Loading...
HomeMy WebLinkAboutAgenda - 06-02-2009 - 6cORANGE COUNTY BOARD OF COMMISSIONERS ACTION AGENDA ITEM ABSTRACT Meeting Date: June 2, 2009 Action Agenda Item No. Co - C SUBJECT: Rogers Road Small Area Plan Task Force Report DEPARTMENT: County Manager's Office Planning and Inspections ATTACHMENTS: 1. Letter Received from Town of Chapel Hill 2. Rogers Road Small Area Plan Task Force Report (Under Separate Cover) 3. Staffs Comments on Plan 4. December 10, 2002 BOCC Minutes - Greene Tract 5. Proposed Letter to Town of Chapel Hill 6. March 26, 2009 Assembly of Governments Meeting Minutes 7. Historic Rogers Road Community Enhancement Plan Development and Monitoring Task Force - Final Report and Recommendations PUBLIC HEARING: (Y /N) No INFORMATION CONTACT: Gwen Harvey, 245 -2300 Craig N. Benedict, 245 -2592 Perdita Holtz, 245 -2611 PURPOSE: To receive the Rogers Road Small Area Plan Task Force Report, in relation to the Historic Rogers Road Community Enhancement Plan Development Monitoring Task Force Report, and consider submitting comments to the Town of Chapel Hill. BACKGROUND: The Rogers Road Small Area Plan Task Force is a Town of Chapel Hill Planning effort focused on the Rogers Road community (see map of study area on pages 7 and 8 of the attached report). The Task Force was created by the Town Council on December 4, 2006 and has been working on a Small Area Plan since early 2007. The Task Force completed its work in early 2009 and a Final Report was discussed at the March 26, 2009 Assembly of Governments meeting. Town Task Force The Task Force's Final Report contains recommendations in several topic areas on pages 20 and 21. The Implementation process begins on page 22. Several recommendations are of particular interest to Orange County because of past area infrastructure funding, future funding sources, and involvement of the Greene Tract, of which Orange County is a joint owner (see further discussion of the Greene Tract below). These particular recommendations include: FA • A road should be built that connects the neighborhood to Weaver Dairy Rd. • Water and sanitary sewer mains should be extended to the community. • The Towns of Chapel Hill, Carrboro, Hillsborough, and Orange County should collaborate to identify and secure funds to be used for financing the entire cost of OWASA water and sewer connections for individual homes within the Historic Rogers- Eubanks community as part of the compensation for the 37 years of hosting the Orange County Landfill and other solid waste facilities. Attachment 1 [of the report] provides a list of available funding sources at the state and federal levels. • Passive recreation opportunities such as trails should be constructed on the Greene Tract. In order to do so, the Greene Tract Concept Plan should be revised by the local governments to reflect changing conditions along with this plan. NOTE: A large portion of the Rogers Road Small Area Plan planning area is comprised of the "Greene Tract." The Greene Tract is a 104 -acre parcel in the joint ownership of Orange County and the Towns of Carrboro and Chapel Hill. Additionally, the County solely owns an adjacent 60 -acre parcel that was originally part of the Greene Tract plus the "Neville Tract" which encompasses 14.7 acres. The BOCC Minutes contained in Attachment 4 provide greater context of the Greene Tract and the jointly agreed upon uses for the Greene Tract. Additionally, there have been more recent discussions regarding the Greene Tract to include a school site on the tract and to reorient the designated affordable housing area on the tract. • The Town should explore options similar to the Homestead Exemption that would enable current property owners, particularly long -time residents, Habitat residents, and descendants of the Historic Community, to retain ownership of their property. • Local governments should collaborate with the community to develop strategies that help ensure that the majority of the housing stock be affordable to those making at or below 80% of the Area Median Income. At the end of April 2009, Orange County received a letter from the Town of Chapel Hill inviting comments on the Report and requesting comments by June 30 (see Attachment 1). The Report was sent to the following County staff for review and comment: County Manager Assistant County Managers (2) County Engineer Director of Solid Waste County Staff Comments Director of Purchasing and Central Services Director of ERCD Director of Planning Director of Community Development Staff's comments are contained in Attachment 3. After receiving comments from local governments and advisory boards, the Town Council will consider amendments to the Chapel Hill Land Use and Comprehensive Plan. Town Plan Implementation The planning area is located in the Chapel Hill Transition Area, as defined by the Joint Planning Agreement (JPA). Page 6 of the Final Report contains a brief synopsis of the JPA. Implementation of the Small Area Plan will require amendments to the Joint Land Use Plan (LUP). The process for amending the LUP is contained in the JPA and requires adoption by all three parties to the JPA. The "Implementation Actions" on page 25 of the Final Report proposes the LUP amendment be heard at the October 2009 JPA Public Hearing. The Town of Chapel Hill will take the lead in initiating proposed changes to the LUP. Implementation Actions associated with community improvements call for establishing a local government work group. This work group will develop a funding and phasing plan for water and sewer services and also identify transportation and traffic calming projects. The concept of a local government work group was discussed — with consensus to establish — during the Assembly of Governments meeting in March. BOCC Task Force In 2007 the BOCC engaged in a parallel planning effort known as the "Historic Roger's Road Community Enhancement Plan Development and Monitoring Task Force" which overlapped on the Town of Chapel Hill's planning area. A final report and recommendations was received as information by the BOCC in December 2008 and a copy is included in Attachment 7. Additional materials related to this effort are available at: http: / /www.co.orange.nc.us /recycling /rogersroad.asp. The County report and Town report share similar findings and conclusions which may be integrated to form a common strategy. County management suggests the BOCC consider authorizing staff to create a framework to cross -match the work of the 2007 County Historic Rogers Road Community Enhancement Plan Task Force with the work of the Town's Small Area Plan Task Force in a coordinated fashion prior to formation of the local government work group. Staff's work should include analyzing timing, phasing, and funding issues to be developed in full by the local government work group. FINANCIAL IMPACT: Implementation of many of the recommendations made in the Town Small Area Plan and /or BOCC Task Force Final Report is expected to have significant fiscal impacts, potentially in the millions of dollars (i.e., water and sewer infrastructure). The local government work group should pursue an aggressive strategy of federal and state grants to help support desired community improvements. RECOMMENDATIONS: The Manager recommends the Board: 1. Receive the Rogers Road Small Area Plan Task Force Report and recommendations of the Report found on pages 20 and 21. 2. Authorize the Chair to sign the letter in Attachment 5, with accompanying staff comments in Attachment 3. 3. Authorize staff to create a framework to cross -match the work of the 2007 County Historic Rogers Road Community Enhancement Plan Task Force with the work of the Town's Task Force in a coordinated fashion prior to formation in the local government work group. Staff's work should include analyzing timing, phasing, and funding issues. i b WNCEIVED APP FPO-2009 March 20, 2009 Ms. Valerie P. Foushee, Chair Orange County Commissioners P.O. Box 8181 Hillsborough, NC 27278 TOWN OF CH"EL HILL Mayor's Office 405 Mazda LW&e= Mng Ja Blvd. Chapel IM NC 275145705 pbw (919) 968 -2714 fax (919) 969 -2063 WW rtowaofchapeU -- Re: Referral of the Rogers Road SmaH Area Plan Task Force Report Dear Valerie, On March 18, 2009, the Chapel dill Town Council adopted a resolution to receive and refer the final report of the Rogers Road Small Area Plan Task Force. After receiving comments from local governments and advisory boards, the Council will consider amendments to the Chapel Hill Laud Use and Comprehensive Plans. Since the entire Rogers Road study is located within the Town's northern joint planning . transition area, one of the steps in implementing this small area plan will be to amend the Joint Planning Area Land Use Plan which would require approval by Orange County. We are truly excited about the opportunity to work with Orange County to plan for the community's future. Your feedback and questions are important. It is our hope that comments could be provided before June •30 iu order for our staff to be able to report back to the Town Council. Please let us know if this is not enough time. If you have any questions, do not hesitate to contact me. Sincerely, Y� Kevin Foy Mayor Joint Planning Agreement Petition to Carrboro and Orange Resolution 2006- 12- 04/R -1 S First meeting of The Town partnered with Final draft reports by the Task force endorsed a final report for between Chapel Hill, Council to County appoint f sets a schedule G the Rogers Road Small Area the Durham Area Design Group, The Design Assistance Team are completed O review by Council and T Carrboro, and Orange County for Greene and initiate a small area plan for Rogers' officials to serve as members of theTask Small Area Plan process O �3 and composition of the tof, Plan Task Force G 6 Rogers Road Urban 4� and available for r+ �j Advisory Boards N6 Neville Tracts Road Community Farce. K Task Force A Council refered s Design Assistance Team comment. a� > ,fl do a N O O Interim Report to facilitated a planning a O workshop on June 7 p d O aO tp d F 00` Carrboro and Orange County . 3 2008 Op ..Od OS1 Q� area, including the p Q� ,JC elements of each Q Habitat for Humanity submitted Council resolution appointed Preliminary staff Cb Town Sponsered - Interim Report to Council The Design Assistance Team the b Task Force meeting to review and comment concept plan for the Rusch Bill Strom and Mark discussions O Rogers Road open rp O presented .O Task Force three on the Town Staff's Hollow Subdivision Kleinschmidtasrepresent- ;Ob .. house at Faith 00 ;ry with NO , course for OP, O itaves for the creation O km Tabernacle Oasis N Council refered ^ plans which emerged ^ suggested d of a small area plan for ry k of Love ^ Interim Report to ^ from the Lune ^ implementation -Q the Rogers Road ^ d F V Carrboro and Orange County W workshop, \,>, emphasizing common {1J Q� area, including the p Q� ,JC elements of each Q GreeneTract i yJ design M Location The Rogers Road study area is approximately 330 acres. It is bounded by the Nor- folk and Southern Railroad to the east, the existing residential neighborhood of Billabong Road and Homestead Place to the south, Rogers Road to the west, and the Orange County Landfill to the north. The Rogers Road study area is located in Orange County northwest of the municipal boundary of the Town of Chapel Hill and northeast of the Carrboro Municipal Boundary (Figure 2). It is also located in the Chapel Hill Transition Area, which includes areas planned to become part of the Town of Chapel Hill and within the Town's Urban Service Boundary. The Transi- tion Areas of Chapel Hill and the Town of Carrboro were established with Orange County in 1987 though the Joint Planning Agreement (Figure 1). Almost half of the study area (164 acres) consists of the jointly owned Greene Tract. Approximately 60 acres was deeded exclusively to Orange County pursuant to the 1999 interlocal "Agreement for Solid Waste Management." The remain- ing 104 acres is jointly owned by Orange County, the Town of Chapel Hill and the Town of Carrboro. The Greene Tract was originally purchased in 1984 as a potential future landfill and is located southeast of the existing Orange County landfill. A concept plan prepared by a Greene Tract Workgroup' was approved by the joint owners in late 2002. This plan identifies that 18.1 acres of the jointly owned por- tion will be developed for housing and the remaining acres of the jointly owned portion will be preserved and managed as open space. The remaining portion of the study area consists of approximately 80 lots and tracts in the historic Rogers Road neighborhood. The properties are primarily ac- cessed via Purefoy Drive off Rogers Road. The Joint Planning Agreement of 1987 In 1984, the Town of Chapel Hill and Orange County entered into a Joint Planning Agreement that called for the development of a Land Use Plan for the areas immediately surrounding Chapel Hill and Carrboro, but located outside the extraterritorial planning jurisdictions of the two towns. These areas outside of each Towns's respective corporate limits and planning jurisdiction were known as Joint Planning "Transition Areas" Initially, the Town of Carrboro was not a party to the Joint Planning Agreement. The staffs and Planning Boards of Chapel Hill and Orange County prepared a Land Use Plan. The Town Carrboro was also updating its Land use Plan and began to participate in the Joint Planning process. A public information meeting was held in November of 1985. The results of this meeting combined with public hearings in January and April of 1986 were merged to produce the Joint Planning Area Land use Plan. The Plan was adopted by the Chapel Hill Town Council and the Orange County Board of Commissioners on October 13, 1986. Following efforts to streamline the review process for developments located in transition areas, the Town of Carrboro joined Chapel Hill and Orange County in adopting a new Joint Planning Agreement on November 2, 1987. The Town of Chapel Hill Comprehensive Plan, a long range plan for future development of the Town reflects the Joint Planning Agreement and identifies an Urban Services Boundary. This boundary defines the future town limits in which it is intended that the Town will grow and provide typical urban services. The Rogers Road Study Area is within this boundary. 'The Greene Tract Work Group was comprised of elected officials. They met in 2002 to determine the use for the re- maining 109 acres of the of the Greene Tract and to discuss the disposition of the property. The Work Group agreed that the three public purposes of open space, affordable housing, and recreation were the uses to be programmed for these 109 acres. Wy _!— ao Acres prari9 e CO, Ades (oidabtr`` � t "'Ing g6 Acres Open Spice r l4orace VW"Vlarns Tract (carol r<a North) Residents Of Rogers and the 1700s when Eubanks Roads can trace and Black woods, some Of the earliest f ace their family landholdings woods, a'nilies ' back families settled in the area in Orange count to like the After em Y such as the Ho sale Rogers and Nu ancipation, Bans at the Durham ns began farming American development fanner's ming in the elopment b area, taking their crops boom experienced and enduring the Great p for families joined the by Ora epression, p Orange agricultural Rogers �fubanks g County in the 0 wring the rural focu Road neighborhood, 196 s and 1970s more s as Properties built. es were The area slow! divided among siblings Y lost its Ss and new housing was In 1972, the north side of to serve Orange Road became the site of Orange Count was the first a solid waste t Y and permitted s andfill expansion was constructe solid waste disposal on the southside o f d to lesser standards Posal site in landfill, reside Euban than the 1995 residents in the ks Road. Asa Landfill of negative i Rogers Road stud result of their 'pacts Y area have to the include • associated with ave endured increased truck modern solid several decades rats traffic illegal aste disposal and vultures. at dumping, a Practices. T Put stench hese contaminated wells, Figure 3 - --- Aerial Image of range Count, Development and Infrastructure Concepts The early meetings of the Rogers Road Task Force addressed the manner in which new infrastructure such as sanitary sewer and additional road access could be provided in association with new developments, particularly on the Greene Tract. The Task Force also developed a set of guiding principles and recommendations. This section describes the findings of the Task Force prior to the community design workshop in June of 2008. Concepts for Sewer Extension Most of the Rogers Road study area is served with water by the Orange Water and Sewer Authority ( OWASA). Water lines extend eastward from Rogers Road. OWASA sanitary sewer has been extended into the southwestern part of the study area. OWASA policy is to utilize gravity flow rather than pumping stations. Pumps are not desirable because they may fail during storms and they involve operating costs for electricity and maintenance. In March 2007, as part of the Rogers Road Task Force discussions, OWASA staff presented a conceptual layout of a sanitary sewer network that could provide service to existing lots within the Rogers Road study area. The conceptual layout identifies new lines that would need to be constructed and an existing line extend- ed to provide gravity sanitary sewer service to existing lots. This includes extending the existing line from the southwest, a new line to Eubanks Road in the northeast and a new line to the west which could be provided in cooperation with the Town of Carrboro. Figure 4 on page 11 is the existing and conceptual sewer network plan for the study area. There is one concept for the Rogers Road study area with two versions ( A and B). Both rely on the extension of sewer mains into the northeastern terri- 110 1 tory of Carrboro. They differ in that Concept A serves the Neville Tract and the adjoining 24 acre Harris property from a new line to the north that ties onto the extension for the Orange County Landfill. Concept A has greater potential to facilitate subdivision of the Har- ris property. Construction is estimated to cost $ 2.9 million' in 2007 dollars. Concept B serves the same properties via a new line to the west. Construction is estimated to cost $ 2.5 million' in 2007 dollars. Neither Concept A or B serve properties off Sandberg Lane or 3 lots off Merin Road. Concept C shows how gravity sewer could be provided to those lots not served by A or B via a new line along Billabong Lane. Billabong Lane is beyond the study area. A third concept,Concept C, would add $1.3 million' in 2007 dollars to the construction cost of Concepts A or B and extend service to the properties in the southeastern corner of the study area. In accordance with existing OWASA policies, benefiting properties would bear the cost of extending water and sewer lines. The Task Force also reviewed the assessment process for neighborhoods pursuing water and sewer service. Task Force members expressed great concern over the ability of existing homeowners to bear the cost of installing main lines, hooking up to services and paying utility bills, thereby decreasing the affordability of low - cost housing that currently exists in the study area. Z The proposed sewer and water lines are preliminary configurations provided by OWASA (Orange Water and Sewer Authority). If the Town decides to pursue these or other concepts, additional engineering and professional services will be needed to provide site -level detail and overall determination of project feasibility. These estimates do not include the additional cost for connecting individual properties to the sewer system. Rogers Road and Surrounding Area Existing and Conceptual Sewer Network Sewer Extension Cost Estimates Adjusted for Inflation from 2007 Estimate Concept A $3,110,400 Concept B $2,721,600 Concept C $1,393,200 Concepts A +C $4,503,600 Concepts B +C $4,082,400 OWASA Proposed—Sewer GravitySewerMains - - - - -- Proposed Landfill Gas Pipe Routing I _ I Rogers Road Study Area Area of Focus Abp by - Chapel Hill Planning Sowce: Sewer Data from 0WABA T N Concepts A and B are i identical except that B I � ' � X"', f __.,� extends sewer to the orange county Landfill - �� properties west of the t Neville Tract. i t - Note the differences between A and 8 t� � PROPOSED LANDFILL ` B GAS PIPE ROUTING - Neville \ �I j Tract A� i -Nj Greene Tract aQ8 J� Bil In i ll r Carrrboro _ / Ha estead Rd rlgure 4 - conceptual sewer networK proposea py OWASA Transportation Improvements Most properties in the study area are accessed from Purefoy Drive off Rogers Road. Rogers Road is a two lane facility currently classified as a collector street by the North Carolina Department of Transportation (NCDOT). The traffic volume in 2007 was approximately 5,000 vehicles per day, a rise from 3,000 vehicles per day in 1990. (In general traffic on Rogers Road has increased by 4 to 6 percent per year.) Purefoy Drive as currently constructed is sufficient to accommodate 500 - 1,500 vehicle trips per day. The Task Force recommendations propose that new development in the study area may require expansion or upgrade of existing streets. The Task Force identified the need for additional access to the neighborhood and more internal road connec- tions (See Figure 6) In particular they identified the need to have a north -south roadway connection through the study area to connect to Eubanks Road. Orange County owns approximately 70 percent of the property with frontage on Eubanks Road including the landfill site, the solid waste operations center and the animal shelter. The Task Force considered options to provide an east to west road connection to the neighborhood through the Greene Tract. Transit Service Currently, the Rogers Road area is served by Chapel Hill Transit paratransit and Share -a -Ride services. Chapel Hill Transit has received funding to revise existing transit service in the Rogers Road area. It is anticipated that this expansion of tran- sit service will be implemented by the end of the second quarter of 2009. Figure 5 shows one option for extending transit service along Rogers Road. Until additional operational and funding details are finalized, this route remains conceptual in nature. 12 HS Route Proposed Extension EUBANKS RD N WEAVER DAIRY RD PUREFOY DR 0 HOMESTEAD RD H SCHOOL R )I C.N.H.S � Z Smirk Middle it S""11 Elam. A Z H � 7J r r o = ESTES DR S 0 m o I I i[ W �c Legend • Stops�st F - Proposed Extension w� °o - HS Route Streets � mPA Source: Chapel Hill Transit 0 0.25 0.5 1 Miles Date: 5/27/08 1 1 1 1 1 1 1 1 1 Figure 5 - HS Route Proposed Extension mm s Road Small Area Plan Roger Raced Network Options 1 Conned °ns • Road 0 0 235 410 g4 Feet The Greene Tract The Task Force received information from the Director of the Orange County Environment and Resource Conservation o the Greene Tract, The The 2002 Greene environmental sensitivity and importance Tract Concept Plan was adopted by Orange County, Chapel Hill, and Carrboro. The plan's sole component is a map that delineates the acreage of the jointly owned Greene Tract would be used for Affordable Housing and Open Space (Figure 7). The Greene and Neville Tracts Current Parcel ownership Land Use Visioning Exercises 0Q, Prior to the interim Report, the Task Force took part in a land use visioning exer- cise in which they explored different building types, arrangement, and density. Members expressed a preliminary preference for residential densities between 1 -8 Units /Acre, recreational, and small commercial landuses tgers Road study area. Additionally, Town staff utilized 3 -D modeling oftware o the scale of the proposed Habitat for Humanity project adjacent to Purefoy Road. Greene Tract COMOPt Plan 2002 For the Task Force to further develop its vision, the Town contracted with the Durham Area Designers (DAD) to host a workshop in the Summer of 2008. The information from early Task Force meetings provided a foundation for this interactive process. The community design workshop was on Saturday, June 7, 2008. The objective was to find a community consensus for components of the proposed small area plan. The Components of a small area plan include: • Land use guidelines • Appearance guidelines • An expanded multi-modal transportation network • Infrastructure improvements • Community development strategies The workshop included a presentation describing the community and introduced tools and concepts for use during the workshop. Attendees divided into three teams desig- nated A, B, and C. Two members of the DAD Urban Design Assistance Team were at each team table to facilitate the work and provide design assistance for visualizing the team members' ideas. The workshop included two design sessions at which each team developed ideas. These ideas included a new road and trail network, suggestions for types of development in specific areas of the community, and plans for preservation of Rogers Road's unique cultural heritage. After each of the design sessions, each team shared its ideas with the group. This process allowed ideas to become the property of each team as it molded its conceptual plan of future development in the Rogers Road community. The individual plans developed by each team are included in Figure 8 on page 16. 15 From the analysis of the different schemes developed at the design workshop, the Urban Design Assistance Team proposed a plan for both land use and open space as well as written recommendations. This work was presented to the task force and workshop attendees at a meeting on July 31, 2008, at which time the findings and the proposed land use plan were presented for discussion and approval. The final land use plan (Figure 9) and recommendations are presented in the next section. 16 If'' lnl Areas of Commonality 1 Connection north to Eubanks Road 2 Connection across the railroad track on Weaver Dairy Extension using Purefoy Road 3 Two plans and possibly the third show an east west road to the north of Purefoy, connectinf; to Rogers Road J Cross roads at the center of the ,urea to become a community center with mixed use development rright include a community center /libiary S School near the center of the area 6 Buffer on the north side of study area to shield the area from the landfill site 7 The historic house is retained in all plans and made part of the proposed Church complex 8 Greater density of development to lessen this individual cost of sevjer, at the a ,,ime time, reas near Ro ers Rcad and along the north vde of area seen as less dense to retain thf, current feel of the area 9 Farmers' market and community gardens 10 The community needs to write a cultural history and create a plan to preserve its cultural heritage Land Use Master Plan Once the community design workshop was com- pleted, the Durham Area Design Group merged key concepts from the plans of each team into a composite Land Use Master Plan (Figure 9). The Master Plan and associated road network is meant to be conceptual in nature. If this report is adopted as a component of Chapel Hill's Comprehensive Plan, this land use plan would serve as a guide for Chapel Hill and Joint Planning Area Land Use Map amendments. Figure 10 is the Task Force's Land Use Plan in a format prepared by Town staff. The Rogers Road Master Plan also suggests potential alignments for new roads recommended by the Task Force. Figure 11 "Conceptual Street Network with Existing Streets" is meant to be concep- tual in nature. It is intended to be viewed as a guide for future development rather than definitive alignments endorsed by the Task Force. The Task Force believes that any new development should adhere to principles of connectivity and utilize a grid street pattern in more densely developed areas. 17 Figure 9 - Composite Land Use Plan prepared by the Durham Area Designers i I I /- _- r j A is T Figure 10 - Recommended Land Use is Road small Area plan ap Feet N Rogers t NetworK o °' o Conee�:va� scree _.:..a streets iwsi + selected Existing sveets +! EonceP al sveet IStudy prea IA1 'all Corridor Map by chapel HO pla s Road Task Road Design by mm— MMMW tual Street Figure 11 Concep _ Ex treets Transportation and Infrastructure - Bus service should be provided to the existing community and bus service should be extended as the community develops. - Improve transportation access through all modes (vehicles, bicycle and pedestrian, transit). - New points of ingress and egress to the community should be established. - A road should be built that connects the neighborhood to Weaver Dairy Rd. - Water and sanitary sewer mains should be exteneded to the community. - The Towns of Chapel Hill, Carrboro, Hillsborough, and Orange County should collaborate to identify and secure funds to be used for financing the entire cost of OWASA water and sewer connections for individual homes within the Historic Rogers- Eubanks community as part of the compensation for the 37 years of hosting the Orange County Landfill and other solid waste facilities. Attachment 1 provides a list of available funding sources at the state and federal levels. Open Space and Recreation - Active recreation opportunities need to be provided for the Rogers Road community. - Passive recreation opportunities such as trails should be constructed on the Greene Tract. In order to do so, the Greene Tract Concept Plan should be revised by the local governments to reflect changing conditions along with this plan. - If a school is built in the community, explicit facility sharing relationships should be established prior to construction. Design and Land Use - The Recommended Master Plan on page 17 should become the basis for a future land use plan amendment for the Rogers Road area. - The Town should take the lead in initiating intergovernmental land use discussions (as required by the Joint Planning Agreement) by articulating a new vision for growth in the area. - New development should be compact and offer a range of housing types. This will facilitate the development for a neighborhood core in the eastern part of the study area, as will the presence of a school and a neighborhood commercial district. - Minimum setback requirements for new development should reflect the Task Force's desire to have a front porch community where life meets the street. Houses should be built close to sidewalks. - The Task Force desires that the currently developed areas near Rogers Road and the peripheries of the study area maintain their current densities. This would allow this part of the community to maintain its rural feel. Design and Land Use New roads near the neighborhood core should have curb and gutter. A maximum building height of 45' is recommended to maintain the community's character. Community Preservation -The two remaining historic buildings in the study area should be preserved and integrated into future community facilities. - The Town should explore options similar to the Homestead Exemption that would enable current property owners, particularly long -time residents, Habitat residents, and descendants of the Historic Community, to retain ownership of their property. - Local governments should collaborate with the community to develop strategies that help ensure that the majority of the housing stock be affordable to those making at or below 80% of the Area Median Income. Residents need to be informed of development pressures and opportunities in the Rogers Road area. This could happen through information sessions periodically hosted by the Town. The Town and the Community should collaborate to find innovative ways to rehabilitate declining residential properties in the area. - Local governments with jurisdiction should revisit ordinances pertaining to the replacement of manufactured housing and strive to develop rules to allow existing housing to remain in place. - The Town and the Rogers Road community should maintain the type of meaningful dialogue that was made possible by the efforts of the Task Force and by the work done during the design workshop. Implementation The Rogers Road Task Force developed a long -range vision for future land uses and desirable community enhancements. The proposed Rogers Road Small Area Plan Implementation Plan supports the Task Force vision and addresses the related social, economic, and environmental issues that affect the Rogers Road Community. Because of Joint Planning Jurisdiction, collaboration between the Towns of Chapel Hill and Carrboro, along with Orange County, will be necessary to implement many of the Task Force recommendations. Outlined below are a series of implementation actions and preliminary implementation schedule intended to achieve the recommendations of the Task Force. Figure 12 on pages 24 -25 is a proposed implementation schedule. W The Task Force suggested that this log cabin, located in the Rogers Rood Study Area, could be a focal point for a Community Garden or a Farmers Market in the future. 22 A: Task Force to provide the Rogers Road Task Force Report to the Town Council with a request that the report be adopted as a component of the Town's Comprehensive Plan and with an associated amendment to the Chapel Hill Land Use Plan. B: Town Council to initiate the Joint Planning process to amend the Joint Land Use Plan. C: Establish a work group of elected officials and appointed staff from each jurisdiction and OWASA to identify responsibilities that Chapel Hill, Carrboro, Orange County, and OWASA would need to assume to implement the Rogers Road Small Area Plan vision. C,: Work group to develop a utility funding and phasing plan for water and sewer connections for review by the three local governments. Cz: Work group to identify transportation and traffic calming projects and funding options consistent with the recommendations of the ,." Rogers Road Small Area Plan. C,: Review Greene Tract agreement and related Concept Plan to incorporate the recommendations of the Rogers Road Small Area Plan D: Town Council to ask the Chapel Hill - Carrboro City Schools to determine the facility needs to construct an elementary school in the Greene Tract. E: Town Council to ask the Greenways Commission to prepare an update of the Chapel Hill Greenways Master Plan to reflect the trail system proposed by the Task Force, for Council consideration. F: Town staff to develop an annexation strategy for the Rogers Road area reflecting the final water and sewer implementation plan (developed by work group established through C) and the provision of additional Town services. This strategy should include land loss prevention measures intended to keep existing residents in their homes. ementati on Town staff to facilitate dialogue about annexation with the residents through the work group established in action C. G: Town Council to establish a Community Preservation Steering Committee to assess the feasibility of restoring the historically significant buildings of the Rogers Road study area, preserving the cemetery, and addressing other issues of historical significance. H: The Town staff to host a development information workshop at which town staff, developers, and property owners could discuss market trends and potential development options. The Town staff to work with residents to identify appropriate sites for a community garden project in the Rogers Road area. The Town should explore options similar to the Homestead Exemption that would enable current property owners, particularly long -time residents, Habitat residents, and descendants of the Historic Community, to retain ownership of their property. Chapel Hill Activities Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Council receives and refers Rogers road Report to Chapel Hill • • Advisory Boards fore review -Adopt Task Force Report as component of Comprehensive Plan . -Amend Chapel Hill Land Use Plan Initiate discussions with Chapel Hill- • Carrboro City Schools with regard to proposed school site on the Greene Tract. Town to assist in establishment of a . preservation steering committee Work with Greenways Commission to . update Greenways Masterplan Develop annexation stategy that incorporates land loss prevention • strategies Rogers Road development work group The Town should explore options that would help current property owners, particularly long -time residents, Habitat • residents, and descendants of the Historic Community preserve their property, I I I I I I I I n t r o d u c t i o n The Rogers Road Small Area Plan Report summarizes the activities and recommen- dations of the Chapel Hill Rogers Road Small Area Plan Task Force. The information included in this Report represents work undertaken by the Task Force to identify key issues and prepare a small area plan intended to address those issues. The Report draws from the interim report from June of 2007 (Appendix 1) and the Urban Design Workshop held in June 2008 (Appendix 2). The Rogers Road Task Force was created by the Chapel Hill Town Council on December 4, 2006 and held its initial meeting in February of 2007. In establishing the Rogers Road Task Force, the Council identified the following topics to be ad- dressed. - Desirable Land Uses and a Revision to the Land Use Plan - Water and Sewer Extension Plan - Roadway Network Transit Service Plan - Zoning Ordinance and Map Amendment At the initial meetings of the Task Force, members reviewed background information about existing conditions and infrastructure within and adjacent to the study area. The Task Force met a total of six times between February 15, 2007 and the submission of an interim Report to the Town Council on June 21, 2007. Subsequent meetings of the Task Force included two consultant -led workshops with the Rogers Road Urban Design Assistance Team during the summer of 2008. The workshops produced a draft land use plan and recommendations for policies to support the proposed land uses. Final meetings of the Task Force focused on gathering feedback for the consultant's work and reviewing a range of implementation strategies. This Report begins with a review of background information about the study area and relevant planning efforts. The following sections detail information presented to the Task Force about concepts for new development and infrastructure in the area. The last sections include the final recommenda- tions of the Task Force and the suggested course for implementation of the Rogers Road Small Area Plan. Page Introduction 4 Background Timeline Location History Development and Infrastructure Concepts 10 Concepts for Sewer Extension Expanding Road Access The Greene Tract Land Use Exercise Community Design Workshop 15 Task Force Recommendations 20 Implementation 22 Attachment 1 27-28 NC Water and Wastewater Funding Sources Appendix 1 Rogers Road Small Area Plan Task Force Interim Report - June 2007 Appendix 2 Recommendations for the Rogers Road Small Area Plan - A report by the Durham Area Designers 0 Task Force Members Delores Bailey Joal Hall Broun Robert Campbell Moses Carey Robert Dowling Barbara Hopkins Neloa Barbee Jones Susan Levy Council Member Mark Kleinschmidt Bonnie Norwood Council Member Bill Strom James Stroud Ruby Sinreich Tom Tucker Laura Wenzel l Rogers Road Small Area Plan Task Force Final Report Prepared by the Rogers Road Task Force 3 Joint Planning Activities Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Refer Rogefs Road Task Force Report to Orange County, Carrboro, OWASA, and • Chapel Hill - Carrboro City Schools Amend Joint -Land Use Plan Assembly of Governments Meetings Establish local government work group . Develop funding and phasing plan for water and sewer service Identify transportation and traffic calming projects A c k n o w I e d a e m e n t s Town of Chapel Hill Planning Staff J.B. Culpepper - Director David Bonk - Long Range and Transportation Planning Manager Garrett Davis - Long Range Planner Scott Simmons - Graphics Specialist Orange Water and Sewer Authority Ed Holland - Director of Planning Joe Leo - Engineering Technician Orange County Craig Benedict - Director Perdita Holtz - Planning Systems Coordinator / Planner III Town of Carrboro Roy Williford - Director "tiOW N„�F\ �'� j NC Water, Wastewater and Stormwater Funding Sources Compiled by UNC EFC June 2008 Attachment 1 Organization Program Purpose or Use of Funds Application Dates North Carolina Gloria Nance -Sims, Director Department of Community Development To improve housing and economic Typically, spring through http; /Iwww.nccommerce.comfen/ gnance- sims@nccommerce.com Commerce, Division of Block Grams (CDBG) development for low and moderate the year's end. CommunftyServloes/ 919 733 -2850; 919 733 -5262 (fax) Community Assistance (HUD funds) income communities 4313 Mal Service Center (DCA) Raleigh, NC 27699 Roger Davis, Program Director Water and Wastewater Loans Funds are for eligible community Applications received www.rurdev.usda.gov / roger.davis@nc.usda.gov and Grants water, sewer, storm sewer, and year round. nc /wwd.htm (919) 873 -2061 solid waste projects. 4405 Bland Road Raleigh, NC 27609 These grants may be available to Roger Davis, Program Director Emergency Community Water eligible rural communities in event Contact NC State office. www.rurdev.usda.gov/ roger.davisC2nc.usda.gov Assistance Grants rants of natural disaster or other acts Applications received nc/wwd.htm (919) 873 -2061 that cause significant damage to a year round. 4405 Bland Road water or sewer system. Raleigh, NC 27609 USDA Rural Development Very Low - Income Housing 504 REPAIR LOANS AND Mel Ellis, NC Program Director Repair Loans and Grants GRANTS -Single Family Housing Contact a local USDA usda www. rurdev. .g ov/nc/ mel.elis@nc.usda.gov (Section 504) makes loans and grants to provide Rural Development 504rep.htm (919) 873 -2060 rural residents with safe and Office. Area contacts listed at www.rurdev.usda.gov /nc/d affordable homes. IiSLhtm Roger Davis, Program Director Water and Wastewater Loans Funds are for eligible community Applications received www.rurdev.usda.gov / roger.davisCmnc.usda.gov and Grants water, sewer, storm sewer, and year round. nchvwd.h[m (919) 873 -2061 solid waste projects. 4405 Bland Road Raleigh, NC 27609 Philip Trader Economic Development ptrader @eda.doc.gov Public Works and These grants support projects that Proposals are accepted (404) 730.3017 Department of Department f Development Facilities Grant p promote economic development in on a continuing basis. www•eda,gov Economic Development Administration Commerce Program economically distressed areas. 401 West Peachtree Street NW Suite 1820 Atlanta, GA, 30308 -3510 Sid Harrel Planning, designing, and sid.harrel @ncmail.net NC Division of Public Water Supply Section - construction for the purpose of DWSRF application www . ws/srfri us / deh. . . .p enr state nc (919) 715.3216 Environmental Health Drinking Water SRFd.oan upgrading, expanding, extending, deadline is September 30 ndex'htm Public Water Supply Section Program rehabilitating or consolidating each year. Division of Environmental Health 1634 Mal water systems. Service Center Raleigh, NC 27699 -1634 Grants fund projects to protect Beth McGee; Deputy Director and restore surface water quality, beth.mcgeeC�cwmtf.net Clean Water such as stormwater management Application deadline is (919) 716.0055 Management Trust stream restoration, wetland March 1 each year. ' www.cwmtf.net Clean Water Management Fund (CWMTF) Grants acquisition, and improvements or Trust Fund repairs to wastewater treatment 1651 Mail Service Center systems. Raleigh; NC 27699 -1651 UNC; "..........,.a .. •. f—caau Iniormallon eam0eae hfI1101 r— konmentel Finance Center In AMr 2007. Phew eonta i Pmymm manajarWrther, u0•to -date 0nto matlen. NC Water, Wastewater and Stormwater Funding Sources Compiled by UNC EFC June 2088 Attachment 1 n,n UNC •� cx�rau.. n.n:na --.1 wdw Inf —fien wmped bj)k% Enviroma Firma Camw in d er 2007. Please w w program nwdprkexur, up.beate inrtrmadom Daniel Blaisdell, Chief North Carolina Clean Water Stale Revolving The CWSRF program is available Applicants must be scheduled on Priority www.nccgl.net/fap/cwsrt/ daniel.blaisde8@ncmail.net (919) 715 -6211 Construction Grants Fund to fund a wide oar ety of water Funding List before index.html DEN Construction Grants and Loans Section quality projects. March 31st. and Loans Section 1633 Mail Service Center Raleigh, NC 27399 -1633 ARC offers Community Olivia Collier, Appalachian Program Manager Appalachian Regional Supplements to Other Federal Development Supplemental Contact your state ARC ocollierOnccommerce.com (919) 733 -2853 exL 252 Commission (ARC) Grants Grants for water projects in the designated Appalachian regions in program manager for more information. www.arc.gov Appalachian Regional Commission Grant Program 13 eastern states. 1307 Glenwood Avenue Raleigh, NC 27699.4313 The Rural Center administers Julie Haigler Cubeta, Senior Director, Physical grant programs to help rural Application deadlines are Infrastructure Office Supplemental Grants PPI communities develop the water P 5:00 p. . 5:00 p.m. on the last www.ncruralcenter.org/ jhaiglercubeta @ncrurakenter.wg Program, Capacity Building 9 P y 9 and sewers stems the need to y y business days of March grants/water.htm (919) 250 -4314; (919) 250.4325 (fax) Grants Program support local economic growth and September. N.C. Rural Economic Development Center and ensure a reliable supply of 4021 Carya Drive clean water. Raleigh, NC 27610 NC Rural Economic Development Center Julie Haigler Cubeta, Senior Director, Physical Grant funds are used to generate Infrastructure Office Economic Infrastructure newjobs in rural or urban, economically istressed y Pre- applications taken on www.ncruraicenter.org/ jhaiglercubeta @ncruraicenter.org (919) 250 -4314; (919) 25D -4325 (fax) Grants communities through water and a rolling basis. infrastructure/ N.C. Rural Economic Development Center wastewater improvement projects. 4021 Carya Drive Raleigh, NC 27610 Section 319 funds support projects designed to reduce Kim Nimmer, Grant Program Coordinator nonpoint source distribution. The Proposals will be kimberiy.nimmer@ncmad.net (919) 733 -5083 ext. 582 Clean Water Act Section 319(h) Grants NC Division seeks Base Funded Proposals (funding for education accepted for about three �P : / /h2o.enr.stale.nc.us/nps/ Section_319_Grant_- Program. Water Quality Section and demonstration of innovative months beginning in Htm Division of Water Quality best management practices) and November 2007. NC DEN Incremental Funded Proposals P.O. Box 29535 (water quality restoration funding). Raleigh, NC 27626 -0535 North Carolina Division of Water Quality Grant program was established to Heather Boyette Section 319 Non point Source Po Provide funding for efforts to curb non point (NPS po ) pollution. Applications accepted between February 13 arxf http : //h2o.enr,state,nc.us /nps/Sec heather.boyette@ncmail,net 919 -733 -5083, ext. 357 Grant Program including that which occurs though May 15, the year prior. Uon_319_GranLProgram.htm 512 West Salisbury Street . stormwater runoff Raleigh, NC 27604 Shelly Miller North Carolina Division of Soil and Water Community Conservation To reduce the input of nonpoint source pollution through best http:/Avww.ent.state.nc.us/dswc/p shelly.miller@ncmail.net 919 -715 -6107 Conservation Assistance Program management practices ages/ccap —programhtml Division of Soil and Water Conservation 1614 Mail Service Center Raleigh, NC 27699 -1614 n,n UNC •� cx�rau.. n.n:na --.1 wdw Inf —fien wmped bj)k% Enviroma Firma Camw in d er 2007. Please w w program nwdprkexur, up.beate inrtrmadom Rogers Road Small Area Plan Task Force Interim Report June 21, 2007 Rogers Road Small Area Plan Task Force: Mayor Pro Tern Bill Strom Council Member Mark Kleinschmidt Bonnie Norwood Robert Dowling Susan Levy James Stroud Tom Tucker Ruby Sinreich Laura Wenzel Delores Bailey Neloa Barbee Jones Barbara Hopkins Robert Campbell Timothy Peppers 3 Interim Findings This interim report includes a potential sanitary sewer plan to serve existing property in the study area. The plan was developed with the assistance of OWASA staff. The report also includes potential options for a road network to open up and connect the neighborhood. Keeping the neighborhood affordable is the key issue from the work so far. How to get sanitary ,sewer and additional road access to the neighborhood without causing financial hardship to existing residents? Who should pay for these facilities and how should they be paid for? The Task Force believes that the development of housing on the Greene Tract ought not proceed without providing current residents of the neighborhood the opportunity to be served by sanitary sewer. The Task Force recommends: • The development of an action plan to address sanitary sewer provision. • The development of an action plan to address additional road access to the neighborhood. • That the Town Council of the Town of Chapel Hill receive and refer this interim report to the Board of County Commissioners, the Carrboro Board of Aldermen and the OWASA Board of Directors concerning the provision of sanitary sewer and that the Council refer the report to the Board of County Commissioners concerning additional road access. • That the Chapel Hill Town Manager be authorized to work with the staff of Orange County, the Town of Carrboro and OWASA to draw up action plans and proposals for the provision of these facilities. Guiding Principles The Task Force has developed the following principles to guide the development of the small area plan: • Provide alternative road access into and out of the neighborhood • Improve transportation access through all modes (vehicles, bicycle and pedestrian, transit) • Manage existing and through traffic • Maintain affordable living to current residents • Preserve the environment and cultural heritage of the study area • Foster a sense of community amongst the residents • Encourage rehabilitation of declining residential properties • Encourage a full range of services for existing and future residents • Don't leave the existing residents behind • Provide utilities to meet community needs • Encourage well built, affordable, smaller homes • Improve the standard of facilities for the community 2 Background The Rogers Road study area is located in Orange County to the north west of the existing town limits of the Town of Chapel Hill; it also adjoins the Town limits of Carrboro to the west. The study area is located in the Chapel Hill Transition Area, an area which is planned to become part of the Town of Chapel Hill. The future growth of the Town of Chapel Hill and the Town of Carrboro was established with Orange County, through a Joint Planning Agreement in 1987. The Town of Chapel Hill Comprehensive Plan, a long range plan for future development of the Town, reflects the Joint Planning Agreement and identifies an Urban Services Boundary which defines the future town limits in which it is intended that the Town will grow and provide typical urban services. The Rogers Road study area is located within the Urban Services Boundary. The study area is approximately 330 acres. It is bounded by the Norfolk and Southern Railroad to the east, the existing residential neighborhood of Billabong Road and Homestead Place to the south, Rogers Road to the west and the Orange County Land fill to the north. Draw an imaginary vertical line through the middle of the study area. East of the line almost half of the study area (164 acres) consists of the Greene Tract. Approximately 60 acres of the Greene Tract is owned by Orange County and 104 acres is jointly owned by Orange County, the Town of Chapel Hill and the Town of Carrboro. The Greene Tract was originally purchased in 1984 as a potential future landfill. It is located south east of the existing Orange County landfill. A concept plan prepared by a Greene Tract Workgroup was approved by the joint owners in late 2002. The concept plan identifies that 18.1 acres of the jointly owned portion will be developed for housing and the remaining acres of the jointly owned portion will be preserved and managed as open space. West of the imaginary line the study area consists of approximately 80 lots and tracts of the Rogers Road Neighborhood. The properties are mostly accessed via Purefoy Drive off Rogers Road. Rogers Road Small Area Plan Task Force Following a community open house in December 2006, the Rogers Road Small Area Plan Task Force was formed and began meeting in February 2007. The Task Force has met six times holding a meeting on the second Thursday in the month. The charge of the Task Force is to take a more detailed look at the impacts of providing public services in the study area, especially the extension of sanitary sewer, and the impacts of developing an affordable housing site on the Greene Tract. The Task Force has been reviewing background information about existing conditions and infrastructure of the study area in order to establish a vision for the future. To date the Task Force has focused on how to improve facilities for existing residents in association with planning for future development of the study area. 4 Sanitary Sewer Plan Most of the Rogers Road study area is served with water from OWASA. Water lines extend eastward from Rogers Road. OWASA sanitary sewer has been extended into the southwestern part of the study area. OWASA policy is that to work best sewers need to run downhill so that wastewater will flow using gravity rather than being pumped mechanically. Pumps are not desirable because they may fail during storms and they involve operating costs for electricity and maintenance. In March OWASA staff presented a conceptual layout of a sanitary sewer network that could provide service to existing lots within the Rogers Road study area. The conceptual layout identifies new lines that would need to be constructed and an existing line extended to provide a gravity sanitary sewer service to existing lots. Topography in the study area indicates that portions of the study area would best be served with gravity sewer falling in different directions from the study area. This includes extending the existing line from the south west, a new line to Eubanks Road in the north east and a new line to the west which could be provided in cooperation with the Town of Carrboro. Appendix 1 is maps showing a conceptual sewer network plan to serve most of the existing lots in the study area. There is one concept for the study area with two versions; Concept A serves the Neville Tract and the adjoining 24 acre Harris property via a new line to the north. Concept A has greater potential to facilitate subdivision of the Harris property. Construction is estimated to cost $ 2.9 million. Concept B serves the same properties via a new line to the west. Construction is estimated to cost $ 2.5 million. Neither Concept A or B serve properties off Sandberg Lane or 3 lots off Merin Road. Concept C shows how gravity sewer could be provided to those lots not served by A or B via a new line along Billabong Lane. Billabong Lane is beyond the study area. Construction of the lines in Concept C would add $1.3 million to the construction cost of Concepts A or B. Appendix 2 provides more detail from the OWASA on the conceptual sewer network plan and a breakdown of the cost to construct the lines. It also sets out indicative non - construction costs to hook up existing homes to the lines. The Task Force reviewed the OWASA water and sewer extension policies. In accordance with the OWASA policies, benefiting properties would bear the cost of extending water and sewer lines. The Task Force also reviewed the assessment process for neighborhoods pursuing water and sewer service. Members expressed great concern over the ability of existing homeowners to bear the cost of installing main lines, hooking up to services and paying utility bills, thereby decreasing the affordability of low -cost housing that currently exists in the study area. The Task Force believes that the development of housing on the Greene Tract ought not proceed without providing current residents of the neighborhood the opportunity to be served by sanitary sewer. 5 Appendix 3 outlines the cost per lot to provide sewer with an assessment project. It also shows how that cost could be reduced by additional development in the neighborhood, increasing the number of lots. In other words how the assessment cost could be reduced by splitting it between 200 lots as opposed to 100 lots. The Task Force recommends that an action plan is made to address sanitary sewer provision. The Task Force requests that the Town Council of the Town of Chapel Hill, the Board of County Commissioners and the Carrboro Board of Aldermen work with OWASA to develop an action plan for the provision of sanitary sewer. Additional Road Access Properties in the study area are mostly accessed via Purefoy Drive off Rogers Road. Rogers Road is currently classified as a collector street by the North Carolina Department of Transportation (NCDOT). Rogers Road carries approximately 5,000 vehicles per day, a rise from 3,000 vehicles per day in 1990. In general traffic on Rogers Road increases by 4 to 6 percent per year. We would anticipate continued growth in vehicle traffic along Rogers Road linked to continued development along both Homestead Road and Eubanks Road in Chapel Hill and Carrboro. Purefoy Drive as it exists currently is sufficient to accommodate 500 trips per day and will accommodate the projected trips from the future Habitat for Humanity development proposed at Purefoy Drive. The Task Force understands that new development in the study area may require expansion or upgrade of existing streets. The Task Force identified the need for additional access to the neighborhood and internal road connections. In particular it identified the need to have a north -south roadway connection through the study area to connect to Eubanks Road. As Orange County owns approximately 70 percent of the property with frontage on Eubanks Road including the landfill site, the future operations center and the future animal shelter, the Task Force identified that Orange County needs to be an active partner in the small are planning process and in its implementation. The Task Force recommends that the Town of Chapel Hill and Orange County act cooperatively to secure a roadway corridor through the Orange County property to Eubanks Road. Appendix 4 is a conceptual road network providing potential access to and internal connections in the study area. The Task Force The Task Force considered options to provide an east to west road connection to the neighborhood through the Greene Tract. It identified that this would be constrained by the permanent preservation of the Greene Tract and the difficulty in securing a vehicular crossing of the railroad. The Task Force considers that a greenway connection should be explored through the Greene Tract. Greene Tract The Task Force received information from Dave Stancil Director of the Environment and Resource Conservation Department at Orange County concerning the environmental r� �j sensitivity and importance of the Greene Tract. The Greene Tract lies at the headwaters of three watersheds. Excepting the 18.1 acres of the Greene Tract which is identified by for housing development by the 2002 Greene Tract Concept Plan, the Task Force supports the placement of Conservation Easements on the Greene Tract. The Task Force believes that the development of housing on the Greene Tract ought not proceed without providing current residents of the neighborhood the opportunity to be served by sanitary sewer. Land Uses In March the Task Force took part in a land use visioning exercise, members expressed a preliminary preference for low- density residential, recreational, and small commercial land uses in the Rogers Road study area. Further exercises will be scheduled to identify preferred locations for uses within the study area. Landfill and Establishment of Waste Transfer Center The Task Force has not actively discussed the operation of the County Landfill. This is because this matter is being addressed separately by the Orange County Historic Rogers Road Community Task Force. Members of the Rogers Road Small Area Plan Task Force have raised concerns about potential contamination of water from the landfill site and how contamination might affect future development. Members have also raised concerns about the proposed relocation of the Convenience Center. Conclusion A small area plan for the Rogers Road Area is essential to coordinate the provision of infrastructure and services to the neighborhood. Additional transportation access and the provision sanitary sewer are needed to improve the infrastructure of existing residents and for the orderly development of housing on the Greene Tract. The Task Force is greatly concerned about the cost of providing sanitary sewer to existing residents of the study area and recommends that the Town Council of the Town of Chapel Hill, the Board of County Commissioners, the Carrboro Board of Aldermen and the OWASA Board of Directors work together to provide sanitary sewer to the study area. The Task Force believes that the development of housing on the Greene Tract ought not proceed without providing current residents of the neighborhood the opportunity to be served by sanitary sewer. The Task Force also recommends that the Town Council of the Town of Chapel Hill and the Board of County Commissioners, work together to secure a roadway corridor through the Orange County property to Eubanks Road. Rogers Road Study Area Concept A Omrwcou* (1" =200') Nwom In= t � d i f Or C n snpe ou!KN `' � C+reana Tract .ti., s s — - Fuhue DewbMnent t �r� 18.1 Aaft Hebttat for HuntenRy ��... CafMfN Tractj r N�nnolM •r/ j • VaW V MY<'aM3 b _ . t a s ;Sy p ✓ '. ••r sn 5•••r urr. awr Type 6 V 1 - E.Mq NYIw Oar .4 . `4 Fa 9r•rn � —.r � '. $eyyel Exter+WOn b1/ Tavn of iiYy:bQfO; [N4e w sr t NE Annembw Ayu a..._T= �•,a._co - _ +a 3 0 250 500 ty,ry_Tr•e_Q•eq•.Ca :.. , b � F _ _•. _Feet Rogers Road Study Area r - Concept B Y _ (1,0 -200') ..F c i Neville Tract t ► ii r ,. Groans Trod. F S sF { }Oran-p- Caw* wr ♦ _ {J s afore Davalopmant 18.1 Acres I ! i b ►+aaitat for Humanly Site,---1 -_. 5 a t s �^ \"�—=Y ' Sewer Extension by Town of Carrboro, ., • N«os L to NE Annexation Area w �• ;- V'aMM�_BwYN}4n ROJe � J � r _.. -- -- - -- - --. - t Type OVASA r Rogers Road Study Area w- - Concept C " (1 " =200') E n E 1 _ + 0" ; \�.' `;, • tract , l_ . R 18.1 Aaea _ ♦ r MabrtM far Hrmandy Sft t t* k 1,Gmm Trod, s q, • 4 ' n ,y w t Sewer Exteruan by town Of Canbcro .... �'a'"d �' to NE Anrwxation Ame „ s x p 0 250 51 0 10WASA1 ORANGE WATER AND SEWER AUTHORITY Quality Service Since 1977 1.3 "_3t1]:.W1111MAI TO: Gordon Sutherland FROM: Ed Holland DATE: June 22, 2007 SUBJECT: Preliminary Concept Plans and Cost Estimates for Providing Sewer Service to the Rogers Road Study Area BackLyround and Overview Per our recent meetings, OWASA staff has provided three concept plans and associated cost estimates (preliminary) for a sewer collection system that could serve the Town of Chapel Hill's study area east of Rogers Road. Virtually all existing parcels in the study area have access to OWASA water lines; therefore, this exercise focused on sewer service only. If the Town or others decide to pursue these or other sewer concepts, additional engineering and professional services will be needed to provide site -level detail and an overall determination of project feasibility. The concept plans represent three potential gravity flow configurations. None incorporate sewage pumping stations, which OWASA only approves in unusual circumstances where property cannot be served by gravity options. We have found that pumping stations are expensive to maintain and less reliable over time, due to the greater risk of mechanical failure and resulting sewage spills, than are gravity systems. As shown in Concepts A and B, wastewater from most of the study area would flow toward the upstream portion of a sewer line that the Town of Carrboro is extending approximately 900 feet to an area that was annexed in 2006. According to North Carolina annexation laws, that facility must be completed by the end of January 2008. Our concept drawings do not include portions of the sewer system that will be installed for properties within the study area that are being developed by Habitat for Humanity, nor do these concept plans anticipate service to most of the Greene Tract, which are intended to remain as permanent open space. Under Concepts A and B, sewer service would not be available to 11 existing parcels in the study area, as indicated by purple cross - hatching on the drawings. Additional sewer lines near the southeastern portion of the study area would be needed to serve 10 of those 11 lots, as shown in Concept C. None of the three concepts plans could provide sewer service to the single small lot in the extreme northwest corner of the study area. Preliminary Rogers Road Sewer Concepts June 22, 2007 Page 2 Concepts A and B are identical, except for the manner in which gravity service is provided to the several parcels immediately west of the Neville Tract. Concept A, which directs gravity flow northward to the new sewer line that will serve the Orange Regional Landfill, would be approximately 10 percent more expensive than Concept B, but would likely offer gravity service to a greater number of future lots. Concept B represents a slightly less expensive configuration, but may not offer sufficient flexibility if the two properties immediately west of the Neville Tract are subdivided for further development. These preliminary conclusions still need to be confirmed by engineering analyses and field surveys. Concept C offers sewer service to the 10 existing lots within the study area that could not be served by either Concept A or B. Concept C would also provide service to approximately 20 additional lots in the Billabong Lane vicinity, which is outside of the delineated Rogers Road study area. A combination of either Concept A or B, plus Concept C, would therefore be needed to serve all existing properties within the study area, except for the single lot in the northwest corner of the study area, which cannot be served by gravity sewer under any of the three configurations. Preliminary Cost Estimates Project Costs — The table on the next page summarizes the preliminary estimated cost components of each concept plan. These were derived through the same methods used to estimate OWASA's own capital project costs. Further details are available on request. The following important caveats should be observed as these estimates inform the Roger Road Small Area planning process: • If the Town or others decide to pursue these sewer system concepts, additional engineering and professional services will be needed to provide site -level detail and overall determinations of engineering feasibility. • Construction cost estimates reported below are only preliminary and are not based on any assessment of field conditions. Cost estimates typically become more precise as detailed engineering design proceeds. • Estimates are based on the best information available as of June 2007. OWASA assumes that project costs will escalate at a rate of 8 percent per year. We recommend that this inflation factor be used in any future interpretation of these estimates. • The overall extent of these concept plans and the number of unserved parcels will change in the future if (or as) individual development projects extend new lines to currently unsewered properties. Preliminary Rogers Road Sewer Concepts June 22, 2007 Page 3 The table includes ry oject costs only. Additional per lots costs for connecting individual properties to the sewer system are discussed in the section below. Estimated Project Costs of Three Sewer System Concept Plans for Chapel Hill's Rogers Road Study Area Concept Concept Concept Concepts Concepts A B C A +C B +C Engineering Design $220,000 $190,000 $100,000 $320,000 $290,000 Construction $2,180,000 $1,900,000 $970,000 $3,150,000 $2,870,000 Construction Administration $110,000 $100,000 $50,000 $160,000 $140,000 Construction Inspection $110,000 $100,000 $50,000 $160,000 $140,000 Contingency $260,000 $230,000 $120,000 $380,000 $340,000 Totals $2,880,000 $2,520,000 $1,290,000 $4,170,000 $3,780,000 Individual Connection Costs — As noted, the preceding table only includes estimates of constructing the sewer collection system itself. Additional ep r lot costs for connecting to the new system would include the following: OWASA Service Availability Fee — This one -time connection fee represents the proportional cost of "buying in" to OWASA's existing facility infrastructure (main sewer lines, treatment plant, etc.) and is assessed according to the square footage of residential properties. The sliding scale of availability fees that will be effective as of October 1, 2007 ranges from $2,441 for homes of less than 1,300 square feet to $4,514 for homes of greater than 3,800 square feet. Fees for multi- family residences will be $2,645 per unit. A different scale of availability fees applies to non - residential sewer connections. Private Plumbing Costs — The pipe that extends from a building to the OWASA sewer line is called a lateral. Unlike pipes in OWASA's system, the lateral is part of the private property served by the public sewer. Installation and maintenance of the lateral is the responsibility of the property owner, who typically contracts with a private plumber for installation. Costs depend on several factors, especially the distance from the building to the OWASA sewer line. A recent telephone survey of several local plumbers indicated prices in the range of $25 per foot. That is, installation of a 50 -foot lateral would cost approximately $1,250, a 100 -foot lateral would cost approximately $2,500, and so forth. Sewer Tap Charge — This fee is for physically connecting the private sewer lateral to the OWASA sewer line. The base tap charge, effective as of October 1, 2007, will be $318. Preliminary Rogers Road Sewer Concepts June 22, 2007 Page 4 Monthly User Fees — In addition to the one -time service availability fee, tap charge, and private plumbing costs, all OWASA customers pay monthly water and sewer bills that include a fixed service charge plus a water and sewer commodity charge based on the number of gallons used each month. The typical water plus sewer bill of a residential customer using an average of 6,000 gallons per month will generally range from $60 and $70 per month. Bills will vary according to the actual amount of water used. OWASA staff has appreciated the opportunity of providing this information to support Chapel Hill's Rogers Road Small Area Planning process and will be glad to answer questions or provide further details as needed. Ov �4&_l Edward A. Holland, AICP Planning Director attachments cc: Mason Crum, P.E. June 21, 2007 SAMPLE FINANCIAL ANALYSIS: Sewer Asessment project with Town Assistance* OWASA SEWER EXTENSION INTO ROGERS ROAD STUDY AREA "To receive Town assitance calculation assumes property is in town limits CONCEPT A: ROGERS ROAD WITHIN TOWN LIMITS (ANNEXATION) COST DISTRIBUTION ON PER -LOT BASIS(excluding proposed Habitat project) EST. COST OF PROJECT FOR CONCEPT A $2,900,000 # OF LOTS 50 TOWN ASSISTANCE PER LOT (UPPER LIMIT) $4,500 TOTAL TOWN REIMBURSEMENT (if funds were available) $225,000.00 TOTAL ASSESSMENT COST AFTER ASSISTANCE $2,675,000.00 TOTAL ASSESSMENT FEE PER LOT (AFTER ASSISTANCE) UPFRONT SEWER TAP FEE %_ UPFRONT AVAILABILITY FEE (dependent on sq ft of house) 1000 1500 2000 2500 AVAILABILITY FEE (Oct1,2007) 44 0.0" #MAO AWN UPFRONT PLUMBING EXTENSION COST PER LINEAR FT $25.00 $25.00 $25.00 $25.00 ESTIMATED COST FOR 100 LINEAR FT u , "A" ,. .vvmd) TOTAL COST TO CONSTRUCT & RECEIVE SERVICE PER LOT $K11111140 111";W04 #% Average Household Gallons Consumed /Month 6,000g Monthly Bill $59.00 page 1 of 3 June 21, 2007 CONCEPT A: ROGERS ROAD WITHIN TOWN LIMITS (ANNEXATION) COST DISTRIBUTION ON PER -LOT BASIS(excluding proposed Habitat project) Assuming 50 additional lots created by new development EST. COST OF PROJECT FOR CONCEPT A $2,900,000 # OF LOTS 100 TOWN ASSISTANCE PER EXISTING LOT (UPPER LIMIT) $4,500 TOTAL TOWN REIMBURSEMENT (if funds were available) $225,000.00 TOTAL ASSESSMENT COST AFTER ASSISTANCE $2,675,000.00 TOTAL ASSESSMENT FEE PER LOT (AFTER ASSISTANCE) UPFRONT SEWER TAP FEE UPFRONT AVAILABILITY FEE (dependent on sq ft of house) AVAILABILITY FEE (Oct1,2007) UPFRONT PLUMBING EXTENSION COST PER LINEAR FT ESTIMATED COST FOR 100 LINEAR FT TOTAL COST TO CONSTRUCT & RECEIVE SERVICE PER LOT Average Household Gallons Consumed /Month Monthly Bill 1000 1500 2000 2500 $25.00 $25.00 $25.00 $25.00 � r 6,000g $59.00 June 21, 2007 CONCEPT A: ROGERS ROAD WITHIN TOWN LIMITS (ANNEXATION) COST DISTRIBUTION ON PER -LOT BASIS(excluding proposed Habitat project) Assuming 100 additional lots created by new development EST. COST OF PROJECT FOR CONCEPT A $2,900,000 # OF LOTS 150 TOWN ASSISTANCE PER EXISTING LOT (UPPER LIMIT) $4,500 TOTAL TOWN REIMBURSEMENT (if funds were available) $225,000.00 TOTAL ASSESSMENT COST AFTER ASSISTANCE $2,675,000.00 TOTAL ASSESSMENT FEE PER LOT (AFTER ASSISTANCE) UPFRONT SEWER TAP FEE UPFRONT AVAILABILITY FEE (dependent on sq ft of house) AVAILABILITY FEE (Oct1,2007) UPFRONT PLUMBING EXTENSION COST PER LINEAR FT ESTIMATED COST FOR 100 LINEAR FT TOTAL COST TO CONSTRUCT & RECEIVE SERVICE PER LOT Average Household Gallons Consumed /Month Monthly Bill 6,000g $59.00 1000 1500 2000 2500 , ..,... M $25.00 $25.00 $25.00 $25.00 6,000g $59.00 June 21, 2007 CONCLUSIONS: Concept A (50 existing lots) PER LOT COST WITH TOWN ASSISTANCE TO EXISTING LOTS: $59,000 to $60,000 + MONTHLY BILL Concept A (50 existing lots + 50 new lots) PER LOT COST WITH TOWN ASSISTANCE TO EXISTING LOTS: $32,000 to $33,300 + MONTHLY BILL Concept A (50 existing lots + 100 new lots) PER LOT COST WITH TOWN ASSISTANCE TO EXISTING LOTS $23,000 to $24,400 + MONTHLY BILL 'THESE FIGURES COULD INCREASE OVER TIME WITH RISING CONSTRUCTION COSTS; OWASA ESTIMATES CONSTUCTION COSTS COULD INCREASE 8% PER YEAR it Final Report ♦ Rogers Road Small Area Plan Task Force Recommendations for The Rogers Road Small Area Plan Based by the work of the Rogers Road Task Force October 30, 2008 Prepared by the Rogers Road Urban Design Assistance Team Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force The Study Area The Rogers Road community which is the subject of this report is an area of approximately 330 acres. It is bounded by the Norfolk and Southern Railroad to the east, the existing residential neighborhood of Billabong Road and Homestead Place to the south, Rogers Road to the west and the Orange County Land fill to the north. Almost half of the study area (164 acres) consists of the Greene Tract. Approximately 60 acres of the Greene Tract is owned by Orange County and 104 acres is jointly owned by Orange County, the Town of Chapel Hill and the Town of Carrboro. A concept plan prepared by a Greene Tract Workgroup was approved by the joint owners in late 2002. The concept plan identifies that 18.1 acres of the jointly owned portion will be developed for housing and the remaining acres of the jointly owned portion will be preserved and managed as open space. See maps and aerial photographs of the area in the Appendices to this report. 2 1 Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force The Rogers Road Small Area Plan Task Force The Rogers Road Small Area Task Force was formed in early 2007. It was convened to take a detailed look at bringing additional public services to the Rogers Road community, especially the extension of sanitary sewer service, and to examine the potential impact of locating an affordable housing development on the Greene Tract. The task force consists of fourteen members including residents of Rogers Road, elected officials, and other interested stakeholders. The task force published an interim report in July of 2007. Shortly afterwards, the team approached the Durham Area Designers to facilitate a public design workshop to explore components to include in a small area plan for the Roger Road area. This report summarizes the results of the task force design workshop and the subsequent development of a consensus plan by the task force. 3 Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force In its interim report of June 2007, the task force established these guidelines for development of a small area plan: • Provide alternate road access into and out of the neighborhood • Improve transportation access for all modes (vehicle, bike and pedestrian, transit) • Manage existing and through traffic • Maintain affordable living for current residents • Maintain the environmental and cultural heritage of the study area • Foster a sense of community amongst the residents • Encourage rehabilitation of declining residential properties • Encourage a full range of services for existing and future residents • Don't leave existing residents behind • Provide utilities to meet community needs • Encourage well - built, affordable, smaller homes • Improve the standards of facilities for the community 4 Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force An objective of the Rogers Road workshop was to find a community consensus for components of the proposed small area plan. Components of a small area plan include: • Land use guidelines • Appearance guidelines • An expanded multi -modal transportation network • Infrastructure improvements • Community development strategies 5_1 Rogers Road Small Area Plan Recommendations 0 Final Report ♦ Rogers Road Small Area Plan Task Force The community design workshop occurred on Saturday, June 7, 2008. A list of attendees is found in the appendices. The workshop began with a presentation that described the community and introduced tools and concepts for use during the workshop. Attendees divided into three teams which were designated A, B, and C. Two members of the Urban Design Assistance Team were at each team table to facilitate the work and provide design assistance for visualizing the team members' ideas. Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force 7 Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force In the first team sessions, participants shared stories/ histories of the Rogers Road community. The teams then brainstormed ideas which were then shared with the other teams. The heart of the workshop were two design sessions in which each team developed ideas for community development. The ideas included a new road and trail network, suggestions for type of development in specific areas of the community, and plans for preservation of Rogers Road's unique cultural heritage. Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force Stories/ Histories Land along Rogers Road area became the property of freed blacks after the Civil War. A number of family have figured prominently in the history of the neighborhood —the Hogans, the Nunns, the Rogers, the Purefoys, and the Walkers. Livelihood in the community came both from without and from within. At various times, there was agriculture, a saw mill, and interneighborhood sales of milk and eggs. Vegetable gardens, cows, and chickens provided food for residents, and the surpluses were shared. Two significant houses the Lloyd— Rogers house dating from c. 1850 and the log house built in the 1930s remain in the study area. 9 Rogers Road Small Area Plan Recommendations 10 Final Report ♦ Rogers Road Small Area Plan Task Force After each of the design sessions, each team shared its ideas with the group. This process allowed good ideas to become the property of each team as it moulded its conceptual plan of future development in the Rogers Road community. Rogers Road Small Area Plan Recommendations follo of the m wed n points of each plan* workshop' the of the design steps in ref At the end ne Rogers Road the am ,,%eu en6ng the to Implement and plan' 5ma11 Area -�— plan rs Road small Area Rope I.I. Final Report ♦ Rogers Road Small Area Plan Task Force Team A Plan 121 Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force • Create five new connections to neighboring roads • Create a neighborhood commercial center • A variety of housing types with density varying from 1 unit per acre at edge to town house density at commercial center • Build -to lines to create a front - porch community • Use development potential to leverage funding for desired infrastructure • Create a community center using old house and incorporate public art to honor cultural heritage • Buffer to north 13 Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force Team B Plan 14 Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force • Create two connections to neighboring roads • Create traffic circle at Rogers and Purefoy Roads • Incorporate development that is sensitive to historic fabric • Preserve the 1700's house and the log cabin • Bike trails into the Greene tract • Ask new church to incorporate the existing cemetery into their proposed cemetery 151 Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force Team C Plan I Rogers Road Small Area Plan Recommendations 17 Final Report ♦ Rogers Road Small Area Plan Task Force = Create two new connections to neighboring roads • Create a neighborhood center around a square with library, school, community center, and shops • Create neighborhood commercial at intersection of Purefoy Drive and Rogers Roads • Create history center at the 1700's house • Preserve log cabin and create a small park that can incorporate a farmers' market • Create a parkway with walking and biking trails through Greene tract Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force The Roger Road Urban Design Assistance Team meet after the workshop to analyze the three plans for ideas which they held in common as well as for area of disagreement or unique ideas. That analysis is presented on the following pages. From the analysis, the team prepared a master plan for land use and for open space. Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force Analysis of Design Schemes Areas of Commonality • Connection north to Umstead Road • Connection across the railroad track on Weaver Dairy Extension using Purefoy Drive • Two plans and possibly the third show an east -west road to the north of Purefoy, connecting to Rogers Road • Cross -roads at the center of the area to become a community center with mixed use development; might include a community center /library • School near the center of the area • Buffer on the north side of study area to shield the area from the landfill site 191 Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force Areas of Commonality (cont.) • The historic house is retained in all plans and made part of the proposed Church complex; Church suggested making a history center; other uses included making it part of the Senior Housing in the Church program, or part of a community center. • Greater density of development to lessen the individual cost of sewer; at the same time, areas near Rogers Road and along the north side of area seen as less dense to retain the current feel of the area • Farmers' market and community gardens • The community needs to write a cultural history and create a plan to preserve its cultural heritage 201 Rogers Road Small Area Plan Recommendations 21 Final Report ♦ Rogers Road Small Area Plan Task Force Differences between the schemes and unique ideas • Team A proposed to extend Sandberg Lane and connect to Rusch Road to provide an additional point of access to the community • Team A also proposed to extend Purefoy Drive across the Greene Tract to Weaver Dairy Road and to extend Merin Road north to connect with this new section of Purefoy Drive • The Harris tract is gridded in Team A's plan while Team C showed a rural pattern with less density to west becoming more dense toward the cross -roads • Team A wanted a retail site or two at the crossroads; hence, the school was placed on the Neville tract. But the school could be located at the cross -roads without compromising the concept Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force Differences between the schemes and unique ideas (cont.) • Team B and C located proposed school on a portion of the 18 acres; Team C suggested • Team C proposed a branch library that would support community center activities • Team A said that new residential construction should be front -porch style, close to street. • Team C saw potential for neighborhood commercial use located at Rogers Road and Purefoy Drive • Rail station on Team B's plan anticipates commuter rail Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force Validation of the Small Area Plan Proposal From the analysis of the different schemes developed at the design workshop, the Rogers Road Urban Design Assistance Team proposed a land use plan for both land use and open space as well as written recommendations. This work was presented to the task force and workshop attendees at a meeting on July 31, 2008, at which time the findings and the proposed land use plan were presented for discussion and approval. As a result of those discussions, the final plan and recommendations are presented on the following pages. 2-31 Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force Recommendations for Small Area Plan A detailed summary task findings is located in the Appendix. In general, the findings fell in five categories: • Transportation • Cultural Heritage • Infrastructure Improvements • Green Space • Strategies for Community Preservation as well as Development The task force's recommendations and master plan spring from these findings and are presented on following pages. Rogers Road Small Area Plan Recommendations 25 Final Report ♦ Rogers Road Small Area Plan Task Force ROGERS ROAD DESIGN ASSISTANCE We" o :rzs.�a►- ROOERS ROAD SMALL AREA PLAN &VORxsNOP OCTOOM 2MB MASTER PLAN LAND USE Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force ROGERS ROAD DESIGN AASSSIISTANCE ROOERS ROAO SMALL AREA PLAN WORKSHOP OCTOBER. 2008 WD MASTER PLAN OPEN SPACE Rogers Road Small Area Plan Recommendations 27 Final Report ♦ Rogers Road Small Area Plan Task Force Task Force Consensus Recommendations • The masterplan should become the basis for a future land use plan amendment for the Rogers Road area. • The community offered support for a neighborhood core that includes a school, neighborhood commercial, and varied housing types from individual residence to town house. This should be supported in the Small Area Plan. • The community also expressed a desire to maintain current densities on the peripheries of the area Rogers Road Community Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force Consensus Recommendations Design • The community did not actively speak about design, perhaps because the various buildings in the area are rather diverse; however, it was clear that there were form issues about which they did have opinions. • The Small Area Plan for Rogers Road should include density requirements that reflect the community's vision. • It should also address height limitations. The community does not want excessive height. A 45' maximum height would be in keeping with the character of the area. • The community also expressed a desire for a so- called front porch community, where houses are built to a line close to sidewalks. • There were not strong sentiments for design guidelines; more frequently, we heard a desire for small scale, affordable development. Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force Consensus Recommendations Design (cont.) • The expressed desire for less density at the periphery suggest that the Small Area Plan should both address minimum lot size as well as lot coverage requirements. • Street design standards were important to the community. The community wanted to maintain the rural feel of the community at its edges. Streets and roads in this area would not have curb and gutter; in areas where there is greater density, the streets would have a more urban character with curb and gutter. Both street profiles would include sidewalks and street tree planting strips. • Suggested street profiles for these streets are shown on the following page. The profiles also show the location of houses relative to the street, a location which illustrates the front -porch community concept. Rogers Road Small Area Plan Recommendations Final Report ♦ Rogers Road Small Area Plan Task Force [Street profiles] 301 Rogers Road Small Area Plan Recommendations 31 Final Report ♦ Rogers Road Small Area Plan Task Force Consensus Recommendations Cultural Heritage Plan It can never be too often to remark on the fact that the Rogers Road community is unique and significant. The Rogers Road area was one of first local areas with significant land and home ownership by African - Americans in the early post -Civil War period and into the 20th Century. It is emblematic of a unique historical story of African - Americans in Chapel Hill. • As such, it should be engaged in a process of creating a cultural heritage preservation plan. • The Small Area Plan should include a formal project to write the history of the region. The school system would be a good partner as the history can become a part of a curriculum on the history of the Town. • The most significant�physical artifacts which carry this history are the 1700's house, adjacent graveyard, and the log cabin. Rogers Road Small Area Plan Recommendations at a 14 x.. '+'eL V �t K. w ' ..tea .aw a AI.,* ' r I •' x, r : x I yr e Afr�� r` e... �y .F' • . i .. r� t& �; �.�. i 'mob •"r, : fs� 'I Mrom Olmn G 33 Final Report ♦ Rogers Road Small Area Plan Task Force Consensus Recommendations Cultural Heritage Plan • There is a proposed development plan for St. Paul's AME Church. The indication from the church has been that it may not be able to renovate and preserve the 1700's house. If such is the case, it is very important to find other means to preserve the house. Although it is historically preferable to have it remain where it was built, it would be acceptable to move it to avoid its demolition. It could become part of a community center. • The graveyard poses a similar problem, and while State law allows remains to be moved, the preference is that the cemetery remain where it is and be protected. Rogers Road Small Area Plan Recommendations 34 Final Report ♦ Rogers Road Small Area Plan Task Force Consensus Recommendations Open Space Plan To the east of the Rogers Road community, an area has been identified by the town as preserved open space, the so- called Greene tract; there were discussions about the character of this space. • Should the Greene tract remain a passive natural area, or should there be plans for more active recreation? • The team feels that the Greene tract can remain largely passive open space, much of it preserved as typical landscape of the Piedmont. • However, it seems appropriate to create trails and a parkway across the tract. Rogers Road Small Area Plan Recommendations 35 Final Report ♦ Rogers Road Small Area Plan Task Force Consensus Recommendations Open Space Plan (cont.) • There was also a discussion of how fixed the boundaries of the open space should be. There was some sentiment to borrow some of the land for the proposed school and other community uses in order not to take away land area from the 18 acres designated for affordable housing. • Part of the Greene Tract near the school should be developed for more active recreation. • The area around the log cabin should be set aside for community gardens and for a small farmers' market. Rogers Road Small Area Plan Recommendations 36 Final Report ♦ Rogers Road Small Area Plan Task Force Consensus Recommendations Transportation • The task force recommends that the Town secure dedication of rights -of -way that will allow the development of a street grid with multiple access points to the community. • Streets should be designed to a "country road" standard at the peripheries of the community. • A bike and pedestrian trail system should be developed; the trails should be separated from the road system and all trails should lead eventually to the proposed school location. • The bike and pedestrian trails should be integrated into the plan for the broader greenway systems. • As a neighborhood center develops around the school and other community facilities, the Chapel Hill Transit System should bring buses into the center. Rogers Road Small Area Plan Recommendations 37 Final Report ♦ Rogers Road Small Area Plan Task Force Consensus Recommendations Transportation (cont.) • With the introduction of roads that pass through the community, traffic calming methods should be used in the design of the streets and crosswalks. • We also recommend consideration of a roundabout at the intersection of Rogers Road and Purefoy Drive. In addition to improving safety at the intersection, it would serve as a traffic calming device. • The task forces recommends that the Town negotiate with N.C. Railroads to secure permission to have an at- grade crossing where Purefoy Drive is proposed to be extended to Weaver Dairy Road. Rogers Road Small Area Plan Recommendations qfl Final Report ♦ Rogers Road Small Area Plan Task Force Recommendations Infrastructure • From the very start of the task force's work, one of the most important issues was to bring OWASA sewer and water to the properties in the Rogers Road community. • The major impediments to implementation are the initial sewer assessment and the fear that sewer and water service will cause an increase in property values and taxes. • We do recommend that extension of sewer and water to all properties in this community. The proposal to bring a school and other community facilities and greater residential concentrations at the center of the community will not be possible without the extension. • In the following section, we make recommendations which are aimed at reducing the negative economic effects that might result from extending sewer and water to Rogers Road. Rogers Road Small Area Plan Recommendations 39 Final Report ♦ Rogers Road Small Area Plan Task Force Consensus Recommendations Community Preservation and Redevelopment • We recommend that the Small Area Plan incorporate mechanisms which will educate the community on development in order to empower it to develop its assets. • Town and county should explore options similar to a homestead property valuation system which keeps taxes low on a property that is not being redeveloped even if neighboring properties are increasing in value because of redevelopment. • Such plan may incorporate a requirement for payment of a set number of years of back taxes is the property is redeveloped to capitalize on the value created by adjacent development. • The Town of Chapel Hill should initiate a discussion about annexation as part of the future dialogue on providing services to the Rogers Road community. Rogers Road Small Area Plan Recommendations M Final Report ♦ Rogers Road Small Area Plan Task Force Consensus Recommendations Our final recommendation is that the Town and the Rogers Road community maintain the type of dialogue which was made possible both by the efforts of the task force and by the work the community did together during the design workshop. This grassroots democracy in action can only strengthen Chapel Hill and its varied communities. Rogers Road Small Area Plan Recommendations Attachment 3 5 Orange County Staff Comments on Rogers Road Small Area Plan Task Force Report Cost of Water /Sewer Improvements (County Manager's Office): The most problematic part of implementation may be gaining public financing for water /sewer improvements and the most controversial the Homestead -like exemption to address long term property ownership and affordability. It should be clear that grants are to be primary or sole funding source for water and sewer improvements. Claim of Well Contamination (Solid Waste): Comment in second paragraph (p 9, History) regarding contaminated wells is absolutely not true; not a single piece of reliable /legitimate evidence has ever been presented, and two series of evaluations of local wells by the Orange County Health Dept. has in fact concluded no trace of landfill contamination has been discovered. The County strongly refutes this assertion. Roadways Problematic (Solid Waste): Given the minimal landfill buffers and storm water and other landfill support features that are present, it seems unlikely that the roadways noted would be feasible from a regulatory perspective. It is also not likely that public roadways would be considered located so close to the actual waste disposal cells. Alternative routes should be explored. Use of Neville Tract (Solid Waste): The Neville Tract is an essential component of landfill operations, serving as the source of final cover soil for landfill closures (C &D landfill will close approximately 2027) and is the site where emergency storm debris is stored following being ground. Until a new location for emergency storm debris management is obtained, this tract is a critical part of local emergency management infrastructure. Planning efforts should focus on the Greene Tract and assume Neville is not available for some time. Protection of Streams and Wetland (Environment and Resource Conservation Department (ERCD) Special care should be taken to avoid encroachment on two Bolin Creek headwater streams and associated wetlands on this property as identified by Goldstein & Associates, Inc. (2000). A copy of the Goldstein report is available from ERCD. Any school facilities should be designed and sited to avoid the Bolin Creek headwater streams and associated wetlands by Goldstein & Associates, Inc. (2000). Construction of Trails and Other Recreation Opportunities on the Greene Tract: (ERCD) ERCD supports the construction of natural trails and a paved greenway trail as long as those facilities are properly located to minimize adverse environmental impacts. The Composite Land Use Map (Figure 9) on p 17 identifies a large pond, which probably no longer exists on this property. There may have been a pond at one time, but that area is entirely forested. Preservation of Cultural Resources /Historic Properties in the Development Process (ERCD): A cultural resources (archaeology) survey of the Greene Tract conducted by TRC Garrow & Associates (2000) uncovered two historic sites, two prehistoric sites, and four "isolated finds." The consultants determined that the two historic sites were potentially eligible for the National Register of Historic Places and warranted further research before potentially disturbing land use activity occurred. The proposed road network through the Greene Tract shown on p 13 -19 of the report appears to avoid the two sites, but ERCD recommends examining this area more closely. Due to the historic nature of the study area, ERCD would recommend that additional archaeological investigation (surface and subsurface investigation) be conducted in the rights of way of any future roads or potentially paved trails once those corridors are formally surveyed. The Town and County may wish to work together to conduct additional archaeological investigation as part of the development process for the future school site identified by the orange area on page 18 of the report. The Town and County may likewise wish to retain an archaeologist to be "on call" during construction to monitor work and record any finds during the development process for publicly- funded projects within the Rogers Road Study Area. The Task Force recommends preserving and integrating two historic buildings into the future community facilities (p 21) . The Lloyd- Rogers House (OR 431), a two -story Greek Revival building (ca 1850s), located on the AME Church property is listed in the County's inventory of historic properties. The rear portion of the house was removed earlier this year; some stabilization measures may be needed to protect the house from deterioration to ensure its potential use for the future. The second historic property referenced in the report is the one -story log house located at the end of Edgar Street. This building has been identified in the report as a potential focal point for a community garden or farmers market. This building was not recorded in the countywide survey, although it probably should have been. Based on photos and a brief drive -by, the 1930s date of construction seems on target. Like the Lloyd- Rogers House, the log building is in need of maintenance. It may be prudent to pursue general cost estimates for renovating these buildings as part of the long -term planning process implementing the Small Area Plan. App,,,, md orc Vlia4z — Z�c n bw /0/ 2002 AU4 v4 4 Btisfriiess Award of OYqI)t%gWwftAqAOgf6vAl Ik�: Scif tware The Board awarded �..proposaLand approved -the provedwd-authofiked: to wi is ... vf� us '!o '7.2, 10 f bu rel, ance fief: f - r -- - ' ­ . MUN affQunt6f*$44-0,WOplus-anannu;alrr( tifeixt tep. -o $ 4 , sin. _bvod Wad a0a -khdffll Ah hdiho WM GGS provioaw y Bib Oor in a mi may and nco'OfMctiq -Aipnd C-i ty Alt gaff review authorized the Fina n. OMM 16. 061.11 tbe° tuodlog through COB. Oxftute the d Moto SL. Multu L Detenv4-Trainina AnEgmen h. NA Q, Firem `s- and -ides-cus Tho BOOM i ' 4 forlo-atibn r"i SA Carolina aIe:FIr9men!s:a-nd Re Squad WC, ortifi�affon document. L Tftitt-66 Abboihtffii Wft Rena " Gedd The.- %aW O -4%f mf) H qr I LR id Ain fir thO �i4r re., t IrusfeeAp ntmerifto-theSo TKO 6batd APPOntod. Mr. by.,Odorg.i Sbift Grange ft d' lict, k. 1311"gl e. w., Fees: forts amg Le 1% 80drd appftdd OfW fe-oft f with an-effective date of December K. 2002 I. Agor of, Rftom mm datigfUo . . , ThU -It6m`*as 'teftvb&6 al ponMOdrati on. m. Telecom] fiutdLOtfchTd 9 ThisAtqm was. remove- wnd placed a.! VOTE 04004991SIT'' : 13 ZU Ak LUJINANIMOUS- SL _ t jjd pf tho: Option pension fundndauthoflzed't'hel- Cha-fr-to: sign 'the ig Local R -41 of Fund :for the and AWdehtlal pk>)dots: la f-busepal-Ate la forsepprater c9nWored.awardi A-,qontraqtj4,.Dr- Henry Mequ.jO,..jo;#ibsQmQt;nt;of $0100for " Mo. ffscalyeAr to Provide'., cultural compa.tomy building WairlihOd Odwity-,e her" Jacobs would like t6 use diff0dint w- dt'din"g. tl%n cultu . ral co "...teritytudhas, �E5 Xve .. -I m6tion was rnfade p)( CornrrfioiObot Jawbs;'. socoftdad by Odlkhilsslow *Idofis: to.-Awned 'Dr.. Henry Alleguid 16 Me- a mo unt: of $.Sj I W fbifiscal yea r 20M. 400 3-to provIid_'Xu Qmp, cy 'bW!din A training to-CounVemplq om — 1, - 0 Aggroval.-of Recommerkdallons-A-001 -d[ftwe Traci Workt T h W. Board ?;ofisidorod f 6 tmal approval of re'oo-mmon daflfrom. ofit -tho G ro 6ne.Tract Irk: Group regarding ,the 104 acres of the Greene Pact remalhing. ih.joird:ownership. Go mlssl idefflify-WIWI-ho tkkfs-ato. Rod V.-Miat said that WWWirig must hM: happened Mith'the Ointitig. He explained whot the colors-repropentaq on'the: map.- Conirrifulorier Gordon said that thisi MgOflation Is: a: hilkstolM. the W.-mM4,Ad6d CovA in.h%tio ne" ts, C 6 and Brawn for their Work; on"this as as, the othdr 06op''10i that W06A.: 6-1 d a'' this: A motion vms niade. by Commis§jonor Gordcm, s com o ,.Ocop.joeo �y- rn.!".jpt�i below: ARE-SSOLUTF6N..RtPOk-TlN WHEREM. 0=90-00uhty AN ft lePhO 0:0-or amiddhapoi Oil --am almd ft:propb knower as: th6 MtdfierTrkCt:'!hr1984 as 9n1_':-atiie.V6f theli joint volid*6 MAiadio. provisidns--of the 1999 interlocal 'Agreeiment1or SvIldWasts'M ainagement"t and WHEREAS., under :the abObb-iritaft -81 --disPosJU0 m :of tlfo.40 re ge 01 WHEN': S 'ho sod date of 011.0i, "Ur92100a poywl ;w0oryoo'.1n, fho a sec the &% uobh Whibli ff*Coonly .&sWtft6d overall ,g M-omont.wAs , Apr' 17j.2 the MSPOrItWifity f6f thlid waste management In Grange Cmuntyr r and WHEREAS, -thid. Grb n Tradt - Wo* WO u p -.co, fiside' red di rd dtiorr-f ro ni-th-6 rod- odalo '0'- d.- Vub"Ir-i -0 b 000. f ft.; 'Pomm"tis frqM intaTested-efteme 1 nd.`�n n jq -in rosponse to y rg_ $too W 0k,i-roup hquirles--in d0elbpirig a rom brKselect concept plan-f6rthob'algrm-o6% Oregn -a nd W EkEAS-,.tfi- 0. H W.OkGfoup. tdPoided to 0-th.f0b 0V0.rh1h'§ boards: -.'.:djkW Mitch. 21" 2002 that It had reached s6big-antled.'agreement. on a concept ncept plan proAdin-g.for-approx4matefy,7B:acres to- be -Ormwrkod:fiiDrtopon space prdt000d Oy--mmomfion 00somonto'"I' OPPAOX14D.Ataily"Is.- oorowb be Ui-K - " .9na 0. Nh s OU Id e jpoed on; the remaining, acres; -and- additionAls icep ThwOf0tL.Vi0%#.,00­th,6 06&ept pjan as bp'6fV.%p;W9`. thOuld b&. 1*000W.4by AX104jiting A conservation easement- between appropr1rata rties Tire Btarst oft. r. .mvr�tr d 0 PortA oftho. It I Gtedhi& Tract' by-io0ibutibg 't- t. Ith. ion- eatemen V ell appropriate: .P. Process to The= C(�ap HID Tqw jlbuqqi -qqqplj. consider e 4nd. moos tot the :06440YR6aLd area: . a The. OrdotW.. Abbld be: 'r6h6m, 6d: in a: man sillo'biffdAftet.6f this.4f" at Th ou d-take; AVOY.W.- , no, - qyft 411 , M .voabf thopUbIl. n.., t' vicihlty of the breene Tract, as cata note accompanyiII91ablem and WHEREAS- -thd &Ve nt OF d Of all tht66jufj$d idloft opprbv # . reso UV*nS__0) tet1 di ho th 6 b6fgain ng peuiod beyond-A*1 . -00popp 0410pn`attli- nv to iwtpi reach pnse:nOutort tKo basic uses 6b eatiablii li 4 fgrlfi tippqif I� I I a&bsm titre -Unfbisd Ned; and m��M:, the Wm*�Oromp wdWjo-. teehro* report-fam." COuro EnoweeiroutlinIfi§, th'o 15.'a#10 vilternatives available and appreA. mafe-oosts r for prodding sewer service to, &portion-6-f the i Greens Tract, which service would be newssaryTortho VVHEREAS; the Work. Group concluded by -comerisus.1hat: Offmi, cqr.rfing,-;.qp .-of the land' should by the V 4 . nros.01..e­.'j 1. 60 , id lie a fdr. 06tarm (A otor`Jh-�1041 blishlog., how, much r u sWIfIc:,PurPd.t4s, 6nd4hat the t7jd0.6* Ilm rdfi6dMd:.oh th6,ddc6thPdh'y-1fiSj doUftirift the -acres iNtipgTk prAq.Jq brda,We hoqpng bq.�sqd -for. affib t4rVW by: asidw-etli AMWO hie gidt ik OF '0 n6 , midacd.esoth-eGfeo. T� V Put dyR.5d' NNW, THEREF_QRE,I3EI RES# LVEt� THAT the Ororo Tract Wo* OtOVAM hOMW:rooqMmehd thatthd Cdfftr6 136cittl .of Alddrfth., the-Chd* Hill Tftftf Cdtihdil, AM thb.Orah& CdUhty Boded of Coal wfa.io net% am. Opt".izopr mvp flc Group%_cons'"' W-6 tAiddol MMSfIdlatim4dr- a any concept plan" fdr tWat poftn oft-he:- Greene Tract diAdeeded ekeI&M 1y16' Of'A'A' Obl.; C-ou*- with the atctrepge to i3�a set ` for p ' .; p 0.0 Y :0" .9m n"PO ejmjqft:Opprbodmgt1rjg 95M aer o S and 1b 'acreage 6raft . able.. Ousing oo l mating 1.8. IS acres; - .OE"IT M4RT.H)Ek.RF%-QQVtO Tf;fAT'* the .'Orooflo-TrarVVOrk..Oto.up dovis h0ireby.: ro.00mmend to tho: thro §OVbMffi§ bbzfift that the WerditfdfoY MWOM h6usifid be plbidoflh-tho- LA-W Trust; 8EIT FURTHeRREWWtO THAT1110-OrOOM TMO Wrk OrAW Odes her o6 Yreto man d tO ' th r 09 the 'SbIId-Wasft"_ndfIII "Ili boardsthdt..th*­ ah.da.aftin gae-o.0tiold govern ng M- #O:h6VS.in9.;a(.nd OP40 speOMAM.' BE IT FURTHER RESOLVED THAT *the ---Weono- Traict.-W orkGroup does hereby recommend to the. three gomp "Ing bo ds that fho frigg vvin. g . mechanism; m.'for . raimbursdroonttu th o S 0110 easearients= pro fdbtiiig t> e. dosignategi'vpenspace, vo.t►-,spe U 1 4003 r approval [y ppr .jI1Akinqeff4OnosoqnoTthonJ VOTEt- UNANIMOUS . The Board ootisider-O! ampO.",rits- to kha: P-qOnt C e: to4w Wftm tolored pOWkh-her qu Ion .-And the ji ii-%% f t.6 th Deal' ' B:o . .r! T h :V th .e. q­u ad . n s. Ie d A o th MOp rOP$ohse chadn " ' .. The first .tinge suggested or g ris to r. ffig ball9pr 10t e'Sugg iho' fire & * SffiihhuM.0i. t h d sign b,* ho; 10 as.ith d h fdO r6q u tr4fo §t g 1 vi h g t I la, p rop o and -five o 'hoot (page AO). and the loemations. the IWrites I 'The other change was: number n the salmo I* mean m O*g Mv... 0 *w6jr hgg 0-:b0., dg M Ono �.Ijn the'. nWhibO Of-`.Weft ng thi ��: b at the fliddribbal-ft.offi- too q a rldotO to theltower. T can ro -the, repord.j VthwBq;Rrd:zi* s.-Wlih if... Also, sheMolb. wo millmoo that p 1 '64, 2" rMittod '"too --sure tKW ft (Olbtonaa to: Me of PO Wev. ShOVA"too -co- th ur: touKeTS Or IhAft. 1150..'Sot -20 OU -0 fbdo '; Id & td:thd D" rd 6FAdJUMf eiW ete Wdh height-DT shoder indicates na.particu., asked wfiewthe inconthte was, "0: a d pWa C.F said th e! It would lse a ciais; kspbvial-v this. Geaff Giedtill pointed out j foe 15.0-feat grid: More and sO lmngdt- on the *.c.o ft-UhIN : says, p47#460,6 t6.1wodjtffuhjcaflb.*n t6w6fs -I. foot In b lass: B. special use permit... He Mat the ordinance sfill'400 Promote co-lecOtIOn it is . L a p' . 06- ce". d U mi I incentive. happen if the '201 feet. Craig Benedict ire fer than '150 k4ti" some — of -like f.br-the County C 011 under plIq to say. "arid towers -2200 ierz to considerevery-thing that mdang .-A lot In terms 6f;O* A motion. w44 -...opmm-issioner.-Gordon,--soeQ.rded Comffii��[cynerJ4v6bs*tcr Poo, b ... . _. - . ­ . e.... ..,. . . . . Y _y -Ing. W.) Mit% AS approve the twa-1000�11 0WO& WAsOd b.. the Plannii BJ thAhO dMoridin _PMM W't 'Met in Height :or shorter, it es I g.-I-Is ;T#$O�Om height; itis" "Pecia, ... UM`5 -p.e A I use: ..r.mi andj n f$0,16of in a permit: ''he: 0 Co' -!Wtobdr Ji3d*W.. ks.kdd whdt'th 'pr000ss inceffliVO *tS fbt so t..,.h' four - 0 ave: carriers: Co Kissioner Gordon -said :that1vould takeout the process incentive a it -eilfaw the. o wlqwom more Omn. 50 f0vfeat: Oa-unit 40 -t :9 iO hd r"Od td�) t- 4 -1 NO, V( ffifflit;S a. Attachment 5 10 { {To be printed on County letterhead }} June 3, 2009 Kevin Foy, Mayor Town of Chapel Hill 405 Martin Luther King Jr. Blvd. Chapel Hill, NC 27514 -5705 Re: Comments on Rogers Road Small Area Plan Task Force Report Dear Mayor Foy: Thank you for the opportunity to review and comment on the Rogers Road Small Area Plan Task Force Report. This important planning effort has been reviewed by several County Departments and comments are included in the enclosed sheets. The Board of County Commissioners formally received the Small Area Plan at its June 2, 2009 meeting and considered its ramifications in respect to the BOCC- appointed Historic Rogers Road Community Enhancement Plan Development and Monitoring Task Force which completed its work in 2008. We look forward to continued cooperation with the Town as the small area plan moves through the adoption process in accordance with the provisions of the Joint Planning Agreement. We are also eager in engage with the Town of Chapel Hill and Carrboro in the creation of the local government work group intended to work aggressively on implementation strategies, including grant financing to secure recommended community improvements. If you have any questions, please do not hesitate to contact me. Sincerely, Valerie P. Foushee Chairperson Enclosure {Note: Attachment 3 is the enclosure} Excerpt of Meeting Minutes SUMMARY MINUTES OF A ASSEMBLY OF GOVERNMENTS OF THE CHAPEL HILL TOWN COUNCIL THURSDAY, MARCH 26, 2009, AT 7:00 P.M. Present were Chapel Hill Mayor Kevin Foy, Mayor pro tern Jim Ward, Council Member Matt Czajkowski, Council Member Laurin Easthom, Council Member Sally Greene, Council Member Ed Harrison, Council Member Mark Kleinschmidt, Council Member Jim Merritt, Council Member Bill Strom, Carrboro Mayor Mark Chilton, Carrboro Alderman Jacquelyn Gist, Carrboro Alderman Joal Hall Broun, Carrboro Alderman Lydia Lavelle, Orange County Commission Chair Valerie Foushee, Orange County Commissioner Alice Gordon, Orange County Commissioner Pam Hemminger, Orange County Commissioner Barry Jacobs, Orange County Commissioner Bernadette Pelissier, Orange County Commissioner Steve Yuhasz, and Hillsborough Mayor Tom Stevens. Staff members present were None. *** * * * * * * * * * * * * * * * * * * * * * * * * * * * * * ** 3. Receive a petition from Rogers' Road residents Minister Robert Campbell addressed the petition submitted by Rogers' Road residents. He said the community had bore the burden of all of the community's trash and had been denied public services. He said each petition requesting services in the past had been delayed for some reason. He said the recommendation is that all entities should collaborate to find funds for the Rogers Road — Eubanks community. He said the petition submitted by the residents in December 2008 included a list of available funding sources. He said the residents were asking elected officials to commit to a specific date when services outlined in the petition will happen. Council Member Kleinschmidt said he had chaired the taskforce appointed to address the Rogers Road requests for services. He said other elected officials as well as several members of the community, and at large members of boards and commissions had served on that taskforce for the last two years. He said they received information from Orange County, OWASA, and town governments, to achieve services and a vision for the Attachment 6 11 12 community. He said the Rogers Road community was an old community that in recent years had experienced urban encroachment. He said located in one part of the community is the dump, and that Carrboro had annexed a great deal of one side of Rogers Road. Council Member Kleinschmidt said the taskforce had charettes to determine a vision of how to incorporate the pressures of growth, and what elements make it a special place. He said the area was owned by the jurisdictions around the table. He said on page 25 of their materials there is a chart with a summary of the joint planning activities that refers the report to all entities including schools, the establishment of a community work group, and a funding and phasing plan for water and sewer services. He said the goal was to develop access to those services. Alderman Gist said out of the group working on mitigation measures of living near the dump, came the running of water lines up Rogers Road. She said the problem was not so much getting the lines to the houses, but the water pressure presented problems for old plumbing fixtures. She cautioned that getting water into the houses was the issue, not running water lines down the road and to the houses. Alderman Broun said they should constitute the work group and set a deadline for boards to come up with some plan. Mayor Foy called for each separate board to review the information and take some kind of action. Mayor Chilton said the work group had done great work and the process for moving forward. He said he was prepared to move forward. Commissioner Jacobs said he and Chair Foushee and Commissioner Cary had met with the community and a list of concerns had been raised at that meeting that should be incorporated into this report. He said they had looked into contracting with a plumbing company to do all the waterlines. Commissioner Broun asked if each entity would go back and appoint people for this work group and set a deadline. Commissioner Gist said the smaller the group the better and suggested a core group with one member from each body and begin the process with a Saturday retreat to determine the next steps. Mayor Foy said each board could develop its own process to appoint members. Mayor Chilton suggested one member and an alternate. Minister Campbell suggested there be a community resident and an alternate. There was unanimous agreement from the Assembly. J a. ,, 13 ORANGE COUNTY BOARD OF COMMISSIONERS ACTION AGENDA ITEM ABSTRACT Meeting Date: May 1, 2008 Action Agenda Item No. SUBJECT: Rogers Road Community Enhancement Task Force — Recommendations DEPARTMENT: Solid Waste Management PUBLIC HEARING: (YIN) I No ATTACHMENT(S): INFORMATION CONTACT: Recommended Enhancements Recommended Historic Rogers Road Gayle Wilson, 968 -2885 Enhancement Area Map PURPOSE: To present for Board of County Commissioners' consideration the Historic Rogers Road Community Enhancement Plan Development and Monitoring Task Force's recommended Historic -Rogers Road Enhancement Area Map delineation and list of proposed community enhancements. BACKGROUND: At the May 3, 2007 BOCC meeting the BOCC created the Historic Rogers Road Community Enhancement Plan Development and Monitoring Task Force. The purpose of the Task Force was to develop and forward to the Orange County Board of Commissioners a proposed plan, including financing options, for enhancements in the historic Rogers Road Community. The Task Force was also charged with recommending the geographical size /parameters of the Historic Rogers Road community, for which the recommended enhancements would be provided The Task Force has met seven times, with the first meeting held on June 6 and the most recent meeting on November 12. A June 26, 2007 interim report was provided. At the September 12 Task Force meeting the attached map was adopted by consensus and is being recommended to the BOCC for consideration. At the November 12 meeting the Task Force adopted a final list of community enhancement recommendations. FINANCIAL IMPACT: There will be a substantial financial impact related to implementation of many of the Task Force's. community enhancement recommendations. RECOMMENDATION(S): The Manager recommends that the Board receive the Historic Rogers Road Task Force's Recommended Historic Rogers Road Enhancements - and Area Map. 14 ON Memorandum To: Board of County Commissioners Through: Laura Blackmon, County Manager From: Gayle Wilson, Solid Waste Management Director Subject: Historic Rogers Road Community Enhancement Plan Development and Monitoring Task Force Final Recommendations - Neighborhood Enhancement List and Area Designation Date: April 24, 2008 At the November 12, 2007 meeting of the Rogers Road Community Enhancement Task Force the list of community enhancement recommendations was finalized and recommended to be presented to the Board of County Commissioners for consideration and implementation. The list is presented below: 1 a_ Do not use Eubanks Road as a site for the transfer station. Leave the Solid Waste Convenience Center at its current location on the north side of Eubanks Road. Upgrade the convenience center waste containers to enclosed waste containers as soon as possible.. This will help reduce odor and the number of rodents escaping into the Rogers and Eubanks Roads communities. Orange Couttty lb. Extend water and sewer mains be extended to provide public service to the recently endorsed Rogers Road Community Enhancement Area, (which is the landfill impacted area), including Ms. Nunn's property, at no cost to any of the residents. The Task Force further recommends that water and sewer connections and OWASA impact fees for these connections be provided to the Rogers Road Community Enhancement area at no cost to any of the residents. Orange County, Chapel Hill, and Carrboro should utilize Community Development Block Grants, other grants, or local funds where allowed by state law to pay for adding water and/or sewer mains, house connections, and OWASA impact fees. Chapel Hill. Carrboro, Orange County and OWASA 2. Reduce the odor from the landfill and convenience center now!! Pursue a masking agent atomization for landfill working face. Complete landfill leachate sewer project to eliminate leachate storage basin as soon as possible. Confer with OWASA and utilize best management practices for the landfill industry to control odor and vermin.. For finance: lease the landfill areas to a private company that can harvest the methane gas for profit and to help in odor reduction. Orange County and Chapel Hill 3. Build a barrier wall (beginning with below the surface of the ground) to impede stop rodents and other animals from leaving or entering the landfill and to decrease noise, improve air quality. Plant more trees and other vegetation to obscure the view of the landfill mount. Orange County and Chapel Hill 15 M 4. The Task Force recommends that water and sewer mains be extended to provide public service . to all of the Task Force recommended Community Enhancement Area (map attached), including Ms. Nunn's property. The Task for also recommends that Orange County, Chapel Hill, and Carrboro provide public water and sewer in the Community Enhancement Area where water and sewer service are to be extended in paying the costs of connecting to water and sewer. This assistance can take the form of Community Development Block Grants, other grants, or local funds where allowed by state law. Costs for all residents should be eliminated or minimized to the extent possible. Chapel Hill, Orange County, Carrboro, and OWASA 5 Institute a moratorium on property taxes. Pay for /subsidize future taxes for the residents in the community enhancement area for as long as any solid waste facilities remain in their community. Pay impact stipend to property owners whose land is adjacent to the landfills. Be vigilant about not allowing residents to lose their homes and/or property because of their inability to pay taxes; advocate for residents who become at risk of losing their homes and/or land due to inability to pay property taxes. Return property taxes paid from the time of the opening of the landfills. (This would include Millhouse Road residents.) Orange County 6. Build park and other recreation facilities within the Rogers Road Community Enhancement Area such as basketball and park type equipment: jungle gym, swings, picnic tables, benches. The Parks and Recreation Department should maintain these facilities. Children within the Enhancement Area should be provided summer youth employment opportunities. Chapel Hill, Carrboro and Orange County 7. Add NCDOT traffic calming bumps on Rogers Road and decrease speed limit to 25 mph. The Task Force recommends that Orange County erect "Children Playing" and "School Bus Stop" signs on Rogers Road. Residents of the Community Enhancement Area will identify appropriate locations for these signs. Chapel Hill_ Orange County Carrboro and DOT 8. Add sidewalks to both sides Rogers Road from Homestead Road to Eubanks Road. Chapel Hill and Carrboro 9. Widen Eubanks Road and add shoulders and turn lanes at landfill facilities. These areas are extremely unsafe and congested — especially in the mornings. Given the garbage and UPS trucks and city buses, Eubanks Road is too narrow to be safe. Chapel Hill Orange County, Carrboro and DOT 10. Bring the bus service down Rogers Road at least three times (morning, noon and evening). The Task Force also recommends that Chapel Hill Transit re -route the North -South connector bus 2 16 M line to serve Rogers Road on either its northbound or southbound trip, beginning as soon as possible. For the duration of the 2007/2008 service year, the Community Enhancement Area should be designated as a Shared Ride Feeder Zone. Build an enclosed and lighted waiting area at the bus stops. Chapel Hill and Carrboro . 11. Add publicly financed street lights for public roads and streets. Chapel Hill and Carrboro 12. Add fire hydrant north of Edgar Street, between the properties of Tim and Edward Peppers and Nola Mae West. This hydrant will service properties that presently are more than 400 feet and as far as 1500 feet from a fire hydrant. C el Hill 13. Modify building, zoning, and other ordinances that make it difficultlimpossible for landowners in the Community Enhancement Area to develop their property. Chapel Hill, Carrboro and Orange County 14. Do not allow industrial zoning. Do not allow any zoning that makes this community vulnerable to big developers. Chapel Hill, Carrboro and Orange County 15. Do not allow any large development (including affordable house) on Purefoy Drive that has no other means of egress into the Purefoy, Sandberg, and Edgar Road area other than Purefoy Road. Chapel Hill 16. Ensure adequate representation of this community in local government'decisions that affect this community, including land use ordinances. Orange County, Chapel Hill, and Carrboro 17. Re -unify this community by de- annexing the west side of this community from Carrboro. Carrboro Do not divide this community between different jurisdictions. Do not annex this community Carrboro and Chapel Hill 18. Document in writing all meetings concerning this neighborhood and have these documents officially recorded and filed. Orange County, Chapel Hill. Carrboro 19. The Task Force recommends that residents living near the Orange Regional Landfill take initiative in identifying perpetrators of illegal dumping near the landfill to assist in successful prosecutions. Identification of vehicles, license tags, drivers, and/or types of articles discarded should be made when possible. The BOCC should coordinate with the Orange County Attorney to pass legislation, which provides for civil penalties for illegal dumping to make it easier to penalize people who litter or dump. In addition, the BOCC will publicize the names of those convicted of illegal dumping. The BOCC should increase enforcement of anti- dumping laws in the Community Enhancement Area. 3 17 5 The Task Force recommends that additional "No Littering" signs be erected in the neighborhoods near the landfill. Orange County 20. Allow power to be turned on in power outages in a different order so we are not next to last every time. Duke Power 21. Pay more attention to our roads during ice and snow events. Chapel Hill, Carrboro, and DOT 22. Expand fire, EMS, and sheriff services as soon as possible. Chapel Hill, Orange County, Carrboro 23. St. Paul Church purchased a 20 -acre property that holds 3 -story house and neighboring cemetery filled with history of local families. Community would like to see efforts that that section of the property be protected from demolition and preserved as a Historic Site. Chanel Hill, Orange County, and Carrboro Note: St. Paul AME has purchased five adjoining properties along the northeast corner o Rogers Road and Purefoy Road The parcel that contains the 3 -story house and cemetery was included in that purchase. The house was recorded as part of a countywide survey for historic properties or historic architectural resources in the early 1990's. These countywide surveys were conducted throughout the state in conjunction with the North Carolina State Historic Preservation Office. This particular house was first recorded in 1992, and re- surveyed during a 2006 update According to notes ofthe survey there is a white cemetery (Hogan) in the front yard and a black (slave) cemetery somewhere in the back 4 ►- J� '� ; �c��''t -: jam. ,,,,,;: --rte- t���r► �..�.�.. _ _ _ a ♦ L � 4 - J