special Projects Planner position will be
retitled Land Use and Preservation Planner, and split between Planning and
the ERCD, with the majority of work duties in the Planning Department.
Note: Attachment C to this report contains major functions for the Natural
Resource Conservation Manager and the reconfigured Land Use and
Preservation Planner position.
In addition to these positions, there are two permanent time-limited positions
that are funded from projects that would be among the duties of the new
ERCD.
23
6. Shaping Orange County's Future Project Planner -Proposed
reassignment of existing permanent time-limited position.
This position works exclusively with David Stancil on the Shaping Orange
County's Future project, and is 100% funded from the joint project budget,
which contains appropriations from the Towns of Chapel Hill and Carrboro as
well as Orange County. Since Shaping Orange County's Future
administration will be moving to the new department, it is recommended that
Project Planner Pam McIntosh move to the new department to optimize
coordination. This position is scheduled to end on June 30, 1999.
Associated Costs: None
Impact to Planning Department: None, all duties would transfer.
7. Water Resources Planning Technician -Proposed reassignment of
existing permanent part-time, time-limited position.
This is a permanent, part-time, time-limited position that coordinates the GIS
ground water database component of the Water Resources project. It is
funded in entirety by the Water Resources project budget, and is under the
supervision of David Stancil as project coordinator. Like the above time-
limited position, this position would end June 30, 1999. Since the Water
Resources project would become part of the ERCD duties, it is recommended
that Planning Technician Margaret Jones move to the new department for
the duration of her employment.
Associated Costs: None
Impact to Planning Department: None, all duties would transfer
Total Estimated Start-Ua Costs of New Department - FY 99
New Administrative Assistant (half-year, includes benefits): $18,000
New Natural Resource Conservation Manager
(half-year, including benefits): $25,000
Furniture/computer needs for two new positions: $ 7,000
New printer/software licenses: $ 2,000
Total $52,000
The following table shows the changes to the Planning Department that would
take place if the recommended changes are instituted. It should be noted that a
significant portion of the duties of the Planning Department would also move to
the new ERCD with the reassigned personnel.
24
25
Appendix C
Major Functions of:
1. Land Use and Preservation Planner
2. Natural Resource Conservation Manager
20
Land Use and Preservation Planner (Planner III
This would be a split position, shared between the Planning Department and the
Environment and Resource Conservation Department. The majority of the
position's duties would be in the Planning Department.
Planning Department Duties
In the Planning Department, the position would be assigned to the
Comprehensive Planning Division. Job duties and responsibilities would include
working with special projects, ad hoc committees, and policy analysis.
Specifically, the Land Use and Preservation Planner would:
• Evaluate proposed amendments to the Land Use Element of the County's
Comprehensive Plan
• Perform statistical analysis, including population projections and estimates
and an annual New Housing Starts report
• Work with the Comprehensive Planning Supervisor to coordinate Small Area
Plans authorized by the County Commissioners
• Work with the County Attorney as staff support to the Water and Sewer
Boundary Task Force
• Serve as staff support to the Bingham and Chapel Hill Township Advisory
Councils
• Provide information to citizens regarding the Land Use Element of the
Comprehensive Plan
• Work on additional special planning projects, such as cooperative planning
efforts with other jurisdictions
• Coordinate and oversee Neighborhood Information Meetings and issues
related to the Flexible Development provisions of the County Subdivision
Regulations
Environment and Resource Conservation Department Duties
Duties and responsibilities with the Environment and Resource Conservation
Department would include:
• Staff support to the Historic Preservation Commission
• Staff support to the Agricultural Districts Advisory Board
27
Natural Resource Conservation Manager
This new position would be located in the Environment and Resource
Conservation Department (ERCD) and report to the Department head.
This position will work with the other members of the ERCD on the creation,
maintenance and implementation of the County's strategic natural resource
conservation plan, focusing on the following areas:
Identification of Resources: This position will be the primary staff person
responsible for identification of the County's natural resources and prioritization
of natural resource acquisition needs. In assessing the land conservation needs
and acquisition priorities, the position will apply a knowledge of environmental
science in developing recommendations. The Natural Resources Conservation
Manager will work with other department staff to develop and evaluate a
comprehensive resource database that prioritizes and targets the County's
natural resource preservation efforts.
Acquisition of Highest Priority Natural Resources: The position will be
responsible for developing specific strategies to conserve land and other natural
resources. This will include obtaining appraisals and negotiating the purchase
and/or donation of targeted natural resource properties, whether through
purchase in fee-simple or interests at less-than-fee levels such as conservation
easements or other agreements. This also will include negotiation of terms and
development of draft agreements and contracts for acquisition.
Financing and Funding: The Natural Resources Conservation Manager will
identify grant opportunities and will seek grant funding to augment County
matching funds, including the development of grant applications. The position will
seek to maximize available state and Federal funds to achieve the department's
goals though the acquisition and management of natural resource properties.
Education/Outreach: The position will build partnerships with landowners,
interest groups and the general public through education and outreach in support
of the ERCD goals including acquisition and maintenance of natural resources.
28
Appendix D
Memorandum and Materials from
Soil and Water Conservation District
(Note: New information only. Does not include packet of
materials previously distributed on August 26)
.. --'' (~ P R 2 9 REC'0 N RTH CA O
1'~ O R LINA DEPARTMENT OF
ENVIRONMENT AND NATURAL RESOURCES
DIVISION OF SOIL AND WATER CONSERVATION
e~
- - -'~,-~ Apri124, 1998
~~
NCDENR
Deaz Soil and Water Conserva±ion Distr+.ct S~~pervisors and Staff:
}
JAMECS B. HUNT JR. '~-;^~ ~~
GOV[R"cR We are contacting you about an exciting new USDA program-the
- Conservation Reserve Enhancement Program (CREP). This program was
established by the 1996 Farm Bill to cost-effectively meet specific
conservation and environmental objectives of the state and the nation. A state
wAma McDEtvlTr
Si:GxtMARY can propose to enhance the familiaz Conservation Reserve Program (CRP) aS
long as the program is consistent with the CRP regulations. A successful
,::~ proposal will mean open enrollment for producers and over four dollars of
.~
~
federal funds for every state dollar spent on the project. Four states have
c. DEWEYB°TT9
'`~
- already received approval for CREP projects and each one totaled $200
D1R6CTOR
._~ million or more. North Carolina must move quickly to submit its proposal
~..-. ; because USDA funds are limited and enrollment authorization ends on
_~ ~ ~~
~~ September 30, 2002.
~~
:;
~_ ..~~~
`~~ ~ The Department of Environment and Natural Resources, with
,
'
.Y::°- assistance from a working group consisting of interested agencies, including
`- ~ the Fazm Service Agency, the Natural Resources Conservation Service, and
~-~ y
'` the Division of Soil and Water Conservation, has been developing a draft
~
--
proposal for North Carolina. We now have enough details worked out to
_.: shaze it with you and ask for your comments and support.
Briefly, North Carolina is proposing a $274.5 million program to
earoll up to 100,000 acres of active farmland near rivers, streams, field
""- ~ ditches, and wetlands in 15-year CRP contracts and permanent
easements. USDA requires the state to provide at least 20 percent of the total
-' project costs. USDA will pay annual rent, bonuses, and maintenance fees for
. ~;: _ . = 15 yeazs and 50 percent of installation costs for eligible BMPs. The state
".. ~
' ~ proposes to pay for purchasing permanent easements on approximately 65,000
_
~~~~?
~= -, acres after the CRP contracts expire (however, the state's payment must be
made when the property is enrolled), and proposes to pay up to 40 percent on
installation of the riparian forested buffer BMP on approximately 50,000
- - ~
- ~.. acres. The geographic focus covers the Chowan, Neuse, and Tar-Pamlico
- ." "==-~; river basins and the Jordan Lake watershed.
:.
..~ We aze enclosing for your review the pertinent portions of the
proposal-the executive summary, project description, and cost analysis. We
- ~<.~-N want to bring to your attention the recommended role for the affected Soil and
Water Conservation Districts (pg. 17) and the recommended $7.50 per acre
per yeaz through the year 2002 for each acre enrolled by a District in
29
soa a~ wn~~
P.O. BOX 27667, RALEIG N. NORTH CAROLINA 2761 1.7687 ~
PHONE 91 9-733-2302 FAX 91 9-71 5-3559 CONSERVA(ION
AN EQUAL OPPORTV NITY /AFFIRMATIVE ACTION EMPLOYER - 50 a RECYC LE O/10°~a POST-CONSUMER PAPER ~~
30
permanent easements (page 21). This payment is to help offset the additional costs of the
Districts for participating in the program.
The draft proposal will be presented to the Clean Water Management Trust Fund
trustees on Apri127 and to the Soil and Water Conservation Commission on May 13 to
secure their support and commitment of matching funds. During the next six weeks, we
will be contacting other stakeholders before submitting the final proposal.
Please call any of us if you have questions or contact Donna Moffitt at 919/715-
6103 to provide feedback on the draft proposal or if you would like to have a copy of the
complete proposal. We would appreciate letters of support sent to Assistant Secretary for
Natural Resources Sherri Evans-Stanton, DENR, P.O. Box 27687, Raleigh, NC 27611-
7687 before May 13.
We are totally behind this proposal and hope that you will be, too. We think this
project is a tremendous opportunity to work together to improve water quality, erosion
control and wildlife habitat in the targeted river basins and watershed in North Carolina.
Thank you for your consideration.
Sincerely,
C. Dewey Botts
Soil and Water Cons.
919/715-6097
Enclosures
Sincerely,
Mary Kollstedt
Natural Resources Cons. Serv.
919/873-2101
cc: Sheen Evans-Stanton
Donna Moff tt
Tim Jones
James Ferguson
Eddie Stroup
Carroll Pierce
Cecil Settle
ASTC-FOs
DSWC Area Coordinators
Sincerely,
Philli . Farland
Farm Service Agency
919/875-4800
�� .�>... . o. .
�;�ss�..__rya.,g _��2qc;v-:!/a•�•.Jroas`cr S'/i!Cli,`= ��V=�;`raC?��i=c'icr J,-�=s ) n
T�tr C_n�?s��•,:.����;t
r-; Channels.zither natural or constructed.that Small areas whose purpose is providing 'Nellheatl protectien areas.�esigr.atetl by;he ]�
cover and a Nater source'or wildlife.Water Environmental Protecticn,�cenc��i EFA1 or an �=������ 1 1��i��/�l i i i:
(+� are planted��vnh suitzble vegetation `�
to p�otect seil°rom zresion during rains. is impoundeo using embankments.berms.or appropriate State agency.heio assure the
Grass�.vaten.vays can help heal gullies and other methods.and surrounded by a small safery of municieal water;ucclies drawn from Cuqtinuou5$i�rt-��(�/��r Ki,ii-Prr��rrr:
�,vashouts.and creatly red�ce'oss of ropsoil area plante0 with permanent cever. wells.Vegetation planted m an area�urround- �
and the s2Cimentauon of;treams.ponds. ing�he wellhead w�ll he� P�'�rrric'es
p crctect the•.vater
and lakes. suCply trOm contaminatipn.
_ _,��_ ���--���---� �_���...,'�-y�„�::^,�;.�� ` Each oi the conseivancn praNices out-
-=- " -- "'°Y� �"� � �Y iined above��.v�ll be sub�ect;o`urther r=puire-
�� �='���-..-..o.R-� . - me�ts under an approvetl ccnservaticn plan
_ a..-�
_ " ��_.�:�,,:�.q� � -; tlesigned!o maxim¢=2Hecaveness and .
--t -�.. I - :c;,.+c•7••�w..=y. � _ iongevlry. r �
`�� L ;�` s
���--1__. J� To learn more about;he CJns2rvaL'on ����'--s��'^��.'+rt.-.�-.-z,.,,__
� Rr ,.s • Reserve Program,•Nn[e to t^e foilowing �-'���--"' ' �-�f
_{. address:
- USDA FSA Public Affairs StaH
1400 Independence Avenue,SW I
3�R-:c�ar�nr'/=oe!a,rcn STOP 0506
Washington DC 20250-0506
Vegetation planted ro reclaim areas in which
saline water is seeping ro the surface.Planted Information on FSA can also be tound on the
-� areas"upstream"reduce the amount of water FSA's Worltl Wide`Neb home page.al
recharging the seep.and salhtolerent plants www.fsa.usda.gav
reclaim the contaminated seepage area.
The Unrtetl Stales Oepariment o��gnculNre�USDA)
prohibit5 diSCriminatwn in'�IS Programs on the oa5i5 0� . .
race.color.nauo�al ongin.;ea,�engion.age.oisabAity. '%!._.YM�.�I�,s '' '_��: ;'!�
political be�iels antl marnal or!amn�al;tatus.i Not�il � �i. �l�
orohibiled bases app�y to�II programs.�Pwso�s��vnh '�' � — � �.�
aisab�lities'.vho rgquire dllemaUVe'neans!or
communicat�on ol program�nlormauon ib2ilie.iarqe onn�.
audiolape,etc.)snould CoMact USOA s 7.1RGE7 Ctnter
at 202-720�2600 Iwwe ana'001. .�,
To lile a complamL�nnte me Secre�ary ol Agncu�Wre.U.S.
Department ol Agncunure.'Nasnmgton.D.C.,20250.or
call 1-800-2a5-63<O I�KeI�r i.2021�20-i 1271TOO1.
USDA is an CQU31 employme�t ooportuni�/9molpyel.
PA�1609
August 1997
US�F1 United Sqtn �
7�— Departmenl ol
� Agriculture
N
M
The Conservation Reserve Program(CRP) agricultural commodiry in any 2 years hom Riparian Buflers - .
�s tne Federal Govemmeni's single largest 7992 to 7996.The acreage must also be
environmental improvement program and one determined eligible and suitable fo/any of the Areas ot trees and/or Shrubs,next to ponds, �
of its most productive and cost-etticient.It is following practices: . lakes,and streams that fitter out pollutants
admmistered by ihe U.S.Depariment ot from runoff,as well as providing shade for
Agriculture s Commodity Credit Corporation (ish aod other wildlite.The vegetation's
(CCC)through the Farm Service Agency Filter Strips na[ural Ntler also provides footl and sheRer for
(FSA). valuable wildlife.
Established in 1985,the CRP encourages Areas of grass,legumes,or other vegetation Riparian buffers are planted so that runoH
farmers to voluntarily plant permanent areas of that fitter runoff or waste water by trapping must filter through them befare it reaches a
grass and trees on land that needs protection sediment,pesticides,organic matter,or other pond,lake,or stream.Buflers can also be
from erosion,to act as windbreaks,or in pollutants.Filter strips are established on placed next to wetlands,such as marshy or
places where vegetation can improve water cropland at the lower edge of a field or adja- swampy areas. = -- -- --
'—�-�--�..s
qualiry or provide food and habitat for wildlife. cent to bodies of water. _ __ __,____�,� +�+ - _
The farmers must enter into contracls with 4J����"
the CCC lasting between 70 and 15 years. °��
In return,they receive annual rental payments, � �
incentive payments for certain activities,and
cost-share assistance to establish the '—
protective veqetation.
In previous years,a landowner had to ��
apply ro participate in CRP during announced
sign-up periods.Since September 1996, ����
however,owners have been able to si9n up
for the program any time during the year for
certain high-prioriry conservation practices.
Provided certain eligibility requirements are
met.acreage is automatically accepted into
the program at a per-acre rental rate not to �� ' � � �` –
exceed the CCCs maximum payment amaunL � �� �� ?� � Shefter Be/ts,Fie/d Wlndbreaks.and
. Land owners and operators may be �\!� �'�A� r . . ' �; !.�' � Living Snow Fences
eligible to participate in the CRP.Landowners �li� .' �" � '� Y� �- �.,¢��;.
must have owned the acreaqe for at least 1 �°f Befts of trees or shrubs planted in single or
year and operators must have�eased the � " � multiple rows.Such tree rows and hedges
acreage for at least 1 year to be eligiWe. � I� li '� reduce wind erosio�,protect growing ptants,
land eligible for enrollment includes crop- �I II � and provide habital for wildlNe.They can also
land that is physicalty and legally capable of I shefler stnrctures and livestodc.Field wind-
being cropped in a normal manner,and that breaks proted flelds from erosion,and snow �=. �
has been planted or considered planted to an fences help manage snow. �/�'-��
• �d'�]��C. �
33
Appendix E
Establishment of New Department
Background Information
1. June 22, 1998 Agenda Abstract
2. May 25 Memoranda on Establishing New
Department
34
ORANGE COUNTY
BOARD OF COMMISSIONERS
Action Agenda
Item No ~~
ACTION AGENDA ITEM ABSTRACT
Meeting Date: June 22, 1998
SUBJECT: PROPOSAL TO FORM A NEW ENVIRONMENT AND RESOURCE CONSERVATION
DEPARTMENT
-------------------------------- -------------------------------
DEPARTMENT County Commissioners
--------------------------------
ATTACHMENT(S): Yes - Two May 25 Memos
1. Proposed Revision to Commissioners
Goals and Objectives
2. Comprehensive Resource Conservation
Program
PUBLIC HEARING YES NO x
BUDGE T AMENDMENT : _YE S NO
INFORMATION CONTACT
Commissioner Alice M. Gordon
TELEPHONE NUMBER
Hillsborough 732-8181
Chapel Hill 968-4501
Mebane 227-2031
Durham 688-7331
-----------------------------------------------------------------------
PURPOSE: To establish a new Environment and Resource Conservation
Department.
BACKGROUND: Orange County places a great deal of emphasis on
environmental matters, including environmental protection, and
therefore has established a Commission for the Environment.
Furthermore, in the Commissioner's Goal on Natural Resource Protection,
the County Commissioners have recognized that resource conservation
should have a distinct identity and a higher profile in county
government. According to the revised milestones for evaluating
resource conservation as a function of county government, the
commissioners are scheduled to make a decision about this function in
June, 1998. Instead of, establishing a new division of the Planning
Department, the commissioners should establish a new Environment and
Resource Conservation Department to oversee the County's activities in
the areas of environmental protection and resource conservation. The
two memos attached explain the rationale supporting this recommendation
and provide the conceptual framework for implementation.
RECOMMENDATION: Establish a new Environment and Resource Conservation
Department. Approval of the new department includes the following steps:
1. Establishment of the New Department
The Board of County Commissioners hereby establishes a new
Environment and Resource Conservation Department.
r'
35
2. Conceptual Framework
The Commissioners hereby adopt the conceptual framework for
this new department outlined in the May 25, 1998 memorandum from Alice
Gordon to the Board of Commissioners and Manager entitled "Proposed
Revision to Commissioners Goals and Objectives."
3. Implementation
The Commissioners hereby instruct the manager, utilizing this
conceptual framework, to formulate recommendations concerning the actual
staffing of the department, amount of funding needed, space requirements,
and other details, and to bring those recommendations as an agenda item
to the Commissioners by mid-September, 1998.
4. Comprehensive Resource Conservation Program
Since one of the proposed tasks of the new Environment and
Resource Conservation Department is to devise and implement a
comprehensive resource conservation program, the Commissioners also
instruct the manager to provide recommendations concerning the
implementation of that program as an agenda item by mid-September, 1998,
using the conceptual framework provided in the May 25, 1998 memorandum
from Alice Gordon to the Board of Commissioners and Manager entitled
"Comprehensive Resource Conservation Program."
36
NfEMORANDUM
To: Board of Commissioners and Manager
From: Alice Gordon
Subject: PROPOSED REVISION TO COMMISSIONERS GOALS AND OBJECTIVES
Date: May 2 S, 1998
CATEGORY: Resources Protection and Development
GOAL: Natural Resource Protection (page 3 )
TASK: Evaluate "Resource Conservation" as a separate division in the
Planning Department to give the function identity and a higher profile.
According to the Revised Milestones for evaluating Resource
Conservation as a function of county government, the commissioners are
supposed to make a decision about this function in June 1998. Instead of
establishing a new division of the Planning Department, I recommend that the
commissioners establish a new Environment and Resource Conservation
Det~artment to oversee the county's activities in the areas of environmental
protection and resource conservation.
ENVIRONMENT AND RESOURCE CONSERVATION DEPARTMENT
Rationale
The county commissioners have already recognized that resource
conservation should have a distinct identity and a higher profile in county
government. This separate function has been analyzed in the Technical
Report entitled ~~rvation as a Function of Local Government. Orange
County, April 1997. Using this report as a foundation but revising some of the
concepts in the report, the commissioners should establish a new department
to implement this function to give it the focus and resources it needs.
Over the past decade the Planning Department has added a number of
resource conservation activities and support for new advisory boards which in
other jurisdictions are sometimes handled by a separate department. Also, the
commissioners have discussed other initiatives, such as acquiring conserva-
tioa easements or acquiring school park sites, which do not have enough
county support to allow successful implementation. We need a comprehensive
resource conservation program to protect land resources such as significant
forests, farms, and historic sites Orange County should also protect its other
important resources, such as air and water. All of these efforts should be
centralized in a new department.
FunctionslDutigs icompare with page 3-1 of the Technical Report)
EnvimgmQgt~ Protection. Responsible for the county's efforts in the
area of environmental protection. including protection of air quality, water
resources, land and other resources, as stated in the county's current goals and
objectives aad as stated in the charge to the Commission for the Environment.
Land Acquisition and Related Activities. Responsible for conservation-
related Land acquisition. conservadon easements, transfer of development
rights and purchase of development rights and similar programs related to
natural resource conservation, farmland preservation and conservation of
cuicural, historical and archaeological resources. It would. be advantageous to
have expertise in this area for smart negotiation of land purchases/easements.
r~
Page 2
Coherent Resource Conservation Program and Resource Records.
Responsible for developing a coherent resource conservation program
encompassing all of the county's land preservation activities, and for keeping
the records and developing GIS maps documenting the preserved areas. The
deparnnent would take the lead in identifying natural resources to be
protected and conserved, and would coordinate the conservation of resources
recommended by other departments, such as Recreation and Parks.
Staff Suaoort for Relevant Boards and Commissions. Provision of
administrative, technical and professional support to the Board of
Commissioners, Commission for the Eavirozunent, Water Resources Committee,
Historic Preservation Commission, and committees related to environmental
protection and the conservation of natural and historical resources . This
would include support for the formation of a Land trust, if one is formed. It
would also include support for the Shaping Orange County's Future Task Force,
perhaps as a joint effort with the Planning Department.
Staff Suonort for Implementation of Relevant Ordin ces. This
function would need further discussion, but the department probably would
pmvide staff support for the implementation of appropriate ordinances such
as the Environmental impact Ordinance.
Liauson with At2Dropriate Deoartinents and Agencies. This depastrnent
should closely coordinate its activities with the Planning Deparment.
St f
Staffing would be similar in quantity to that suggested for the Planning
Deparment division, but the focus and expertise of the staff would differ. Costs
should be similar to forrni.ng a separate division in the Planning Department.
Full time player - Deparament Head tlevel of expertise probably Planner III)
Full time planner (probably Planner II?
Fart time GIS stag' person and some clerical assfstance.
In terms of existing staff, the changed focus of this resource
conservation effort and the intent to include environmental protection would
.make David Stanch a core person, considering his background and current
activities as an environmental planner. He could also finish his responsibili-
ties concerning Shaping Orange County's Future. Une of the current GLS
staffers, Miriam Coleman or Beth McFarfand, would also be appropriate. Emily
Cameron would no longer be central in this conf guradon, and the subdivision
concept plans and landscaping functions would seem more appropriate in
Current Planning where they should remain. Other staff would be discussed.
Implementation
The commissioners would approve the formation of the new department
in principle, following the proposal given above, and direct the staff to
formulate appropriate wordimg for the Goals and Objectives and also for an
implementing resolution. The goats and resolution would be approved by the
commissioners at ttie June Z regular meeting. The actual staffing of the
depamnent and other details of bringing it into existence would occur
according to a time schedule and guidelines developed and approved later by
the staff and commissioners.
37
38
~IENIORANDUNI
To: Board of Commissioners and yfanager
From: Alice Gordon ~~IG
Subject: Comprehensive Resource Conservation Program
.Date: say 25, 1998
In considering our Goals and Objectives, I have proposed that the
commissioners form a new Environment and Resource Conservation
Department rather than a new section of the Planning Department. One of the
casks of [hat new department would be to devise and implement a
comprehensive resource conservation program. The purpose of this memo is
to describe chat program and suggest a method for its implementation.
COytPREI~[ENSI~ RESOURCE CONSERvATIO?~ PROGR4M
Rationale
Orange County's natural resources, and other resources, are
disappearing at an alarming rate. For example, in the last decade 10 percent of
the county's prime forest land has been lost. The county commssioners could
actively work to slow this trend by initiating, finanting, and implementing a
comprehensive resource conservation plan for Orange County. The plan
should include conservation not only of forest land. but also farmland and
historic sites and other significant resources.
Elements of the Program
School/Park Acquisition (existing oolicv) Purchase of park sites
which can be used Inter for schools or for schools in combination with parks.
Financed by reserving the equivalent of one cent on the taY rate:
a~ai~; ition of Other Sigpificant County Resources Purchase of parcels
significant for their natural resources or for other valuable features.
Financed by continuing to reserve the equivalent of one cent on the tam rate,
gad then leveraging these funds by seeking grants from available state funds
such as the Clean Water Trust Funds.
Further Description of a Comprehensive Resource Con~Servatioa Program
As a first step, we could document the loss of natural resources and
other resources using GLS maps, and then project what future buildout would
be (assuming present trends) in the ne.~cc fifty years. The county has data
from the Triangle Land Conservancy documenting the location and extent of
the rernafning prime forest land. The second phase of that study will establish
conservation priorities for these lands. We also have documented the most
significant farmland gad historic sites. With this information in hand we
should move quickly to draw comprehensive resource protection maps. The
digitized data bases for these .maps will be dynamic and capable of continuous
updating reflecting the changes in status.
39
Fage 2
Using this information, we should devise a comprehensive resource
conservation plan for Orange County. Once we have this plan, vve can begin to
acquire Iand. We have a fund now of between one and two million dollars for
school/park sites, but ao active method of finding and acquiring sites. We
have no comprehensive plan for the acquisition of other resources. However,
Iand prices are escalating at an unprecedented rate and potential sites are
being developed. With this ,fund we can set about purchasing Iand whether in
the form of conservation easements, purchase of development rights, fee
simple; or other conservation tools.
Although two million dollars is a relatively small amount of money, it
can be considered seed money for future funding, used perhaps to match
available state funds from the Natural Heritage and Clean Water Trust Funds.
Later we can seek other methods of financing to provide a continuing source
of funds to purchase and maintain natural areas, farmland, and recreational
properties, which will balance the quality of life in our community as
development in our area i.acreases.
To faalitate the development and implementation of a Comprehensive
Resource Conservation Frogram we should focus county efforts in a new
Environment and Resource Conservation Department as proposed.
Ordination of County Departments to Support This Program
Planning Department. There would be e:ctensive cooperation between
the Planning Department and the new Environment and Resource
Conservation Department For example, they would cooperate in the writing of
new elements for the county's comprehensive plan and on efforts related to
Shaping Orange County's Future.
Recreation and Parks. The parks task force is working to develop a
master plan for recreation and parks. Their recommendations would be
integrated into the comprehensive resource conservation program.
Purchases could be arranged by the new department, and the departiment
could keep a record of all such purchases.
Other Deflartrnents and Boards. There woul
departments and/or advisory boards. For e.~cample,
cooperation with the Purchasing Department and
Districts Advisory Board.
Implementation
d be cooperation with other
there would most likely be
with the Agricultural
1. Continue the one cent schooL'park reserve fund.
2. Hold a work session in August or as soon as can be arranged to discuss
this proposed program and its relationship to existing preservation goals and
programs.
40
Appendix F
Comments from the Orange County
Board of Health
(October 1, 1998)
t•°°`. °' B. (~r~ngP (n>~untg ~Ie~l~ ~e~~>rtntent ~°°°`" "ed'~~~
`' ~ Rosemary L. Summers, MPH, DrPH ~ 41
Timothy 1. Ives, Chair Health Director Brenda Crowder Games, Vice Chair ~ ~
e• Orange Caunry Board of Health Orange County Board of Health
•wn. ~.Y,,. war. ~wrr
Management Division
Richard & Whitted Human Services Center Joyce Lee, Administrative Officer Southern Human Service Center
300 W. Tryon Street, P.O. Box 8181 2501 Homestead Road
Hillsborough, N.C. 27278 Chapel Hill, N.C. 27516
Telephone: (919) 732.8181 Fax: (919) 6443007 Telephone: (919) 96&2022 Faxs (919) 96&
To: Margaret Brown, Chair County Commissioners
Through John Link, County Manager
From: Orange County Board of Health
Through Rosemary Summers, Health Director/~~
Re: Recommendations from 9/24/98 Meeting
Date: September 29, 1998
The Board of Health at its regular meeting had several comments they wished to share with the
Commissioners as the new Environment and Resource Conservation Department (ERCD) is
developed. Recommendations fell into two substantive categories:
• A need for clear articulation of collaboration requirements between the new department and
already existing departments with overlapping responsibilities,
• A need for clear authority and accountability indicators for the new department.
You invited draft language to be submitted that would reflect these two areas.
The following are suggested changes to the draft of 8/26 based on the Board of Health
discussions.
I. Mission of the ERCD
To promote and coordinate the conservation of natural and cultural resources in Orange
County.
II. Scope of Responsibility (new added section)
The ERCD will have primary responsibility for developing a plan and program for the
acquisition of land for resource conservation and developing and maintaining an integrated
database for natural and cultural resources. In addition, it will collaborate with other relevant
county agencies in areas of overlapping responsibility to provide support for Commissioner
adopted goals in the natural and cultural resource area. The ERCD will have no regulatory or
rulemaking authority.
III. Major Activities (this replaces much of the section labeled "Mission" under the current
draft)
1. Coordinate with other relevant county departments, Commissioner goals for natural and
cultural resource conservation. These will include Natural Resource Preservation,
Historic Preservation, Farmland Preservation, Water Resources and Watershed
Protection.
Chapel Hill Durham Mebane
(919) 9684501 (919) 688.7333 (336) 227-2031
42
2. As is on page 1 under mission.
3. Integrate current and future data into a comprehensive natural and cultural resource
database. Discussion as is on page I under mission.
=l. Collaborate with other county agencies in providing staff support to boards and
commissions with overlapping responsibilities. For example, the Commission for the
Environment and the Water Resources Committee staff support should be a shared
responsibility with the Division of Environmental Health of the Health Department.
Each department would jointly staff the Commission.
5. Develop collaborative relationships with other departments/agencies.
Add second paragraph on page 3, under number 5.
The Orange County Health Department (OCHD) has specific regulatory authority granted by
state statute in the areas of water supply protection and on-site sanitary sewage disposal systems
In addition, the interface of the environment with human health has always been a core public
health function. The expertise of the staff within environmental health and their already
established linkages to expertise at the state level will be a valuable resource for the new
department. With these functions in mind, the health department should be one of the core
collaborators with the ERCD in any areas involving groundwater, water protection, water
resources, air quality, and agricultural land uses.
Add air quality, agricultural and industrial use of land to chart under environmental health on
page 4.
III. Tasks for ERCD (same as section II, page 4 in current draft)
Water Resources Project
Add at end: The Environmental Health Division of the OCHD should be irrvolved as
implementation plans begin to be developed as part of the Water Resources Element of the
Comprehensive Plan.
Initiatives from Commission on the Environment.
Add at end: In the water resources and air quality areas, joint-staff ng arrangements
with the Environmental Health Division of the OCHD should be pursued
Development of Comprehensive Natural and Cultural Resource Inventory
Staff Boards/Commissions.
For those areas in which an already existing staff and board exist with oversight responsibilities,
a written plan for collaboration should be established for staffing and communication of relevant
issues. A "Staff Advisory Committee"should be established to assist in coordination. Annual
joint meetings of relevant boards and commissions should be established to encourage linkages.
For example an anmial joint meeting of the Commission for Environment and the Board of
Health should be part of the regular meeting calendar.
43
Developing Elements of Comprehensive Plan.
Substitute for second sentence: The water resources element of the plan should have
substantial ongoing input from the Environmental Health Division of the OCHD and from the
Board of Health.
The Board appreciates the opportunity to review the proposal and offers these changes for your
consideration. They certainly support the commissioner's desire to have a coordinated,
comprehensive natural and cultural resources program Orange County.
Cc: Board of Health
Ron Holdway
44
JUNE 2Z. 1998 8000 REGULAR MEETING DR AFB'
d Proposal to form a new Environment and Resource Conservation
beoarbment
The Board considered establishing a new Environment and Resource
Conservation Department
Commissioner Gordon said that we have been taking about having this as a
separate department instead of a separate function. She recommends that this
deparb»ent be established and she read the steps for implementation as included in
the agenda.
Commissioner Crowther said that he does not want this to be a separate
department He supports bringing resource conservation ~ a higher level. However.
he beNeves we already have the Soil and Water Conservation Department. and that
some of the things we would kke to do are being done at the state and federal level.
He also wants to see what functions our Economic Development Department will be
doing.
Commissioner Carey said that he has some similar concerns. He would like
to see a comprehensive report before they take any further action on creating a new
department. He feels that the Cost of County Government will increase if we add
another departmerrt. He would like to see it in an existing department until we see how
it progresses. He feels that the Soil and Water Conservation Aepartment does a great
job.
Commissioner Halkiotis supports what Commissioner Gordon is proposing.
He would like to see this move ahead. He would hope that the County Manager could
find existing resources to put into resource conservation. He feels this concern goes
far beyond what the state is supporting and he does not ses this as a part of the
Planning Department.
Commissioner Gordon feels that people are interested in environment and
resout~ce Protection and that hardly anything the County does is directed toward these
two areas. She feels the department is sorely needed.
A motion was made by Commissioner Gordon, seconded by Chap Brown
tv establish a new Environment and Resource Conservation Department to inGude the
four steps as outlined in the agenda abstract and incorporated here by reference.
VOTE: Ayes, 3; Nos, 2 (Commissioners Carey and Crowther)
DRAFT