Loading...
HomeMy WebLinkAboutAgenda - 03-31-1999 - 1c-14• ,Afl" wx_,4 1(7--J_ Memorandum TO: County Commissioners From: John M. Link, Jr. County Manager Date: March 20,1999 RE: Project Management The Board has historically expressed concern about the high cost of construction for County funded projects. Both Board members and County staff have explored ways to address this challenge through various means of project management. I attended a session at a recent City /County manager conference that dealt with value engineering. Based on what I learned during this session, I believe value engineering can fill the gap that we have recognized and allow us to use the County's construction dollars more effectively and efficiently. What is Value Engineering? Value Engineering offers a way to stretch construction dollars and to obtain a much needed second opinion based on a reliable and measurable approach. Value engineering systematically searches out high cost areas in a design and arrives at the best balance between cost, performance and reliability. Value engineering is not a design review. In summary value engineering offers the following benefits: • it follows a Value Engineering job plan that analyzes the project from a variety of angles in order to obtain the best answers for the specific project; • it uses a multi disciplined approach to "see" the project from as many different points of view as possible; • it questions everything. There are no "sacred cows" with value engineering. • it separates "needs" from "desires" • it employs life cycle cost analysis of critical components • it maintains a sensitivity to the design and the designer's point of view when creating • it also, however, analyzes the project from the owner /operator's points of view. - As a general rule of thumb, it is suggested that any project whose estimated construction cost exceeds $5 million will benefit significantly from the value engineering process. As indicated earlier, Value Engineering is not review of a final design in an effort to cut a project such that it falls within budget. In fact, the continuum of value engineering effectiveness shows it to be most effective if begun during the design concept phase. r *. County Commissioners Project Management Page 2 Savings opportunities Preliminary Final design Design design concept Implementation Costs As listed below, it is a process that shows greatest benefit if employed at several points in the design /construct process: • Early in the schematic design phase; • Concurrently with the engineering review; • When cost data becomes available; • During the working drawings phase (design is approximately 95% complete); and • Throughout construction. A system of checks and balances is maintained by carrying out the process during each of these phases. Mid - stream adjustments are thereby effected with minimal, if any, cost or time impact and a more successful projects are realized. The Process The job plan, which is critical to the successful Value Engineering process encompasses six distinctive phases as follows: 1. Information gathering. • This phase familiarizes the Value Engineering team with the contract plans and specifications. It involves a functional analysis of the project that looks at the total system first and then each of the component parts. Energy utilization models as well as cost models are prepared in advance of this stage and are shared with the Value Engineering team. 2. Speculative /creative phases. • This phase of the job plan is used to generate many ideas for the project in an effort to remove barriers to a free flow of ideas. 3. Evaluation /analytical phase. • The Value Engineering team will analyze the ideas resulting from the creative session and will select the best ideas for further development. 4. Development/recommendation phase. • The Value Engineering team members prepare alternative designs for consideration with life cycle cost comparisons of the original designs and proposed alternatives. All recommendations are documented with sketches, basic concept and recommendation of alternatives. 5. Report phase. • The Value Engineering team presents the results of their work to the designer and owners. County Commissioners Project Management Page 3 6. Implementation phase. • The project designer will provide responses on the alternatives identified and will incorporate them into the design, upon agreement with the owner. The Managers who have seen Value Engineering work for their projects indicate that possibly the most critical element of this process is that it be carried out by a certified value specialist (CVS) who has experience in construction. There are firms who provide this service and I would recommend that this step be incorporated into all County funded projects. The Value Engineering process would ensure that County funded projects are designed and built to the most efficient standards available. County Proiect Management As you know, currently the management for County projects is provided by a team of County staff members who: • ensure that the projects stay on track as it respects schedule and budget; • serve as the County's representative for construction /contract related issues; • work in tandem with the designer to provide inspections to assure that the quality of work is as specified. • ensure the project is properly closed out upon completion and that documentation and warranty information is obtained; • follows up with contractor and /or designer regarding warranty issues as they may arise during warranty period, which extends for one year from completion. Recommendation With this in mind, I would propose to the Board that the County routinely employ Value Engineering strategies for all projects in excess of $5 million, and that the Board recommend the same approach to the School Boards for School Capital Projects. I would further recommend that we review all projects for Value Engineering potential and include any project below that threshold if we determine it would benefit from Value Engineering. _ The Value Engineering process would broaden this partnership among County and /or School staff, the designer and the contractor(s) to bring a project to fruition in the best way possible. In an effort to give you insight regarding the Value Engineering process, I am attaching information from a firm that provides this service who attended the recent City /County Manager's conference. I would propose that this subject be discussed as part of the work session agenda with the School Boards on March 31, 1999. Should you have questions or comments in advance of that work session, please feel free to call me. CONDUCTING A VE STUDY CONDUCTING A VALUE ENGINEERING STUDY As indicated on the following diagram, all of our VE studies follow a definite task flow. This strict application of proven management principles assures that the results will be well developed, easily understood recommendations with optimizzed cost savings. On the pages following the diagram are the steps that we take during each phase of the study and the input that we expect from the Design Architect/Engineering firm. We have used the following approach on our past studies with great success: • Prestudy Preparation Phase • Project Study Workshop Phase • Post Value Engineering Study Phase The organized approach that we use both in preparation for the workshop and during the value engineering workshop, allows us to maintain a quick turn around time for the project study and the submittal of the Preliminary Value Engineering Reports. This approach also allows us to maintain the proper coordination among the Designer, the Owner and the value engineering consultant. a Prestudy Preparation Phase The preparation and organization for a value engineering study are vital to its success. This phase of the project is used to bring the VE team up to speed on the project and to remain abreast of the progress of the project. The prestudy phase is also used to orient the Owner and the Designer in the work that the VE team will be doing. The Owner and Designer are an integral part of the value engineering effort and it is the coordinator's responsibility to ensure that they are informed as to what the VE team is doing. • Arrange a value engineering coordination/orientation meeting with the Owner and Designer to review the organization and management of the study approximately three weeks prior to the workshop. This meeting will also explain the principles of value engineering and the proposed project approach. VALUE ENGINEERING PROJECT STUDIES TASK FLOW DIAGRAM PRESTUDY PHASE pro9ect coordiination . Verity Schedule prestudy preparation • Collect Design Data construction cost (CC) model • Distribute by Process annual cost (ACC) model • Include Energy life c cle cost (LCCy) model • Include CC ' Outline Format for Cost Data • Distribute to Team • Distribute by Trade • Include Labor a Include AC • Format for Members Construct Graphic Model : Include aS�pplies/ . Distribute Cosh Degsrnde Presentation • Cost Data • Define High CC Areas • Distribute Costs •Compare to Previous Cost Models ' Orientation Meeting • =9 RojecT Constraints • Compare to CC Model • Define High LCC Areas orientation • Introduction by Program Coordinator • Project Description and Presentation by Designer • Site Visit or Familiarization • Define Owner Require- ments PROJECT STUDY PHASE information phase • Analyze Project Costs creative phase • Introduction to Creative • Function Analysis Thinking. • Fast Diagram •Creative Idea listing • Identify H�ah Cost Areas, f • Quantity of Idea LCC and CC 2• Association or ideas • Identify High Energy Areas 3' �n �I e • Develop Cost/Worth Rallos 4. Man Hkkg Effect • Check Comotitertzed kiwi Brainstorming Bank From Previous Studies judgement phase • Eliminate Impractical Ideas • Maintain Quality • Improve Efficiency • List Advantages and Disadvantages • Select Ideas for Development IMPLEMENTATION PHASE (POST STUDY PROCEDURES) ve study report final acceptance • prepare VE Preliminary • Submittal of Redesign Report Estimate to Owner • Conduct Post Workshop • SubmlHal of VE Reports Meeting with Owner and to RegWatory Agencies Designer • Approval and Incorpora- • Designer Prepares Final Lion Into Final Design Report I development I phase • Develop Preliminary Design of Ideas • Prepare ABemate Design Sketches • Prepare Estimate .' CCo �rree on Ufe Cycle Use Computerized Cost Estimating and Design Criterla Databases presentation phase • Summarize Findings • Present VE Ideas to Owner - Designer •Determine Acceptance of Ideas Iff PACIFIC ENVIRONMENTAL SERVICES, INC. • Value Engineering Program Coordinator arranges for the collection of project study material. Informative design- data should be distributed to team participants at least two weeks prior to the workshop to prepare the study team for the project. This would include design reports and preliminary plans, if available. The Designer would distribute this data to the appropriate people. Design drawings, cost data, specifications, design calculations, reports and pertinent regulations are required during the project. • Develop a Cost Model • Develop a project Energy Model. This model indicates where energy is consumed in the project. It is an indication of high energy usage areas that will require further investigation by the VE team. • Arrange for the logistics of the VE study. • The Designer should prepare a brief outline of the background and rationale for the project. Any constraints or areas in the design that are not to be analyzed should be clearly outlined. • Analyze and validate original cost data prior to the workshop study. The primary concern in the prestudy preparation phase is that all parties are well coordinated regarding the progress of the project and the changes occurring during the design and that there is ample information available for the VE team. Project Study Workshop Phase Value engineering is a systemized approach for searching out high cost areas in a design and arriving at the best balance between cost, performance and reliability. It is not a design review. This basic VE Job Plan is followed in all value engineering studies. Value engineering requires the proper positive attitude and removal of roadblocks that thwart creative thinking. w Our experience has indicated that a project orientation by the program coordinator sets the stage for the study. A presentation by the Designer, giving the rationale for design, is also required. A brief presentation on the concept for each discipline in the design will benefit the value engineering study. We would expect to utilize this procedure and propose to establish a format for the study based on the following agenda. WORKSHOP AGENDA Introduction Project Orientation Project Description and Presentation by the Designer Information Phase y Familiarization by team members with the contract plans and specifications. Continue familiarization with project and begin the Functional Analysis of the project. Prepare a graphical presentation of the Cost Model, which is prepared prior to the study. Look at the total system first and then at the component parts. Review energy utilization of the system design using the Energy Model prepared in the prestudy phase. Creative Phase Begin creative idea listing. The aim is to obtain quantity and association of ideas, to eliminate roadblocks and to allow free flow of ideas. Judgement Phase The value engineering team analyzes the ideas listed in the creative session and selects the best ideas for further development. Development Phase Value engineering team members prepare alternate designs for consideration with life cycle cost comparisons of the original designs and proposed alternatives. All recommendations will be backed up with sketches, basic concept and recommendation of alternatives. Presentation Phase Pacific Environmental Services, Inc. will provide all VE worksheets to be used during the study. The results of the team efforts will be summarized in an oral presentation at the end of the study. Our experience has shown that representatives of the Design Architect/Engineer's firm and the Owner's staff who will review the VE team recommendations should attend the oral presentation. All work prepared at the end of the 40 -hour study will be complete with the back -up data, rationale, references, design calculations, sketches, etc. that will be included in the preliminary VE study report. A copy of this data will be given to the Designer at the conclusion of the oral presentation so their personnel may begin working on responses while the preliminary VE report is being prepared. Post Value Engineering Study Phase Upon completion of each value engineering workshop, the value engineering consultant will prepare the Preliminary Value Engineering Report for submittal to the Owner. The value engineering report will include the following: • Project Description and Design Concept of Project. • Original Design and Proposed Alternatives, showing sketches, design calculations and a comparison of the cost of owning and operating the facility. • Life Cycle Cost Comparison. • Potential Contract Savings. A ■ DESIGNER'S INPUT The Design Architect/Engineering firm provides written material for the VE team members to review in advance of the VE workshop. The Designer's staff may also provide a verbal presentation of this material to the VE team as one of the first items of the 40-'hour workshop to accelerate the orientation of the team into the potential alternatives. After the project study workshop, the Designer evaluates the recommen- dations of the VE team and drafts a report on implementation of the VE recommenda- tions. This section is intended as assistance to the Designer's staff in accomplishing their vital input into the VE effort for their project. Information Required from Designer One of the key elements in a value engineering study is the information and background on the project. Effectively relating this information to the VE team will make their efforts more productive. Our experience has shown that if the teams are well informed about the background of the study, their efforts will not overlap comparisons already made by the Designer's staff. The following is a listing of data, generally in descending order of importance, that is needed to conduct the VE studies. This material will be discussed and refined if necessary during the orientation meeting conducted with the Designer prior to the first VE effort: • 35 % Plans • 35 % Specifications • Project Engineering Documentation (PED) • 35 % Cost Estimate • Other Pertinent Background Information Affecting Current Design b Presentation by Designer The Design Architect/Engineering firm for a project has spent much time and effort in the analysis of design alternatives, process selection, building layout, equipment operating systems, building structure, and other areas of the design. Value engineering is not intended to be a review of previous design effort, but a process of developing new combinations for review and acceptance by the Designer and the Owner. Within the 40- hours of a VE study, the team members must become familiar with the project, must zero in on high cost areas, and develop alternative concepts. Being cognizant of the Designer's knowledge of the project helps to bridge the gap and to get a better feel for the rationale used in the development of the project. The following outline is given to assist the Designer in developing his orientation w presentation to the VE team, usually given on Monday morning of the study week: 1. Rationale and history of development of the project. 2. Statement of the problem - What is the Project? 3. Reason for selected sites or site layout. 4. Constraints imposed upon you as the Designer by the Owner, regulatory agencies, etc. 5. Options and /or ideas you would like the VE team to look at. 6. Site characteristics (power, soil conditions, traffic patterns, existing conditions). 7. Public participation for the project ancr areas of public concern. 8. Description of project design. a. Layout/Civil b. Mechanical c. Electrical d. Architectural e. Structural f. Operations 9. What comparisons were made in developing the design? 10. Factors influencing the development of the design. 11. Description of Capital Cost and O &M Costs for the project. Key Questions to Remember Are: • What did the Designer select? • Why was this selection made? • What alternatives were explored? After the Designer's staff make their presentation, the VE team members will be asking more specific questions about the detailed aspects of the project. The intent is to get a free flow of information in an informal atmosphere. It is anticipated the presentation by the Designer's staff should take approximately 1 I - 2 hours. Therefore, in -depth details are not needed for the presentation. U: \SHARED\ABE\VEQUAL%CONDVESf.UDy VALUE ENGINEERING EXPERIENCE MISCELLANEOUS BUILDING PROJECTS 1982-1998 RESULTS OF STUDIES TOTAL CONSTRUCTION COST OF $1,510,110,000 49 PROJECTS TOTAL BUILDING SQUARE FEET 3,904,000 SUMMARY OF KNOWN RESULTS NUMBER OF PROJECTS . 47 KNOWN CONSTRUCTION COST $1,401,310,000 PRESENT WORTH OF IMPLEMENTED $163,702,000 SAVINGS RETURN ON INVESTMENT 95:1 u:4 shared %abe\vequals\veexpMiscres.doc MISC Page 1 of 3 MISCELLANEOUS BUILDING PROJECTS u:\ sharedlabe %vaquals%veexpNniscrea.doc P.W. IMP PROJECT DATE LOCATION CONST. COST SAVINGS* RETURN ON ($11000) (511000) INVESTMENT 49. Vaccine Research Center 1998 National Institutes of Health 23,400 1,627 179:1 1 -5 Story, 83,500 SF Bethesda, MD 48. Embassy Building in Uzbekistan 1998 Department of State, FBO 12,162 1,668 56:1 1 -2 Story, 40,400 SF, Renovation /Addition Washington, D.C. 47. Moderization Building 37 1998 National Institutes of Health 85,400 4,420 152:1 1 -6 Story, 100,000 SF Lab Bethesda, MD 46. Performing Arts Center 1998 CNU 35,419 2,850 31:1 1 -2 Story, 173,000 SF Concert Hail Newport News, VA 45. SR 826 Improvements -Road Reconstruction 1998 Miami, FL 43,000 1,465 31:1 1.5 mile, Palmetto Expressway 44. Sports Wellness Facility 1998 CNU 15,900 2,130 85:1 1- 2Story, 115,200SF, Indoor Track Newport News, VA 43. Thomas Nelson Community College 1998 Hampton, VA 6,120 480 20:1 1 -3 Story 49;100 SF, Classroom 42. NOVA Community College Parking Garage 1998 Alexandria, VA 11,000 600 24:1 2 level, 500 Spaces 41. Residence Hall II 1998 Christopher Newport Univ. ICNU) 11,074 283 13:1 1 -4 Story, 117,000SF Newport News, VA 40. 1-4 Improvements -Road Reconstruction 1998 Orlando, FL 165,000 18,000 360:1 6.2 KM, 2 Interchanges 39. Family Housing Repairs 1997 Sabana Seca, PR 24,610 14,568 388:1 144 Units, 227,000 SF 38. NOVA Community College 1997 Leesburg, VA 7,127 740 23:1 1- 3Story, 49,000 SF, Lab /classroom 37. Fairfax Community College 1996 Fauquier County, VA 8,290 950 29:1 1 -2 Story, 57,400 SF, Academic Building 36. Air Cargo and Air Passenger Terminals 1996 Naples, Italy 13,900 687 17:1 1 -3 -Story, 1 -2 Story, 105,000 SF 35. Water Treatment Plant 1996 Public Works Department 28,500 1,171 47:1 30 mgd St. Joseph, MO u:\ sharedlabe %vaquals%veexpNniscrea.doc MISC Pace 2 of 3 34. Intercoastal Waterway Bridge Replacement 1996 Corps of Engineers 16,000 1,200 60:1 5 Lane, Bascule Bridge Chesapeake, VA 33. Phase II Academic Building CISAT Campus 1995 James Madison University 25,189 2,517 93:1 1 -4 Story 214,600 SF Harrisonburg, VA 32. MSO Office Building, Dhahran, Saudi Arabia 1994 Khatib and Alami Assoc. 39,200 1,450 50:1 196,000 SF, 4 -Story Bldg. 31. Camp Le Jeuns, NC 1993 Atlantic Division, NAVFAC 7,800 224 14:1 250 t pd Landfill 30. Water Supply Dams; Rehabilitation of 3 Dams; 1993 City of Norfolk, VA 19,750 3,800 130:1 Earthen Type 29. Police/Fire /Rescue Bldg. 1992 Port Authority of New York and 11,000 2,700 54:1 JFK Airport, Renovation/New; 2 -Story, 26,000 SF New Jersey 28. Medical Research Lab & Vivarium, 1 -9 Story 1991 University of Virginia 25,663 1,800 51:1 152,200 SF Addition 27. International Airport, 2 -2 &3 Story Bldgs Additions 1991 Bangor, Maine 10,323 1,050 47:1 and Renovation; 150,000 SF 26. Juvenile Detention Center, 2 -2 Story Bldgs; 200 1990 City of New York DGS 57,804 4,150 136:1 Inhabitants, 168,000 SF 25. Carpenter'slCrafts Storage Bldg.; 1 -1 Story, 1990 Nevada Test Site, DOE 1,285 200 10:1 17,000 SF Bldg.; Prefab. Metal 24. Infrastructure and Power Plant; 1 -1 St., 56,350 SF 1990 Kuwait University, Kuwait 38,500 4,150 83:1 Utility Systems 23. Signalization System for Subway System 1990 DORTS, Taipei, Taiwan 120,000 24,250 255:1 22. Renovation 1241,000 SF) and Addition 1990 Kuwait University, Kuwait 37,000 3,010 60:1 1244,200 SF) College of Social Sciences 21. Advanced Photon Source Facility, 7 -1 Story 1990 Argonne Labs, Chicago, DOE 140,354 17,000 113:1 Bldgs. High Tech Complex, 781,000 SF, Research Lab 20. Highway Beautification Landscaping 5 Mile Stretch 1989. Henderson, Nevada 7,260 950 34:1 Urban Highway 19. Employment Security Office, 2.2 Story Bldg. 1989 Salt Lake City, Utah - GSA 5,956 407 16:1 & Parking Garage, 74,900 SF 18. Old Birdhouse Conversion, Bronx Zoo 1989 City of New York DGS 8,600 186 5:1 30,200 SF Historic Renovation 17. Bong Peak Mine • Iran Ore Conveyor 1989 Liberia, Africa 19,600 4,850 84:1 (7km) and lifting (80 m) 17 Million Tons/Year u: UharoMabelvequa lalvasxpWIscrea.doc MISC P... 7 of 9 16. Subway Station and Approach Terminals (8,800 ft. Twin Bore 5.4 m Diameter) 1989 DORTS, Taipei, Taiwan 160,000 7,773 91 :1 15. Police Precinct 2 -2 Story Bldgs., 55,000 SF 1988 City of New York DGS 13,214 380 24:1 14. Queens Museum Reconstruction, 74,000 SF Historic Rehabilitation 1988 City of New York. DGS 11,808 2,300 61:1 13. Administration Building Area 6 - 31,500 SF 1 Story Building 1988 Nevada Test Site, DOE 2,487 700 35:1 12. NAK Waste Disposal Facility 1,988 Oak Ridge, TN DOE 1,066 210 30:1 11. Hospital, 124 Bed, 2 -Story Skilled Nursing Facility, 63,400 SF 1988 Santa Clarita Health Care Assn. Valencia, CA 6,862 243 13:1 10. DOT /DEP Standards and 5 Projects (Reconstruction/Rehab.) 1987 City of New York OMB 72,300 5,100 110:1 9. Fire House Standards Design 1987 City of New York OMB 2,174 310 9:1 8. Flushing Meadows Zoo Rehabilitation - 13 Acre Zoo and Children's Farm 1987 City of New York OMB 8,970 1,610 32:1 7. Library Addition 22,000 SF Second Floor Addition 1986 City of New York DGS 4,807 633 30:1 6. Parking Garage - 517 Spaces, 4 Level Underground, 190,000 SF 1986 City of Chapel Hill, North Carolina 4,937 510 21:1 5. Standard Road and Bridge Specifications Nationwide 1984 U.S. Forest Service 500,000 per yr. 19,000 per year 655:1 4. Region X Hazardous Waste Site Clean -Up 1984 U.S. EPA 9,270 1,510 42:1 3. Arizona DOT, 1010 Lighting Desigrf, 15 Mile Segment 1983 Arizona DOT Phoenix, AZ 5,500 2,487 104:1 2. Orange Grove Road 1982 Pima County Arizona 4,855 820 30:1 1. Kino Boulevard Interchange 1982 City of Tucson Arizona 5,200 630 25:1 u: \shared\abe %vequala\veexplmiscrea.doc