HomeMy WebLinkAboutAgenda - 02-02-1999 - 9e1ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: February 2, 1999
Action Agenda
Item #
SUBJECT: Additional Funding for Process to Determine Whether to Challenge the Nuclear Regulatory
Commission Staff s proposed fording of "No Significant Additional Hazard" for Storage
of Waste Nuclear Fuel Rods at Shearon Harris Nuclear Power Plant
DEPARTMENT: County Manager
ATTACHMENT(S):
PUBLIC HEARING: Yes x No
BUDGET AMENDMENT: Yes x No
INFORMATION CONTACT:
County Engineer Extension 2303
TELEPHONE NUMBERS:
Hillsborough - 732-8181
Durham - 688-7331
Mebane - 227-2031
Chapel Hill - 967-9251/968-4501
PURPOSE: To present for BOCC review and discussion a proposition that the Board authorize the
expenditure of an additional $1500 in legal fees to determine whether to challenge the NRC staff's
proposed finding of "No Significant Additional Hazard" for CP&L's proposal to expand its high level
nuclear waste storage operation for used nuclear fuel rods at the Shearon Harris nuclear power plant.
BACKGROUND: CP&L has submitted an application, with accompanying technical documentation,
to the Nuclear Regulatory Commission (NRC) as necessary to obtain a modification to the Shearon
Harris plant's existing operating permit allowing it to expand its storage capacity for spent nuclear fuels
rods by: a) completing construction of two existing but incomplete temporary storage pools for spend
fuel rods; and b) re-racking the spent fuels rods into a more densely packed configuration. NRC staff
has completed a preliminary review of the documentation submitted and has proposed to make a finding
that the CP&L proposal entails "No Significant Additional Hazard" to the level of hazard inherent in
CP&L currently permitted operations. Orange County is currently involved in a process to evaluate: 1)
CP&L's proposals for expanding its spent fuel rod storage capacity; and 2) the need for the County to
formally intervene in the NRC's permitting process. The County has engaged the services of technical
and legal consultants to evaluate the CP&L proposals and to prepare documentation for a possible
formal intervention in the NRC permitting process.
The County's legal consultant, Diane Curran, has advised County staff that the NRC permitting process
may allow CP&L to proceed with its proposed expansion and re-racking activities and construction
during a public hearing process generated by a successful intervention. If the County did decide to
intervene and did intervene successfully, it would also have to challenge the proposed finding of "No
Significant Additional Hazard" to ensure that CP&L not be allowed to initiate re-racking and pool
construction activities during the public hearing process. In the event that the work being done by
Gordon Thompson does provide the technical basis for intervening in the permitting process, his work
will also provide the technical basis for challenging the finding of "No Significant Additional Hazard".
However, there would be approximately $1500 in additional legal costs involved in filing and
coordinating the documentation for the challenge. The BOCC's currently approved level of funding for
technical and legal consulting work does not include any funds to challenge the proposed finding of "No
Significant Additional Hazard". All of the work, both technical and legal, for the intervention and the
challenge can be accomplished simultaneously. The information for the intervention and the challenge
would be ready for review by the BOCC atd its February 9, 1999 deliberation on either proceeding with
or terminating the intervention effort.
RECOMMENDATION: As the Board decides. Should the Board decide to proceed with the legal
work necessary to file a challenge to the proposed fmding of "no significant
additional hazard", the Manager recommends that the funding again be
provided through the Commissioners' Contingency account.
NOTE: The Town of Chapel Hill has determined that it will provide $5000 in funding toward the
costs of evaluating and developing the technical and legal basis for intervening in the Shearon
Harris permitting process. Durham County has also determined that it will provide $5000 in
funding to the process, subject to the positive recommendation of its Environmental Affairs
Board.
ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date:
D~aC~~ 4~t
Action Agenda
Item #
SUBJECT: Funding for process to obtain standing with the Nuclear Regulatory Commission in
the permitting process for expanded storage of waste nuclear fuel rods at Shearon Harris
nuclear power plant
DEPARTMENT: County Manager PUBLIC HEARING: Yes No
ATTACHMENT(S):
County Engineer's memo
WAIS Document Retrieval from Federal
Register for 1/13/99
BUDGET AMENDMENT: Yes No
INFORMATION CONTACT:
County Engineer Extension 2303
TELEPHONE NUMBERS:
Hillsborough - 732-8181
Durham - 688-7331
Mebane - 227-2031
Chapel Hill - 967-9251/968-4501
PURPOSE: To present for BOCC review a report on: 1) the process required to obtain the standing
required to intervene in the Nuclear Regulatory Commission (NRC) proceedings for. the
review and approval of Carolina Power and Light's (CP&L) application to amend its
operating permit to allow it to expand its high level nuclear waste storage operation for
used nuclear fuel rods at its Shearon Harris nuclear power plant; and 2) the cost of funding
the legal and engineering/technical consulting services necessary to review the CP& L
waste storage expansion proposal and permit application and create and file the documents
with the NRC as necessary to obtain standing.
BACKGROUND: CP&L's has proposed to use its existing operational and partially constructed
temporary waste storage pools at its Shearon Harris facility to store spent nuclear
fuel rods from the Harris facility as well as it own Brunswick and Robinson nuclear
power plants. To carry out this strategy, two existing but incomplete pools at the
plant must be completed. This, in turn, requires that CP&L submit an application to
modify the Harris operating permit to the NRC.
In accordance with standard NRC procedures, the permit modification application
has been submitted; NRC staff have proposed to make a fording that CP&L's
expansion plans represent no significant h~.~.ard; and the NRC has published the
notice of the application and the proposed staff finding - as of January 13, 1999 - in
the Federal Register. The public, again in accordance with standard NRC
DaQff~
procedures, is accorded a thirty day period in which to make comments to the NRC
relative to the NRC staff finding, permit application and approval. For the Harris
application, the comment deadline is February 12, 1999.
The NRC's process for providing comment relative to permit and permit
modification applications is complex and appears to be designed to inhibit or
preclude public participation in its review and approval process. The public input
process requires that any concerned party submit comments or contentions to the
NRC as to perceived inadequacies in the NRC staff finding, permit application or
activity being permitted. The NRC staff reviews both the contentions and the
credentials or particulazs of the party making the contentions. If the staff deems that
the contentions may have validity and that the party making the contentions has a
legitimate or valid claim to being affected by the permitted activity, that party is
deemed to have the "standing" necessary to participate or intervene in the
application comment and review process. The fact that a party is deemed to have
standing and has submitted valid or potentially valid contentions does not
necessarily mean that the permit applicant will have to abandon or modify its plan.
The NRC may ultimately require that the applicant submit additional information or
it may deem that the contentions aze, in the final analysis, invalid. The NRC can
and does issue permits over the objections of all parties deemed to have standing.
Those parties may then appeal the NRC decision in the federal judicial system. It
does appear, however, that any parry having concerns about or objections to the
activity being permitted must get or have attempted to acquire standing before the
NRC to preserve or establish its right to appeal NRC decisions.
If Orange County wishes to intervene in the permitting process by establishing
standing before the NRC or preserve its right to a judicial appeal of an NRC
decision regazding the CP&L permit application, it must act immediately. The
County must fund and acquire the technical and legal assistance to evaluate CP&L's
proposal and permit application and to file the documents necessary to make
contentions and establish standing with the NRC. The estimated cost of these
consulting and legal services ranges between $12,000 and $18,000. While it may
ultimately be possible to convince other concerned local jurisdictions to fund a
portion of these costs, the comment period time frame is too short to allow for the
necessary intergovernmental consultations and legislative action and still complete
the consulting work.
RECOMMENDATION: As the Board decides.
MEMORANDUM .
TO: County Commissioners
John Link, County Manager
FROM: Paul Thames, PE, County Engine
DATE: January 15, 1999
SUBJECT: Process for obtaining standing with the Nuclear Regulatory Commission in the
proceedings for the permitting of expanded storage of waste nuclear fuel rods at Shearon
Harris nuclear power plant
The federal government's failure to provide permanent storage facilities for the high level radioactive
waste, in the form of spent fuel rods, produced by this county's nuclear power plants has caused a
number of problems for the nuclear power industry. The industry has faced a particularly serious
problem in finding or developing "temporary" storage facilities for spent fuels rods. Such storage is
designated as temporary because, although the period of storage may be measured in years or decades,
the federal government still responsible for providing permanent storage for this material. The answer
for many power companies has been to utilize waste storage technologies designed and developed for
short term storage as stopgap measures for a much longer term, though not permanent, waste storage
problem.
CP&L's Shearon Harris nuclear power plant, located in Chatham County, has been storing its waste on
site for a number of years in its existing temporary storage pools. These facilities were designed to store
the materials for the relatively short period of time between removal of the material from the reactor core
and its shipment to permanent storage. The Shearon Harris temporary storage pool facilities have also
been used to store the spent fuel rods from CP&L's nuclear plants at Brunswick, NC, and Robinson, SC.
Consequently, the storage capacity of the existing facilities at Shearon Harris has been nearly exhausted.
CP&L has now proposed to expand the capacity of Shearon Harris facilities to accommodate additional
waste storage by completing the construction of two temporary storage pools begun nearly twenty years
ago but left uncompleted when the overall capacity of the generating facility -and projected need for
temporary storage -was reduced.
CP&L has submitted an application to amend its operating permit (to allow the expansion of its
temporary storage facilities) to the NRC. NRC staff have reviewed the application and propose to make
a finding that the CP&L expansion plan represents no significant increase in hazard over that of
currently permitted and approved operational practices. In accordance with standard NRC procedures,
the notice of the application and the proposed staff fmding of no significant hazard has been published -
as of January 13, 1999 - in the Federal Register. The public, again in accordance with standard NRC
procedures, is according a thirty day period in which to make comments to the NRC relative to the
proposed NRC staff finding of no significant increase in hazard and the permit application and approval.
The deadline for public comment is February 12, 1999.
Various local individuals, organizations and governments, including Orange County, have expressed
reservations about these existing and proposed nuclear waste storage practices and plans. Furthermore,.
these same individuals and entities have expressed concern about the lack of and process for the
providing of public input into the regulatory approval procedures. Some individuals and organizations
have advocated opening a dialogue with CP&L to create the opportunity to have technical concerns
addressed and to provide public scrutiny into the planning, permitting and operational process. CP&L's
participation in any such dialogue is strictly voluntary. It is required only to conform to NRC standards,
policies and procedures. In the event that the process of voluntary dialogue fails, only the federal
regulatory and judicial processes are available to address unresolved issues.
The NRC's process for providing comment relative to permit and permit modification applications is
complex and appears to be designed to discourage, inhibit or preclude public participation in its review
and approval process. The comment process requires that a concerned party submit comments or
contentions to the NRC relative to inadequacies in NRC staff findings, the permit application or
problems with the activity or action being permitted. The NRC staff reviews both the contentions and
the credentials or particulars of the party making the contentions. If the staff deems that the contentions
may have potential validity and that the party making the contentions has a legitimate or valid claim to
being affected by the permitted activity, the party is deemed to have the "standing" necessary to
participate in the permitting comment and review process. The fact that a party is deemed to have
standing or have submitted valid or potentially valid contentions does not mean that the permit applicant
will be forced to abandon or modify its plan. The NRC may ultimately require that the applicant submit
additional information or it may deem that the contentions have been addressed adequately. The NRC
may issue the permit over the objections of any and all parties deemed to have standing. Those parties
may then appeal the NRC decision in the federal judicial system. It does appear, however, that any party
having concerns about or objections to the activity being permitted must get or have attempted to get
standing before the NRC to preserve or establish its right to appeal NRC decisions.
If Orange County wishes to intervene in the permitting process by establishing standing before the NRC
or by judicial appeal of an NRC decision relative to the CP&L permit application, it must act
immediately to fund and acquire technical and legal assistance. The technical and legal consultants will
evaluate the NRC staff finding, the CP&L proposal and the permit application materials. They will
work together to develop and evaluate contentions to be submitted to the NRC and will handle the
process to establish standing for Orange County. The cost of this consultation and activity is estimated
to be between $12,000 and $18,000. It may be possible to convince other concerned local jurisdictions
to ultimately fund some of these costs. However, the comment period time frame is so short and the
consultants' work so time consuming as to preclude efforts to coordinate the legislative actions required
to obtain such funding commitments prior to beginning the work.
Other than the obvious financial issues, there are additional potential implications to an Orange County
action to intervene in the permitting process. CP&L may be alienated or threatened by County
intervention activity to the point that it withdraws from any voluntary public discussion and input
activities. Conversely, the intervention may provide leverage necessary to convince CP&L to
participate in a voluntary discussion and public input process. At this time, no one -including County
staff -has knowledge or information sufficient to predict a CP&L reaction to a County or local
government attempt to become formally involved in the actual NRC permit approval process.
If I may provide additional information, please advise.
Health and Economic Consequences of Accidents
from High-Level Nuclear Waste Storage
The following is a summary of key points from a 1997 study performed for the U.S. Nuclear
Regulatory Commission by the Brookhaven National Laboratories (BNL). The BNL study
describes various types of serious accidents that can occur in High-Level nuclear waste
storage pools. _
- The largest accidents considered in the BNL study could kill approximately 100 people
immediately, cause 140,000 cancer deaths, contaminate over 1.5 million acres of
farmland so badly that it could never be decontaminated, and cause over 500 billion in
.property damage not including costs of health damage.
- Even a much smaller accident involving leaks from only 700 to 1,700 fuel assemblies
could cause nearly 20,000 cancer deaths, cause $25 billion in property damage off-site
from the plant while permanently contaminating up to 16,000•acres of farmland.
CP&L proposes a total of over 8,000 fuel assemblies at Shearon Harris.
- Of the 8 most severe accidents studied by BNL, 4 would exceed $50 billion in off-site
property damage, 3 would exceed $100 billion, and 2 would exceed $200 billion with a
maximum of $566 billion of off-site property damages. ,
- Four of these accidents could force the abandonment of 100,000 acres of farmland or.
more, with a maximum of 1.7 million acres that would be too radioactive to ever clean
up; 4 accidents would also exceed 25,000 cancer deaths, 3 of which could exceed
50,000 deaths.
- By comparison, a severe meltdown of a nuclear unit considerably larger that Shearon
Harris would be expected to cause 88. to 160 quick deaths,'35,000 to 110,000 cancer
deaths and the loss of 1.3 million acres of farmland, according to a 1995 study also
conducted by Brookhaven National Laboratory. While that study did not estimate
economic damages from a meltdown, the largest numbers we know of range from $200
billion to over $300 billion - or about half as much as the most serious spent.fuel
accident that BNL reported in the 1997 study.
- Over the 27 years CP&L proposes to operate the expanded waste pools, the probability
of the most severe accident according to BNL would be about 1 in 18,000, which is 12
times higher than previous NRC estimates for a severe spent fuel accident.
Chernobyl had an estimated 1 in 10,000 chance of an accident by comparison.
- BNL estimates the probability of an accident causing nearly 20,000 cancer deaths
and $25 billion in property damage has a cumulative probability of about 1 in 125.
- independent scientists believe BNL may have underestimated the probabilities of
accidents.
- The BNL study did not consider worst case accidents. CP&L's plans would have more
than 3 times as much waste fuel in storage as considered by BNL. ,
: Jan 1999
Waste Awareness andAeductionNeiwork 919-490-0747 Fax 493-6614 NC-WARNC~POBOX.COM
NC WARN )~ FO Box 61051, Durham, NC 27715-1051
i
1
February 15, 1999
UNITED STATES OF AMERICA
NUCLEAR REGULATORY COMMISSION
BEFORE THE NRC STAFF
In the Matter of )
CAROLINA POWER & LIGHT ) Docket No. 50-400
(Shearon Harris Nuclear
Power Plant) )
DECLARATION OF DR. GORDON THOMPSON
I, Gordon Thompson, declare as follows:
A. Introduction
1. I am the executive director of the Institute for Resource and Security Studies (IRSS), a
nonprofit, tax-exempt corporation based in Massachusetts. Our office is located at 27
Ellsworth Avenue, Cambridge, MA 02139. IRSS was founded in 1984 to conduct technical
and policy analysis and public education, with the objective of promoting peace and
international security, efficient use of natural resources, and protection of the environment.
2. This Declaration pertains to an application by Carolina Power and Light (CP&L) for
an amendment to Facility Operating License No. NPF-63, which covers the Shearon
Hams nuclear power plant. The staff of the Nuclear Regulatory Commission (NRC) has
reviewed CP&L's application and proposes to determine that the amendment request
involves no significant hazards consideration. The NRC has sought public comments on
the proposed determination.l Through this Declaration, I offer comments on the NRC
staff s proposed determination. I have prepared these comments pursuant to an agreement
by IRSS to provide technical information and other. services to Orange County, North
Carolina.
B. My Professional Background
3. I received an undergraduate education in science and mechanical engineering at the
University of New South Wales, in Australia. Subsequently, I pursued graduate studies
at Oxford University and received from that institution a Doctorate of Philosophy in
mathematics in 1973, for analyses of plasmas undergoing thermonuclear fusion. During
my graduate studies I was associated with the fusion research program of the UK Atomic
Energy Authority.
4. During my professional career, I have performed technical and policy analyses on a
range of issues related to international security, energy supply, environmental
protection, and sustainable use of natural resources. Since 1977, a significant part of
my work has consisted of technical analyses of safety and environmental issues
related to nuclear facilities. These analyses have been sponsored by a variety of
nongovernmental organizations and local, state and national governments,
1 Federal Register: January 13, 1999 (Volume 64, Number 8), pages 2237-2241.
2
predominantly in North America and western Europe. Drawing upon these analyses,
I have provided expert testimony in legal and regulatory proceedings, and have served
on committees advising US government agencies. My CV is provided here as
Attachment A.
C. Scope of My Review
5. In prepazation of this Declaration, I reviewed the NRC's Federal Register notice for the
proposed license amendment, the Final Safety Analysis Report for the Sheazon Harris
Nuclear Power Plant, the Final Environmental Statement related to the operation of
Shearon Harris Nucleaz Power Plant, Units 1 and 2 (NUREG-0972, October 1983), and
CP&L's application for the proposed license amendment. I also reviewed various
correspondence and technical documents relating to the propose license amendment and
to risks of spent fuel storage, which aze identified below.
6. The information that has been provided by the NRC and CP&L to date does not
contain all of the detail that I would need to provide a complete, final statement about the
hazards associated with the proposed license amendment. I would expect to review the
full body of detailed evidence and present my final evaluation in the context of a hearing.
However, even the limited information provided so far is adequate to permit me to
identify serious safety concerns which preclude the NRC from making a "no significant
hazards" determination. These issues should be addressed through the systematic, public
process that a prior licensing hearing can provide.
D. The "No Significant Hazards" Standard
7. The NRC has stated its standard for determining that a license amendment request
involves no significant hazazds consideration.2 The standard is met if operation of the
facility in accordance with the proposed amendment would not: (1) involve a significant
increase in the probability or consequences of an accident previously evaluated; or (2)
create the possibility of a new or different kind of accident from any accident previously
evaluated; or (3) involve a significant reduction in a margin of safety.
8. In my professional opinion, based on the preliminary evidence provided by the NRC
and CP&L, operation of the Shearon Harris plant in accordance with the license
amendment proposed by CP&L will violate all three of the conditions set forth in the
preceding paragraph. Therefore, the NRC staff should reverse its position and should
determine that CP&L's license amendment request does not involve no significant
hazards consideration.
E. The License Amendment in Context -Spent Fuel Management at Harris
9. Before discussing my concerns about the safety implications of the proposed license
amendment, I provide here some background information about spent fuel management at
the Harris plant and CP&L's proposal to increase the spent fuel storage capacity at
Harris. Unless specified otherwise, the information presented here is drawn from CP&L's
license amendment application or from CP&L's Final Safety Analysis Report (FSAR) for
the Harris plant.
2 Ibid.
3
10. The Harris plant features one pressurized-water reactor (PWR). The core of this
reactor contains 157 fuel assemblies, with acenter-center distance of about 8.5 inches.
The Harris plant was to have four reactors but only one was built. A fuel handling
building was built to serve all four reactors. This building contains four fuel pools (A, B,
C, D), a cask loading pool and three fuel transfer canals, all interconnected but separable
by gates. Pools A and B contain fuel racks. Pools C and D are flooded but do not
contain racks. The cooling and water cleanup systems for pools C and D were never
completed.
11. Pool A now contains six PWR racks (360 fuel assembly spaces) and three BWR
racks (363 spaces), for a total pool capacity of 723 fuel assemblies. Pool B contains
twelve PWR racks (768 spaces) and seventeen BWR racks (2,057 spaces), and is licensed
to store one additional BWR rack (121 spaces), for a total pool capacity of 2,946 fuel
assemblies. Thus, pools A and B now have a combined capacity of 3,669 fuel
assemblies. The center-center distance in pools A and B is 10.5 inches for PWR fuel and
6.25 inches for BWR fuel.
12. Pools A and B store spent fuel from the Harris reactor and from CP&L's Brunswick
plant and Robinson plant. The Brunswick plant has two boiling-water reactors (BWRs)
while the Robinson plant has one PWR. Shipment of spent fuel from Brunswick and
Robinson to Harris is said by CP&L to be necessary to allow core offload capacity in the
pools at Brunswick and Robinson.
13. CP&L seeks an amendment to its operating license so that it can activate pools C and
D at Harris. By activating these pools, CP&L expects to have sufficient spent fuel
storage capacity for all four CP&L reactors (Harris, Robinson and the two Brunswick
reactors) through the end of their current operating licenses.
14. CP&L plans to install racks in pool C in three campaigns (approximately in 2000,
2005 and 2014), to create 927 PWR spaces and 2,763 BWR spaces, for a total pool
capacity of 3,690 fuel assemblies. Thereafter, CP&L plans to install racks in pool D in
two campaigns (approximately in 2016 and at a date to be determined), to create. 1,025
PWR spaces. Thus, the ultimate capacity of pools C and D will be 4,715 fuel assemblies.
The center-center distance will be 9.0 inches for PWR fuel and 6.25 inches for BWR fuel.
15. The PWR racks in pools C and D have a smaller center-center distance than the racks
in pools A and B (9.0 inches instead of 10.5 inches). This arrangement allows more
PWR fuel to be placed in a given pool area but also means that PWR fuel in pools C and
D is more prone to undergo criticality. In response, CP&L proposes to include in the
Technical Specifications for Harris a provision that PWR fuel will not be placed in pools
C and D unless it has relatively-low enrichment and high burnup.3
F. Some Technical Safety Issues Raised By the Proposed License Amendment
16. CP&L's plan for the activation of pools C and D raises a variety of technical safety
issues. This. section of my Declaration describes some of those issues. Later parts of the
Declaration relate these issues to the NRC's standard fora "no significant hazards"
determination.
s License amendment application, Enclosure 5
4
17. NRC regulations require that spent fuel storage pools must be cooled by safety grade
cooling systems. When the Harris plant was designed, the intention was that pools C and
D would be cooled by the component cooling water (CCW) system for the second unit of
the Harris plant a That unit was never built, and therefore the Unit 2 CCW system does
not exist. In the absence of a second CCW system, CP&L plans to cool pools C and D
by connecting their cooling systems to the CCW system of the first unit. This system
already provides cooling to pools A and B and serves other, important safety functions.
Attachment B provides supporting information.5 It should be noted that CP&L
considered, but has not pursued, the option of cooling pools C and D by a new,
independent system that could have had dedicated emergency diesel generators.
Attachment C provides information in support of this point.6 Three significant safety
issues are raised by the fact that the spent fuel pool cooling arrangement originally
designed for pools C and D of the Harris plant was not completed. These issues relate to
the heat loading of the existing CCW system, the load on the existing emergency diesel
generators, and the loss of some important quality assurance documentation for cooling
piping at pools C and D.
18. Heat load. According to CP&L's license amendment application, the bounding heat
load from. the fuel in pools C and D will be 15.6 million BTU/hour:~ At present, the
CCW system cannot absorb this additional heat load. Thus, CP&L proposes to include in
the Technical Specifications for Harris an interim provision that the heat load in pools C
and D will not be allowed to exceed 1.0 million BTU/hour.8 CP&L claims that an
additional heat load of 1.0 million BTU/hour can be accommodated by the existing CCW
system, and that the fuel to be placed in pools C and D will not create a heat load
exceeding 1.0 million BTU/hour through 2001.
19. Apparently, CP&L contemplates a future upgrade of the CCW system, so that the
CCW system can accommodate an additional heat load of 15:6 million BTU/hour from
pools C and D. This contemplated upgrade is not described in the present license
amendment application. Attachment C indicates that CP&L plans to perform the upgrade
of the CCW system concurrent with a power uprate for the Hams reactor. Apparently, a
4.5 percent power uprate will be associated with steam generator replacement, and there
will be a subsequent further power uprate of 1.5 percent. A chart in Attachment C shows
that the projected CCW heat load, including the reactor power uprate and the use of pools.
C and D, will substantially exceed the capability of the present CCW system.
20. To summarize, CP&L's short-term plan (through 2001) for cooling pools C and D is
to exploit the margin in the existing CCW system, so as to accommodate an additional
heat load of 1.0 million BTU/hour. CP&L's longer-term plan is to upgrade the CCW
4 The Harris pools have their own closed-circuit cooling systems, which can transfer heat to the relevant
CCW system through heat exchangers.
5 Attachment B is a portion of a set of viewgraphs (titled "Harris Spent Fuel Pool 'C' and 'D' Activation")
shown by CP&L representatives during a meeting with NRC staff on 16 July 1998. ~
6 Attachment C is an NRC staff memo about a meeting between CP&L representatives and NRC staff on 3
March 1998, together with a portion of a set of viewgraphs (titled "HNP Spent Fuel Pool'C' and'D'
Activation") shown by CP&L during that meeting. ~
~ License amendment application, Enclosure 7, page 5-16.
s License amendment application, Enclosure 5.
5
system, in a manner not yet specified, so as to accommodate an additional heat load of
15.6 million BTU/hour. The CCW upgrade must also accommodate an increase in the
rated power of the Harris reactor. Attachment B indicates CP&L's expectation that the
design of the CCW upgrade will commence in mid-1999 and will be completed in early
2001, one year after pool C enters service.
21. In order to avoid exceeding the available margin in the existing CCW system while
cooling pools C and D, CP&L may be obliged to require its operators to divert some
CCW flow from the residual heat removal (RHR) heat exchangers during the
recirculation phase of a design-basis loss-of-coolant accident (COCA) event at the Harris
reactor.9 This raises a safety issue because, during the recirculation phase of a COCA,
operation of the RHR system is essential to keeping the reactor core and containment in a
safe condition. Both CP&L and the NRC have identified the proposed additional heat
load on the Unit 1 CCW system as an "unreviewed safety question," i.e., a safety
question that has not been previously reviewed by the NRC Staff.10 It should be noted in
this context that exploitation of the margin in the existing CCW system may involve
changes in design assumptions that include fouling factors and tube plugging limits. See
Attachment C. The discussion of CCW capability which is provided in Enclosure 9 of
CP&L's license amendment application is insufficient to determine the nature and
significance of the assumptions made by CP&L.
22. Backup diesel generators. The cooling systems for pools C and D will draw
electrical power from the electrical systems of the existing Harris plant. If electricity
supply to the cooling pumps for pools C and D is interrupted, the pools will heat up and
eventually boil. CP&L says that pools C and D will begin to boil after a time period "in
excess of 13 hours", assuming a bounding decay heat load of 15.6 million BTU/hour.il
To prevent the onset of pool boiling in the event of a loss of offsite power, the Harris
operators may be obliged to provide electrical power to pools C and D from the
emergency diesel generators, which also serve pools A and B and the reactor. In the
present license amendment application, CP&L does not address the ability of the
emergency diesel generators to meet the additional electrical loads associated with pools
C and D. CP&L does mention in the Harris FSAR the potential for connecting "portable
pumps" to bypass the pool cooling pumps should the latter be inoperable.12 However, the
characteristics, capabilities and availability of such portable pumps are not addressed in
the present license amendment application. Meeting the electrical load of pools C and D
from the systems of the existing Harris plant is a safety issue because it could increase the
probability of design-basis or severe accidents at the Harris reactor or at pools A through
G.
23. Lack of QA documents. Activation of pools C and D will require the completion of
their cooling and water cleanup systems, and the connection of their cooling systems to
the existing CCW system. CP&L states that approximately 80% of the necessary piping
was completed before the second Harris reactor was cancelled.13 However, some of the
9 License amendment application, Enclosure 9.
to Ibid; Federal Register notice for this application.
11 License amendment application, Enclosure 7, page 5-8.
12 Harris FSAR, page 9.1.3-4, Amendment No. 48.
13 License amendment application, Enclosure 1, page 4.
6
quality assurance documentation for the completed piping is no longer available. Much
of the completed piping is embedded in concrete and is therefore difficult or impossible
to inspect. To address this situation, CP&L proposes an Alternative Plan to demonstrate
that the previously completed piping and other equipment is adequate for its purpose.ia
Nevertheless, the cooling systems for pools C and D will not satisfy ASME code
requirements. Attachment D provides supporting information.15 Failure to satisfy ASME
code requirements could increase the probability of design-basis or severe accidents at
pools C and D.
G. The Degree of Hazard Posed by Spent Fuel Storage at Harris
24. The NRC and CP&L have performed and published site-specific analyses which
provide information about potential severe accidents at the Harris reactor. However, to
my knowledge neither NRC nor CP&L has performed any site-specific analysis which
examines potential severe accidents affecting any of the Harris fuel pools,. including pools
C and D.
25. The NRC examined severe reactor accidents in its Final Environmental Statement for
the Harris plant.16 Site-specific consequence modelling was performed by the NRC for
hypothetical accidents that released as much as 82 percent of the inventory of cesium
isotopes in the reactor core. CP&L has submitted to the NRC an Individual Plant
Examination (IPE) for the Hams plant.~~ In addition, CP&L has submitted a similar
analysis (an IPEEE) for "external" initiating events.lg The IPE and IPEEE studies
examined the potential for severe reactor accidents that could release substantial amounts
of radioactivity.
26. In the absence of similar studies for the Harris pools, one must perform scoping
calculations to indicate the degree of hazard posed by spent fuel storage at Harris. The
degree of hazard is important when one considers the relevance of a safety issue to a
determination of "no significant hazards". If preliminary evidence about a safety issue
suggests the potential for accidents with either high probability or large consequences,
then the NRC staff should not make a determination of "no significant hazards".
27. The radioisotope cesium-137 is one important indicator of the hazard potential posed
by a nuclear facility. This isotope has ahalf--life of 30 years, emits intense gamma
radiation, and is released comparatively readily during severe accidents. The 1986
Chernobyl accident released about 90,000 TBq (27 kg) of cesium-137 to the atmosphere,
which accounted for most of the offsite radiation exposure attributable to that accident.
la License amendment application, Enclosure 8
15 Attachment D is a portion of a set of viewgraphs (titled "1OCFRSO.SSa Alternative Plan") shown by
CP&L representatives during a meeting with NRC staff on 16 July 1998.
16 NRC, Final Environmental Statement related to the operation of Shearon Harris Nuclear Power Plant,
Units 1 and 2, NUREG-0972, October 1983.
17 CP&L, Shearon Harris Nuclear Power Plant, Individual Plant Examination Submittal, Final Report, 31
August 1993.
18 CP&L, Shearon Harris Nuclear Power Plant Unit No. 1, Individual Plant Examination for External
Events Submittal, June 1995.
Official estimates indicate that this exposure will cause 50-100 thousand extra cancer
fatalities worldwide over the next 70 yeazs.19
28. The core of the Harris reactor contains 157 PWR fuel assemblies. At shutdown, this
core contains about 155,000 TBq (47 kg) of cesium-137.20 When a spent fuel assembly is
discharged from the reactor, it will contain more cesium-137 than the average assembly at
shutdown. CP&L plans an eventual, aggregate capacity in the Harris pools of 3,080
PWR assemblies and 5,304 BWR assemblies. Note that the cesium-137 content in each
BWR assembly will be about one. quarter the cesium-137 content in each PWR assembly,
if both assemblies have been dischazged for an equal period.21 After dischazge, the
content of cesium-137 in a fuel assembly will decay exponentially with ahalf--life of 30
years.
29. As a simplified illustration, assume that all fuel assemblies in the Harris pools have
been discharged for an equal period. Further assume that all four pools are full and
contain 3,080 PWR assemblies and 5,304 BWR assemblies. The pools will then contain
as much cesium-137 as 4,406 PWR assemblies. (3,080 + 5,304 x 1/4 = 4,406) Note that
4,406 PWR assemblies represent 28 cores of the Harris reactor.
30. If an accident can be postulated that releases to the environment a significant fraction
of the cesium-137 in the Harris pools, then it is clear that the consequences of this
accident would be large. The offsite radiation exposure could be an order of magnitude
larger-than the exposure from the Chernobyl accident. Activation of pools C and D could
lead to an accident which creates offsite radiation exposure as much as two times higher
than the exposure that would arise from a similar accident involving only pools A and B.
H. Loss of Water from Spent Fuel Pools at Harris
31. Loss of water from one or more of the Harris pools could initiate a release to the
environment of a significant fraction of the cesium-137 in the pools. This potential exists
because the cladding of PWR or BWR fuel is a zirconium alloy which can react
exothermically with air or steam. Thus, if the water in a fuel pool is removed and the fuel
is partially or totally uncovered, one must be concerned about the possibility of a
runawayair-zircomum or steam-zirconium reaction. Such a reaction could release
cesium-137 and other radioisotopes from affected fuel-into the fuel building. That
building was not designed to contain radioisotopes released during a vigorous exothermic
reaction in the pools, and it can be assumed that most of the volatile radioisotopes
entering the building from the affected fuel would be released from the building as an
atmospheric plume.
32. Several reports prepared by or for the NRC have examined the conditions under
which a runaway zirconium reaction might occur.22 However, these reports have
~9 Allan S Krass, Consequences of the Chernobyl Accident (Cambridge, Massachusetts: Institute for
~ Resource and Security Studies, December 1991).
20 NRC, Final Environmental Statement, page 5-50.
21 The ratio of one quarter derives from the parameters shown in the license amendment application,
~ Enclosure 7, page 5-15.
22 Relevant reports include: V L Sailor et al, Severe Accidents in Spent Fuel Pools in Support of Generic
Safety Issue 82, NUREG/CR-4982, July 1987; E D Throm, Regulatory Analysis for the Resolution of
Generic Issue 82, "Beyond Design Basis Accidents in Spent Fuel Pools", NUREG-1353, April 1989; and R
8
concentrated almost entirely on a postulated condition of instantaneous, complete loss of
water from a pool. Such a condition is unrealistic in any scenario which preserves the
configuration of the spent fuel racks. If water is lost by drainage or evaporation and no
makeup occurs, then complete loss of water will always be preceded by partial
uncovering of the fuel. If makeup is considered, the water level could fall, rise or remain
static for long periods.
33. Partial uncovering of the fuel will often. be a more severe condition than complete
loss of water because, during partial uncovering, convective heat loss is suppressed by the
residual water at the base of the fuel assemblies. As a result, longer-discharged fuel with
a lower heat output may undergo a runaway steam-zirconium reaction during partial
uncovering while it would not undergo a runaway air-zirconium reaction if the pool were
instantaneously emptied.
34. I am aware of only one instance in which reports produced by or for the NRC address
the hazard posed by partial uncovering, namely in a report prepared for the NRC by
Sandia Laboratories and published in 1979.23 Part of this report did address a situation of
partial uncovering, but used a crude heat transfer model and neglected to consider the
onset of asteam-zirconium reaction. Nevertheless, the report found (page 76) that
"......an incomplete drainage can potentially cause a more severe heatup problem than a
complete drainage, if the residual water remains near-the baseplates". A portion of the
1979 Sandia report is provided here as Attachment E. An internal NRC memo mentions
the consideration of partial uncovering in the 1979 Sandia report.24. Otherwise, it appears
that the NRC has ignored the hazard posed by partial uncovering. This hazard was not
reflected in the regulatory analysis whereby the NRC purportedly resolved Generic Issue
82.25
35. In a situation of falling water level, a fuel assembly might first undergo a runaway
steam-zirconium reaction, then switch to anair-zirconium reaction as water falls below
the base of the rack and convective air flow is established. In this manner, a runaway alr-
zirconium reaction could occur in a fuel assembly that is too long-discharged (and
therefore produces too little heat) to suffer such a reaction in the event of instantaneous,
complete loss of water. Conversely, a rising water level could precipitate a runaway
steam-zirconium reaction in a fuel assembly that had previously been completely
uncovered but had not necessarily suffered a runaway air-zirconium reaction while in that
condition. The latter point is highly significant in the context of emergency measures to
recover control of a pool which has experienced water loss. Inappropriate addition of
water to a pool could exacerbate the accident.
36. The NRC's failure to consider partial uncovering of fuel should be borne in mind
when one reviews NRC-sponsored reports that purport to address the hazard posed by
water loss from a fuel pool. This hazard should be re-analyzed through detailed
J Travis et al, A Safety and Regulatory Assessment of Generic BWR and PWR Permanently Shutdown
Nuclear Power Plants, NUREG/CR-6451, August 1997. ~
23 Allan S Benjamin et al, Spent Fuel Heatup Following Loss of Water During Storage, NUREG/CR-0649,
March 1979. ~
24 Internal NRC Memorandum from J T Han to M Silberberg, "Response to a NRR request to review SNL
studies regarding spent fuel heatup and burning following loss of water in storage pool", 21 May 1984. ~
25 E D Throm, op cit
9
modelling. The modelling should consider both partial and complete uncovering and the
transition from one of these states to the other. Also, the modelling should cover: (1)
thermal radiation, conduction, and steam or air convection; (2) air-zirconium and steam-
zirconium reactions; (3) variations along the fuel rod axis; and (4) radial variations within
a representative fuel rod, including effects of the pellet-cladding gap. Experiments will
probably be required to support and validate the modelling.
37. Until the problem of water loss is re-analyzed in this manner, there is no basis for
determining when fuel has been discharged for a sufficiently long period that it will not
suffer a runaway zirconium reaction in the event of water loss. If the problem were to be
properly analyzed through validated models, such a determination could be made within
some margin of error, but the determination should consider site-specific factors. For
example, the detailed design of a rack might be an important site-specific factor.
38. No determination of this kind has been made for pools C and D at Harris, nor does
the methodology now exist to make such a determination. In any case, there is nothing in
the license amendment application and its proposed modifications to the Harris Technical
Specifications which prohibits the placing of freshly discharged fuel in pools C and D.
Reports previously prepared for the NRC concede that freshly discharged fuel can
experience a runaway air-zirconium reaction in the event of complete water loss.
39. A variety of events, alone or in combination, could lead to partial. or complete
uncovering of spent fuel in the Harris pools. This class of events should be subjected to
the kind of systematic analysis that is performed in an IPE and an IPEEE. Relevant
events include: (1) an earthquake, cask drop, aircraft crash, human error, equipment
failure or sabotage event that leads to direct leakage from the pools; (2) siphoning of
water from the pools through accident or malice; (3) interruption of pool cooling, leading
to pool boiling and loss of water by evaporation; and (4) loss of water from active pools
into adjacent pools or canals that have been gated off and drained. Interactions with the
Harris reactor should be considered. For example, a reactor accident might release
radioactivity that precludes personnel access to the plant for purposes of maintaining or
restoring pool cooling.
I. Increased Probability or Consequences of Accidents Previously Evaluated
40. The Federal Register notice of this license amendment application claims that the
probability of a spent fuel assembly drop or a misloaded fuel assembly is not significantly
increased if the license amendment is approved and pools C and D are activated. This
claim is false, because activation of pools C and D will roughly double the total number
of fuel handling operations to be conducted at Harris. Assuming that the general nature
of fuel handling operations continues as before, the probability of a fuel assembly dxop or
misloaded fuel assembly, integrated over the entire period of the Harris operating license,
will increase significantly, by a factor of two. This point has been made by David
Lochbaum of the Union of Concerned Scientists, in a 22 January 19991etter to the NRC
Commissioners. A.copy of his letter is provided here as Attachment F. If probability is
integrated over the remaining period of the Harris operating license, rather than over its
total duration, then activation of pools C and D will more than double the probability of a
fuel assembly drop or a misloaded fuel assembly.
41. A spent fuel assembly drop or a misloaded fuel assembly are members of a broader
class of accidents that could arise during the movement of fuel from other CP&L stations
to Harris, and during fuel movement within Harris. This class of accidents will include
design-basis accidents and severe accidents. Assuming that the general nature of fuel
movement continues as before, the probability of accidents in this class, integrated over
10
the entire period of the Harris operating license, will double if pools C and D are
activated. If integrated over .the remaining period of the operating license, the probability
will more than double.
42. The PWR racks in pools C and D will be safe against criticality for a compazatively
narrow range of fuel enrichment and burnup. Thus, assuming that the general nature of
fuel-movement continues as before, the probability of a criticality accident will be
significantly increased if pools C and D are activated. This probability will increase on a
per-movement basis, so it will more than double when integrated over the entire period of
the Harris operating license. The consequences of a criticality accident may also be
significantly increased.
43. Activation of pools C and D will add to the electrical load and CCW heat load of
existing Harris systems. It will also add to the burden of work on the Harris operators.
These effects will increase the probability of two categories of design-basis or severe
accidents. First, they will sigmficantly increase the probability of accidents associated
with the Harris reactor, because the reactor's CCW and electrical systems and its
operators will be under greater stress. Second, they will significantly increase the
probability of accidents at the Harris pools that are attributable to interruptions in cooling
and electricity supply and to increased operator stress. Also, the inability of cooling
piping at pools C and D to meet ASME code requirements could significantly increase
the probability of design-basis or severe accidents at these pools.
44. As mentioned in paragraph 24 above, to my knowledge there has been no site-specific
analysis of severe accidents affecting any of the Harris pools. To the extent that such
accidents have been previously evaluated, their consequences will be significantly
increased by the activation of pools C and D. The fuel storage capacity of these pools
will roughly double the storage capacity at Harris, creating the potential for a doubled
inventory of radioactivity. Severe accidents could affect some or all of the Harris pools.
As I have discussed in pazagraph 30 above, the potential doubling of radioactivity in the
pools could significantly increase the consequences of severe accidents.
J. Possibility of New or Different Kinds of Accident from any Accident Previously
Evaluated
45. To my knowledge, there has been no site-specific evaluation of the probability or
consequences of severe accidents at pools A and B at Harris. A variety of severe
accidents are possible and should be subjected to the kind of systematic analysis that is
performed in an IPE and IPEEE. The NRC has performed evaluations of accidents
involving loss of water from fuel pools, generically and for sites other than Harris.
However, these evaluations are seriously deficient because they failed to consider partial
uncovering of fuel. To summarize, at pools A and B there exists the possibility of new or
different kinds of accident from any accident previously evaluated. The same possibility
will exist at pools C and D if these are activated.
46. Provision of electrical power and CCW service from the existing Harris plant to
pools C and D could introduce the potential for design-basis or severe accidents that aze
new or different from any accident previously considered. The IPE and IPEEE studies
performed for Harris did not address the provision of electrical power and CCW service
to pools C and D. As an example of the potential for new or different accidents, the need
to provide cooling to pools C and D will place increased stress on the CCW system and
the plant operators during adesign-basis LOCA.
11
47. Severe accidents at some or all of the Harris pools could lead to offsite radiation
exposure an order of magnitude larger than the exposure from the Chernobyl accident.
Activation of pools C and D could significantly increase both the probability and
consequences of such accidents. Thus, CP&L's proposed license amendment poses a
"significant hazazd" by any reasonable definition of that term.
J. Significant Reductions in Margins of Safety.
48. Activation of pools C and D will create an additional heat load on the existing CCW
system. CP&L proposes to meet this load in the short term by exploiting the margin in
the CCW system. In my professional opinion, the reduction rn the CCW safety margin
caused by the increased heat load is significant. Both the NRC and CP&L have also
recognized that increasing the heat load on the CCW system constitutes an unreviewed
safety question. The safety margin will be especially reduced if, during a LOCA, the
operators must divert water from the RHR to the spent fuel pools. This will increase
stress on the operators and create opportunities for human error.
49. As pools C and D become filled and the reactor receives a power uprate, the load on
the CCW system will increase further. CP&L offers no assurance that the present margin
of safety will be restored by upgrading the CCW system to accommodate these burdens.
50. CP&L proposes to activate pools C and D using cooling systems that will not satisfy
ASME code requirements. This action could potentially cause a significant reduction in
mazgins of safety for pool cooling. CP&L's Alternative Plan has not been subjected to
any public scrutiny or rigorous review. It deserves, at the least, thorough consideration at
a licensing hearing before the license amendment is issued.
51. CP&L proposes to provide electrical service to pools C and D from the existing (Unit
1) electrical system at Harris, having rejected the option of dedicated emergency diesel
generators to serve pools C and D. The existing diesel generators already serve the safety
systems in Unit. l and spent fuel storage pools A and B. By adding pools C and D to the
load carried by the Unit 1 diesel generators, CP&L would add stress on the diesel
generators and on the plant operators. In the event of a loss of offsite power, these effects
could significantly reduce the margin of safety at the Harris reactor and the fuel pools.
L. Environmental Review
52. As discussed above, the original design of the Shearon Hams plant called for
cooling of spent fuel pools C and D by the Unit 2 CCW system. The FEIS for the
operating license presumably based its conclusions on this design. I have seen no
analysis by the NRC Staff, erther in the 1983 FEIS or in a subsequent Environmental
Impact Statement or Environmental Assessment, of the environmental impacts of altering
the Shearon Harris design to provide for cooling of pools C and D by the Unit 1 CCW
system.
M. Conclusions
53. From the preliminary evidence presented by the NRC and CP&L, I conclude that
operation of the Shearon Harris plant in accordance with the license amendment proposed
by CP&L will violate all three of the NRC's conditions for a determination of "no
significant hazards." Therefore, the NRC staff should reverse its position and should
determine that CP&L's license amendment request does not involve no significant
hazards consideration.
12
54. The proposed license amendment raises serious safety concerns which deserve prior
consideration at a licensing hearing.
************************
I declaze, under penalty of perjury, that the foregoing facts provided in my Declazation
aze true and correct to the best of my knowledge and belief, and that the opinions
expressed herein aze based on my best professional judgment.
Executed on 12 February 1999.
Gordon Thompson
HARMON~CURRAN,SPI ~ 19196443004-004 N0. 113 D02
~-a- 99
i°~~`
HAaMOIV, GETRRAIV, sic ~ FJS»a, L.L.P.
2001 S STREET, N.W.
StJITB 430
WASHI1~iGTON, D.C. 20009-1125
~rer.~o~e
(202} 325-3;00
FAY
(20?) 32$•6918
PRIVILEGED AND CON1P'IDENTIAL
ATTORNEY-CLIENT COMMUNICATION
AND ATTORNEY WORK PRODUCT
February i, 1999
Orange County Poard of Commissioners
do Paul Thames, County Engineer
919ifi44-30004
SUBIECT: Legat Services Contract for Shearar Harris License Amendment Proceeding
Dear Commissioners:
I understand that the County has appropriated $b,000 to retain my services for legal
representation in the first stages of the Nuclear Regulatory Commission's license amendment
proceeding for the proposed expansion of the Shearon Harris spent fi~ pool. In partieetlar, the
Coutrty wishes to hire me for the purposes of a Request for Hearing/Fetition to Intervene
and a set of cornentions. As further discussed below, I would also urge the County to consider
challenging the NRC's "No Significant Hazards" finding. The purpose of this letter is to set forth
proposed terms of my representation of the County in these matters.
Proceda~t Baelcground of the Case
Ln a Federal Register notice issued vn Ianuary 13, 1999, the NRC announced its intention to
amend the Shearon Harris license to permit expansion of the spent fuel pool, aYUi offered the
public an opportunity to reque~ a hearing by February 1 Z, 1999. The hearing offered in the
Federal Register is guaranteed by the federal Atomic Energy Act to airy member of the public. that
can show "standing, °' i.e., that he or she maybe adversely affected by the proposed action. In
order to become a party to the case, it is necessary to file a Request for Hearing and Petition to
Intervene.
Ordinarily, the NRC must hold the hearing before the license is issued. However, a provision in
the Atomic Energy Act allows the NRC to take the licensing action before the hearing is
completed, if it finds the proposed action would pose "no significant hazard," in other words, if it
is relatively innocuous. In this case, the NRC has made a preliminary determination that the
Shearon I4arris spell fuel pool expansion would pose no significant hazards. The Federal
02i01~99 14:31 HARMON~CURRAN.SPI ~ 19196443004-004 N0.113 D03
~N, CLAN, SPl~LBERG & EISEI~R'ERG, L.L.P.
orange County Commissioners PIiIV1LEGED AND CONI4TDENTIAI.
February 1, 1999 ATTORNEY-CLLENT CONIM'UNICATId)N
Page 2 AND ATTORNEY WORK PRODUCT
Register notice offers the public an opportunity to comment on whether this determination is
reasonable, or whether instead the proposed action poses a significant danger, such that the
hearing should be held before the license amendment is granted. These no significant hazards
comments are also due February l2.
If no such comments are made, or if the comments are rejected, Carolina Power & Light can go
ahead and put the new racks into the spent fud pool before'the hearing is completed ar even
started. This is a disadvantage to any members of the public who are seeking to litigate whether
the proposed license amendment is reasonably safe, because it gives the proposed action
momentuar that it otherwise would not have.
Later on in the proceeding, probably inmid-March, any party that has requested a hearing will
also be asked to submit "contentions," which set forth the issues that they wish to raise in the
hearing. Those contentions that are admitted ittto the hearing will determine the scope of the
issues that can be raised in the hearing.
Descript~ Af L,egat Services
As requested by the Board, I will prepare a Request for Hearing and Fetition to Irnervene on
behalf of the County, to be filed on February 12. Working with Gordon Thompson, I will also
prepare contentions challenging the safety of the proposed license amendment. I will also prepare
any reply filings that are necessary and attend any prehearing conference scheduled by the NRC
Incensing Board.
My fee for this work is $150/hour plus expenses, including copying (tt~ 5.151page, long distance
charges, postage, and travel costs- Although I will do most of the work on the case, I may
receive assistance from my partners or associate attorneys, who charge $l50/hour and $100/hour,
respectively. My estimate for completing the work is $6,t~0. Bills are sent out monthly, and
payment is expected withip 30 days.
In addition to the work described above,l would urge the Board to consider filing No Significant
Hazards Comments. Although it is difficult to gain reversal of No Significam Hazards findings, I
believe it is worthy of seriws consideration. The proposed amendment would make Shearon
Harris the largest spent fuel storage facility on the East Coast. with a very large inventory of spent
nuclear power plant foal. Consequently, an accident involving loss of coolant from the pool could
have very severe consequences. Moreover, as discussed above, it is worthwhile to try to stop the
the proposed expansion from gaining the momentum generated by pre-hearing implementation.
I estimate that preparation ofNo Significant Hazards comments would take an additional ten
hours of my time, costing $1,500. It would also require ih. Thompson to prepare an affidavit
14:31 HARMON~CURRAN~SPI -~ 19196443604-004
~IbR11~ON, t~IRRAN, SP~.BERG & EISSIVBEII<G, L.L.P.
N0.113 D04
Orange County Commissioners PRIVILEGED AND CONFD3ENTL4L
February 1, 1499 ATTORNEY-CLIENT GOMMU1rlICATION
Page 3 ANA ATTORNEY WORK F1EiODUCT
setting forth the reasons that the prapased amendment poses a significant hazard to public health
and safety. I recommend that you request Dr. Thompson to address the significance of the
hazards posed by the proposed spent fuel pool expansion in the memorandum he is preparing for
submission on February S, and ask him for an estimate for the cost of preparing an affidavit.
If you wish to retain my services for the filing of a Request for Hearing/Petitian to Intervene and
No Significant Hazards comments, please provide an authorized signature below. In addition,
please send a retainer of $2,x00. If you do not wish me to prepare the No Significant Hazards
camrnents, please cross out the last two Paragraphs on page 2.
I hope that you will contact me soon about your wishes, as the time frames set by the Commission
leave little time to prepare. Please call me if you have any quesrions about this letter.
I very much look forward to representing you in this proceeding.
Sincerely,
' e Curran
l ~,C~ ~1 ~~,4~.o(,orJ (name)
L' l,_.,;_, (title}
Orange County Board of Commissioners
3
Date
ec: Dr. Gordan Thompson, Institute for Resource and Security Studies
Tou~n o f Chape l H i 1 L Fax ~ 919-96?-8406 Jan 13 ' 99 12 ~ 31 P. 03/04 `~
~THEREAS, the Council understands that Carolina Pawer & Light has plans for the expansion of
the high level radioactive waste storage facilities at the Sheacota Harris Nucleax Pawer Plaza in
. Wake County; and
WHEREAS, the Council understands that there are risks inherent with the doubling of the
storage capacity of the temporary storage pools for the high level radioactive waste far. the
.purpose of long term storage of high. level radioactive waste, not only from the Shearon Harris
..plant, but also from two other nuclear. power plants from elsewhere in North and South Cazolina;
....and
~J'HEREAS, the Council has concerns about the plans to expand the waste storage capacity at the
.Shearon fTarris facility and the lack of public input into the approval process for those; and
~fTHEREAS, the. Council believes that commruuties should consider alteniative forms of energy
production that are .safer for the environment;
NOW, THEREFORE, BE IT IEtFSOLVED by the Council of the Town of Chapel Hill that the
Council requests that the North Carolina Department of ~zzviroztzaezrt and Natural Resources and
the Nucleaz Regulatory Commission.conduct puUlic hearings in which Carolina Fower & Light ,
and appropriate regulatory staff-
1) explain the plans to expand tbe~ storage. facilities for high Ievel radioactive waste at the
Shearon Harris Nuclear Power Plant;
2} .outline the risks, or lack thereof, and explain the risk assessment methodology employed to
develop risk projections related to the use of facilities designed for short term storage of high
level radioactive wastes for longterm storage;
3) outline the risks, .or lack thereof, atzd explain~the risk assessment methodology employed to
develop risk projections associated with the transportation and handling of materials from
other distant nuclear power generating facilities;
4) accept and consider public cozzaments relative to support for or opposition to operating or
examining such a facility in this ~azea;
5) explain why transporticxg spent fuel rods ~ is ~ safer than a semi perx~aanezat storage (that is,
"swimming pool" storage) onto their site of use, as transpo'ng them increases risks; .
6) explain why transporting spent: fuel mds from two regions of zelativeiy low population
. density (South Carolina and $runswick County, l\TC} to an area of much higher population
density (Wake County) minimatzes the overall risk to people; and
7) requests that the Chapel Hill Town Council be included in discussions with Carolina Power.
and Light and the Orazzge County Commissioners, and that these questions be answered in a
public forum.
Tou~n of Chapel Hill Fax~919-967-$406 Jan 13 '99 1231 P.04~04
\S '..
BE IT FURTHER RESQ~.VED that the Council opposes any proposed expansion o~ him level
radioactive waste storage facilities at CP&L's Shearon Harris Nuclear Power Plant:
. This the 11 ~` day of January, 1999.
~;
,~