Item No. ~p _~f
SUBJECT: Joint Master Recreation and Parks Report
DEPARTMENT: County Manager, ERCD PUBLIC HEARING: (Y/N) No
ATTACHMENT(S): INFORMATION CONTACT:
Executive Summary Albert Kittrell, ext 2307
Work Group Report (maps under David Stancil, ext 2590
separate cover)
TELEPHONE NUMBERS:
Hillsborough 732-8181
Chapel Hill 968-4501
Durham 688-7331
Mebane 336-227-2031
PURPOSE: To receive the report of the Joint Master Recreation and Parks Work Group.
BACKGROUND: In November 1997, the Board created the Joint Master Recreation and Parks
Work Group. The group was charged to update and modify the Master Recreation and Parks
Plan to be a joint long-range capital facilities plan, including an inventory of facilities, an
assessment of needs and standards, and a review of payment-in-lieu programs and long-term
parkland acquisition goals.
The Work Group, comprised of elected board and advisory board representatives from each
jurisdiction, has worked to explore these and other topics. The report, completed on May 26,
contains a number of recommendations for the County and other jurisdictions, including the
formation of a new Parks and Resource Lands Council as a long-term coordinating mechanism.
The attached executive summary highlights those recommendations.
FINANCIAL IMPACT: None at this time. Some recommendations of the report, to be
considered later, would have financial implications.
RECOMMENDATION(S): Receive as information. The Manager recommends that the Board
consider the recommendations from the Work Group over the summer and plan to discuss the
report (and subsequent referral to advisory boards) in August/September.
z
Executive Summary
Report of the Joint Master Recreation and Parks
_ Work Group
June 15, 1999
Introduction
On -November 19, 1997, the Board of Commissioners created a Joint Master
Recreation and Parks Work Group. The Work Group was developed to follow up
on two reports: a 1996 Assembly of Governments report "Recreation and Parks
Issues in Orange County, NC", and a May 1997 report entitled "Coordination of
Parks and Recreation Services for Carrboro, Chapel Hill and Orange County",
developed by the area Managers.
The charge to the Work Group was to:
"update and modify the Master Recreation and Parks Plan to be a joint /ong-
range capita/ faci/ities plan for Orange County, Carrboro and Chape/ Hil/... "
Although not listed in the charge, Town of Hillsborough and OWASA
representatives participated in the work group effort. In accomplishing this task
the Work Group was asked to address the following topics:
- An update of recreational facilities countywide
- An update of local recreation and parks needs
- Develop standards for park facilities and design
- Joint siting, design and management of school and park sites
- Tangible and realistic parkland acquisition goals
- Reassess payment-in-lieu of dedication programs (and service area
boundaries for programs)
- Dedication provisions for greenways in the Joint Planning Area
The Work Group began on December 17, 1997. The group met monthly over the
next 17 months (including six months of additional subcommittee work) to
produce a report. While the Work Group reviewing a great deal of research and
discussed a wide variety of topics, a summary of the report may best be
considered in the following six topical categories:
i. Where Are We Now?
In evaluating the status of recreation and parks in the County, the Work Group
created two committees. The Resource Inventory Committee worked during the
spring and summer of 1998 to develop a template for tracking all existing
recreational facilities, and discuss a map or brochurq to convey these facilities to
3
the public. The inventory of facilities (including quasi-public and private "fee-
based" locations) is included as Appendix C to the report. The inventory would
be maintained for future use, and contains information on the type of activities
available at each location.
The Needs Assessment Committee met during the spring and summer of 1998 to
update recreation and parks needs from each jurisdiction. These needs are found
on pages 4-7 of the report, and run the gamut from active recreation facilities to
community parks, greenways and "low-impact" recreation. In summary, the
orimarv needs identifiPri fnr aarh ii iricriirtinn ~eiarc•
.~
Carrboro Acquire/develop Northern Community Park,
communi mnasium
Chapel Hill Complete Northern Community Park, Southern
communi Park
Hillsborou h River Walk Fairview Park Occoneechee Park
Orange County Complete Efland-Cheeks Park, Northern Human
Services Center Park, acquire parkland in
Bin ham/Little River Tw s
An evaluation of previous bonds and projects constructed with those monies is
also provided on pages 7-10 of the document. A summary of needs appears on
page 19.
The Work Group discussed the concept of a Countywide set of standards for
facilities and park design. The development of a common set of standards was
recognized as important, but because of time considerations was deferred by the
Work Group. Recommendation B on page 35 addresses this topic.
2. Where Do We Go From Here
With knowledge of needs and facilities, the Work Group then turned its attention
to future concerns. One such area was a set of goals and criteria for future land
acquisition and facility sitings. In general, the goals and criteria (pages 12-14)
encourage joint siting of schools and parks, preservation of resources in
conjunction with parks development, awareness of environmentally-sensitive
lands, the existence of matching funds, considering the intensity of use, and
locations for linear parks.
The work of the Schools and Land Use Councils was recognized as an important
piece of the recreation picture, and the idea of joint management of school and
park sites (as well as possible joint acquisition) is a theme throughout the report.
One topic that the report notes regards impediments to locating new active
recreation facilities. These impediments exist primarily in the context of lighting,
intensity, traffic and noise. In defining both active and low-impact recreation, it is
4
important to be consistent with surrounding land uses. Ideas on ways to mitigate
the impacts of larger active facilities include co-location of schools and parks,
combining active and low-impact recreation in larger park settings to buffer
residential areas, and the need for a proactive land acquisition program to
purchase lands for long-term use as parks (and/or schools).
The potential for coordinating parks planning exists beyond the scope of the local
governments involved in this effort. In particular, the report notes the significant
potential for coordination with UNC, OWASA and Duke University in meeting
long-term needs of mutual interest. While UNC provides many facilities used by
students (and local residents), there is also an undefined impact on local
recreation facilities from faculty and staff of the University. Programs such as the
Carolina Outdoor Recreation Center offer a means for sharing resources, and the
potential exists for collaboration on future recreational facilities with UNC.
Likewise, OWASA currently provides recreation facilities at both University Lake
and Cane Creek Reservoir. OWASA holds over 3,000 acres of land in the County,
some of which appears to offer the opportunity for coordinated recreational use.
A memo from the OWASA Board (Appendix F) indicates a willingness to discuss
certain parcels for future public use. And finally, Duke Forest also provides a
recreational resource to County citizens. While concerns about protecting the
integrity of the forest resources will be paramount, opportunities exist to work
with Duke in the future, particularly in terms of carefully-located trails that fit
with the University's plans.
3. Adequate Provision of Parkland and Natural Corridors
One of the most prominent needs identified is to preserve green corridors,
whether in an urban or rural setting. This section of the report addresses the
potential for linking some existing and proposed greenway networks in Chapel
Hill, Carrboro and Hillsborough to future parks and regional open space such as
Eno River State Park and Duke Forest.
The importance of existing and future greenways in the Towns is noted, as well
as the existence of a schematic plan for greenways extending from the Chapel
Hill/Carrboro area into the Rural Buffer, developed in 1986 as part of the Joint
Planning Area Land Use Plan. Wildlife corridors in the rural areas were introduced
into County planning efforts through the 1988 Inventory of Natural Areas and
Wildlife Habitat, and are important to the overall County and regional ecosystem
as part of the "green infrastructure." These corridors are undeveloped riparian
stream corridors or overland connectors that exist in a natural state. Any trails
would exist only as they have evolved over time by use of wildlife or humans.
However, as the County and Towns continue to grow, it will become important to
link Town parks to regional corridors such as Eno River State Park, nodes of
5
open space such as Duke Forest, and future County parks and open space.
Linking future rural parks and open space to Town parks via a few unpaved trails
could greatly expand low-impact recreational opportunities. The identification of
strategic corridors that might tie together these recreation facilities is suggested
as a practical- long-term goal. Using criteria and a classification scheme, the
potential for a select few woodland trails as part of a Countywide (and
eventually) regional corridor scheme is noted. Three examples of such trail links
are offered (two within the Towns or Rural Buffer, one in the rural areas linking
Cane Creek and Eno River State Park) are offered.
4. Coordinated Land Acquisition for Parks
The 1996 and 1997 reports point to the need for coordinated capital funding,
and this is one of the goals of this project. In discussing parks needs and goals,
the Work Group placed a strong emphasis on the need to begin land acquisition
for long-term park needs now.
Orange County has taken steps in 1999 to create a mechanism that could be
used in this fashion. The new Department of Environment and Resource
Conservation began operation on January 4, with a primary focus on
acquisition/easements of critical land resources. A Land Acquisition Program for
Orange County is currently being developed for discussion in the fall of 1999:
This program will develop and/or use inventories, criteria and a management
structure for the acquisition and stewardship of land resources deemed critical to
the public interest, working with other existing land trusts and entities. The
program will involve the preservation of natural areas and wildlife habitat,
farmland, riparian buffers, and the acquisition of lands for long-term parks use.
The County is hiring a Land Resources Conservation Manager, with expertise in
site evaluation and land acquisition this summer. This position will coordinate
land acquisition efforts, and would use the criteria developed in the Master
Recreation and Parks effort to evaluate land purchases for parks (please see the
Recommendations section for additional details). The outline of the Land
Resource Acquisition Program may be found in the report on page 26.
Funding for long-term parkland acquisition would likely involve local bonds and
allocations, and grants from programs such as the state Parks and Recreation
Trust Fund. Information on this program is provided on pages 27-28.
S. Payment-in-Lieu Programs
All of the jurisdictions in the County have provisions in their development
ordinances addressing dedication or provision of recreation facilities. Carrboro
and Orange County also have payment-in-lieu of dedication programs, which
allows for the payment of a fee based on the number of lots in lieu of providing
recreation facilities. Orange County has special legislation that would allow for
6
the use of an impact fee for public uses including recreation, but this proviso has
not been utilized to date.
As of 1999, Carrboro has collected $453,000 through its payment-in-lieu
program. Orange County currently has $488,000 available, allocated by four
districts in which the money must be spent. The County has also received land
dedications totaling 44 acres since 1986, although this land is in small pieces
exclusively in Bingham and Chapel Hill Townships.
The Work Group found that difficulties exist with the existing payment-in-lieu
programs. The funds must be geographically earmarked and spent within the
area collected. They must also be supplemented with matching funds for use.
Considerable research was performed to explore programs in other jurisdictions,
and a special meeting with Richard Ducker from the Institute of Government was
held to review payment-in-lieu possibilities.
6. Recommendations
Using the research and deliberations of 17 months, and with the charge and
goals of the project in mind, the Work Group developed nine recommendations,
summarized as follows (these recommendations also appear on pages 34-40).
A. Create a Parks and Resource Lands Counci/
As we move to coordinate long-term recreation and parks planning, the need for
a permanent joint council (to meet quarterly) was identified, building on the
useful nature of the Work Group itself. Possible duties might include:
- Develop and review standards
- Develop future parks bond proposals
- Provide a coordinating mechanism for parks plan updates
- Make recommendations on allocations of future bond moneys
- Coordinate acquisitions though the County Land Resource Acquisition
Program
A resolution asking the local boards to create the Parks and Resource Lands
Council is attached as Appendix L.
B. Inter jurisdicriona/Standards
As previously noted, impediments exist to the creation of common standards that
could be used Countywide for recreation and parks facilities. If coordinated
funding were pursued, the need for some coordinated standard would be
important. The Parks and Resource Lands Council is recommended as a
mechanism to accomplish this goal.
7
C. Joint Siting, Design and Management ofSchoo/ and Park Sites
Coordinating efforts and responsibilities with the Schools and Land Use Councils
will be important, given the emphasis from both groups on the benefits of joint
school/park development. As discussed in the section on land acquisition, it is
recommended-that Orange County, with dedicated staff resources, a program for
land acquisition, and a role in school siting, should take the lead role.
D. Public/Private Partnerships
One of the most exciting prospects is the potential for partnerships. Coordination
between the local governments on future parks, such as a large district park
between Hillsborough and Chapel Hill/Carrboro, will be paramount. Opportunities
also exist with OWASA, and it is recommended that the Parks and Resource
Lands Council work to identify properties for partnership and meet to explore.
these possibilities. Coordination with UNC on future parks also appears practical
and should be pursued. While Duke Forest is a different type of recreational
entity, it plays an important role in the County's open space network and future
discussion of less-sensitive portions of the Forest as links in the open space
network should be pursued. Finally, opportunities for coordination with the state,
other land trusts and private firms offer many possibilities for future needs.
E. Joint Capita/ Facilities P/arming /Coordinated Land Acquisition -
A meeting of the Managers of each jurisdiction is recommended to develop a
plan for coordinating long-term land acquisition. With land prices continuing to
escalate and little land available for parks within the Town jurisdictions, action is
needed now to identify and acquire future park sites. Use of the individual
Capital Improvement Plans could be a fundamental part of this ~ funding
mechanism. By timing and matching fund availability, the Towns and County will
be able to work together more effectively, with the County serving in a lead role
in site identification and acquisition, working with the Parks and Resource Lands
Council and the individual elected boards.
F. Open Facilities Policy
In the spirit of inter-governmental coordination, the Work Group feels that all
County citizens should have the opportunity to use facilities within the County,
regardless of their jurisdiction of residence. Attempts to restrict use will be
cumbersome administratively and not constructive in the collaborative future of
parks planning. A resolution to this end for consideration by the elected boards is
found as Appendix F. Pursuit of a similar policy with UNC and OWASA is
recommended, as is a review of hours of operation at Cane Creek/University
Lake.
G. Payment-in-Lieu Changes
After considerable discussion and review, the Work Group finds that the existing
payment-in-lieu programs are not likely to produce sufficient funds to meet long-
8
term needs. It is recommended that Orange County and Carrboro develop plans
to match other funding with the current payment-in-lieu funds to use these
resources. Even with its limitations, the existing payment-in-lieu program should
be kept and modified where possible. The potential for an impact fee or impact
tax should be explored, using existing legislation.
H. Address Existing Needs
While more thorough standards are needed, apopulation-based standard from
the 1996 Assembly of Governments report was used to determine needs for
parklands. Using this standard, the County as a whole has a current deficit of
645 acres of parkland. With expected population growth, this is County and
Towns combined with have a deficit of 1,265 acres by the year 2025.
Based on average land sales (weighted for urban and rural lands) and existing
bond funds, the cost of purchasing lands to erase the long-term deficit is $10.12
million in 1999 dollars. Since this will unquestionably rise in the future, the Work
Group again recommends immediate action in terms of land.acquisitions.
I. Use of Current Funds and Future Funding Needs
While it may be more practical to develop recreation facilities over time as the
population increases, amore-proactive approach to land acquisition is needed to
identify and purchase sites that offer both active and low-impact recreation
potential. Matching funds from the different jurisdictions (coordinated through
the aforementioned joint capital funding mechanism) should be an important
component, and an acreage threshold and additional standards for joint
school/park sites are also warranted.
To address long-term needs, the Work Group recommends that the following
actions occur:
- The remaining $2.89 million for land acquisition from the County parks bond
should be used for acquisition of lands identified as sites for long-term
acquisition as soon as possible.
- The remainder of the $10 million in long-term land acquisition should be
addressed through an $8 million parks bond placed before the voters in
November 2000. The Parks and Resource Lands Council should develop the