HomeMy WebLinkAboutAgenda - 02-03-2009 - 4n ORANGE COUNTY
BOARD OF COMMISSIONERS
ACTION AGENDA ITEM ABSTRACT
Meeting Date: February 3, 2009
Action Agenda
Item No. 4- -n
SUBJECT: Capital Project Funding
DEPARTMENT: Finance PUBLIC HEARING: (YIN) No
ATTACHMENT(S): INFORMATION CONTACT:
This item has been delayed from Gary Humphreys, 245-2453
previous Board meetings due to time
constraints.
PURPOSE: To approve a plan addressing additional funding needs related to the School and
County Capital Project Funds by appropriating fund balance of $3.5 million in FY 2008-09 and
$2.4 million in FY 2009-10.
BACKGROUND: This item was previously discussed with the Board at work sessions on
October 28 and November 18, 2008. In preparation for year end reconciliation, a review of the
School and County capital project funds revealed a difference in budgeted and actual revenues.
In general, the differences in budgeted and actual revenues exist because:
1. Differences existing prior to the transition from the financial legacy system to MUNIS
business system in 2003 were never corrected;
2. Proceeds from past debt financings were set aside in an unallocated account or line item
instead of being allocated to specific projects;
3. Grant monies were budgeted and not awarded/received;
4. Total expenditures exceeded the project budget by varying amounts;
5. Specific projects were budgeted but monies were never transferred from the General
Fund; or
6. Bond monies to be issued are already budgeted but the revenue is not yet received.
Based on staffs internal analysis, unallocated revenues within the capital project funds can be
transferred to projects where there are shortfalls. This will leave a revenue shortfall of $5.9
million. The following chart summarizes the funds available and net shortfall by capital fund.
2
Source of Funds School Capital County Capital
Project Fund Project Fund
Additional Funds Needed $8,430,000 $9,291,944
Unallocated Alternative Financing $1,347,000
Unallocated Bonds 907,000
School Capital Reserve Funds 580,000
From Closed Projects 455,000
Interest Earnings $ 875,000
Revenue Available within Projects 2,136,255
Total Funds Available by Fund $3,289,000 $3,011,255
Grand Total Funds Available $6,280,689
Park Bonds to be issued to complete project funding 5,500,000
Net Shortfall $5,141,000 $780,689
Total Both Funds _ $5,921,689
Staff Proposal for Covering Remaining Shortfall
As stated earlier, $5.9 million in additional capital funding is needed to cover the shortfall.
Based on current year cash flow needs, at least $3.5 million of the shortfall is needed in the
current fiscal year. The remaining $2.4 million will be needed in FY 2009-10.
Staffs analysis shows the majority of the remaining shortfalls resulted from differences between
the pay-as-you-go funds budgeted for projects in the two capital p roje ct funds and the amount of
money transferred to the two capital projects funds from the General Fund. Most of these
differences existed when the conversion to MUNIS was made. This means they occurred prior
to the end of FY 2003 over one or more fiscal years. If those additional amounts of pay- as-you-
go revenue had been transferred from the General Fund, the fund balance would be less than it
currently stands.
Staff recommends the Board approve a two-year funding plan to replenish the shortfall by
appropriating General Fund available fund balance.
The County's General Fund undesignated fund balance at the end of FY 2007-08 is 13.9% of
expenditures or $23.8 million. If this plan is implemented, based on conservative projections,
the projected available fund balance at the end of FY 2008-09 could be approximately 12% of
expenditures or $21.85 million. The appropriation of $2.4 million in FY 2009-10 would decrease
the available fund balance to 11.1% or $21.64 million. While this percentage amount is higher
than the Local Government Commission recommendation of a minimum 8 percent of
expenditures, it is below staffs recommended target of 15 percent of expenditures.
Staff will bring budget amendments to the Board to implement the recommended action if
approved by the Board. Additionally, budget amendments will be brought to the Board in those
cases where project expenditures have exceeded the project budgets and where appropriation
of other identified sources, such as the transfer of the remaining School Capital Reserve Funds,
is necessary.
3
As best practice, local governments should only appropriate fund balance for non-recurring
purposes such as capital. While it is preferable to be able to achieve the fund balance goal in
order to meet needs in time of fiscal stress, the use of the fund balance to meet non-recurring
priorities is understandable. It would be prudent to not let the fund balance fall below 11% in
order to provide for cash flow as well as maintaining the County's excellent bond rating. Once
funding the shortfall is completed, it is recommended steps be taken to rebuild the fund balance
of the General Fund.
FINANCIAL IMPACT: The financial impact of the recommended action is the projected
reduction of the fund balance of the General Fund to as low as 11.1% of projected FY 2009-10
expenditures.
RECOMMENDATION(S): The County Manager recommends the Board approve the two year
funding plan which includes 1) Appropriating $3.5 million from the fund balance of the General
Fund for transfer to the School Capital Project Fund and County Capital Project Fund; 2)
Include the remaining appropriation of $2.4 million from the fund balance of the General Fund
needed to complete the correction of the shortfall in the Fiscal Year 2009-10 budget; and 3)
Direct staff to take those actions necessary to reallocate available funding to correct the project
shortfalls and to bring back to the Board the budget amendments necessary to implement this
plan.