HomeMy WebLinkAboutAgenda - 04-06-1999 - 9cORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: Apri16, 1999
Action Agenda
Item No. ~- C,,
SUBJECT: Contract Approval: Y2K Project Coordinator Services from McGladrey & Pullen, LLP
DEPARTMENT: Purchasing & Central Services/ PUBLIC HEARING: (Y/N)
County Manager
ATTACHMENT(S):
Proposal
INFORMATION CONTACT:
Pam Jones, ext 2650
Rod Visser, ext 2300
TELEPHONE NUMBERS:
Hillsborough 732-8181
Chapel Hill 968-4501
Durham 688-7331
Mebane 336-227-2031
PURPOSE: To consider approving a contract with McGladrey & Pullen to provide Y2K project coordinator
services.
BACKGROUND: The Board is familiar with issues that might affect various aspects of the County's operations
as a result of the Year 2000 software bug (Y2K). At the February 15, 1999 goal setting work session, the Board
indicated its desire to pursue Y2K preparedness as a high priority for 1999, and to proceed with securing the
services of a Y2K coordinator. The County Manager will be in charge of the proposed Y2K coordinator, who will
collaborate with staff in executing the County's remediation, testing, and contingency plans. While County staff
have been diligent for the past year or more to identify and address many Y2K issues, it has become apparent that
constraints imposed by the day-to-day workload make it improbable that without additional personnel resources,
we can guarantee that all Y2K issues are addressed within the given timeframe. Rather than hire an individual(s)
to manage this project, County staff have pursued outsourcing.
A Request for Qualifications (RFQ) for the Y2K project coordinator was solicited from eight firms suggested by
staff at the North Carolina Association of County Commissioners. A County assessment panel interviewed four
firms which responded most appropriately to the County's RFQ, and conducted second round interviews with the
specific proposed project managers of two very impressive firms. The panel included County Manager John Link,
Assistant County Manager Rod Visser, Purchasing & Central Services Director Pam Jones, Information Systems
Director Dick Taylor, and Information Technology Committee Chair John Smith. Based on the review conducted
by the panel, staff recommends that the Board award a contract for Y2K project coordinator work to McGladrey &
Pullen, LLP.
McGladrey & Pullen is a large, well-known consulting firm with specialties that include accounting and
information technology services. They were one of the finalists when the County reviewed proposals for auditing
services in 1998. The individual who will serve as the actual project coordinator, Jiin
McGimsey, is very well-qualified and well-rounded. Prior to his focusing on IT issues and becoming a Certified
Novell Engineer, Mr. McGimsey managed or served on annual financial audit engagements for Craven, Pamlico,
and New Hanover Counties. The assessment panel was particularly impressed by Mr. McGimsey's familiarity
with county government operational issues, and with his demonstrated organizational and communication skills.
While he can bring information technology skills to bear as needed, and can readily secure additional technical
resources from his firm because of its size and breadth of experience, Mr.McGimsey's most important attribute
will be his ability to manage the project and keep the Y2K project team on schedule.
Duties of the Y2K coordinator will include, but may not be limited to, the following:
• Confirm as sufficient those items that have been identified by staff as potentially affected by Y2K problems,
and identify other problematic areas that may not have been considered thus far;
• Collaborate with County staff to establish the timetable and milestones that will be required to meet the
established early-Summer deadline for critical systems testing;
• Assist as needed with identifying resources who can provide independent certification of compliance;
• Identify Subject Matter Experts (SMEs) for critical areas not easily assessed (e.g. embedded microchips);
• Maintain all databases that substantiate Y2K compliance progress;
• Ensure that staff assigned Y2K tasks are compiling/submitting information in accordance with established
timetables;
• Assist with the preparation of public information to be disseminated according to a timetable to be established
by the County;
• Assist in communicating Y2K compliance information through the most effective means.
The Y2K Project Coordinator will have an on-site project office in the Government Services Annex. It is
anticipated that the Coordinator will be on site a significant portion of the workweek for the first month or more of
the contract. After that time, the Coordinator will be on-site for weekly coordination meetings and other times, as
the job requires. Much of the verification work can be accomplished from the Raleigh office via electronic
communication. The contract proposed will include a minimum of 200 hours of direct service, plus SME time for
embedded chips and some additional review of Public Safety and Human Services issues. The total amount of this
contract is $40,000. Should the scope and cost exceed this amount, staff would request that the Board consider the
additional work at that time.
As quickly as the Y2K coordinator contract is approved, the coordinator will meet with the County's Y2K steering
committee to determine the status of the County's progress. The Y2K steering committee includes John Link, Rod
Visser, Albert Kittrell, Pam Jones, Dick Taylor and Paul Thames. Based on the information provided to the
Coordinator, the Y2K compliance implementation strategy and timetable will be reviewed with the Board at the
May 4, 1999, Commissioner's meeting. The presentation will include those items upon which we need to focus, as
well as those tasks that have already been accomplished.
FINANCIAL IMPACT: The contract proposed will include a minimum of 200 hours of direct service, plus SME
time for embedded chips and some additional review of Public Safety and Human Services issues. The total
amount of this contract is $40,000. Should the scope and cost exceed this amount, the Board would be requested
to consider the additional work at that time. Staff suggests that funds not yet obligated from the 1998-99 IT Plan
implementation be diverted to cover the cost of this contract. Funds thus borrowed will be restored to the 1999-
2000 Information Technology Capital Project for their originally intended purposes (such as legacy system review
and replacement) in the 1999-2009 CIP.
RECOMMENDATON(S): The Manager recommends that the Board approve a contract with McGladrey &
Pullen for Y2K Coordinator services in an amount not to exceed $40,000; and authorize the Manager to sign the
contract, contingent upon Attorney and Staff review.
3
Ms Pam Jones
Purchasing Director
Orange County
March 9, 1999
Page Two
AGREED AND ACCEPTED
Please call Jim McGimsey (919) 781-1055 or Kirk Olsson at
(651) 221-1154 if you have any questions regarding our proposal. We look forward to
being of service to Orange County. If this proposal is in accordance with your
understanding of the services to be performed by us, please sign and date the enclosed
copy and return it to us.
Sincerely,
McGLADREY & PULLEN, LLP
James R McCrimsey, Manager
Integrated Technology Solutions
Bert Hazdy, Senior Manager
Integrated Technology Solutions
Agreed to and Accepted by:
Orange County
Name and Title
1999
Date
Proposal for
Year 2000 Consulting Services
Orange County
II. ASSESSMENT METHODOLOGY
A. SCOPE
The scope of the project will include the following major systems and related
equipment and softwaze components within Orange County:
• Main computer system(s)
• Local azea networks (LANs)
• Applications or interfaces developed by third parties
• Various PC softwaze applications
We will assess the effectiveness of the County's Yeaz 2000 compliance efforts, and
provide recommendations for potential improvements to the process.
B. APPROACH
To accomplish the project objectives, we perform the following major activities:
1. Review and evaluate the County's technology plans and direction; especially as
they relate to Year 2000 compliance, including:
• Allocation of resources for technology
• Annual and strategic business plans
• Plans for the use of technology in the future
2. Review and evaluate the technology infrastructure within the County, including:
• Current hazdwaze, including main computer systems, LANs and PCs, imaging
system, audio response system and other technology.
• Current operating software, including operating softwaze, programming
languages, database software, and report writers.
• Application software, including turnkey and custom applications.
• Application interfaces to other processing systems.
• Policies, practices and guidelines relating to information technology.
3. Determine the County's source of information systems (IS) support for hazdwaze
and related applications and operating system softwaze.
4. Provide our Year 2000 Readiness Questionnaire and review responses to the
questionnaire.
5. Obtain a comprehensive inventory of all hazdwaze and softwaze used throughout
the County.
® 1998, McGladtey 8t Pullen, rt.~
Proposal for
Year 2000 Consulting Services
Orange County
6. Assess the financial and operational capabilities of the hazdwaze and software
vendors or developers to provide Yeaz 2000 processing capabilities, including:
• Compliance with the American National Standards Institute
• Presentation format
• Database format
• Data entry forms
• System generated forms
• Documentation
• Other considerations
7. Determine whether all affected applications will have Yeaz 2000 renovations
complete with testing well underway by December 31, 1999.
8. Identify the significant applications that will not have Yeaz 2000 renovation
complete by December 31, 1999.
9. Consider the effect to the County's strategic and operating plans should all
systems not be Yeaz 2000 compliant by December 31, 1999.
10. Idernify corningency plans to ensure the financial institution's ongoing operations
if its systems will not be Yeaz 2000 compliarn by December 31, 1999. We also
will consider contingency plans should hardware or software systems not function
correctly on January 1, 2000, because of the millennium date change.
11. Determine whether the County is coordinating modification and testing activities
with vendors, servicers, and organizations with whom critical data is received or
sent.
12. Establish a process to certify that a vendor(s), product(s) and future releases or
modifications aze Year 2000 compliant.
13. Determine how the County will maintain sound internal controls over the
software change process for Year 2000 issues. We will determine the need for
internal or external audit functions to assess the soundness of internal controls
associated with the Year 2000 effort.
14. Determine whether the County has adequate resources for the Yeaz 2000 initiative
by identifying:
• The type of technical expertise that will be needed
• The amount of time needed for corrective action
15. Assess the anticipated additional systems resources required specifically for
operating systems, telecommunications networks, and security software to handle
Yeaz 2000 processing.
® 1998, McGladrey Bt Pullen, r.i.P
Proposal for
Year 2000 Consulting Services Orange County ~p `
16. Consider the adequacy of computer resources for testing Year 2000 changes while
performing day-to-day processing activities.
17. Assess the impact of Yeaz 2000 efforts on business continuity/recovery planning.
18. Develop a plan for renovating, testing, and implementing solutions for Year 2000
processing.
19. Prepare our report that describes the results of the Year 2000 compliance
assessment and plans.
C. REPORTING
We will prepaze an assessment report describing:
• The computer systems' Year 2000 processing capability.
• Assessment of the adequacy of resources devoted to Yeaz 2000 problems.
• The adequacy of the orgatization's plans for identifying, correcting, testing, and
implementing solutions for Year 2000 processing.
• The date methodologies selected to provide Yeaz 2000 processing.
• The status of the vendors' plans and the capabilities to complete necessary
changes with testing well underway for mission critical systems by December 31,
1999.
• Effectiveness in coordinating Yeaz 2000 processing capabilities with the hardware
and softwaze vendors, corporate borrowing customers, and payment systems
providers.
• The effect of the Year 2000 effort on the County's strategic and operating plans.
• The effectiveness of internal controls for the Yeaz 2000 process.
We also will prepaze recommendations, as appropriate, on any additional actions
necessary to ensure the County's safety and soundness associated with its Yeaz 2000
processing capabilities.
D. PROJECT BENEFITS
The benefits of this project will include:
• An assessment of the County's ability to implement Year 2000 related changes.
• Identification of systems and equipment still in need of change to become century
compliant.
• Identification of vendors which need to provide Yeaz 2000 compliant
certification(s).
• Identification of constituents who may be impacted by the County-provided
electronic information or vendors who provide electronic information to the
County that must be Yeaz 2000 compliant.
® 1998, McGladrey & Pullen, r.[.P
Proposal for ~~
Year 2000 Consulting Services Orange County
• Better understanding of technology alternatives and resources required for the
Year 2000 conversion.
• Identification of procedures that potentially may need to be altered due to century
compliance.
• Identification of critical areas where temporary operating procedures should be
developed in the event that Year 2000 conversion efforts are not completed in
time.
• Observations and recommendations for improvements that will help ensure that
the County is Year 2000 compliant.
® 1998, McGladrey & Pullen, L~
Proposal for
Year 2000 Consulting Services
Orange County
I. OVERVIEW
A. BACKGROUND
In less than 10 months and for the first time in history, computer-based information
systems will be faced with a new century. Some experts report that over 90% of
computerized systems will have difficulty coping with this issue, in varying degrees.
Many organizations aze in "denial syndrome," thinking that they still have two yeazs
to address the problem or that it's a program maintenance problem. Others who
understand the risks involved realize that this is a business survival issue. Even
today, as awareness increases, organizations aze signing contracts and installing
systems without insisting on Year 2000 compliance certifications from their vendors.
The first phase of addressing this issue is to assess your organization's exposure to the
date change. This includes identifying the impact on all hazdwaze, softwaze,
networks, processing platforms, as well as customer and vendor interdependencies.
The assessment should extend beyond information systems and include
environmental systems that are dependent on embedded microchips, such as security.
and alarm systems, elevators, vaults, telephones, FAX machines, HVAC (heating,
ventilation, and air conditioning) equipment, etc.
B. PROJECT OBdECTIVEs
The objectives of this project are as follows:
To review the Yeaz 2000 efforts on the County's strategic and operating plans and
systems.
To develop an effective plan for identifying, renovating, testing, and
implementing solutions for Year 2000 processing.
To determine how the County should coordinate Year 2000 processing
capabilities with its customers, vendors, and payment systems partners.
The result of the assessment is to identify strengths and weaknesses, and to provide
recommendations for improving systems and procedures within the County to
become Year 2000 compliant.
® 1998, McGladrey 8t Pullen, t,r.t-
Proposal for ~
Year 2000 Consulting Services Orange County
C. MCGLADREY BENEFITS
A number of important factors contribute to good, productive working relationships
between clients and their consultants. These factors include the skills and
personalities of the persons assigned to an engagement, the quality of the services
delivered, experience, costs, and more. We believe we have some special qualities
that distinguish us from other public accounting and consulting firms, as described
below.
1. This project will be staffed by consultants that have extensive experience in
government operations, information systems, technology planning and Yeaz 2000
compliance issues.
2. Our staff continually performs technology assessments, planning and studies. As
a result, we have experience with a wide variety of government organizations in a
broad range of processing environments. In addition, we have regular contact
with all leading systems and technology providers and aze well informed with
respect to vendor and government industry developments.
3. Our organizations do not sell hardware or software to the government sector;
therefore, we will be completely independent and objective in regard to all aspects
of this project. We will provide an objective and independent assessment of
needs, and are influenced only by the vendor's capabilities to satisfy the
requirements identified during the project.
4. Our existing understanding of network operating systems platforms such as
Novell NetWare, UNIX, Windows NT server, AS/400, DEC and other host-based
systems, in addition to our wide area and local azea network design experience,
will significantly reduce the amount of time required by your staff to educate us
on yow systems.
5. Many of our consultants hold certifications in Novell NetWaze, Master Certified
NetWare Engineers (MCNE's), CNE's, Microsoft's Certified Professional's
(MCP), Bay Networks and Cisco Systems trained staff, information security
experts, and former federal regulators.
6. We have developed the 2000 Planner7FA software, which provides an automated
technique for tracking and monitoring Year 2000 compliance planning efforts.
?. We have written several books on various information technology topics,
including:
• Year 2000 Planning
• Strategic Information Technology Planning
• IT Development
• IT Management
• Systems Selection
• Computer Crime
• Disaster Recovery Planning
® 1998, McGladrey & Pullen, ~
~,
~~,
Proposal for
Year 2000 Consulting Services Orange County
8. We have significant experience working with financial institutions in developing
and implementing their Year 2000 plans. This industry has taken a leadership
position in resolving the Year 2000 problem. The experience gained while
working with these clients will be utilized on this project.
9. Providing services of the highest quality is a basic tenet of our Firm. We believe
this fundamental strength is enhanced by our orientation to help clients anticipate
future needs. This approach is part of our basic service to clients.
10. Several of our consultants hold certifications from the Information Systems Audit
& Control Association (CISA), and are Certified Business Continuity
Professionals (CBCP).
l l .Our strategic plan is to continue to be the leaders in servicing government entities.
12. Our mission and client service philosophy is based on helping our clients succeed.
® 1998, McGladrey & Pullen, t.[.p
Proposal for
r Year 2000 Consulting Services
Orange County
,~
i;
~ j
Project Team
Organization Chart
PROJECT
DIRECTOR
Geoffrey Wold
TECHNICAL
ADVISORS
Bob Shriver
Mack Manning
Roger Peters
PROJECT
MANAGER
Kirk Olsson
QUALITY
ASSURANCE
Stan Mork
ORANGE
COUNTY'S
Project Coordinator
ORANGE
COUNTY'S
Project Team
McGLADREY 8~
PULLEN
Y2K
COORDINATOR
Jim McGimsey
ORANGE
COUNTY'S
Technical Staff
ORANGE
COUNTY'S
Department Personnel
® 1998, McGladrey & Pullen, r.r.P
i~
Proposal for
Year 2000 Consulting Services
Orange County
Timing and Fees
D. TIMII~iG
At this time, we anticipate that we can begin this engagement within two weeks after
your notification to proceed. We anticipate that the elapsed time to complete the
Yeaz 2000 review and assessment should be approximately two to four weeks.
We request that an appropriate person from the County be assigned to this project to
help coordinate the project internally, and assist us with various data gathering tasks
as required.
E. FEES
Our fees aze based on the actual time spent on a project at our standazd hourly rates,
plus direct expenses. Travel-related expenses will be in addition to the above fees
and aze billed as the actual amount incurred. The fees outlined above will remain
valid for 90 days from the date of issuance of this proposal. Travel time is billed at
half the normal rate and mileage is billed at .31 S centslper mile.
Our normal policy is to bill monthly as work progresses. Iiy during the course of this
project, the nature or scope of our work should change, we would discuss such
matters with you and any expected effect on our fee estimate. ff we find that our fees
for providing the services as proposed aze less than estimated, we will bill you the
reduced fees.
The following are the normal billing rates for individuals who would work on this
project:
Bert Hardy -Project Director $225.00
Jim McGimsey -Project Manager $150.00
Kirk Olsson -Governmental Manager $265.00
Roger Peters - Y2K Manager $225.00
Stan Mork -Project Partner $305.00
Our fees are based on the assumption that the County will perform the following
activities:
• Provide an inventory of all hazdwaze, including model numbers.
• Provide an inventory of all software, including version/release level and vendor
comact information.
• Complete our Year 2000 Readiness Questionnaires.
• Enter various inventory-related information into the 2000 PlannerTM softwaze.
• Gather existing vendor contracts.
• Cazefully review our resulting report.
® 1998, McGladrey & Pullen, LLP