ACTION AGENDA ITEM ABSTRACT
Meeting Date: May 19, 2009
Action Agenda
Item No. L}- - ('
SUBJECT: Approval of School Capital Project Ordinances
DEPARTMENT: Budget
ATTACHMENT(S):
PUBLIC HEARING: (Y/N) No
Capital Project Ordinances for FY 2009-10 INFORMATION CONTACT:
a) Chapel Hill Carrboro City Schools Donna Coffey, (919) 245-2151
Projects
b) Orange County Schools Proiects
PURPOSE: To consider approval of School capital project ordinances for FY 2009-10.
BACKGROUND: On April 28, 2009, Orange County and Chapel Hill Carrboro City Boards of
Education shared with Commissioners their prioritized capital investment budget for FY 2009-
10. Both school districts have particular capital projects where work needs to occur during the
early summer months when students are not in class. In order for work to begin immediately as
school adjourns for summer break, school districts must have Commissioner approved capital
project ordinances in place to award bids for the planned projects. Tonight staff requests the
Board approve the attached capital project ordinances for FY 2009-10. There are four projects
falling. into this category and need approval by the Board tonight. Staff will bring the remaining
school and county capital project ordinances to the Board for approval at the June 2, 2009
meeting.
FINANCIAL IMPACT: Total pay-as-you-go funding of $1,375,000 provides the revenue for the
following projects:
CHCCS Window Replacements
(Lincoln Center) $206,210
CHCCS Roofing Projects (Lincoln
Center, Carrboro Elementary,
Seawell Elementary) $943,790
OCS -Central Elementary Cooling
Tower $100,000
OCS - Efland Cheeks Elementary
Cooling Tower $125,000
Total $1,375,000
RECOMMENDATION(S): The Manager recommends the Board of County Commissioners
approve the School capital project ordinances for FY 2009-10.
a
Window Replacements
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds for the replacement of old and inoperable
windows at various elementary, middle, and high schools. Funding for the
project comes from savings from Public School Building Funds, savings from
other projects within the District and alternative financing.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2008-09
FY 2009-10 Through FY
2009-10
Sales Tax $870,000 $206,210 $1,076,210
Im act Fees $0 $0 $0
1992 Bond Funds $0 $0 $0
1997 Bond Funds $0 $0 $0
Pro'ects $0 $0 $0
Alternative Financin $655,000 $0 $655,000
Total Fundin $1,525,000 $206,210 $1,731,210
Section 4. The following amount is appropriated for this project:
Through FY
2008-09
FY 2009-10 Through FY
2009-10
Plannin /Arch/En in $25,000 $0 $25,000
Land/Assoc Fees $0 $0 $0
Construction $1,500,000 $206,210 $1,706,210
E ui ment/Furnishin s $0 $0 $0
Other $0 $0 $0
Contin enc $0 $0 $0
Total Costs .$1,525,000 $206,210 $1,731,210
Section 5. This ordinance remains in effect from July 1, 2002 until June 30, 2010.
Adopted this 19th day of May 2009.
3
Roofing Projects
Chapel Hill-Carrboro City Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1. The project authorized provides funds to repair and replace roofs at many of the
schools in the district. Proceeds from the Schools' portion of the one-half cent
sales taxes, alternative financing, and transfers from completed projects within
the District finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within
the budget contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2008-09
FY 2009-10 Through FY
2009-10
Sales Tax $883,626 $943,790 $1,827,416
Im act Fees $0 $0 $0
Alternative Financin $3,015,000 $0 $3,015,000
1992 Bond Funds $0 $0 $0
1997 Bond Funds $0 $0 $0
Transfers from Completed
Pro'ects
$488,500
$0
$488,500
Total Pro'ect Fundin $4,387,126 $943,790 $5,330,916
Section 4. The following amount is appropriated for this project:
Through FY
2008-09 FY 2009-10 Through FY
2009-10
Plannin /Arch/En in $205,000 $0 $205,000
Land/Assoc Fees $0 $0 $0
Construction $4,182,126 $943,790 $5,125,916
E ui ment/Furnishin s $0 $0 $0
Other $0 $0 $0
Contin enc $0 $0 $0
Total $4,387,126 $943,790 $5,330,916
Section 5. This ordinance supersedes all previous Renovations -Roofing Capital Projects
for the Chapel Hill-Carrboro City Schools.
Section 6. This ordinance, originally adopted July 1, 1998, shall remain in effect until June
30, 2010.
Adopted this 19th day of May 2009
4
Central Elementary Renovations
Orange County Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section
13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital project is
hereby adopted.
Section 1.The project authorized provides funds to renovate present space adjacent to the
media center for a computer laboratory and a video station as well as the production
and work areas of the media center. Proceeds from the Schools' share of pay-as-
you-go capital funds finance this project.
Section 2.The officers of the County are hereby directed to proceed with the project within the
budget contained herein.
Section 3.The following revenue is anticipated to complete this project:
Through FY
2007-08
FY 2009-10 Through FY
2009-10
Sales Tax $199,000 $100,000 $439,000
Impact Fees $0 $0 $0
PSBF $0 $0 $0
1997 Bond Funds $0 $0 $0
Other $Q $0 $0
Total Project Funding $199,000 $100,000 $439,000
Section 4.The following amount is appropriated for this project:
Through FY
2007-08
FY 2009-10 Through FY
2009-10
Plannin /Arch/En in 0 0 0
Land/Assoc Fees 0 0 0
Construction 159,000 100,000 399,000
E ui ment/Furnishin 40,000 0 40,000
Other 0 0 0
Contin enc 0 0 0
Total A ro nation 199,000 100,000 439,000
Section 5. The following amounts have been transferred to another Orange County Schools
Capital Project:
Through FY Through FY
20Q7-08 FY 2008-09 2008-09
Transfer to Orange High Track and
Football Feld Project (FY 20009) $0 $54,732 $54,732
Total Costs $0 $54,732 $54,732
5
Section 6.This ordinance supersedes previous Central Elementary Renovations Capital
Project ordinances for the Orange County Schools.
Section 8. This ordinance remains in effect from July 1, 1998 until June 30, 2010.
Adopted this 19th day of May 2009.
S
Efland-Cheeks Elementary Renovations
Orange County Schools
Capital Project Ordinance
Be it ordained by the Orange County Board of County Commissioners that pursuant to Section 13.2
of Chapter 159 of the General Statutes of North Carolina, the following capital project is hereby
adopted.
Section 1. The project authorized provides funds to add storage for indoor and outdoor physical
education equipment and an office for the Physical Education teacher. Also included are
installation of energy efficient windows and air conditioning and electrical upgrades.
Proceeds from the Schools' portion of the one-half cent sales taxes and the 1997 bond
referendum finance this project.
Section 2. The officers of the County are hereby directed to proceed with the project within the budget
contained herein.
Section 3. The following revenue is anticipated to complete this project:
Through FY
2008-09
FY 2009-10 Through FY
2009-10
Sales Tax $477,000 $125,000 $602,000
Impact Fees $0 $0 $0
PSBF $0 $0 $0
1997 Bond Funds $85,000 $0 $85,000
Other $0 $0 $0
Total Project Funding $562,000 $125,000 $687,000
Section 4. The following amount is appropriated for this project:
Through FY 2008
09
FY 2009-10 Through FY 2009
10
Plannin Arch/En in $20,000 $0 $20,000
Land/Assoc Fees $0 $0 $0
Construction $532,000 $125,000 $657,000
E ui ment/Furnishin s $10,000 $0 $10,000
Other $0 $0 $0
Contin enc $0 $0 $0
Total A ro riation $562,000 $125,000 $687,000
Section 5. This ordinance supersedes previous Efland-Cheeks Elementary School Renovations capital
project ordinances.
Section 6. This ordinance remains in effect from July 1, 1998 until June 30, 2010.
Adopted this 19"' day of May 2009.