HomeMy WebLinkAboutAgenda - 06-02-2009 - Informtion Item 1T n -Fo r mq'~ ~ o r~ _'~" ~ rr,
Memorandum
TO: County Commissioners
FROM: Pam Jones, Director of Purchasing and Central Services
RE: History of County Campus Acquisition
Date: May 18, 2009
The following is a chronology of the development of the new County Campus on
West Margaret Lane. It is provided in response to a Commissioner request.
2000-2006: County conducted Space Needs Study defining the operational
space needs for all County departments in 2000. This analysis was updated in
2004 and again in 2006.
June 19, 2006: Pursuant to NCGS 143-318.11 (a) (5) "to discuss the County's
position and to instruct the County Manager and the County Attorney on the
negotiating position regarding the terms of a contract to purchase real property
for county offices" the Board met in closed session on June 19, 2006, to consider
three options for developing a county campus. By a vote of 4-1, Commissioners
approved a letter of commitment for the campus property on South Churton and
West Margaret Lane in Hillsborough, with several contingencies.
October 3, 2006: In closed session and pursuant to NCGS 143-318.11 (a) (5)
the Board discussed the terms of a contract presented by the County Attorney to
acquire the County campus.
October 17, 2006: Pursuant to NCGS 143-318.11 (a) (5) the Board met in closed
session and the County Attorney reviewed revised terms of the contract to
acquire the county campus. Contingencies included in the contract involved the
approvability of the project with the Town, funding availability and the delivery of
acceptable contract documents from the Construction Manager at Risk, who
would construct the three buildings on the campus. The Board agreed the terms
of the contract as presented were acceptable and they would allow the County
Attorney to prepare the item to go forward for public hearing on November 2,
2006.
November 2, 2006: Public Hearing was held on the County acquiring the County
Campus property on S. Churton Street and West Margaret Lane. Following the
public hearing, the Board voted to acquire the properties, assuming the
contingencies of the contract could be met.
March 27, 2007: Upon recommendation of the Library Director and staff, the
Board of Commissioner contracted with Phillip Barton to provide interior space
planning for the new library.
May 22, 2007: Public input sessions were held for the Library interior design.
Three sessions were held for staff, the Library Task Force and the Public on this
date. Resulting comments were incorporated into the final design submitted by
Mr. Barton.
June 26, 2007: The County Campus Purchase and Sale Agreement and
Construction Manager at Risk (CMR) Contract were approved with the following
contingencies:
• Design contracts for buildings would be borne by the County consistent
with State Law;
• The Gateway Center property would be acquired contingent upon the
developer successfully closing a deal with Weaver Street Market for the
first floor of the Gateway Center;
• All regulatory approvals could be obtained for the proposed facilities;
• The CMAR could satisfy the criteria of his loan underwriter.
o Note: The County was required to make no progress payments
during the construction of the County Campus project. The first
payment was made in February 2009 when the Gateway Center
was purchased. Payments for the Library and office buildings are
anticipated after July 1, 2009.
• The County could obtain LGC approval and underwriting approval of debt
structuring within the County's policy of 15% of General Fund with 7%
annual growth.
• Execution and delivery of contract documents from the CMR with his
construction contractors. (Note: CMR required to follow public bidding
regulations in the selection of contractors to carry out the work.)
• The developer must submit evidence of a clean bill of environmental health
on all properties.
June 11, 2007: BOCC approved professional services contracts for the design of
the office building and library.
January 15, 2008: BOCC considered modifications to the contract as requested
by the developer. While none of the modifications changed the project cost, the
developer reserved the right to increase cost if the bids for the project were
substantially beyond the original estimate. Programming of the office building
and library had taken longer than the developer anticipated, but were necessary
to ensure the designs were vetted by the County and would ultimately yield a
facility usable for the long-term.
October 21, 2008: The Board approved an additional $445,569 for sustainable
design elements to be added to the buildings. While basic sustainable design
features were included in the design of the buildings originally, the contract
provided that the County would pay for additional sustainable design elements it
deemed appropriate. The buildings were designed with energy efficient HVAC
systems however the County opted to look for even deeper long term savings
2
since HVAC is a primary energy consumer in a building. The installation of the
four-pipe systems approved by the Board not only added an expected eight
years to the life of the systems, but recouped the capital cost in a very
respectable 8.9 years.
April 7, 2009: The Board approved an additional $225,788 to install emergency
generators for the office building to ensure continued operations of the County's
data center during power outages. The office building also contains several
conference rooms which could serve emergency response needs if power were
available. An emergency generator was not included in the original proposal, but
is prudent given the occupancy of the building.
Total cost of the expanded County campus is budgeted at $25,700,000, which
includes all development and construction costs, as well as costs to upfit and
furnish the Gateway Center offices, the office building and the Library. The
Gateway Center property was purchased as of February 23, 2009 pursuant to
the contract. The office building and library are scheduled for completion in
Summer 2009.