SUBJECT: Chapel Hill Parks and Recreation Commission — Northern Community Park
DEPARTMENT: Manager PUBLIC HEARING: (Y/N)
BUDGET AMENDMENT: (Y/N )
ATTACHMENT(S):
10/5/98 Mayor Waldorf Letter
Project Summary
INFORMATION CONTACT:
Albert Kittrell, ext 2300
TELEPHONE NUMBERS:
Hillsborough 732 -8181
Chapel Hill 968 -4501
Durham 688 -7331
Mebane 336- 227 -2031
PURPOSE: To receive a report from the Chapel Hill Parks and Recreation Commission concerning the
development of the Town's Northern Community Park.
BACKGROUND: Funds were included in the successful November 1997 County bond referendum to
assist in the development of the Town of Chapel Hill's Northern Community Park. Earlier this year, the
Board of Commissioners conveyed to the Chapel Hill Town Council the County's desire that it be
included in the planning for this project, and the Southern Community Park project which will follow.
Representatives of Chapel Hill Parks and Recreation will make a presentation and respond to the Board's
questions about the Northern Community Park.
RECOMMENDATION(S): The Manager recommends that the Board receive the report for information
only at this time.
N
S f
` CAE
TOWN of CHAPEL HILL
306 NORTH COLUMBIA STREET
CHAPEL HILL, NORTH CAROLINA 27516
OFFtcB op rim MAYOR
October 5, 1998
Ms, Margaret Brown
Chair
Orange County Board of Commissioners
1509 Smith Level Road -
Chapel Hill, NC 27516
Dear Margaret:
(919) 968 -2714
FAX (919) 967 -8406
2
On September 28 the Council voted to fund abatting cage for the Northern Community Park,
using our bond funds, and to initiate a conceptual study for the final phase of the park. We
continue to support strongly an indoor swimming pool on that site, consistent with the way the
1996 bonds were promoted to the citizens. The study will explore different pool options and non-
pool uses that might be accommodated in a community center -type building.
Our Parks and Recreation Commission would like to schedule a presentation to the
commissioners on the Northern Community Park, to give you a good picture of the progress to
date and solicit the commissioners' questions and ideas about the next phase. Dan Costa, Chair of
the Parks and Recreation Commission, will be in touch to schedu8le this presentation to your
board.
We are very excited about this park, and believe it will be a great resource for the citizens.
Sincerely,
Rosemary I. Waldorf
CC: Orange County Commissioners
Dan Costa
Council Members
NORTHERN COMMUNITY PARK PROJECT
The project was begun in 1990 when the site was purchased. The park is located off
Airport Road and Homestead Road and encompasses almost exactly 40 acres.
Council approved an initial conceptual plan in 1993. Council approved a site plan in
1994.
Funding has come from a variety of sources: Town 1989 park bond funds, Town 1996
park bond funds, County 1997 park bond funds, and Capital Improvement Project funds.
The project, as is currently approved and funded, is $4,578,000. This includes $250,00 in
design and engineering; $35,000 in land purchase (beyond initial purchase); and
approximately $30,000 in OWASA tap fees. The site has been very grading intensive.
The basic infrastructure of the park should be completed by the end of 1998. At that
point, the park will contain an outdoor basketball court and a picnic area ready to use.
Two 300' softball fields and 2 full size soccer fields —all lighted and irrigated —have
been developed and should be ready for use in the fall, 1999. The turf has not been
determined —still considering sodding or seeding. All roads, paths, utilities, etc. have
been installed for the park. The concession/shelter by the skateboard facility should be
completed by the end of 1998.
What's left to do?
Skateboard Facility:
The main slab has been poured. A Skateboard Design Committee (comprised of
community youth and adult skateboarders and staff) has been working with a planner to
develop a site plan. There is a budget for $60,000. Staff expects the facility construction
to be completed by spring, 1999.
Playground:
The playground facility has been put out to bid. The bids will be opened December 15,
1998. A committee of citizens has been formed to review proposals. $60,000 is
budgeted for the project. Staff anticipates construction during the winter /spring, 1999 to
be completed by late spring /early summer, 1999.
Batting Cage Facility:
At its September 28, 1998 Council adopted allocated $200,000 in Town park bonds all
for development of batting cage project. Staff is currently working with the architectural
firm that designed the park to develop a conceptual plan for the batting cage. The next
step will be engineering drawings then the Town will go out on bid for construction. At
the current schedule, staff anticipates the batting facility to be ready for public use in
early fall, 1999.
Aquatic Facility /Community Center:
At its September 28, 1998 Council appropriated $53,000 from FY98 -99 budget for
conceptual plan process of aquatic facility /community center. Staff anticipates
3
4
developing a bid process for conceptual plans in early, 1999. Cost estimates for the
building are approximately $3.5 to $4 million. Currently there is not sufficient funding to
complete the project. Current remaining money is approximately $2,055,000 ($1.2
million in 1996 Town park bonds and $855,000 in 1997 County park bonds allocated for
Northern Community Park).
At its August 24, 1998 meeting the Chapel Hill Town Council adopted a recommended
timetable for use of $2,000,000 in funds from the 1997 Orange County parks bonds. The
adopted schedule is:
YEAR
AMOUNT
SCHEDULE OF TOWN NEED FOR FUNDS
1998
$145,000
Construction of concession/restroom building at Northern
Community Park
1999
$205,000
School soccer field at Southern Village ($105,000) and Southern
Community Park conceptual plan/construction drawings
($100,000)
2001
$795,000
Construction of Phase I of Southern Community Park
2002
$855,000
Construction at Northern Community Park .
Future Development of Southern Community Park
No Council decisions have been made at this point, except soccer field at school. The
field will be available for use in the fall, 1999 and will be fully lighted and irrigated.
There is no conceptual plan for the remainder of the park at this point.
' County Corn Meeting
12/15/98
DL Costa — P &R Chair
NORTHERN COMMUNITY PARK PROJECT
The Northern Community Park is located off Airport Road and Homestead Road and
encompasses almost exactly 40 acres of land north of the Duke Power Headquarters
Facility. This is beautiful area which in the park design has preserved much of the
natural foliage and the flowing stream cutting through the site. The project was begun in
1990 when the site was purchased from the Maddry family. The Chapel Hill Town
Council approved an initial conceptual plan in 1993 and approved the site plan in 1994.
So far a total of $5,649,000 has been allocated or pledged toward the current project.
- $2,147,000 in 1989 park bonds
- $100,000 in Town Capital Improvement Program (CIP) funds
- $3,257,000 in Town 1996 park bond funds
- $145,000 in Orange County 1997 park bond funds for the
restroom/concession building
Funds have been used for the following general purposes:
- $250,000 for design and engineering fees
- $1,115,000 for land purchase
- $30,000 for OWASA fees
- $4,054,000 for construction and misc. fees such as legal and construction
administration
- $200,000 in current contingency fund
Current Schedule
The site required extensive grading and was delayed last winter due to extreme wet and
mud conditions. Construction progress has improved tremendously since the onset of dry
conditions this past summer.
The basic infrastructure of the park should be completed by the end of 1998. At that
point, the park will contain:
- an outdoor basketball court with 2 hoops
- a picnic area of 5 outdoor tables and a covered picnic shelter with 4 tables
- trails and sidewalks
- parking
- extension of Stateside Drive
County Corn Meeting
12/15/98
DL Costa — P &R Chair
What is there left to do? In 1999 the other park amenities currently approved by the
Council will come on line:
- In February -March the playground structure should be complete. The current
budget is $60,000 for playground equipment. Bids will be opened December
16, 1998 for the equipment and installation. Work should begin in January or
February.
- In April -May the skateboard park should be finished. At this time we have
completed the slab, fencing, and lights. The restroom/concession building is
almost finished. The skateboard committee has almost finished its work on
designing the ramps. Once a design has been completed we need to secure
insurance and then construct the ramps.
- In September two 300' softball fields and two full size soccer fields with
irrigation and lights should be ready for use. The approach to establishing
field turf has not been determined. The staff is still considering various
options such as sprigging, sodding and/or importation of additional soils.
- In October - November the batting cage complex should be complete. At its
September 28, 1998, meeting the Chapel Hill Town Council adopted the P &R
Commission's proposal for the allocation of $200,000 in Town park bonds
for development of batting cage project. Staff is currently working with the
architectural firm that designed the park to develop a conceptual plan for the
batting cage. The next step will be engineering drawings, which will be
followed by requests for construction bids.
Aquatic Facility /Community Center:
For several years citizens of the Town have requested expanded or new aquatic facilities
for public use. The 1996 bond of $5M was passed by the Town's citizens to provide for
the development of NCP, including the building of a community center and indoor pool.
The high bids on NCP, anticipated higher construction costs in the Triangle, and the need
to use some funds ($428 K) for the completion of Northside (Hargraves) Gym has left
insufficient funds from the bond to complete the pool and community center.
However, the Town Council and the P &R Commission are committed to fully develop
the NCP project. In fact, in an effort to get ahead of the process — having learned from the
Southern Village Gym proposal of 1996 - the P &R Commission has had initial
discussions with members of the CH- Carrboro School Committee and Superintendent
Neil Peterson to explore how we could better leverage P &R and school construction
funds to provide for mutual needs. Obvious areas of common interest are fields, and
facilities — notably, in our minds would be the aquatic facility. Without funding to
provide funds for pools at each high school, the teams are in need of practice pool-
time ... right now provided by P &R at the Estes Rd. CC. Perhaps, joint efforts in the future
can be productive for the schools and community at large.
For the moment... at its September 28, 1998, meeting the Town Council appropriated
$53,000 from FY98 -99 budget for a conceptual plan process for an aquatic
facility /community center. Staff anticipates developing a bid process for conceptual
t
County Corn Meeting
12/15/98
DL Costa — P &R Chair
What is there left to do? In 1999 the other park amenities currently approved by the
Council will come on line:
- In February -March the playground structure should be complete. The current
budget is $60,000 for playground equipment. Bids will be opened December
16, 1998 for the equipment and installation. Work should begin in January or
February.
- In April -May the skateboard park should be finished. At this time we have
completed the slab, fencing, and lights. The restroom/concession building is
almost finished. The skateboard committee has almost finished its work on
designing the ramps. Once a design has been completed we need to secure
insurance and then construct the ramps.
- In September two 300' softball fields and two full size soccer fields with
irrigation and lights should be ready for use. The approach to establishing
field turf has not been determined. The staff is still considering various
options such as sprigging, sodding and/or importation of additional soils.
- In October - November the batting cage complex should be complete. At its
September 28, 1998, meeting the Chapel Hill Town Council adopted the P &R
Commission's proposal for the allocation of $200,000 in Town park bonds
for development of batting cage project. Staff is currently working with the
architectural firm that designed the park to develop a conceptual plan for the
batting cage. The next step will be engineering drawings, which will be
followed by requests for construction bids.
Aquatic Facility /Community Center:
For several years citizens of the Town have requested expanded or new aquatic facilities
for public use. The 1996 bond of $5M was passed by the Town's citizens to provide for
the development of NCP, including the building of a community center and indoor pool.
The high bids on NCP, anticipated higher construction costs in the Triangle, and the need
to use some funds ($428 K) for the completion of Northside (Hargraves) Gym has left
insufficient funds from the bond to complete the pool and community center.
However, the Town Council and the P &R Commission are committed to fully develop
the NCP project. In fact, in an effort to get ahead of the process — having learned from the
Southern Village Gym proposal of 1996 - the P &R Commission has had initial
discussions with members of the CH- Carrboro School Committee and Superintendent
Neil Peterson to explore how we could better leverage P &R and school construction
funds to provide for mutual needs. Obvious areas of common interest are fields, and
facilities — notably, in our minds would be the aquatic facility. Without funding to
provide funds for pools at each high school, the teams are in need of practice pool -
time...right now provided by P &R at the Estes Rd. CC. Perhaps, joint efforts in the future
can be productive for the schools and community at large.
For the moment ... at its September 28, 1998, meeting the Town Council appropriated
$53,000 from FY98 -99 budget for a conceptual plan process for an aquatic
facility /community center. Staff anticipates developing a bid process for conceptual
' County Corn Meeting
12/15/98
DL Costa — P &R Chair
plans in early1999. Cost estimates for the building are approximately $3.5 to $4 million.
Currently there is not sufficient funding to complete the project. Current remaining funds
total approximately $2,055,000. These include:
- $1.2 million in 1996 Town park bonds
- $855,000 in 1997 County park bonds allocated for Northern Community Park
Alternative funding is being explored by Town staff under direction of Council (2/3 rule
and lease installment plan).
At its August 24, 1998 meeting the Chapel Hill Town Council adopted a recommended
timetable for use of $2,000,000 in funds from the 1997 Orange County parks bonds. The
adopted schedule is:
YEAR
AMOUNT
SCHEDULE OF TOWN NEED FOR FUNDS
1998
$145,000
Construction of concession/restroom building at Northern
Community Park
1999
$205,000
School soccer field at Southern Village ($105,000) and Southern
Community Park conceptual plan/construction drawings
($100,000)
2001
$795,000
Construction of Phase I of Southern Community Park
2002
$855,000
Construction at Northern Community Park
Future Development of Southern Community Par
No Council decisions have been made at this point, except for the soccer field at the
school. The field will be available for use in the fall, 1999 and will be fully lighted and
irrigated. There is no conceptual plan for the remainder of the park at this point.