ATTACHMENT(S):
Attachment 1: Schedule of County
Capital Projects With
Available Balances
Attachment 2: Capital Investment Plan
Description of Projects
INFORMATION CONTACT:
Clarence Grier, (919) 245 -2453
Michael Talbert, (919) 245 -2153
PURPOSE: To balance and fund all individual projects in the County Capital Projects Fund and
provide reserves for future County Capital Projects.
BACKGROUND: The Board of County Commissioners was presented a two year plan on
February 3, 2009 related to School and County Capital Projects. The plan was to fund a $5.9
million dollar shortfall from the General Fund. A total of $4.2 million dollars has been
appropriated from the General Fund, $3.5 million in Fiscal Year 2008/2009 and $7 million in
Fiscal Year 2009/2010. The remaining $1.7 million was approved by the BOCC on May 18,
2010.
As of June 30, 2009, the Comprehensive Annual Financial Report for Orange County had 84
active capital projects in the County Capital Project Fund. Over the past eight years, few if any
capital projects were closed even though many have been completed for several years. The
purpose of a Capital Project Ordinance is to fund the acquisition or construction of a capital
asset.
A Capital Asset is defined by Governmental Accounting, Auditing, and Financial Reporting
(GAAFR) as: land, improvements to land, easements, work of art, and historical treasures,
infrastructure and all other tangible or intangible assets that are used in the operations and that
have initial useful lives extending beyond a single reporting period.
As stated in General Statute 159 -13.2 (c) Project Ordinances, "A project ordinance shall clearly
identify the project and authorize its undertaking, identify the revenues that will finance the
project, and make the appropriations necessary to complete the project."
2
CURRENT SITUTATION: Orange County has established two types of projects in the County
Capital Projects Fund. The first type of project has been established in whole or in part to
construct or acquire a capital asset. The second type of project has been established to act as
a reserve to fund other projects. Both types of projects have rarely been closed even after the
scope of the original project is complete.
On May 18, 2010 the BOCC closed twenty -six County Capital projects that were substantially
completed or never had any activity. Closing these projects provide $245,560 in capital
resources that can be used for other capital priorities.
Attachment 1 lists thirteen active County Capital Projects with available balances, that have had
limited activity over the past few years and could be closed as of June 30, 2010. This action
would provide in capital resources that can be used for other capital priorities.
Attachment 1 also lists three active projects that were set up as reserves. The available funds
identified with these three projects total . The intent is to close these projects and
move the funds to the newly established County Capital Reserve Fund for future County needs.
Attachment 1 also lists three active projects that are not yet complete and will remain active for
their identified purposes. The available funds identified with these three projects of
were volunteered by the Department of Environment, Agriculture, Parks and Recreation
(DEAPR) to assist balancing the County's annual budget without further reductions in programs
FINANCIAL IMPACT: The closing of 16 projects and transferring $825,000 from existing
projects to the Capital Projects Fund Balance will make $1,786,485 available for future County
Capital Needs. When combined with the action taken by the BOCC on May 18 to close 26
completed projects, a total of $2,032,045 will be available to meet County Capital needs.
RECOMMENDATION(S): The Manager recommends the Board approve the closing of 16
projects with total available funds of $961,485 and the transfer of $825,000 from existing
projects to the Capital Projects Fund Balance as listed on Attachments 1.
Attachment I
Fund 61 County Capital
Projects With Available Balances
Subtotal
Reserve Projects with Balances
30024 Capital Repairs Reserve FY 07/08 $ 58,445.16
30025 Facilities Art Reserve FY 09/10 $ 3,310.00
30036 Library Task Force FY 08/09 $ 50,000.00
Subtotal
Active Projects From ERCD & Parks
20011 Lands Legacy $ 450,000
20003 Twin Creeks Park $ 300,000
20030 Central Recreation $ 75,000
Subtotal
Funds Available from Projects TOTAL $ 1,786,485.52
Available
Project
Last
Last Budget
Balance
Number Name
Activity
Amendment
6/1/2010
10004 Court Street Annex
6/30/2008
FY 08/09
$
122,852.69
10010 Historic Courthouse
2/6/2009
FY 08/09
$
58,787.52
10015 New Courthouse
8/7/2007
FY 06/07
$
89,202.97
10027 Southern Human Services
9/29/2008
FY 06/07
$
4,729.35
10030 Dickson House
None
FY 08/09
$
12,500.00
10033 Parks Operations
11/18/2008
FY 05/06
$
38,250.00
10044 Animal Ser Deconstruct
10/16/2009
FY 09/10
$
7,000.00
10049 Whitted HSC Renovations
None
FY 09/10
$
150,000.00
20001 Cate Property
11110/2009
FY 05/06
$
22,063.91
20027 New Hope Creek Pres
6/16/2009
FY 09/10
$
18,741.50
30013 Emergency Power
6/30/2007
FY 06/07
$
81,014.02
30015 Solid Waste Collection Ctrs
6/30/2008
FY 07/08
$
111,301.40
30029 Parking Lot Repairs
6/30/2009
FY 06/07
$
133,287.00
Subtotal
Reserve Projects with Balances
30024 Capital Repairs Reserve FY 07/08 $ 58,445.16
30025 Facilities Art Reserve FY 09/10 $ 3,310.00
30036 Library Task Force FY 08/09 $ 50,000.00
Subtotal
Active Projects From ERCD & Parks
20011 Lands Legacy $ 450,000
20003 Twin Creeks Park $ 300,000
20030 Central Recreation $ 75,000
Subtotal
Funds Available from Projects TOTAL $ 1,786,485.52
C7
•
•
County Capital Investment Plan
Descriptions of Projects
Court Street Annex Renovations
Pay as you Go
Arch- z
Total County Project Budget $250,000
$250,000
Repair the electrical, exterior waterproofing and up fit associated with departmental moves in
accordance with the County's space plan implementation.
Historic Courthouse Repairs Total County Project Budget $215,000
Pay as you Go $215,000
Repair the flagstone sidewalk surrounding the County's Historic Courthouse, repair exterior
brick, repair clock tower, and to resurface the concrete floors on the ground level of the interior.
New Courthouse
Pay as you Go
2004 2/3's Bonds
Total County Project Budget $357,961
$167,961
$190,000
Repair the flagstone sidewalk surrounding the County's Historic Courthouse, repair exterior
brick, repair clock tower, and to resurface the concrete floors on the ground level of the interior.
Southern Human Services Center Total County Project Budget $50,000
Transfer from General Fund $50,000
This phase of the project will begin in fiscal year 2004 -05. The project will refurbishment the
interior of the house on the property including updating and expanding restrooms.
Dickson House
Transfer from General Fund
Total County Project Budget $12,500
$12,500
To continue the refurbishment and upkeep of the Dickson House, reglazing of the windows and
realignment of the gutters is needed. The painting of structure would be covered in the
countywide Painting Project.
Parks Operations Base
2004 2/3 "s Bonds
Total County Project Budget $230,000
$230,000
The Valley Forge Road facility, previously occupied by Orange Enterprises is being vacated.
The 2005 Space Needs Update recommends that the facility be up fit and utilized as office
space for the Recreation Administrative office function as well as the Parks Operations Base.
Funding for this project allows up fit of the interior for the two functions, as well as site work that
will allow some outside storage of materials needed at various park facilities (mulch, gravel,
etc). Funding will also allow the connection of the building to nearby sanitary sewer facilities
and the existing septic system abandoned.
County Capital Investment Plan
Descriptions of Projects
Animal Service Deconstruct
Transfer from General Fund
Total County Project Budget $50,000
$50,000
Project is to fund the deconstruction of the old Animal Services Facility.
Whitted Renovations — Health Dept
Transfer from General Fund
Medicaid Cost Settlement
Total County Project Budget $400,000
$150,000
$250,000
This project is to make reasonable renovations space in the Whitted building, vacated by Social
Services, for the Health Department.
Cate Farm
1997 Bonds
2004 2/3 "s Bonds
Payment in Lieu
Transfer from School Parks Reserve
Total County Project Budget $3,675,000
$2,700,000
125,000
50,000
Orange County acquired this property, also listed as Twin Creeks Park (Moniese Nomp), in
2001 for a County park and a joint educational campus with Chapel Hill- Carrboro City Schools.
The existing farmstead for this old dairy still exists. Structures include a 1929 farmhouse, a
large barn and silo, a granary and other outbuildings. Some of the structures are in need of
immediate stabilization, and others need intermediate and long -term restoration to enable the
County to utilize the structures as part of the park. Stabilization involves completing immediate
repairs to ensure the buildings are structurally sound and weatherproof, such as repairing
structural members, securing siding and reattaching and painting tin roofs, among others.
New Hope Creek Preserve Total County Project Budget $317,424
Grants $173,459
2001 Bonds $143,965
Acquisitions and master plan work for the New Hope Creek Preserve.
Emergency Power Sources
Transfer from General Fund
Total County Project Budget $282,000
$282,000
In recent years, Orange County has experienced a significant number of widespread electrical
power outages, generally as the result of adverse weather. Certain key County facilities,
particularly the Emergency Operations Center and related Emergency Management Department
offices, have backup generators installed that provide for a seamless transfer of the power load
and continuous operations in the event of electrical power failures. Others can receive
2
•
•
•
County Capital Investment Plan
Descriptions of Projects
• generator power through manual transfer switches. However, recent experience has been that
because not all County buildings have backup power sources, many important County services
come to a virtual halt under adverse weather conditions and their immediate aftermath. In early
2003, the BOCC encouraged the Manager and staff to consider including funding for some
emergency generators in the 2003 -2013 Capital Investment Plan.
is
•
Solid Waste Convenience Centers Total County Project Budget $290,000
Transfer from General Fund $290,000
The replacement of routine fencing and signage at convenience sites is included in the early
years of this project plan. Future years allow for the replacement of waste containers and the
installation of concrete pads, barriers and driveways. Baseline funding for this project would not
allow for the potential cost to purchase currently leased sites.
Parking Lot Repairs /Paving Total County Project Budget $240,000
Transfer from General Fund $240,000
Parking lot improvements (including paving) for County facilities are included in the funds for
this project. Funding in FY 2005 -06 provides for paving a portion of Whitted complex parking
lots. Additional parking areas that would be addressed in future years are dependent on the
amount of funding available.
Capital Repairs /Replacement (Emergency)
Reserve Fund
Transfer from General Fund
Total County Project Budget $75,000
$75,000
These reserve funds would enable Public Works to address major system /component needs,
abatement, and other projects that may arise after budget is adopted. Examples of instances in
which these funds would have been used in previous years include a new water heater at the
Jail and HVAC repairs at other facilities.
County Facilities Art Reserve
Transfer from General Fund
Total County Project Budget $25,000
$25,000
In keeping with Orange County's commitment to the Arts, funding of this project would create a
reserve fund from which the BOCC would allocate monies to construction and renovation
projects for approved art projects in County facilities
Reserve for Library Task Force Total County Project Budget $50,000
Transfer from General Fund $50,000
Funds set aside in this project will allow Commissioners to address countywide Library needs
identified by the recently completed Library Services Task Force Report.
3
County Capital Investment Plan
Descriptions of Projects
Lands Legacy Total County Project Budget $17,854,577 •
The Lands Legacy program, adopted in April 2000, seeks to identify and acquire the County's
highest - priority natural and cultural resource lands, and land -bank appropriate sites for future parks
and open space. Since inception, the Lands Legacy program has become nationally and State -
recognized and has protected 1,600 acres of natural and cultural resource lands or future parkland.
During its initial years, funding for the Lands Legacy program consisted of pay -as- you -go funding.
In 2001, voters approved $7.0 million in bonds for the Lands Legacy program. Additional funding for
the project include $300,000 in 2004 two- thirds net debt reduction bonds in fiscal year 2004 -05 and
pay -as- you -go beginning in fiscal year 2005 -06 throughout the Capital Investment Plan period.
Additional funds of $3 million are included in the Conservation Easements Capital Project to obtain
conservation easements and other sensitive lands that may not be open to public access (and
thereby not available for bond funding).
Lands Legacy acquisitions are identified and negotiated through the biennial Lands Legacy Action
Plan, and as opportunities arise and as landowners are willing to sell. Target areas for Lands Legacy
in coming years include continuing to acquire lands for future park sites, the creation of nature
preserves, protection of identified Natural Heritage sites and prime forest lands, acquisition of
farmland conservation easements, and preservation of critical cultural, scenic and archaeological
sites. The County can also use pay -as- you -go funds for Lands Legacy to leverage grant funds from
a variety of State and federal sources. The County has leveraged $3.7 million in grant funds to date
by using local funds as a match.
Identification of lands and negotiation for purchase will be ongoing throughout the CIP period, based
on willing sellers and available funds. The County will continue to seek partnerships with other land
trusts, such as Triangle Land Conservancy, and other local governments and OWASA, as well State •
and Federal programs.
Twin Creeks Park Total County Project Budget $1,850,000
(Formerly Known as Chapel Hill Township District Park)
In 2001, the County purchased 193 acres of land located near the intersection of Old Highway 86
and Eubanks Road for the Chapel Hill Township Park and Educational Campus. Proposed plans for
the site included co- locating the Chapel Hill Township District Park (identified in the adopted 1988
Parks Plan) with Chapel Hill - Carrboro School District Elementary School #10 and other potential
future school facilities. Both projects were included in the November 2001 voter approved bond
referenda.
Park related bonds for the Park (Phase 1) total $1.2 million. In June 2005, the Board allocated an
additional $650,000 from the Soccer Superfund for this project (which includes soccer fields). In
2002 -03, a Master Plan Work Group developed a Master Plan for the site, which identified a 96 -acre
site for the park. Tentative park facilities in Phase I include lighted playing fields, nature trails and a
picnic area surrounding an existing pond. The total 96 -acre park may include as many as four
phases. The completed park would also include renovations to the existing historic farmstead house
and barn located on the property (funds for stabilization and weatherproofing only have been
budgeted to date).
A master plan for the site was approved in May 2005. Discussions with the Town of Carrboro were
held in fall of 2005 regarding the approval process, and on February 7 the Town Board received a
courtesy review of the master plan. A Conditional Use Permit application to the Town of Carrboro
would be prepared in conjunction with detailed engineering work, and is planned to be accomplished
in conjunction with like plans for Northern Park. This work should allow for the CUP application to be •
4
County Capital Investment Plan
Descriptions of Projects
• submitted to the Town in early 2007(Town review and approval expected to take twelve months).
Construction of Phase I of the park would begin thereafter, with completion anticipated in late 2009.
•
Central Recreation Repairs Total County Project Budget $523,940
2004 2/3 "s Bonds $523,940
The Central Recreation facility, located at the Whitted Human Services Center in Hillsborough,
was constructed around 1950. The facility was a school for the Orange County School district.
Major renovations occurred during the early 1980's when the County originally obtained the
property. Since that time, the County has updated other systems within the building (such as
HVAC), however, there is an immediate need to repair public restrooms to address accessibility
issues, to add hot water service in restrooms and to insulate some offices located on the lower
level of the building. The projected cost of this work totals $235,000 and would be funded with
proceeds from the 2004 two- thirds net debt reduction bonds. In fiscal year 2005 -06, pay -as-
you-go funding would allow for replacement of the gymnasium window system. Estimated
project costs for the window system totals $150,000. All of the components of this project would
improve functionality of the facility for citizens as well as address energy conservation.